Monthly State Let Construction Report For Odessa District As Of May 11, 2017 Page 2 Of 2

Last Update: Wednesday, May 17, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-170
Proj IDSTP 2017(151)
Work TypeCONSTRUCT CURB RAMPS & SIDEWALKS
 
0.100394378.00374554.2694.9
Work Order11-29-16
Work Began01-30-17
Work Completed
Time Computed01-30-17
Contract Working Days60
Addl Days Granted15
Working Days Charged52
Percent Time Used69
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-170
BARRICADES UNLIMITED (2.13)
DOUBLE A CONTRACTING, L.P. (4.42)
Contract #10163218
Totals394378.00108675.25374554.2694.9

CountyECTOR
HighwayVA
FromDISTRICTWIDE.
To.
CSJ0906-00-172
Proj IDSTP 2017(590)
Work TypeADA UPGRADE ( 2017)
 
0.100464333.00317153.5068.3
Work Order03-16-17
Work Began04-01-17
Work Completed
Time Computed04-03-17
Contract Working Days91
Addl Days Granted0
Working Days Charged19
Percent Time Used20
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-172
7X OILFIELD SERVIES, INC. (1.61)
PAVEMENT MARKINGS (1.57)
FAASS TRUCKING, INC. (1.80)
Contract #02173019
Totals464333.00317153.50317153.5068.3

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-173
Proj IDNH 2017(796)
Work TypeIH PAVEMENT MARKINGS 2017
 
229.076524246.680.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days42
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-173
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173007
Totals524246.680.000.000.0

CountyANDREWS ETC
HighwayFM 181 ETC
FromSH 176
ToSH 115
CSJ0961-03-014
Proj IDSTP 2017(032)
Work TypeSEAL COAT PROGRAM (2017)
 
246.3777466995.990.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-28-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days56
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0961-03-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09163223
Totals7466995.990.000.000.0

CountyMIDLAND
HighwaySL 250
From0.7 MI W OF FAIRGROUNDS ROAD
To1.0 MI EAST OF FAIRGROUNDS RD.
CSJ1188-02-084
Proj IDC 1188-2-84
Work TypeCONSTRUCT O/P, MAINLANES, AND RAMPS
 
1.70012997699.170.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days306
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1188-02-084
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173202
Totals12997699.170.000.000.0

CountyMIDLAND
HighwaySH 158
FromI20 NFR
ToBS 158
CSJ1188-02-096
Proj IDNH 2017(475)
Work TypeFRONTAGE ROAD REHABILITATION
 
6.0135830487.1037120.000.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-08-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1188-02-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173240
Totals5830487.100.0037120.000.6

CountyMIDLAND
HighwayFM 1788
FromIH 20 SERVICE ROAD
ToFM 1787
CSJ1718-01-033
Proj IDSTP 1502(408)
Work TypeBASE,HOTMIX,SEAL COAT,SIGNS&PAVMRKS
 
16.23710991276.158984840.4581.7
Work Order12-22-15
Work Began03-24-16
Work Completed
Time Computed03-24-16
Contract Working Days360
Addl Days Granted15
Working Days Charged221
Percent Time Used58
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1718-01-033
BARRICADES UNLIMITED (0.73)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.10)
DESERT PAVING, INC. (1.10)
DOUBLE A CONTRACTING, L.P. (1.27)
PERFORMANCE EQUIPMENT SERVICE (0.08)
WILLIS ELECTRIC CO., LP (0.54)
R.E.B. TRUCKING (1.72)
Contract #11153205
Totals10991276.15715541.078984840.4581.7

CountyMIDLAND
HighwayFM 1788
FromSH 191
ToNORTH OF SH 158
CSJ1718-07-037
Proj IDSTP 2013(743)
Work TypeFL BS,HOTMIX,EXT STR,ILLUM,PAV-MRK
 
5.40217335339.7715143689.4887.7
Work Order11-12-15
Work Began01-20-16
Work Completed
Time Computed01-12-16
Contract Working Days240
Addl Days Granted0
Working Days Charged288
Percent Time Used120
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1718-07-037
BARRICADES UNLIMITED (0.24)
DOUBLE A CONTRACTING, L.P. (0.65)
HJC FARMS, INC. (0.37)
WILLIS ELECTRIC CO., LP (1.26)
W.S. CONSTRUCTION COMPANY (6.02)
W.S. CONSTRUCTION COMPANY (12.23)
Contract #08153204
Totals17335339.772358179.5915143689.4887.7

CountyMIDLAND
HighwaySH 349
FromSH 191
ToBI 20-E
CSJ1718-07-042
Proj IDNH 1602(523)
Work TypeRECONSTRUCT AND WIDEN
 
4.0776917371.67248884.233.5
Work Order12-12-16
Work Began03-14-17
Work Completed
Time Computed03-13-17
Contract Working Days160
Addl Days Granted0
Working Days Charged34
Percent Time Used21
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1718-07-042
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.04)
BARRICADES UNLIMITED (1.37)
DUSTROL, INC. (2.32)
HJC FARMS, INC. (1.25)
REECE CONSTRUCTION CO., INC. (6.98)
WILLIS ELECTRIC CO., LP (2.77)
LPZ ENTERPRISES, LLC (13.44)
Contract #11163004
Totals6917371.67142455.66248884.233.5

CountyECTOR
HighwaySL 338
FromCARGO RD
ToTRUNK/FRONTIER ST
CSJ2224-01-087
Proj IDCC 2224-1-87
Work TypeGR,BS,ACP,SIGNALS,LRGSIGNS,PAV MARK
 
0.4032347299.00286757.2712.2
Work Order01-31-17
Work Began04-19-17
Work Completed
Time Computed04-19-17
Contract Working Days117
Addl Days Granted0
Working Days Charged8
Percent Time Used6
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2224-01-087
DOUBLE A CONTRACTING, L.P. (3.48)
DUSTROL, INC. (0.68)
BARRICADES UNLIMITED (1.05)
WILLIS ELECTRIC CO., LP (13.13)
LPZ ENTERPRISES, LLC (3.12)
Contract #10163210
Totals2347299.00192980.68286757.2712.2

CountyREEVES
HighwayRM 652
FromAT SALT CREEK
To.
CSJ2451-03-015
Proj IDBR 2017(327)
Work TypeREPLACE BRIDGE 06-195-0-2451-03-01
 
0.2993993994.330.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days173
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2451-03-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173236
Totals3993994.330.000.000.0

page 1 | page 2