Monthly State Let Maintenance Report For Laredo District As Of Nov 20, 2014 Page 1 Of 1

Last Update: Thursday, November 20, 2014
FTP Icon
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyZAVALA
Highway FM1025
From FM 1025
To VARIOUS
CSJ 6174-30-001
Proj ID RMC - 617430001
Work Type RDWY WIDENING, BLADE LEVEL UP, SPOT BASE
 
12.000 1969602.04 5338.58 3564673.16 99.9
Work Order 02-13-14
Work Began 03-10-14
Work Completed  
Time Computed 03-10-14
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 178
Percent Time Used 98
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6174-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12134022
Totals 1969602.04 5338.58 3564673.16 99.9

CountyWEBB
Highway IH0035
From IH 35 WFR
To VARIOUS
CSJ 6195-44-001
Proj ID RMC - 619544001
Work Type RDWY WIDENING, BLADE LEVEL UP, SPOT BASE
 
18.000 2187870.97 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6195-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144212
Totals 2187870.97 0.00 0.00 0.0

CountyLASALLE
Highway FM0469
From VARIOUS
To VARIOUS
CSJ 6200-68-001
Proj ID RMC - 620068001
Work Type ROADWAY WIDENING AND SPOT BASE REPAIR
 
19.557 3981280.69 438001.56 2568821.96 64.5
Work Order 06-23-14
Work Began 06-23-14
Work Completed  
Time Computed 06-23-14
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 130
Percent Time Used 72
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6200-68-001
MURRAY CONSTRUCTION(0.61%)
FLASHER EQUIPMENT COMPANY(4.13%)
BEAVER CONTRACTORS, LLC(7.08%)
FUQUAY, INC. (0.19%)
Contract # 04144017
Totals 3981280.69 438001.56 2568821.96 64.5

CountyLASALLE
Highway IH0035
From IH 35
To IH 35, ETC.
CSJ 6233-50-001
Proj ID BPM - 623350001
Work Type REHABILITATION OF VARIOUS BRIDGE FACILIT
 
0.305 308760.25 0.00 309173.25 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-07-14
Work Began 03-17-14
Work Completed  
Time Computed 03-17-14
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 92
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6233-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144034
Totals 308760.25 0.00 309173.25 99.9

CountyWEBB
Highway LP0020
From VARIOUS
To VARIOUS
CSJ 6236-51-001
Proj ID RMC - 623651001
Work Type LANDSCAPE MAINTENANCE
 
0.001 414867.00 4715.00 296158.20 71.3
Work Order 12-12-12
Work Began 01-02-13
Work Completed  
Time Computed 01-02-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 668
Percent Time Used 91
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6236-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08124036
Totals 414867.00 4715.00 296158.20 71.3

CountyVAL VERDE
Highway US0090
From US 90
To US 90
CSJ 6244-72-001
Proj ID RMC - 624472001
Work Type UPGRADE OF EXISTING MBGF, DOWNSTREAM ANC
 
0.001 469600.00 194062.50 604312.50 99.9
Work Order 05-01-14
Work Began 05-12-14
Work Completed  
Time Computed 05-12-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 41
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6244-72-001
RPV CONSTRUCTION ( 34.39%)
Contract # 02144029
Totals 469600.00 194062.50 604312.50 99.9

CountyDIMMIT
Highway FM2367
From RM 186
To END OF ROADWAY
CSJ 6247-56-001
Proj ID RMC - 624756001
Work Type RESTORATION OF EXISTING ROAD
 
1.985 527708.19 0.00 2621289.84 99.9
Work Order 06-25-13
Work Began 07-01-13
Work Completed  
Time Computed 07-01-13
Contract Working Days 40
Addl Days Granted 27
Working Days Charged 67
Percent Time Used 100
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6247-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05134010
Totals 527708.19 0.00 2621289.84 99.9

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6248-35-001
Proj ID RMC - 624835001
Work Type GUARDRAIL REPAIR
 
0.001 347687.50 0.00 575790.30 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-13
Work Began 03-12-13
Work Completed 09-10-14
Time Computed 03-12-13
Contract Working Days 365
Addl Days Granted 142
Working Days Charged 507
Percent Time Used 100
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6248-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12124020
Totals 347687.50 0.00 575790.30 100.0

CountyZAVALA
Highway FM2691
From VARIOUS
To VARIOUS
CSJ 6256-47-001
Proj ID RMC - 625647001
Work Type SEAL COAT TYPE WORK CONSISTING OF SURFAC
 
66.677 1324132.79 0.00 1986763.66 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-24-14
Work Began 04-14-14
Work Completed  
Time Computed 04-14-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 100
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6256-47-001
D. I. J. CONSTRUCTION, INC.(9.85%)
Contract # 12134023
Totals 1324132.79 0.00 1986763.66 99.9

page 1