Monthly Local Let Maintenance Report For Pharr District As Of Jul 11, 2014 Page 2 Of 2

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCAMERON
Highway US0083
From SAN BENITO MNT
To CAMERON COUNTY
CSJ 6257-50-001
Proj ID SUP - 625750001
Work Type TECHNICAL ASSISTANCE
 
0.010 53913.60 2073.60 20690.64 38.3
Work Order 08-28-13
Work Began 09-02-13
Work Completed  
Time Computed 09-03-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 290
Percent Time Used 39
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES OF SOUTH TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09132137
Totals 53913.60 2073.60 20690.64 38.3

CountyHIDALGO
Highway US0083
From BROWNSVILLE, RAYMONDVILLE, SAN BENITO
To VARIOUS ROADWAYS
CSJ 6257-51-001
Proj ID SUP - 625751001
Work Type METAL BEAM GUARD FENCE REPAIR
 
0.010 402580.91 40548.80 164674.96 40.9
Work Order 12-31-13
Work Began 00-00-00
Work Completed  
Time Computed 01-06-14
Contract Working Days 608
Addl Days Granted 0
Working Days Charged 176
Percent Time Used 28
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01142130
Totals 402580.91 40548.80 164674.96 40.9

CountyHIDALGO
Highway US0083
From PHARR, EDCOUCH, MISSION
To VARIOUS ROADWAYS
CSJ 6257-52-001
Proj ID SUP - 625752001
Work Type METAL BEAM GUARD FENCE REPAIR
 
0.010 412268.27 9090.00 77981.45 18.9
Work Order 12-31-13
Work Began 00-00-00
Work Completed  
Time Computed 01-03-14
Contract Working Days 608
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01142131
Totals 412268.27 9090.00 77981.45 18.9

CountySTARR
Highway US0083
From ROMA, HEBBRONVILLE
To VARIOUS ROADWAYS
CSJ 6257-53-001
Proj ID SUP - 625753001
Work Type METAL BEAM GUARD FENCE REPAIR
 
0.010 296546.68 4600.00 60572.74 20.4
Work Order 12-20-13
Work Began 00-00-00
Work Completed  
Time Computed 01-02-14
Contract Working Days 608
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01142132
Totals 296546.68 4600.00 60572.74 20.4

CountyHIDALGO
Highway US0083
From DISTRICT WIDE
To VARIOUS COUNTIES
CSJ 6257-54-001
Proj ID SUP - 625754001
Work Type PALM TREE TRIMMING AND REMOVAL
 
0.010 76210.00 11605.00 80610.00 99.9
Work Order 08-08-13
Work Began 00-00-00
Work Completed  
Time Computed 09-03-13
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 301
Percent Time Used 82
Contractor(s)
TIBH INDUSTRIES, INC.
VALLEY VOCATIONAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09132102
Totals 76210.00 11605.00 80610.00 99.9

CountyCAMERON
Highway FM0106
From FM 106
To CAMERON COUNTY
CSJ 6257-55-001
Proj ID SUP - 625755001
Work Type MAINTENANCE OF RIO HONDO LIFT BRIDGE
 
0.010 41349.60 786.54 11461.02 27.7
Work Order 07-29-13
Work Began 00-00-00
Work Completed  
Time Computed 09-27-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09132135
Totals 41349.60 786.54 11461.02 27.7

CountyJIM HOGG
Highway FM1017
From HEBBRONVILLE AND RIO GRANDE CITY MAINT
To VARIOUS ROADWAYS
CSJ 6257-56-001
Proj ID SUP - 625756001
Work Type ROADSIDE MOWING AND LITTER REMOVAL
 
0.010 531653.36 36235.55 192188.29 36.1
Work Order 08-29-13
Work Began 00-00-00
Work Completed  
Time Computed 09-23-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
UPPER VALLEY HELPSOURCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09132104
Totals 531653.36 36235.55 192188.29 36.1

CountyHIDALGO
Highway US0083
From DISTRICT OFFICE
To PHARR MAINTENANCE/AREA OFFICE
CSJ 6257-57-001
Proj ID SUP - 625757001
Work Type GROUNDS MAINTENANCE
 
0.010 41417.28 1725.72 13805.76 33.3
Work Order 07-29-13
Work Began 00-00-00
Work Completed  
Time Computed 09-19-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 285
Percent Time Used 39
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09132105
Totals 41417.28 1725.72 13805.76 33.3

CountyCAMERON
Highway US0077
From VARIOUS
To -
CSJ 6263-89-001
Proj ID SUP - 626389001
Work Type JANITORIAL, GROUNDS, LANDSCAPING
 
0.001 92659.84 7095.86 74186.74 80.0
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6263-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132131
Totals 92659.84 7095.86 74186.74 80.0

CountyCAMERON
Highway US0077
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6268-93-001
Proj ID RMC - 626893001
Work Type INTERSECTION & U - TURN IMPROVEMENTS
 
0.010 436162.05 170085.35 259520.19 59.5
Work Order 03-28-14
Work Began 00-00-00
Work Completed  
Time Computed 05-01-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 58
Contractor(s)
CLORE CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6268-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03142101
Totals 436162.05 170085.35 259520.19 59.5