Monthly State Let Construction Report For Odessa District As Of Sep 21, 2017 Page 1 Of 2

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWARD
HighwayBI 20-D
FromAT SL 464.
To.
CSJ0004-03-049
Proj IDSTP 1702(023)HES
Work TypeINSTALL TRAFFIC SIGNALS
 
0.416562624.3029278.005.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-06-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0004-03-049
JONES BROTHERS, INC. (22.69)
BARRICADES UNLIMITED (6.19)
Contract #05173022
Totals562624.3018934.0029278.005.2

CountyWARD ETC
HighwaySS 57 ETC
From0.1 MI EAST OF FM 1219
To0.1 MI WEST OF FM 1219
CSJ0004-03-050
Proj IDSTP 2017(144)HESG
Work TypeINSTALL FLASHING BEASON AND SIGNALS
 
164.082619319.30115188.2018.5
Work Order11-22-16
Work Began00-00-00
Work Completed
Time Computed02-21-17
Contract Working Days143
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0004-03-050
DOUBLE A CONTRACTING, L.P. (2.32)
BARRICADES UNLIMITED (3.90)
Contract #10163211
Totals619319.301521.46115188.2018.5

CountyWARD
HighwayIH 20
FromFM 1219
ToEAST BI 20-D
CSJ0004-04-086
Proj IDNH 2017(031)
Work TypeRECONSTRUCT PAVEMENT
 
10.72314274035.0110024629.1870.2
Work Order10-21-16
Work Began04-26-17
Work Completed
Time Computed01-20-17
Contract Working Days327
Addl Days Granted0
Working Days Charged159
Percent Time Used48
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0004-04-086
DUSTROL, INC. (2.85)
F & W ELECTRICAL CONTRACTORS, INC. (2.15)
CHEROKEE SERVICES (0.69)
DOUBLE A CONTRACTING, L.P. (1.52)
BARRICADES UNLIMITED (0.58)
RICE ENVIRONMENTAL SERVICES (2.16)
RPV CONSTRUCTION (2.60)
CI CONSTRUCTORS, INC. (0.12)
Contract #09163203
Totals14274035.01963350.6010024629.1870.2

CountyWARD
HighwayIH 20
From1.5 MILES WEST OF FM 1927
ToFM 1219
CSJ0004-04-087
Proj IDNH 2017(276)
Work TypeRECONSTRUCT PAVEMENT
 
9.02613195417.3313095147.3299.2
Work Order12-12-16
Work Began03-27-17
Work Completed
Time Computed03-13-17
Contract Working Days351
Addl Days Granted0
Working Days Charged124
Percent Time Used35
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0004-04-087
BARRICADES UNLIMITED (1.69)
COX PAVING OF TEXAS, INC. (17.30)
DUSTROL, INC. (3.59)
AREA WIDE PROTECTIVE, INC. (0.68)
RPV CONSTRUCTION (0.81)
WILLIS ELECTRIC CO., LP (1.69)
REECE CONSTRUCTION CO., INC. (0.88)
DOUBLE A CONTRACTING, L.P. (1.07)
LPZ ENTERPRISES, LLC (2.76)
R.E.B. TRUCKING (5.50)
DK CONTRACTING, LLC (0.37)
DTM TRUCKING, INC. (0.41)
Contract #11163203
Totals13195417.331024725.9013095147.3299.2

CountyECTOR
HighwayIH 20
From0.6 MI EAST OF FM 1882
To0.1 MI EAST OF WLP 338
CSJ0004-07-121
Proj IDIM 0201(188)
Work TypeEXTEND ON/OFF RAMPS
 
2.01410110072.9610513004.41100.0
Work Order06-01-15
Work Began05-23-16
Work Completed08-23-17
Time Computed09-30-15
Contract Working Days210
Addl Days Granted82
Working Days Charged287
Percent Time Used98
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0004-07-121
BARRICADES UNLIMITED (3.55)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.33)
DESERT PAVING, INC. (2.52)
RPV CONSTRUCTION (2.50)
TEXOP CONSTRUCTION (0.20)
WEST TEXAS RUMBLE STRIP (0.04)
WILLIS ELECTRIC CO., LP (8.13)
DTM TRUCKING, INC. (0.34)
R.E.B. TRUCKING (2.02)
REECE CONSTRUCTION CO., INC. (14.50)
Contract #04153046
Totals10110072.9624181.4110513004.41100.0

CountyMARTIN ETC
HighwayIH 20 ETC
FromAT SH 137
To.
CSJ0005-04-069
Proj IDSTP 2016(650)HES
Work TypeINSTALL INTERSECTION FLASH BEACON
 
1.330759179.13150711.5219.8
Work Order03-14-16
Work Began08-28-17
Work Completed
Time Computed06-13-16
Contract Working Days260
Addl Days Granted0
Working Days Charged197
Percent Time Used75
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0005-04-069
BARRICADES UNLIMITED (5.24)
DOUBLE A CONTRACTING, L.P. (1.20)
Contract #02163240
Totals759179.133540.00150711.5219.8

CountyMARTIN
HighwayIH 20
FromAT BI 20-F WEST
To.
CSJ0005-04-072
Proj IDNH 1702(494)
Work TypeBRIDGE REPAIR
 
0.9841987502.230.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days88
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-04-072
BARRICADES UNLIMITED (3.10)
HJC FARMS, INC. (6.18)
JONES BROS. DIRT & PAVING CONTRACTORS, INC. (37.56)
R.E.B. TRUCKING (5.11)
REECE CONSTRUCTION CO, INC. (6.71)
CONTRACTORS SERVICE COMPANY (1.29)
Contract #07173043
Totals1987502.230.000.000.0

CountyECTOR
HighwayIH 20
FromDIXIE BLVD
ToMONAHANS DRAW
CSJ0005-13-056
Proj IDBR 1702(495)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
4.1003958979.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-13-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173212
Totals3958979.200.000.000.0

CountyMIDLAND
HighwayIH 20
FromWEST OF FM 1788
ToEAST OF FM 1788
CSJ0005-14-080
Proj IDIM 0201(189)
Work TypeEXTEND ON/OFF RAMPS
 
1.15411801426.999783479.1583.0
Work Order06-11-15
Work Began08-09-16
Work Completed
Time Computed10-10-15
Contract Working Days210
Addl Days Granted45
Working Days Charged266
Percent Time Used104
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-14-080
BARRICADES UNLIMITED (2.48)
DTM TRUCKING, INC. (0.24)
R.E.B. TRUCKING (1.44)
TEXOP CONSTRUCTION (0.28)
WILLIS ELECTRIC CO., LP (9.29)
WEST TEXAS RUMBLE STRIP (0.03)
DESERT PAVING, INC. (2.80)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.16)
REECE CONSTRUCTION CO., INC. (7.17)
BOLER EQUIPMENT (2.41)
JOSH FRANKLIN DRILLING, LLC (0.67)
RPV CONSTRUCTION (0.88)
Contract #04153049
Totals11801426.992114399.269783479.1583.0

CountyPECOS ETC
HighwayUS 67 ETC
From0.2 MI S OF CHANCELLOR RD
ToBREWSTER COUNTY LINE
CSJ0075-02-027
Proj IDSTP 1702(215)HESG
Work TypeEDGELINE & CENTERLINE RUMBLE STRIPS
 
420.5572345678.910.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed09-13-17
Contract Working Days160
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0075-02-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173242
Totals2345678.910.000.000.0

CountyPECOS
HighwayUS 67 ETC
From1.1 MI NORTH OF IH 10
To14.2 MI NORTH OF IH 10
CSJ0076-01-028
Proj IDSTP 1702(031)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
15.2435286212.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days288
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0076-01-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173228
Totals5286212.000.000.000.0

CountyCROCKETT
HighwayUS 67
FromAT PECOS RIVER
To.
CSJ0076-03-019
Proj IDBR 1602(181)
Work TypeBRIDGE REPLACEMENT
 
0.3662756477.872566116.6993.0
Work Order08-04-16
Work Began10-31-16
Work Completed
Time Computed10-28-16
Contract Working Days226
Addl Days Granted0
Working Days Charged178
Percent Time Used78
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0076-03-019
CONTRACTORS SERVICE COMPANY (0.33)
BARRICADES UNLIMITED (0.65)
HJC FARMS, INC. (1.70)
GARY A. CRAIN, INC. (0.30)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.94)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.13)
MCL CONTRACTING, LLC (0.30)
Contract #06163010
Totals2756477.87280901.022566116.6993.0

CountyREEVES
HighwayUS 285
FromCR 232
ToSH 302
CSJ0139-03-039
Proj IDNH 1702(685)
Work TypeRECONSTRUCT AND WIDEN
 
10.04715005109.230.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days380
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0139-03-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173004
Totals15005109.230.000.000.0

CountyREEVES
HighwayUS 285
FromRM 652
ToCR 232
CSJ0139-03-040
Proj IDNH 1602(182)
Work TypeREHABILITATION OF EXISTING ROADWAY
 
10.80612525496.023328516.9726.5
Work Order08-19-16
Work Began02-14-17
Work Completed
Time Computed11-18-16
Contract Working Days332
Addl Days Granted0
Working Days Charged122
Percent Time Used36
Contractor(s)
CI CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0139-03-040
BARRICADES UNLIMITED (0.67)
HJC FARMS, INC. (2.02)
PAVEMENT MARKINGS INC. (0.84)
W.S. CONSTRUCTION COMPANY (2.11)
Contract #06163203
Totals12525496.0257866.313328516.9726.5

CountyREEVES
HighwayUS 285
FromAT IH 20
To.
CSJ0139-05-044
Proj IDBR 1702(146)
Work TypeBRIDGE REPAIR
 
0.233936605.40306400.0032.7
Work Order05-09-17
Work Began08-14-17
Work Completed
Time Computed08-08-17
Contract Working Days75
Addl Days Granted0
Working Days Charged18
Percent Time Used24
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0139-05-044
RPV CONSTRUCTION (11.47)
BARRICADES UNLIMITED (3.63)
PMI PAVEMENT MARKING, INC. (2.37)
Contract #04173041
Totals936605.40306400.00306400.0032.7

CountyPECOS
HighwayUS 285
From0.66 MILES NORTH OF IH 10
To1.72 MILES NORTH OF IH 10
CSJ0139-08-037
Proj IDNH 2017(474)
Work TypeROADWAY WIDENING
 
1.0601244957.00957947.8476.9
Work Order04-28-17
Work Began06-19-17
Work Completed
Time Computed06-19-17
Contract Working Days58
Addl Days Granted0
Working Days Charged49
Percent Time Used84
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0139-08-037
BARRICADES UNLIMITED (1.21)
HJC FARMS, INC. (1.19)
DOUBLE A CONTRACTING, L.P. (2.41)
DELGADOS CONSTRUCTION, DBA ERNESTO A. DELGADO (8.68)
Contract #03173214
Totals1244957.00476562.32957947.8476.9

CountyMIDLAND
HighwaySH 349
FromIH 20
ToCR 140
CSJ0380-09-081
Proj IDSTP 2017(326)
Work TypePLANE, HOT MIX, AND PAV MRKS
 
3.1843699830.353072118.1183.0
Work Order02-13-17
Work Began06-05-17
Work Completed
Time Computed05-15-17
Contract Working Days100
Addl Days Granted0
Working Days Charged47
Percent Time Used47
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0380-09-081
CONTRACTORS SERVICE COMPANY (1.38)
DELGADO"S CONSTRUCTION (0.41)
DOUBLE A CONTRACTING, L.P. (2.23)
HJC FARMS, INC. (2.03)
TEXOP CONSTRUCTION (3.06)
Contract #01173013
Totals3699830.35897168.033072118.1183.0

CountyUPTON
HighwaySH 349
FromRM 2401
To6.6 MI SOUTH OF RM 2401
CSJ0380-11-025
Proj IDSTP 1502(619)
Work TypeREHABILITATION OF EXISTING ROAD
 
20.51217114217.0714044546.7782.0
Work Order09-22-15
Work Began05-04-16
Work Completed
Time Computed05-01-16
Contract Working Days374
Addl Days Granted0
Working Days Charged302
Percent Time Used80
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0380-11-025
BARRICADES UNLIMITED (3.10)
HJC FARMS, INC. (0.26)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (5.61)
DTM TRUCKING, INC. (5.27)
ALL-IN CONSTRUCTION (0.50)
Contract #08153004
Totals17114217.07955054.2214044546.7782.0

CountyREEVES
HighwayIH 10
From6.4 MILES WEST OF REEVES CO LINE
ToPECOS COUNTY LINE
CSJ0441-06-035
Proj IDNH 1502(340)
Work TypePLANE,HOTMIX,SEALCOAT,MBGF,PAV-MRK
 
10.8218383558.388067811.40100.0
Work Order11-24-15
Work Began04-19-16
Work Completed09-21-17
Time Computed01-24-16
Contract Working Days100
Addl Days Granted0
Working Days Charged147
Percent Time Used147
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0441-06-035
BARRICADES UNLIMITED (0.44)
DOUBLE A CONTRACTING, L.P. (1.68)
PERFORMANCE EQUIPMENT SERVICE (1.82)
CHEROKEE SERVICES (0.23)
SCR CONSTRUCTION CO., INC. (6.50)
WILLIS ELECTRIC CO., LP (0.19)
R.E.B. TRUCKING (7.23)
HJC FARMS, INC. (0.56)
COX PAVING OF TEXAS, INC. (9.37)
Contract #10153233
Totals8383558.380.008067811.40100.0

CountyMIDLAND
HighwaySH 158
From4 MI SE OF IH 20
ToGLASSCOCK COUNTY LINE
CSJ0463-03-049
Proj IDNH 1702(332)
Work TypePAVEMENT OVERLAY
 
12.1273997554.790.000.0
Work Order07-20-17
Work Began00-00-00
Work Completed
Time Computed08-20-17
Contract Working Days60
Addl Days Granted0
Working Days Charged9
Percent Time Used15
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0463-03-049
DOUBLE A CONTRACTING, L.P. (5.01)
HUDSON, INC. (0.39)
PMI PAVEMENT MARKING, INC. (0.34)
Contract #06173211
Totals3997554.790.000.000.0

page 1 | page 2