Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFANNIN
Highway FM1396
From FM 273
To LAMASCO
CSJ 6135-54-001
Proj ID RMC - 613554001
Work Type BASE REHAB
 
0.010 1443205.99 39977.66 1434159.64 99.9
Work Order 09-04-07
Work Began 09-04-07
Work Completed  
Time Computed 09-11-07
Contract Working Days 125
Addl Days Granted 11
Working Days Charged 154
Percent Time Used 113
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6135-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06074001
Totals 1443205.99 39977.66 1434159.64 99.9

CountyHOPKINS
Highway FM0071
From SH 19
To FM 3505
CSJ 6171-16-001
Proj ID RMC - 617116001
Work Type REHAB OF EXISTING ROADWAY
 
3.860 1058323.50 57673.19 887653.83 83.8
Work Order 03-14-08
Work Began 03-28-08
Work Completed  
Time Computed 04-04-08
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 150
Percent Time Used 89
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6171-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01084001
Totals 1058323.50 57673.19 887653.83 83.8

CountyHOPKINS
Highway FM0071
From CR 3558
To FM 3236
CSJ 6171-17-001
Proj ID RMC - 617117001
Work Type REHABILITATION OF EXISTING ROADWAY
 
4.017 1208436.40 89687.34 494506.64 40.9
Work Order 08-07-08
Work Began 08-07-08
Work Completed  
Time Computed 08-14-08
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 35
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 6171-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06084001
Totals 1208436.40 89687.34 494506.64 40.9

CountyFANNIN
Highway SH0078
From CR 4940
To COLLIN COUNTY LINE
CSJ 6171-18-001
Proj ID RMC - 617118001
Work Type REHABILITATION OF EXISTING ROADWAY
 
0.010 1226492.41 0.00 1223237.02 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-03-08
Work Began 06-03-08
Work Completed  
Time Computed 06-10-08
Contract Working Days 60
Addl Days Granted 12
Working Days Charged 102
Percent Time Used 141
Contractor(s)
R. K. HALL CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6171-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03084001
Totals 1226492.41 0.00 1223237.02 99.9

CountyHUNT
Highway SH0034
From RM 264+0.273
To RM 264+0.623
CSJ 6172-21-001
Proj ID RMC - 617221001
Work Type CONSTRUCT TURN LANE
 
0.350 385402.49 0.00 391449.89 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-09-08
Work Began 06-09-08
Work Completed 10-27-08
Time Computed 06-16-08
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 95
Contractor(s)
RED-GAP CONTRACTORS, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6172-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04084030
Totals 385402.49 0.00 391449.89 100.0

CountyGRAYSON
Highway FM0901
From SH 56
To US 82
CSJ 6175-35-001
Proj ID RMC - 617535001
Work Type REHAB OF EXISTING ROADWAY
 
0.010 823506.40 0.00 129397.39 57.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-12-08
Work Began 09-12-08
Work Completed  
Time Computed 09-19-08
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 50
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 6175-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08084001
Totals 823506.40 0.00 129397.39 57.6

CountyFANNIN
Highway SH0078
From LEONARD
To CR 4940
CSJ 6175-75-001
Proj ID RMC - 617575001
Work Type REHAB OF EXISTING ROADWAY
 
3.756 1169086.80 0.00 1088937.05 95.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-22-08
Work Began 07-22-08
Work Completed  
Time Computed 07-29-08
Contract Working Days 60
Addl Days Granted 8
Working Days Charged 69
Percent Time Used 101
Contractor(s)
R. K. HALL CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6175-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06084011
Totals 1169086.80 0.00 1088937.05 95.7

CountyLAMAR
Highway FM2820
From FM 79
To FM 38
CSJ 6179-18-001
Proj ID RMC - 617918001
Work Type BASE RESTORATION
 
4.500 1436672.17 61452.33 61452.33 4.2
Work Order 10-01-08
Work Began 10-01-08
Work Completed  
Time Computed 10-08-08
Contract Working Days 176
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 10
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6179-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07084007
Totals 1436672.17 61452.33 61452.33 4.2

CountyHOPKINS
Highway IH0030
From FM 499
To LOOP 301
CSJ 6184-50-001
Proj ID RMC - 618450001
Work Type FULL DEPTH REPAIR OF CONCRETE PAVEMENT
 
15.000 422425.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6184-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10084011
Totals 422425.00 0.00 0.00 0.0