Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySTARR
HighwayUS0083
FromROMA, HEBBRONVILLE
ToVARIOUS ROADWAYS
CSJ6257-53-001
Proj IDSUP - 625753001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010296546.68233104.9878.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-20-13
Work Began00-00-00
Work Completed
Time Computed01-02-14
Contract Working Days608
Addl Days Granted0
Working Days Charged607
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01142132
Totals296546.680.00233104.9878.6

CountyHIDALGO
HighwayUS0083
FromDISTRICT WIDE
ToVARIOUS COUNTIES
CSJ6257-54-001
Proj IDSUP - 625754001
Work TypePALM TREE TRIMMING AND REMOVAL
 
0.01076210.0098260.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-08-13
Work Began00-00-00
Work Completed
Time Computed09-03-13
Contract Working Days366
Addl Days Granted0
Working Days Charged362
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
VALLEY VOCATIONAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09132102
Totals76210.000.0098260.0099.9

CountyCAMERON
HighwayFM0106
FromFM 106
ToCAMERON COUNTY
CSJ6257-55-001
Proj IDSUP - 625755001
Work TypeMAINTENANCE OF RIO HONDO LIFT BRIDGE
 
0.01041349.6037866.3291.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-29-13
Work Began00-00-00
Work Completed
Time Computed09-27-13
Contract Working Days730
Addl Days Granted183
Working Days Charged912
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09132135
Totals41349.600.0037866.3291.5

CountyJIM HOGG
HighwayFM1017
FromHEBBRONVILLE AND RIO GRANDE CITY MAINT
ToVARIOUS ROADWAYS
CSJ6257-56-001
Proj IDSUP - 625756001
Work TypeROADSIDE MOWING AND LITTER REMOVAL
 
0.010531653.36538293.1799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-29-13
Work Began00-00-00
Work Completed
Time Computed09-23-13
Contract Working Days730
Addl Days Granted30
Working Days Charged759
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
UPPER VALLEY HELPSOURCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09132104
Totals531653.360.00538293.1799.9

CountyHIDALGO
HighwayUS0083
FromDISTRICT OFFICE
ToPHARR MAINTENANCE/AREA OFFICE
CSJ6257-57-001
Proj IDSUP - 625757001
Work TypeGROUNDS MAINTENANCE
 
0.01041417.2839691.5695.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-29-13
Work Began00-00-00
Work Completed
Time Computed09-19-13
Contract Working Days730
Addl Days Granted0
Working Days Charged711
Percent Time Used97
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09132105
Totals41417.280.0039691.5695.8

CountyCAMERON
HighwayUS0077
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6268-93-001
Proj IDRMC - 626893001
Work TypeINTERSECTION & U-TURN IMPROVEMENTS
 
0.010436162.05601271.6499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-28-14
Work Began00-00-00
Work Completed
Time Computed05-01-14
Contract Working Days60
Addl Days Granted68
Working Days Charged128
Percent Time Used100
Contractor(s)
CLORE CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6268-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03142101
Totals436162.050.00601271.6499.9

CountyHIDALGO
HighwayUS0083
FromDISTRICT WIDE
ToDISTRICT WIDE
CSJ6271-73-001
Proj IDSUP - 627173001
Work TypeDRAIN INLET CLEANING
 
0.010372454.00236626.5263.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-14
Work Began12-11-14
Work Completed
Time Computed12-11-14
Contract Working Days730
Addl Days Granted0
Working Days Charged629
Percent Time Used86
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09142131
Totals372454.000.00236626.5263.5

CountyHIDALGO
HighwayUS0083
FromUS 83, US 77, US 281, SH 550
ToVARIOUS
CSJ6271-74-001
Proj IDSUP - 627174001
Work TypeDEBRIS REMOVAL
 
0.010388340.00437714.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-02-14
Work Began09-15-14
Work Completed
Time Computed09-15-14
Contract Working Days730
Addl Days Granted0
Working Days Charged716
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09142134
Totals388340.000.00437714.5099.9

CountyHIDALGO
HighwayUS0083
FromBROWNSVILLE MNT, EDCOUCH MNT,
ToMISSION MNT, RAYMONDVILLE MNT
CSJ6271-76-001
Proj IDSUP - 627176001
Work TypeJANITORIAL MAINTENANCE
 
0.01068416.8058904.7086.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-14
Work Began09-02-14
Work Completed
Time Computed09-02-14
Contract Working Days730
Addl Days Granted0
Working Days Charged729
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES OF SOUTH TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09142132
Totals68416.800.0058904.7086.0

CountyHIDALGO
HighwayUS0083
FromPHARR MAINTENANCE/AREA OFFICE
ToDISTRICT COMPLEX
CSJ6271-77-001
Proj IDSUP - 627177001
Work TypeJANITORIAL MAINTENANCE
 
0.010202491.90193350.8795.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-14
Work Began09-02-14
Work Completed
Time Computed09-02-14
Contract Working Days730
Addl Days Granted0
Working Days Charged729
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6271-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09142133
Totals202491.900.00193350.8795.4

CountyCAMERON
HighwayBU0077W
FromSAN BENITO MNT/AREA OFFICE
ToCAMERON COUNTY
CSJ6271-78-001
Proj IDSUP - 627178001
Work TypeJANITORIAL MAINTENANCE
 
0.01022996.8031483.8499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-14
Work Began09-02-14
Work Completed
Time Computed09-02-14
Contract Working Days730
Addl Days Granted0
Working Days Charged729
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES OF SOUTH TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09142130
Totals22996.800.0031483.8499.9

CountyCAMERON
HighwayUS0077
FromCITY OF HARLINGEN
ToVARIOUS ROADWAYS
CSJ6272-35-001
Proj IDMMA - 627235001
Work TypeMAINTENANCE OF TRAFFIC SIGNALS
 
0.01097320.0097320.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-26-14
Work Began09-01-14
Work Completed
Time Computed09-01-14
Contract Working Days731
Addl Days Granted0
Working Days Charged730
Percent Time Used99
Contractor(s)
CITY OF HARLINGEN
SUBCONTRACTOR(S) FOR CCSJ: 6272-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09142101
Totals97320.000.0097320.0099.9

CountyCAMERON
HighwayUS0077
FromCITY OF BROWNSVILLE
ToVARIOUS LOCATIONS
CSJ6272-36-001
Proj IDMMA - 627236001
Work TypeMAINTENANCE OF TRAFFIC SIGNALS
 
0.01072240.0072240.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-14
Work Began09-01-14
Work Completed
Time Computed09-01-14
Contract Working Days731
Addl Days Granted0
Working Days Charged730
Percent Time Used99
Contractor(s)
CITY OF BROWNSVILLE
SUBCONTRACTOR(S) FOR CCSJ: 6272-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09142137
Totals72240.000.0072240.0099.9

CountyCAMERON
HighwayIH0069E
FromUS 77/83 INTERCHANGE
ToCAMERON COUNTY
CSJ6272-47-001
Proj IDSUP - 627247001
Work TypeLANDSCAPE MAINTENANCE
 
0.01050824.1964792.5399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-15
Work Began02-03-15
Work Completed
Time Computed02-03-15
Contract Working Days212
Addl Days Granted61
Working Days Charged270
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02152135
Totals50824.190.0064792.5399.9

CountyHIDALGO
HighwayUS0083
FromDISTRICT WIDE
ToVARIOUS COUNTIES
CSJ6273-80-001
Proj IDSUP - 627380001
Work TypePALM TREE TRIMMING AND REMOVAL
 
0.010147560.0087730.5059.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-22-14
Work Began01-26-15
Work Completed
Time Computed01-26-15
Contract Working Days730
Addl Days Granted0
Working Days Charged584
Percent Time Used80
Contractor(s)
TIBH INDUSTRIES, INC.
VALLEY VOCATIONAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09142136
Totals147560.000.0087730.5059.4

CountyHIDALGO
HighwayUS0083
FromVARIOUS COUNTIES
ToVARIOUS COUNTIES
CSJ6274-47-001
Proj IDRMC - 627447001
Work TypeTRAFFIC BARRIER REPAIR
 
0.010136650.00308265.9399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-14
Work Began01-15-15
Work Completed
Time Computed01-14-15
Contract Working Days60
Addl Days Granted40
Working Days Charged82
Percent Time Used82
Contractor(s)
VALLEY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11142101
Totals136650.000.00308265.9399.9

CountyHIDALGO
HighwayIH0002
FromIH 2 AND IH 69C
ToHIDALGO COUNTY
CSJ6287-16-001
Proj IDSUP - 628716001
Work TypeROADSIDE MOWING AND LITTER REMOVAL
 
0.010523750.00507957.0896.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-08-15
Work Completed
Time Computed00-00-00
Contract Working Days256
Addl Days Granted100
Working Days Charged281
Percent Time Used78
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09152133
Totals523750.000.00507957.0896.9

CountyHIDALGO
HighwaySH0495
FromPHARR MNT/AREA OFFICES
ToDISTRICT COMPLEX
CSJ6287-17-001
Proj IDSUP - 628717001
Work TypeGROUNDS MAINTENANCE
 
0.01041417.2836789.1488.8
Work Order08-31-15
Work Began09-14-15
Work Completed
Time Computed09-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged608
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09152130
Totals41417.281725.7236789.1488.8

CountyCAMERON
HighwayUS0083
FromVARIOUS
ToDISTRICT WIDE
CSJ6287-18-001
Proj IDSUP - 628718001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010414800.00293989.5070.8
Work Order09-02-15
Work Began09-08-15
Work Completed
Time Computed09-02-15
Contract Working Days731
Addl Days Granted0
Working Days Charged601
Percent Time Used82
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09152132
Totals414800.0018666.00293989.5070.8

CountySTARR
HighwayUS0083
FromROMA AREA/MNT OFFICES, RGC MNT OFFICE
ToHEBBRONVILLE MNT/FALFURRIAS SUB-STATION
CSJ6287-19-001
Proj IDSUP - 628719001
Work TypeJANITORIAL MAINTENANCE
 
0.01085279.4464992.9476.2
Work Order08-31-15
Work Began09-02-15
Work Completed
Time Computed09-02-15
Contract Working Days731
Addl Days Granted0
Working Days Charged608
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09152131
Totals85279.442983.6864992.9476.2