page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6195-02-001
Proj ID RMC - 619502001
Work Type BLADE LEVEL UP / SPOT BASE REPAIR
 
0.001 2018695.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-17-12
Work Began 00-00-00
Work Completed  
Time Computed 05-14-12
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WAGNER MATERIALS & CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6195-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02124032
Totals 2018695.00 0.00 0.00 0.0

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6195-58-001
Proj ID RMC - 619558001
Work Type SPOT BASE REPAIR OF EXISTING ROADWAY
 
0.980 1893552.00 0.00 3831059.06 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-17-11
Work Began 05-17-11
Work Completed  
Time Computed 05-17-11
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 254
Percent Time Used 69
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6195-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03114014
Totals 1893552.00 0.00 3831059.06 99.9

CountyMAVERICK
Highway US0277
From VARIOUS
To VARIOUS
CSJ 6218-78-001
Proj ID RMC - 621878001
Work Type CLEANING & CRACK SEALING OF HIGHWAYS
 
999.000 577500.00 18900.00 220463.25 40.3
Work Order 10-19-11
Work Began 10-19-11
Work Completed  
Time Computed 10-19-11
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 195
Percent Time Used 53
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6218-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08114026
Totals 577500.00 18900.00 220463.25 40.3

CountyZAVALA
Highway FM0065
From FM 65, RM 412+1.202
To FM 582, RM 414+2.519
CSJ 6218-80-001
Proj ID BPM - 621880001
Work Type BRIDGE REHAB AND CHANNEL PROTECTION
 
0.065 279561.00 0.00 207202.00 74.1
Work Order 08-18-11
Work Began 08-31-11
Work Completed  
Time Computed 09-06-11
Contract Working Days 68
Addl Days Granted 20
Working Days Charged 69
Percent Time Used 78
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6218-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06114008
Totals 279561.00 0.00 207202.00 74.1

CountyWEBB
Highway US0083
From VARIOUS
To VARIOUS
CSJ 6218-81-001
Proj ID RMC - 621881001
Work Type CLEANING & CRACK SEALING OF HIGHWAYS
 
800.000 423200.00 54381.20 317368.26 74.9
Work Order 11-10-11
Work Began 11-10-11
Work Completed  
Time Computed 11-10-11
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 173
Percent Time Used 47
Contractor(s)
AUSTIMPACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6218-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08114013
Totals 423200.00 54381.20 317368.26 74.9

CountyMAVERICK
Highway SH0131
From VARIOUS
To VARIOUS
CSJ 6220-37-001
Proj ID RMC - 622037001
Work Type BLADE LEVEL UP, OVERLAY, AND PVT. EDGE R
 
0.001 1865917.53 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6220-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03124017
Totals 1865917.53 0.00 0.00 0.0

CountyVAL VERDE
Highway US0277
From VARIOUS
To VARIOUS
CSJ 6221-68-001
Proj ID RMC - 622168001
Work Type UPGRADE APPROACH RAIL AND BRIDGE RAIL
 
0.001 373940.00 0.00 368771.75 98.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-02-11
Work Began 05-05-11
Work Completed  
Time Computed 05-05-11
Contract Working Days 85
Addl Days Granted 59
Working Days Charged 142
Percent Time Used 98
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6221-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03114033
Totals 373940.00 0.00 368771.75 98.6

CountyDIMMIT
Highway FM1557
From FM 1557, RM 410+0.004
To FM 1557, RM 412.0.785
CSJ 6224-26-001
Proj ID RMC - 622426001
Work Type RESTORATION OF EXISTING ROAD
 
2.741 782202.24 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6224-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05124010
Totals 782202.24 0.00 0.00 0.0

CountyLASALLE
Highway SH0097
From FM 469
To SH 72
CSJ 6225-55-001
Proj ID RMC - 622555001
Work Type RESTORATION OF AN EXISTING ROAD
 
14.620 3580834.65 1596.23 2193321.07 61.2
Work Order 07-20-11
Work Began 07-26-11
Work Completed  
Time Computed 07-26-11
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 116
Percent Time Used 38
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6225-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06114016
Totals 3580834.65 1596.23 2193321.07 61.2

CountyWEBB
Highway LP0020
From VARIOUS
To VARIOUS
CSJ 6232-80-001
Proj ID RMC - 623280001
Work Type REPAIR OF MISCELLANEOUS CONCRETE
 
0.001 625814.68 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6232-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05124022
Totals 625814.68 0.00 0.00 0.0

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6234-26-001
Proj ID RMC - 623426001
Work Type GUARDRAIL REPAIR
 
0.001 373520.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-08-12
Work Began 03-08-12
Work Completed  
Time Computed 03-08-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 14
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6234-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12114031
Totals 373520.00 0.00 0.00 0.0

CountyVAL VERDE
Highway US0277
From VARIOUS
To VARIOUS
CSJ 6234-30-001
Proj ID RMC - 623430001
Work Type GUARDRAIL REPAIR
 
0.001 381061.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6234-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01124032
Totals 381061.00 0.00 0.00 0.0

CountyDUVAL
Highway US0059
From VARIOUS
To VARIOUS
CSJ 6238-98-001
Proj ID RMC - 623898001
Work Type RESURFACING OF EXISTING ROADWAY
 
120.349 2305783.72 1422079.94 1422079.94 61.6
Work Order 04-03-12
Work Began 04-17-12
Work Completed  
Time Computed 04-17-12
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 11
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6238-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02124020
Totals 2305783.72 1422079.94 1422079.94 61.6

page 1
 