Monthly Local Let Maintenance Report For Lufkin District As Of Oct 16, 2017 Page 5 Of 7

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIIONS IN
ToLUFKIN DISTRICT
CSJ6313-75-001
Proj IDRMC - 631375001
Work TypeDISTRICT WIDE TRAFFIC SIGNAL MAINTENANCE
 
0.001327765.00254004.9477.4
Work Order05-02-17
Work Began05-09-17
Work Completed
Time Computed05-09-17
Contract Working Days365
Addl Days Granted0
Working Days Charged145
Percent Time Used39
Contractor(s)
BAY CITY TRAFFIC
SUBCONTRACTOR(S) FOR CCSJ: 6313-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171101
Totals327765.0044886.54254004.9477.4

CountySHELBY
HighwaySH0007
FromVARIOUS LOCATIONS IN THE SHELBY COUNTY
ToMAINTENANCE SECTION
CSJ6314-24-001
Proj IDRMC - 631424001
Work TypeDITCH AND CULVERT CLEANING
 
0.010169650.00187280.0199.9
Work Order04-17-17
Work Began04-20-17
Work Completed
Time Computed04-20-17
Contract Working Days45
Addl Days Granted45
Working Days Charged26
Percent Time Used28
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171106
Totals169650.0099300.51187280.0199.9

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN THE POLK COUNTY
ToMAINTENANCE SECTION
CSJ6314-74-001
Proj IDRMC - 631474001
Work TypeDITCH AND CULVERT CLEANING
 
0.010204889.05302416.5599.9
Work Order04-19-17
Work Began04-21-17
Work Completed
Time Computed04-21-17
Contract Working Days45
Addl Days Granted0
Working Days Charged45
Percent Time Used100
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171108
Totals204889.05120102.50302416.5599.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS ON US59 AND US259
ToWITHIN THE LUFKIN DISTRICT
CSJ6315-23-001
Proj IDSUP - 631523001
Work TypeLARGE DEBRIS PICKUP AND REMOVAL
 
0.010293400.00158925.0054.1
Work Order03-16-17
Work Began04-01-17
Work Completed
Time Computed04-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged183
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6315-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171130
Totals293400.0018345.00158925.0054.1

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN POLK COUNTY
ToMAINTENANCE SECTION
CSJ6315-48-001
Proj IDRMC - 631548001
Work TypeTREE & BRUSH REMOVAL AND TREE TRIMMING
 
0.010217735.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6315-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171103
Totals217735.000.000.000.0

CountySAN AUGUSTINE
HighwaySH0103
FromVARIOUS LOCATIONS IN SAN AUGUSTINE
ToCOUNTY MAINTENANCE SECTION
CSJ6315-93-001
Proj IDRMC - 631593001
Work TypeTREE & BRUSH REMOVAL
 
0.010209120.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6315-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171101
Totals209120.000.000.000.0

CountySABINE
HighwaySH0021
FromVARIOUS LOCATIONS IN SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6316-67-001
Proj IDRMC - 631667001
Work TypeTREE & BRUSH REMOVAL AND TREE TRIMMING
 
0.010251150.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-06-17
Work Began00-00-00
Work Completed
Time Computed11-01-17
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6316-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171102
Totals251150.000.000.000.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN THE_HOUSTON_COUNTY
ToMAINTENANCE SECTION
CSJ6317-63-001
Proj IDRMC - 631763001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010356050.000.000.0
Work Order07-20-17
Work Began00-00-00
Work Completed
Time Computed08-01-17
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171101
Totals356050.000.000.000.0

CountySABINE
HighwaySH0087
FromVARIOUS LOCATIONS IN THE SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6317-92-001
Proj IDSUP - 631792001
Work TypePICNIC AREA GRNDS & C&G MAINTENANCE
 
0.01082720.2222751.5027.5
Work Order07-01-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171111
Totals82720.223873.6722751.5027.5

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN POLK COUNTY
ToMAINTENANCE SECTION
CSJ6317-93-001
Proj IDSUP - 631793001
Work TypePICNIC & GROUNDS MAINT IN POLK COUNTY
 
0.01036967.127112.2719.2
Work Order06-27-17
Work Began07-10-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6317-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171110
Totals36967.122330.047112.2719.2

CountySHELBY
HighwaySH0007
FromVARIOUS LOCATIONS IN SHELBY COUNTY
ToMAINTENANCE SECTION
CSJ6317-94-001
Proj IDSUP - 631794001
Work TypeDELINEATOR, MBOX, SIGN STR. AND C&G MNT.
 
0.010213500.0026053.8012.2
Work Order07-01-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171102
Totals213500.008483.0026053.8012.2

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN HOUSTON COUNTY
ToMAINTENANCE SECTION
CSJ6317-95-001
Proj IDSUP - 631795001
Work TypeCURB & GUTTER MAINT. HOUSTON COUNTY
 
0.01028500.000.000.0
Work Order06-27-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171106
Totals28500.000.000.000.0

CountyTRINITY
HighwayUS0287
FromVARIOUS LOCATIONS IN TRINITY COUNTY
ToMAINTENANCE SECTION
CSJ6317-96-001
Proj IDSUP - 631796001
Work TypePICNIC, C&G, MBOX, AND SIGN STRAIGHTEN
 
0.01080566.866585.758.1
Work Order06-27-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171109
Totals80566.862470.006585.758.1

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN ANGELINA COUNTY
ToMAINTENANCE SECTION
CSJ6317-97-001
Proj IDSUP - 631797001
Work TypeCURB & GUTTER MAINTENANCE FOR ANGELINA
 
0.01044000.0037294.7984.7
Work Order06-26-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171104
Totals44000.0017706.4537294.7984.7

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN NACOGDOCHES COUNTY
ToMAINTENANCE SECTION
CSJ6317-98-001
Proj IDSUP - 631798001
Work TypeDELINEATOR, MBOX, SIGN STR. AND C&G MNT.
 
0.010120000.0018780.0015.6
Work Order06-27-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171107
Totals120000.0018780.0018780.0015.6

CountyANGELINA
HighwayBU0059G
From1805 NORTH TIMBERLAND DRIVE
ToLUFKIN, TEXAS 75901
CSJ6317-99-001
Proj IDSUP - 631799001
Work TypeGROUNDS MAINT AT DISTRICT COMPLEX
 
0.01025400.003810.0015.0
Work Order06-26-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171103
Totals25400.001270.003810.0015.0

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS IN SAN AUGUSTINE
ToCOUNTY MAINTENANCE SECTION
CSJ6318-01-001
Proj IDSUP - 631801001
Work TypePICNIC AREA GROUNDS & C&G MAINTENANCE
 
0.01013978.0011451.4581.9
Work Order06-27-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days62
Addl Days Granted0
Working Days Charged62
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171105
Totals13978.000.0011451.4581.9

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS IN SAN AUGUSTINE
ToCOUNTY MAINTENANCE SECTION
CSJ6318-02-001
Proj IDSUP - 631802001
Work TypePICNIC AREA GROUNDS & C&G MAINTENANCE
 
0.01086588.001843.772.1
Work Order06-27-17
Work Began07-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171108
Totals86588.001843.771843.772.1

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN NACOGDOCHES
ToCOUNTY MAINTENANCE SECTION
CSJ6318-37-001
Proj IDRMC - 631837001
Work TypeTREE TRIMMING
 
0.01099756.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DEKALB TREE SPECIALIST
SUBCONTRACTOR(S) FOR CCSJ: 6318-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171104
Totals99756.000.000.000.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN ANGELINA COUNTY
ToMAINTENANCE SECTION
CSJ6318-76-001
Proj IDRMC - 631876001
Work TypeHIGH EDGE REMOVAL
 
0.010197500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171105
Totals197500.000.000.000.0