Monthly State Let Construction Report For Odessa District As Of Apr 11, 2014 Page 2 Of 2

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyECTOR
Highway SP 588
From SH 191
To ECTOR COUNTY LINE
CSJ 3571-01-006
Proj ID C 3571-1-6
Work Type INSTALL NEW TRAFFIC SIGNAL
 
2.214 2324375.93 654415.11 2065779.37 88.8
Work Order 03-26-13
Work Began 05-21-13
Work Completed  
Time Computed 05-21-13
Contract Working Days 80
Addl Days Granted 20
Working Days Charged 73
Percent Time Used 73
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3571-01-006
CONTRACTORS SERVICE COMPANY(0.49%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(0.65%)
D & A TECHNOLOGY & DEVELOPMENT, LLC(2.10%)
WILLIS ELECTRIC CO., LP( 14.53%)
PERFORMANCE EQUIPMENT(2.53%)
LPZ ENTERPRISES, LLC (1.64%)
Contract # 01133218
Totals 2324375.93 654415.11 2065779.37 88.8