Monthly Local Let Maintenance Report For Lufkin District As Of Apr 10, 2017 Page 5 Of 6

Last Update: Monday, April 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSAN JACINTO COUNTY
CSJ6306-80-001
Proj IDSUP - 630680001
Work TypeDELINEATOR, OBJ MARKER & MAILBOX MAINT
 
0.01050000.0053822.0099.9
Work Order08-11-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged212
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161134
Totals50000.005112.0053822.0099.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6307-44-001
Proj IDRMC - 630744001
Work TypeILLUMINATION
 
0.001388546.00286008.2573.6
Work Order10-19-16
Work Began10-26-06
Work Completed
Time Computed10-26-16
Contract Working Days365
Addl Days Granted0
Working Days Charged159
Percent Time Used43
Contractor(s)
LUDCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161108
Totals388546.0089340.25286008.2573.6

CountySABINE
HighwaySH0087
FromVARIOUS LOCATIONS WITHIN THE
ToSABINE COUNTY MAINTENANCE SECTION
CSJ6308-42-001
Proj IDRMC - 630842001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010172470.005618.003.2
Work Order01-12-17
Work Began01-12-17
Work Completed
Time Computed01-12-17
Contract Working Days200
Addl Days Granted0
Working Days Charged2
Percent Time Used1
Contractor(s)
T & L CLEANING SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6308-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161107
Totals172470.002518.005618.003.2

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6308-73-001
Proj IDRMC - 630873001
Work TypeINSTALLATION OF WATERBASE STRIPING
 
0.001294400.000.000.0
Work Order12-08-16
Work Began12-15-16
Work Completed
Time Computed12-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged107
Percent Time Used29
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6308-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161103
Totals294400.000.000.000.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6308-74-001
Proj IDRMC - 630874001
Work TypeINSTALLATION OF THERMOPLASTIC STRIPING
 
0.001274570.0068870.0525.0
Work Order12-08-16
Work Began12-15-16
Work Completed
Time Computed12-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged107
Percent Time Used29
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6308-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161104
Totals274570.000.0068870.0525.0

CountySHELBY
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN THE
ToSHELBY COUNTY MAINTENANCE SECTION
CSJ6309-67-001
Proj IDRMC - 630967001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010142140.0010455.007.3
Work Order01-12-17
Work Began01-12-17
Work Completed
Time Computed01-12-17
Contract Working Days200
Addl Days Granted0
Working Days Charged5
Percent Time Used2
Contractor(s)
T & L CLEANING SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6309-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161110
Totals142140.002940.0010455.007.3

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN THE
ToSAN AUGUSTINE COUNTY MAINTENANCE SECTION
CSJ6309-68-001
Proj IDRMC - 630968001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010146806.007020.004.7
Work Order00-00-00
Work Began01-26-17
Work Completed
Time Computed01-26-17
Contract Working Days200
Addl Days Granted0
Working Days Charged3
Percent Time Used1
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161109
Totals146806.00850.007020.004.7

CountySHELBY
HighwayUS0096
FromVARIOUS LOCATIONS IN
ToSHELBY COUNTY
CSJ6310-07-001
Proj IDSUP - 631007001
Work TypePICNIC, GROUNDS AND ISLAND MAINTENANCE
 
0.01083397.5021138.0025.3
Work Order09-27-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161115
Totals83397.506777.0021138.0025.3

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS WITHIN
ToLUFKIN DISTRICT
CSJ6310-18-001
Proj IDRMC - 631018001
Work TypeINSTALLATION OF SPECIALTY PVMNT MARKINGS
 
0.001179448.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-17
Work Began00-00-00
Work Completed
Time Computed01-17-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6310-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161108
Totals179448.000.000.000.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToANGELINA COUNTY
CSJ6310-20-001
Proj IDSUP - 631020001
Work TypePICNIC AREA, HIST MRK & TRAF ISL MAINT
 
0.01037988.9213339.6735.1
Work Order10-15-16
Work Began10-15-16
Work Completed
Time Computed10-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged168
Percent Time Used46
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161106
Totals37988.923340.2513339.6735.1

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToNACOGDOCHES COUNTY
CSJ6310-21-001
Proj IDSUP - 631021001
Work TypePICNIC, GRNDS, TRAF ISLAND MAINT
 
0.01048820.0010427.5021.3
Work Order10-15-16
Work Began10-15-16
Work Completed
Time Computed10-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged168
Percent Time Used46
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6310-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161107
Totals48820.002963.0010427.5021.3

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONA IN
ToSAN JACINTO COUNTY
CSJ6311-14-001
Proj IDSUP - 631114001
Work TypeLANDSCAPE, PICNIC & GROUNDS MAINT
 
0.010109370.0913981.3212.7
Work Order12-12-16
Work Began01-01-17
Work Completed
Time Computed01-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged90
Percent Time Used24
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161101
Totals109370.099373.6613981.3212.7

CountySABINE
HighwayUS0096
FromVARIOUS LOCATIONS IN THE SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6312-50-001
Proj IDRMC - 631250001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010218711.960.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days61
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171102
Totals218711.960.000.000.0

CountySHELBY
HighwayUS0096
FromVARIOUS LOCATIONS IN THE SHELBY COUNTY
ToMAINTENANCE SECTION
CSJ6312-51-001
Proj IDRMC - 631251001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010155717.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6312-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171103
Totals155717.920.000.000.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN THE HOUSTON COUNTY
ToMAINTENANCE SECTION
CSJ6312-52-001
Proj IDRMC - 631252001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010165108.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DON YATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171104
Totals165108.100.000.000.0

CountyTRINITY
HighwaySH0094
FromVARIOUS ROADWAYS IN THE TRINITY COUNTY
ToMAINTENANCE SECTION
CSJ6312-53-001
Proj IDRMC - 631253001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010101948.680.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6312-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171102
Totals101948.680.000.000.0

CountyPOLK
HighwayUS0059
FromVARIOUS ROADWAYS IN THE POLK COUNTY
ToMAINTENANCE SECTION
CSJ6312-54-001
Proj IDRMC - 631254001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010244709.270.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days99
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6312-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171103
Totals244709.270.000.000.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN THE ANGELINA COUNTY
ToMAINTENANCE SECTION
CSJ6312-55-001
Proj IDRMC - 631255001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010189582.940.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days65
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6312-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171105
Totals189582.940.000.000.0

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS ROADWAYS IN THE NACOGDOCHES
ToCOUNTY MAINTENANCE SECTION
CSJ6312-56-001
Proj IDRMC - 631256001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010204371.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days76
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171104
Totals204371.800.000.000.0

CountySAN AUGUSTINE
HighwaySH0147
FromVARIOUS ROADWAYS IN THE SAN AUGUSTINE
ToMAINTENANCE SECTION
CSJ6312-57-001
Proj IDRMC - 631257001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010176801.610.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days49
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171105
Totals176801.610.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6