Monthly State Let Maintenance Report For Paris District As Of Apr 12, 2024 Page 2 Of 4

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6433-52-001
Proj IDRMC - 643352001
Work TypePAVEMENT MARKINGS
 
0.010471520.00139471.3729.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged305
Percent Time Used83
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6433-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234030
Totals471520.0019262.64139471.3729.5

CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6433-54-001
Proj IDRMC - 643354001
Work TypePAVEMENT MARKINGS
 
0.010461060.50119116.3725.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-05-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged271
Percent Time Used74
Contractor(s)
TRAFFIC HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6433-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234231
Totals461060.5026758.04119116.3725.8

CountyFANNIN
HighwaySH0078
From0.001
ToFANNIN COUNTY
CSJ6433-76-001
Proj IDMMC - 643376001
Work TypeEMULSION
 
0.010437700.00342012.32100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-22-23
Work Completed03-19-24
Time Computed00-00-00
Contract Working Days182
Addl Days Granted120
Working Days Charged302
Percent Time Used100
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6433-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234016
Totals437700.000.00342012.32100.0

CountyHOPKINS
HighwayIH0030
From0.001
ToHOPKINS COUNTY
CSJ6433-80-001
Proj IDMMC - 643380001
Work TypeEMULSION
 
0.010273750.0086998.6031.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-01-23
Work Completed
Time Computed00-00-00
Contract Working Days182
Addl Days Granted182
Working Days Charged305
Percent Time Used83
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6433-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234214
Totals273750.000.0086998.6031.7

CountyHOPKINS
HighwayIH0030
From0.001
ToHOPKINS COUNTY
CSJ6433-82-001
Proj IDMMC - 643382001
Work TypeDENSE GRADED HOT MIX
 
0.010685000.00563918.7082.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged303
Percent Time Used84
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6433-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234017
Totals685000.000.00563918.7082.3

CountyHUNT
HighwayIH0030
From0.001
ToHUNT COUNTY
CSJ6433-86-001
Proj IDMMC - 643386001
Work TypeDENSE GRADED HOT MIX
 
0.010620500.00363350.3558.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-28-23
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged309
Percent Time Used85
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6433-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234215
Totals620500.0086725.50363350.3558.5

CountyHUNT
HighwayIH0030
From0.001
ToHUNT COUNTY
CSJ6434-10-001
Proj IDMMC - 643410001
Work TypeEMULSION
 
0.010263970.00347020.7499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-22-23
Work Completed
Time Computed00-00-00
Contract Working Days182
Addl Days Granted182
Working Days Charged315
Percent Time Used86
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6434-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234018
Totals263970.000.00347020.7499.9

CountyRAINS
HighwayUS0069
From0.001
ToRAINS COUNTY
CSJ6434-12-001
Proj IDMMC - 643412001
Work TypeEMULSION
 
0.010273750.00120509.3844.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-22-23
Work Completed
Time Computed00-00-00
Contract Working Days182
Addl Days Granted182
Working Days Charged315
Percent Time Used86
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6434-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234216
Totals273750.000.00120509.3844.0

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6434-84-001
Proj IDRMC - 643484001
Work TypeILLUMINATION MAINTENANCE
 
0.010439885.3082220.7518.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted0
Working Days Charged84
Percent Time Used33
Contractor(s)
YUNEX LLC
SUBCONTRACTOR(S) FOR CCSJ: 6434-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234035
Totals439885.302847.8382220.7518.6

CountyLAMAR
HighwayUS0082
From0.001
ToPARIS DISTRICT
CSJ6435-78-001
Proj IDMMC - 643578001
Work TypeFLEXIBLE BASE
 
0.0101533000.00754533.2049.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-23
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted244
Working Days Charged275
Percent Time Used75
Contractor(s)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6435-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234023
Totals1533000.000.00754533.2049.2

CountyGRAYSON
HighwayUS0075
From0.001
ToGRAYSON COUNTY
CSJ6436-45-001
Proj IDMMC - 643645001
Work TypeEMULSION
 
0.010297490.00107364.8336.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-29-23
Work Completed
Time Computed00-00-00
Contract Working Days182
Addl Days Granted120
Working Days Charged277
Percent Time Used91
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6436-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234024
Totals297490.000.00107364.8336.0

CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS
ToALONG US75
CSJ6437-37-001
Proj IDRMC - 643737001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.010872711.00905095.3299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-09-23
Work Completed
Time Computed00-00-00
Contract Working Days65
Addl Days Granted0
Working Days Charged61
Percent Time Used93
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6437-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234424
Totals872711.0079872.69905095.3299.9

CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6440-51-001
Proj IDRMC - 644051001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0102947460.00488182.4316.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-29-24
Work Completed
Time Computed00-00-00
Contract Working Days138
Addl Days Granted0
Working Days Charged11
Percent Time Used7
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6440-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234032
Totals2947460.00488182.43488182.4316.5

CountyGRAYSON
HighwayUS0069
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6441-62-001
Proj IDRMC - 644162001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0104219509.82386183.999.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted0
Working Days Charged142
Percent Time Used55
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 6441-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234623
Totals4219509.82357623.99386183.999.1

CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS IN
ToHUNT, RAINS, HOPKINS, AND FRANKLIN CO.
CSJ6441-97-001
Proj IDRMC - 644197001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010719833.00258773.0035.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
ROSS SA ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6441-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234209
Totals719833.0018076.00258773.0035.9

CountyLAMAR
HighwayFM0137
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6443-16-001
Proj IDRMC - 644316001
Work TypeMILL AND INLAY
 
0.0106031608.552458756.8840.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-06-23
Work Completed
Time Computed00-00-00
Contract Working Days114
Addl Days Granted0
Working Days Charged46
Percent Time Used40
Contractor(s)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6443-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234425
Totals6031608.55195381.792458756.8840.7

CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS
ToPARIS DISTRICT
CSJ6445-19-001
Proj IDMMC - 644519001
Work TypeDE-ICING SALT
 
0.010891158.0086829.239.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-18-23
Work Completed
Time Computed00-00-00
Contract Working Days182
Addl Days Granted182
Working Days Charged196
Percent Time Used53
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6445-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234033
Totals891158.000.0086829.239.7

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6445-37-001
Proj IDRMC - 644537001
Work TypeRAISED PAVEMENT MARKERS
 
0.010536512.0033137.006.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-26-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged35
Percent Time Used9
Contractor(s)
BRYDL CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6445-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234036
Totals536512.0010029.0033137.006.1

CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS
ToIN HOPKINS AND FRANKLIN COUNTIES
CSJ6446-04-001
Proj IDMMC - 644604001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010525765.0090673.8817.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-23
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted120
Working Days Charged183
Percent Time Used76
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6446-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234034
Totals525765.000.0090673.8817.2

CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS
ToIN HUNT & RAINS COUNTIES
CSJ6447-08-001
Proj IDMMC - 644708001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010412862.50333417.7780.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-23
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted120
Working Days Charged183
Percent Time Used76
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6447-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234224
Totals412862.500.00333417.7780.7