Monthly Local Let Maintenance Report For Laredo District As Of Sep 15, 2016 Page 6 Of 6

Last Update: Thursday, September 15, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDUVAL
Highway US0059
From VARIOUS
To VARIOUS
CSJ 6295-45-001
Proj ID SUP - 629545001
Work Type PICNIC AREA MAINTENANCE
 
0.001 80486.64 3515.29 34219.37 42.5
Work Order 10-08-15
Work Began 10-15-15
Work Completed  
Time Computed 10-15-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 322
Percent Time Used 44
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10152232
Totals 80486.64 3515.29 34219.37 42.5

CountyVAL VERDE
Highway US0277
From US 277
To VARIOUS
CSJ 6296-98-001
Proj ID RMC - 629698001
Work Type INSTALL PVT. MARKINGS AND PVT. MARKERS
 
0.001 267451.12 95574.80 95574.80 35.7
Work Order 07-11-16
Work Began 07-11-16
Work Completed  
Time Computed 07-11-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 8
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06162201
Totals 267451.12 95574.80 95574.80 35.7

CountyWEBB
Highway IH0035
From IH 35
To VARIOUS
CSJ 6297-01-001
Proj ID RMC - 629701001
Work Type INSTALL PAVEMENT MRKGS AND PAVEMENT MRKR
 
0.001 281776.31 130874.89 130874.89 46.4
Work Order 07-25-16
Work Began 07-25-16
Work Completed  
Time Computed 07-25-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 10
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04162201
Totals 281776.31 130874.89 130874.89 46.4

CountyWEBB
Highway IH0035
From IH 35
To US 83, ETC.
CSJ 6297-22-001
Proj ID RMC - 629722001
Work Type LANDSCAPE MAINTENANCE
 
7.000 214488.00 1700.00 20350.00 9.4
Work Order 04-27-16
Work Began 04-28-16
Work Completed  
Time Computed 04-28-16
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 126
Percent Time Used 17
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01162204
Totals 214488.00 1700.00 20350.00 9.4

CountyMAVERICK
Highway SH0131
From SH 131
To SH 131
CSJ 6297-33-001
Proj ID RMC - 629733001
Work Type EXCAVATION, REMOVAL OF EXISTING CMP CULV
 
0.001 137385.00 2100.00 167348.60 100.0
Work Order 03-10-16
Work Began 03-14-16
Work Completed 08-15-16
Time Computed 03-14-16
Contract Working Days 40
Addl Days Granted 14
Working Days Charged 41
Percent Time Used 75
Contractor(s)
DELGADO'S CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6297-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01162208
Totals 137385.00 2100.00 167348.60 100.0

CountyWEBB
Highway SL0020
From SL 20
To VARIOUS
CSJ 6297-39-001
Proj ID RMC - 629739001
Work Type LANDSCAPE MAINTENANCE
 
2.000 228036.50 25950.00 50613.45 22.1
Work Order 04-27-16
Work Began 04-28-16
Work Completed  
Time Computed 04-28-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 126
Percent Time Used 34
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01162206
Totals 228036.50 25950.00 50613.45 22.1

CountyWEBB
Highway IH0035
From IH 35
To VARIOUS
CSJ 6297-41-001
Proj ID RMC - 629741001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
300.200 175466.00 4810.52 50960.52 29.0
Work Order 04-18-16
Work Began 05-23-16
Work Completed  
Time Computed 05-23-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 101
Percent Time Used 27
Contractor(s)
ECO BRIGHT SOLUTIONS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01162209
Totals 175466.00 4810.52 50960.52 29.0

CountyMAVERICK
Highway US0057
From US 57
To VARIOUS
CSJ 6300-70-001
Proj ID RMC - 630070001
Work Type INSTALL PAVEMENT MRKGS AND PAVEMENT MRKR
 
0.001 280398.19 0.00 271703.38 96.8
Work Order 06-14-16
Work Began 06-27-16
Work Completed  
Time Computed 06-27-16
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 73
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6300-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05162201
Totals 280398.19 0.00 271703.38 96.8

CountyWEBB
Highway IH0035
From IH 35
To VARIOUS
CSJ 6300-77-001
Proj ID RMC - 630077001
Work Type MAINTENANCE OF ILLUMINATION SYSTEMS ALON
 
0.001 120800.00 0.00 0.00 0.0
Work Order 07-29-16
Work Began 08-01-16
Work Completed  
Time Computed 08-01-16
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 4
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07162201
Totals 120800.00 0.00 0.00 0.0

CountyVAL VERDE
Highway US0090
From US 277
To VARIOUS
CSJ 6301-03-001
Proj ID RMC - 630103001
Work Type UPGRADE OF EXISTING MBGF, DOWNSTREAM ANC
 
0.001 312383.64 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-08-16
Work Began 08-15-16
Work Completed  
Time Computed 08-15-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05162203
Totals 312383.64 0.00 0.00 0.0

CountyWEBB
Highway IH0035
From IH 35
To VARIOUS
CSJ 6301-09-001
Proj ID RMC - 630109001
Work Type INSTALL PVT. MARKINGS AND PVT. MARKERS
 
0.001 262806.47 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06162202
Totals 262806.47 0.00 0.00 0.0

CountyDUVAL
Highway US0059
From US 59
To VARIOUS
CSJ 6301-80-001
Proj ID RMC - 630180001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
331.190 174092.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6301-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08162201
Totals 174092.00 0.00 0.00 0.0

CountyWEBB
Highway IH0035
From IH 35
To VARIOUS
CSJ 6305-19-001
Proj ID SUP - 630519001
Work Type LITTER PICKUP MAINTENANCE
 
0.001 276022.22 19543.73 41776.94 15.1
Work Order 06-28-16
Work Began 07-01-16
Work Completed  
Time Computed 07-01-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 16
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06162231
Totals 276022.22 19543.73 41776.94 15.1

CountyMAVERICK
Highway US0277
From US 277
To VARIOUS
CSJ 6305-28-001
Proj ID SUP - 630528001
Work Type PICNIC AREA MAINTENANCE
 
0.001 60934.80 3172.15 5251.15 8.6
Work Order 06-28-16
Work Began 07-01-16
Work Completed  
Time Computed 07-01-16
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06162232
Totals 60934.80 3172.15 5251.15 8.6

CountyDIMMIT
Highway US0083
From US 83
To VARIOUS
CSJ 6305-70-001
Proj ID RMC - 630570001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
246.200 271941.57 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6305-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08162202
Totals 271941.57 0.00 0.00 0.0

CountyVAL VERDE
Highway SL0025
From VARIOUS
To .
CSJ 6308-23-001
Proj ID SUP - 630823001
Work Type JANITORIAL AND GROUNDS
 
0.001 140119.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-25-16
Work Began 09-01-16
Work Completed  
Time Computed 09-01-16
Contract Working Days 720
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08162203
Totals 140119.20 0.00 0.00 0.0

CountyWEBB
Highway IH0035
From VARIOUS
To .
CSJ 6308-24-001
Proj ID SUP - 630824001
Work Type JANITORIAL AND GROUNDS
 
0.001 311469.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-25-16
Work Began 09-01-16
Work Completed  
Time Computed 09-01-16
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08162204
Totals 311469.10 0.00 0.00 0.0

CountyKINNEY
Highway RM2804
From RM 2804
To RM 2804
CSJ 6309-31-001
Proj ID EMC - 630931001
Work Type REPAIR OF LOW WATER CROSSING WASHOUTS
 
5.600 98804.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 10
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DELGADO'S CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6309-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08162241
Totals 98804.00 0.00 0.00 0.0