Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyECTOR
Highway VA
From DISTRICTWIDE
To .
CSJ 0906-00-169
Proj ID C 906-00-169
Work Type NON - SITE SPECIFIC TRAFFIC SIGNALS
 
0.001 3256207.30 0.00 845293.96 25.9
Work Order 10-22-15
Work Began 05-12-16
Work Completed  
Time Computed 02-20-16
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 26
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-169
BARRICADES UNLIMITED (2.34%)
DESERT PAVING, INC.(6.04%)
MICA CORPORATION (6.28%)
CONTRACTORS SERVICE COMPANY(2.19%)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.(1.68%)
Contract # 07153220
Totals 3256207.30 0.00 845293.96 25.9

CountyECTOR
Highway VA
From DISTRICTWIDE
To .
CSJ 0906-00-171
Proj ID NH 2016(857)
Work Type IH PAVEMENT MARKINGS (2016)
 
131.391 519081.07 178269.73 416016.11 80.1
Work Order 04-07-16
Work Began 07-11-16
Work Completed  
Time Computed 06-07-16
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 74
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-171
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163016
Totals 519081.07 178269.73 416016.11 80.1

CountyMIDLAND
Highway CS
From FAIRGROUNDS RD FROM LP 250
To EAST PECAN AVE.
CSJ 0906-32-049
Proj ID STP 1502(406)
Work Type HMAC, STRM DRN, C & G, SIGN, SIGNALS, PVMK
 
1.487 6205048.00 233592.92 3818158.77 61.5
Work Order 10-20-15
Work Began 02-29-16
Work Completed  
Time Computed 02-18-16
Contract Working Days 160
Addl Days Granted 20
Working Days Charged 117
Percent Time Used 65
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0906-32-049
CONTRACTORS SERVICE COMPANY(0.49%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (2.86%)
BARRICADES UNLIMITED (1.06%)
HJC FARMS, INC.(0.21%)
WILLIS ELECTRIC CO., LP(5.07%)
LPZ ENTERPRISES, LLC (6.12%)
Contract # 07153049
Totals 6205048.00 233592.92 3818158.77 61.5

CountyANDREWS
Highway FM 181 ETC
From SH 176
To SH 115
CSJ 0961-03-014
Proj ID STP 2017(032)
Work Type SEAL COAT PROGRAM (2017)
 
246.377 7466995.99 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0961-03-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09163223
Totals 7466995.99 0.00 0.00 0.0

CountyMIDLAND
Highway FM 1788
From IH 20 SERVICE ROAD
To FM 1787
CSJ 1718-01-033
Proj ID STP 1502(408)
Work Type BASE, HOTMIX, SEAL COAT, SIGNS & PAVMRKS
 
16.237 10991276.15 738570.89 3677769.34 33.4
Work Order 12-22-15
Work Began 03-24-16
Work Completed  
Time Computed 03-24-16
Contract Working Days 360
Addl Days Granted 15
Working Days Charged 96
Percent Time Used 25
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1718-01-033
BARRICADES UNLIMITED (0.73%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.10%)
DESERT PAVING, INC.(1.10%)
DOUBLE A CONTRACTING, L.P. (1.27%)
PERFORMANCE EQUIPMENT SERVICE(0.08%)
WILLIS ELECTRIC CO., LP(0.54%)
R.E.B. TRUCKING(1.72%)
Contract # 11153205
Totals 10991276.15 738570.89 3677769.34 33.4

CountyMIDLAND
Highway FM 1788
From SH 191
To NORTH OF SH 158
CSJ 1718-07-037
Proj ID STP 2013(743)
Work Type FL BS, HOTMIX, EXT STR, ILLUM, PAV - MRK
 
5.402 17335339.77 482860.13 7312176.04 42.1
Work Order 11-12-15
Work Began 01-20-16
Work Completed  
Time Computed 01-12-16
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 152
Percent Time Used 63
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1718-07-037
BARRICADES UNLIMITED (0.24%)
DOUBLE A CONTRACTING, L.P. (0.65%)
HJC FARMS, INC.(0.37%)
WILLIS ELECTRIC CO., LP(1.26%)
W.S. CONSTRUCTION COMPANY(6.02%)
W.S. CONSTRUCTION COMPANY( 12.23%)
Contract # 08153204
Totals 17335339.77 482860.13 7312176.04 42.1

CountyECTOR
Highway FM 1882 ETC
From 0.16 MI SOUTH OF IH 20
To US 385 SOUTH
CSJ 2005-02-016
Proj ID STP 2016(328)
Work Type SEAL COAT PROGRAM (2016)
 
240.006 10730661.65 526484.20 10542874.58 98.2
Work Order 12-21-15
Work Began 06-23-16
Work Completed  
Time Computed 05-27-16
Contract Working Days 47
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 82
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2005-02-016
BARRICADES PLUS, LLC (0.67%)
FLAT LINE, INC.( 12.96%)
RED 16 CONSTRUCTION(1.15%)
Contract # 11153016
Totals 10730661.65 526484.20 10542874.58 98.2

CountyECTOR
Highway SH 191
From BILLY HEXT RD
To MIDLAND COUNTY LINE
CSJ 2296-01-051
Proj ID NH 2016(565)
Work Type RAMP IMPROVEMENTS
 
2.796 4387311.96 757567.57 2621230.58 59.7
Work Order 04-19-16
Work Began 06-06-16
Work Completed  
Time Computed 06-06-16
Contract Working Days 120
Addl Days Granted 2
Working Days Charged 51
Percent Time Used 41
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2296-01-051
WILLIS ELECTRIC CO., LP(9.39%)
HJC FARMS, INC.(2.56%)
BARRICADES UNLIMITED (0.53%)
LPZ ENTERPRISES, LLC (3.27%)
DOUBLE A CONTRACTING, L.P. (1.20%)
BRICK PAVING PLUS, INC.(2.44%)
INCE ENTERPRISES, INC. (7.53%)
Contract # 01163035
Totals 4387311.96 757567.57 2621230.58 59.7