AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - ODESSA DISTRICT

Last Update: Thursday, July 30, 2015
ITEMS 8020 2003 TO 8251 2018
Items Items Bid Code Range
0100 - 0192
0216 - 0275
0310 - 0354
0400 - 0496
0500 - 0560
0610 - 0690
0740 - 0772
1002 - 1122
2001 - 2144
3003 - 3271
4618 - 4684
6001 - 6834
8020 - 8251
9012 - 9012
8020 2003 - 8251 2018
Item No Description Units July 31, 2015 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
8020 2003 REF PROF PAV MRK TY I (W) 4" (SLD) (100MIL LF     217,803.000 .70000 1
8020 2008 REF PROF PAV MRK TY I (Y) 4" (SLD) (100MIL LF     220,470.000 .70000 1
8251 2003 RE PM W / RET REQ TY I (W) 4" (BRK) (100MIL) LF     144,110.000 .24601 2
8251 2005 RE PM W / RET REQ TY I (W) 4" (SLD) (090MIL) LF     1,293,276.000 .24000 1
8251 2006 RE PM W / RET REQ TY I (W) 4" (SLD) (100MIL) LF     298,567.000 .40955 3
8251 2015 RE PM W / RET REQ TY I (Y) 4" (BRK) (100MIL) LF     124,091.000 .27099 3
8251 2017 RE PM W / RET REQ TY I (Y) 4" (SLD) (090MIL) LF     510,646.000 .24000 1
8251 2018 RE PM W / RET REQ TY I (Y) 4" (SLD) (100MIL) LF     288,271.000 .32430 4