Monthly State Let Construction Report For Odessa District As Of Mar 13, 2017 Page 2 Of 2

Last Update: Monday, March 13, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-170
Proj IDSTP 2017(151)
Work TypeCONSTRUCT CURB RAMPS & SIDEWALKS
 
0.100394378.00141852.1335.9
Work Order11-29-16
Work Began01-30-17
Work Completed
Time Computed01-30-17
Contract Working Days60
Addl Days Granted0
Working Days Charged17
Percent Time Used28
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-170
BARRICADES UNLIMITED (2.13)
DOUBLE A CONTRACTING, L.P. (4.42)
Contract #10163218
Totals394378.00137439.19141852.1335.9

CountyECTOR
HighwayVA
FromDISTRICTWIDE.
To.
CSJ0906-00-172
Proj IDSTP 2017(590)
Work TypeADA UPGRADE ( 2017)
 
0.100464333.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days91
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-172
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173019
Totals464333.000.000.000.0

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-173
Proj IDNH 2017(796)
Work TypeIH PAVEMENT MARKINGS 2017
 
229.076524246.680.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days42
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-173
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173007
Totals524246.680.000.000.0

CountyANDREWS ETC
HighwayFM 181 ETC
FromSH 176
ToSH 115
CSJ0961-03-014
Proj IDSTP 2017(032)
Work TypeSEAL COAT PROGRAM (2017)
 
246.3777466995.990.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-28-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days56
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0961-03-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09163223
Totals7466995.990.000.000.0

CountyMIDLAND
HighwaySH 158
FromI20 NFR
ToBS 158
CSJ1188-02-096
Proj IDNH 2017(475)
Work TypeFRONTAGE ROAD REHABILITATION
 
6.0135830487.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-08-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1188-02-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173240
Totals5830487.100.000.000.0

CountyMIDLAND
HighwayFM 1788
FromIH 20 SERVICE ROAD
ToFM 1787
CSJ1718-01-033
Proj IDSTP 1502(408)
Work TypeBASE,HOTMIX,SEAL COAT,SIGNS&PAVMRKS
 
16.23710991276.156187099.1856.2
Work Order12-22-15
Work Began03-24-16
Work Completed
Time Computed03-24-16
Contract Working Days360
Addl Days Granted15
Working Days Charged183
Percent Time Used48
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1718-01-033
BARRICADES UNLIMITED (0.73)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.10)
DESERT PAVING, INC. (1.10)
DOUBLE A CONTRACTING, L.P. (1.27)
PERFORMANCE EQUIPMENT SERVICE (0.08)
WILLIS ELECTRIC CO., LP (0.54)
R.E.B. TRUCKING (1.72)
Contract #11153205
Totals10991276.15513610.706187099.1856.2

CountyMIDLAND
HighwayFM 1788
FromSH 191
ToNORTH OF SH 158
CSJ1718-07-037
Proj IDSTP 2013(743)
Work TypeFL BS,HOTMIX,EXT STR,ILLUM,PAV-MRK
 
5.40217335339.779756047.1456.3
Work Order11-12-15
Work Began01-20-16
Work Completed
Time Computed01-12-16
Contract Working Days240
Addl Days Granted0
Working Days Charged254
Percent Time Used105
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1718-07-037
BARRICADES UNLIMITED (0.24)
DOUBLE A CONTRACTING, L.P. (0.65)
HJC FARMS, INC. (0.37)
WILLIS ELECTRIC CO., LP (1.26)
W.S. CONSTRUCTION COMPANY (6.02)
W.S. CONSTRUCTION COMPANY (12.23)
Contract #08153204
Totals17335339.77694725.889756047.1456.3

CountyMIDLAND
HighwaySH 349
FromSH 191
ToBI 20-E
CSJ1718-07-042
Proj IDNH 1602(523)
Work TypeRECONSTRUCT AND WIDEN
 
4.0776917371.6742750.000.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-12-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days160
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1718-07-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163004
Totals6917371.670.0042750.000.6

CountyECTOR
HighwaySL 338
FromCARGO RD
ToTRUNK/FRONTIER ST
CSJ2224-01-087
Proj IDCC 2224-1-87
Work TypeGR,BS,ACP,SIGNALS,LRGSIGNS,PAV MARK
 
0.4032347299.0074296.913.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-31-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days117
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2224-01-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163210
Totals2347299.000.0074296.913.1

CountyREEVES
HighwayRM 652
FromAT SALT CREEK
To.
CSJ2451-03-015
Proj IDBR 2017(327)
Work TypeREPLACE BRIDGE 06-195-0-2451-03-01
 
0.2993993994.330.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days173
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2451-03-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173236
Totals3993994.330.000.000.0