Item No Description Units May 31, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
700 2003 POTHOLE REPAIR (STANDARD) TON     5,484.000 103.99816 4
712 2002 JT / CRCK SEAL (POLY MOD ASPH EMULSION) LMI     365.070 625.77404 2
712 2005 JT / CRCK SEAL (RUBBER - ASPHALT) LMI     1,769.906 443.37608 6
730 2002 FULL - WIDTH MOWING AC     135,192.000 22.50214 23
730 2003 SPOT MOWING AC     2,134.000 21.40635 16
730 2056 FULL - WIDTH MOWING - TRACT (1) AC     2,122.000 24.00000 1
734 2001 LITTER REMOVAL AC     22,682.000 9.93444 11
735 2001 DEBRIS REMOVAL (CNTR MEDIANS / MAINLANES CYC     520.000 63.00000 1
735 2003 DEBRIS REMOVAL (FRONTAGE ROADS) CYC     312.000 41.00000 1
735 2005 DEBRIS REMOVAL (ENTRANCE / EXIT RAMPS) CYC     364.000 39.00000 1
735 2068 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (1) CYC     176.000 156.14000 2
735 2069 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (2) CYC     176.000 134.45818 2
735 2070 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (3) CYC     176.000 156.14000 2
735 2071 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (4) CYC     52.000 220.00000 1
735 2072 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (5) CYC     12.000 238.00000 1
735 2073 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (6) CYC     26.000 120.00000 1
735 2074 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (7) CYC     12.000 107.00000 1
735 2075 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (8) CYC     12.000 211.00000 1
735 2076 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (9) CYC     12.000 100.00000 1
735 2077 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (10 CYC     12.000 218.00000 1
735 2078 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (11 CYC     12.000 141.00000 1
735 2079 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (12 CYC     12.000 130.00000 1
735 2080 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (13 CYC     12.000 240.00000 1
735 2081 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (14 CYC     12.000 176.00000 1
735 2082 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (15 CYC     12.000 176.00000 1
735 2083 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (16 CYC     12.000 193.00000 1
735 2084 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (17 CYC     12.000 130.00000 1
735 2085 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (18 CYC     12.000 192.00000 1
735 2088 DEBRIS - FRONTAGE ROADS - AREA (1) CYC     116.000 134.48828 2
735 2089 DEBRIS - FRONTAGE ROADS - AREA (2) CYC     116.000 134.48828 2
735 2090 DEBRIS - FRONTAGE ROADS - AREA (3) CYC     116.000 134.48828 2
735 2108 DEBRIS - ENTRANCE / EXIT RAMPS - AREA (1) CYC     116.000 134.48828 2
735 2109 DEBRIS - ENTRANCE / EXIT RAMPS - AREA (2) CYC     116.000 134.48828 2
735 2110 DEBRIS - ENTRANCE / EXIT RAMPS - AREA (3) CYC     116.000 134.48828 2
745 2006 JANITORIAL MAINT (PICNIC AREAS) CYC     117.000 300.00000 1
745 2007 GROUNDS MAINT (MOWING / TRIMMING) CYC     16.000 225.00000 1
751 2005 LITTER PICKUP (SITE A) CYC     24.000 285.00000 1
751 2006 MOWING, TRIMMING, AND EDGING (SITE A) CYC     40.000 1,840.20000 2
751 2008 PLANT BED MAINTENANCE (SITE A) CYC     24.000 75.00000 1
751 2009 PRUNING (SITE A) CYC     2.000 500.00000 1
751 2016 MOWING, TRIMMING, AND EDGING (SITE B) CYC     8.000 300.00000 1
751 2024 LEAF REMOVAL CYC     2.000 325.00000 1
751 2025 LITTER PICKUP CYC     48.000 239.50000 2
751 2027 MOWING, TRIMMING, AND EDGING CYC     60.000 463.80000 2
751 2030 PLANT BED MAINTENANCE CYC     1.000 1,845.00000 1
751 2031 PRUNING CYC     1.000 2,891.00000 1
752 2020 TREE TRIMMING / BRUSH REMOVAL MI     358.690 1,559.68611 6
752 2021 TREE TRIMMING / BRUSH REMOVAL (CHANNELS) AC     140.400 951.13675 6
752 2022 TREE REMOVAL (4" - 12" DIA) EA     4,581.000 42.44706 9
752 2023 TREE REMOVAL (12" - 18" DIA) EA     2,170.000 66.95853 8
752 2024 TREE REMOVAL (18" - 24" DIA) EA     1,173.000 93.22677 8
752 2025 TREE REMOVAL (24" - 30" DIA) EA     729.000 145.74760 8
752 2026 TREE REMOVAL (30" - 36" DIA) EA     212.000 280.66038 8
752 2027 TREE REMOVAL (36" - 42" DIA) EA     119.000 378.78151 7
752 2028 TREE REMOVAL (42" - 48" DIA) EA     119.000 412.35294 7
752 2029 TREE REMOVAL (48" - 60" DIA) EA     50.000 481.80000 5
752 2030 TREE REMOVAL (60" - 72" DIA) EA     21.000 509.71429 4
752 2045 STUMP REMOVAL EA     40.000 21.50000 3
760 2001 DITCH CLEANING AND RESHAPING (FOOT) LF     101,220.000 1.53598 2
770 2001 REPAIR RAIL ELEMENT (W - BEAM) LF     7,850.000 13.03503 4
770 2002 REPAIR RAIL ELEMENT (THRIE - BEAM) LF     206.500 10.48426 4
770 2003 REP RAIL ELMNT (THRIE - BM TRANS TO W - BM) LF     163.000 5.36810 4
770 2004 REM / REPL TIMBER / STL POST W / O CONC FND EA     300.000 24.50000 2
770 2006 REALIGN POSTS EA     700.000 7.42857 2
770 2008 REPLACE TERMINAL ANCHOR POSTS EA     4.000 1.00000 3
770 2009 REMOVE GDRAIL END TRT / REPL WITH SGT EA     37.000 1,597.97297 2
770 2010 REPL SINGLE GDRAIL TERM IMPACT HEAD EA     47.000 747.44681 4
770 2011 REPLACE SINGLE GDRAIL TERMINAL RAIL LF     3,550.000 21.07746 4
770 2012 REPLACE SINGLE GDRAIL TERMINAL POST EA     445.000 61.68539 4
770 2014 REPAIR STEEL POST WITH BASE PLATE EA     8.000 1.00000 3
770 2018 REM / REPL TIMBER POST W / O CONC FND EA     420.000 23.21429 2
770 2019 REM / REPL STEEL POST W / O CONC FND EA     30.000 1.00000 1
770 2020 REM / REPL TIMBER POST W / CONC FND EA     5.000 1.00000 1
770 2021 REM / REPL STEEL POST W / CONC FND EA     5.000 1.00000 1
770 2022 REM & RESET SGT IMPACT HEAD EA     45.000 195.00000 1
770 2024 REPLACE SGT CABLE ANCHOR EA     16.000 1.00000 1
770 2026 REPLACE SGT STRUT EA     3.000 1.00000 1
770 2027 REMOVE & REPLACE BLOCKOUT EA     100.000 1.00000 1
770 2028 REPLACE HINGED TOP SGT STEEL POST EA     16.000 97.00000 1
770 2029 REPAIR RAIL ELEMENT (W - BEAM FURNISHED) LF     1,500.000 6.00000 2
770 2031 INSTALL BLOCKOUT EA     100.000 1.00000 1
770 2032 REMOVE AND RESET SGT IMPACT HEAD EA     24.000 50.00000 1
770 2035 REPAIR RAIL ELEMENT (CURVED RAIL) LF     158.000 7.65443 2
770 2038 INSTALL BLOCKOUTS (FURNISHED) EA     50.000 2.00000 1
770 2050 REM / REP TIM / STL POST W / O CONC FND (FURN EA     20.000 35.00000 1
774 2006 REPAIR (TRACC) EA     1.000 1,000.00000 1
774 2007 REPAIR (TRACC) LF     49.000 9.14286 2
774 2011 REPAIR (CATCB - FRNT SECT) EA     2.000 475.00000 2
774 2018 REPAIR (CATGR - FRONT SECTION) EA     1.000 1,000.00000 1
774 2019 REPAIR (CATGR - END SECTION) EA     2.000 128.00000 2
776 2031 REPAIR (ALUMINUM RAIL) LF     80.000 28.00000 1
780 2001 EPOXY INJECTION (TY IX) LF     28.000 60.00000 1
784 2006 REPAIR STL BRIDGE MEMBER (PILING) EA     45.000 1,000.00000 1
788 2002 CONCRETE BEAM REPAIR (CFRP) EA     13.000 8,100.00000 1
788 2003 CONCRETE BEAM REP (STRAND SPLICE & CFRP EA     3.000 13,200.00000 1