Monthly Local Let Maintenance Report For Lufkin District As Of May 11, 2017 Page 5 Of 6

Last Update: Wednesday, May 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySHELBY
HighwayUS0096
FromVARIOUS LOCATIONS IN
ToSHELBY COUNTY
CSJ6310-07-001
Proj IDSUP - 631007001
Work TypePICNIC, GROUNDS AND ISLAND MAINTENANCE
 
0.01083397.5027926.5033.4
Work Order09-27-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged181
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161115
Totals83397.506788.5027926.5033.4

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS WITHIN
ToLUFKIN DISTRICT
CSJ6310-18-001
Proj IDRMC - 631018001
Work TypeINSTALLATION OF SPECIALTY PVMNT MARKINGS
 
0.001179448.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-17
Work Began00-00-00
Work Completed
Time Computed01-17-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6310-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161108
Totals179448.000.000.000.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToANGELINA COUNTY
CSJ6310-20-001
Proj IDSUP - 631020001
Work TypePICNIC AREA, HIST MRK & TRAF ISL MAINT
 
0.01037988.9216018.5942.1
Work Order10-15-16
Work Began10-15-16
Work Completed
Time Computed10-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged198
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161106
Totals37988.922678.9216018.5942.1

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToNACOGDOCHES COUNTY
CSJ6310-21-001
Proj IDSUP - 631021001
Work TypePICNIC, GRNDS, TRAF ISLAND MAINT
 
0.01048820.0012470.5025.5
Work Order10-15-16
Work Began10-15-16
Work Completed
Time Computed10-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged198
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6310-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161107
Totals48820.002043.0012470.5025.5

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONA IN
ToSAN JACINTO COUNTY
CSJ6311-14-001
Proj IDSUP - 631114001
Work TypeLANDSCAPE, PICNIC & GROUNDS MAINT
 
0.010109370.0922646.2320.7
Work Order12-12-16
Work Began01-01-17
Work Completed
Time Computed01-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged120
Percent Time Used32
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161101
Totals109370.098664.9122646.2320.7

CountySABINE
HighwayUS0096
FromVARIOUS LOCATIONS IN THE SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6312-50-001
Proj IDRMC - 631250001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010218711.960.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-04-17
Work Began00-00-00
Work Completed
Time Computed06-01-17
Contract Working Days61
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171102
Totals218711.960.000.000.0

CountySHELBY
HighwayUS0096
FromVARIOUS LOCATIONS IN THE SHELBY COUNTY
ToMAINTENANCE SECTION
CSJ6312-51-001
Proj IDRMC - 631251001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010155717.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-17-17
Work Began00-00-00
Work Completed
Time Computed06-01-17
Contract Working Days68
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6312-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171103
Totals155717.920.000.000.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN THE HOUSTON COUNTY
ToMAINTENANCE SECTION
CSJ6312-52-001
Proj IDRMC - 631252001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010165108.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DON YATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171104
Totals165108.100.000.000.0

CountyTRINITY
HighwaySH0094
FromVARIOUS ROADWAYS IN THE TRINITY COUNTY
ToMAINTENANCE SECTION
CSJ6312-53-001
Proj IDRMC - 631253001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010101948.680.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6312-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171102
Totals101948.680.000.000.0

CountyPOLK
HighwayUS0059
FromVARIOUS ROADWAYS IN THE POLK COUNTY
ToMAINTENANCE SECTION
CSJ6312-54-001
Proj IDRMC - 631254001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010244709.270.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days99
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6312-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171103
Totals244709.270.000.000.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN THE ANGELINA COUNTY
ToMAINTENANCE SECTION
CSJ6312-55-001
Proj IDRMC - 631255001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010189582.940.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-17
Work Began00-00-00
Work Completed
Time Computed05-01-17
Contract Working Days65
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6312-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171105
Totals189582.940.000.000.0

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS ROADWAYS IN THE NACOGDOCHES
ToCOUNTY MAINTENANCE SECTION
CSJ6312-56-001
Proj IDRMC - 631256001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010204371.80379.500.1
Work Order04-12-17
Work Began04-25-17
Work Completed
Time Computed04-25-17
Contract Working Days76
Addl Days Granted0
Working Days Charged1
Percent Time Used1
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171104
Totals204371.80379.50379.500.1

CountySAN AUGUSTINE
HighwaySH0147
FromVARIOUS ROADWAYS IN THE SAN AUGUSTINE
ToMAINTENANCE SECTION
CSJ6312-57-001
Proj IDRMC - 631257001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010176801.610.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-04-17
Work Began00-00-00
Work Completed
Time Computed06-01-17
Contract Working Days49
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171105
Totals176801.610.000.000.0

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN THE SAN JACINTO
ToMAINTENANCE SECTION
CSJ6312-58-001
Proj IDRMC - 631258001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010132231.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6312-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171106
Totals132231.770.000.000.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN_HOUSTON COUNTY
ToMAINTENANCE SECTION
CSJ6312-81-001
Proj IDRMC - 631281001
Work TypeHIGH EDGE REMOVAL
 
0.010181500.00148915.0082.0
Work Order03-16-17
Work Began03-20-17
Work Completed
Time Computed03-20-17
Contract Working Days100
Addl Days Granted0
Working Days Charged10
Percent Time Used10
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171102
Totals181500.0049057.00148915.0082.0

CountySABINE
HighwaySH0087
FromVARIOUS ROADWAYS IN THE SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6313-49-001
Proj IDRMC - 631349001
Work TypeDITCH AND CULVERT CLEANING
 
0.010177929.0036789.8020.6
Work Order03-08-17
Work Began03-22-07
Work Completed
Time Computed03-22-17
Contract Working Days64
Addl Days Granted0
Working Days Charged10
Percent Time Used15
Contractor(s)
L&S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6313-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171101
Totals177929.0034083.0036789.8020.6

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIIONS IN
ToLUFKIN DISTRICT
CSJ6313-75-001
Proj IDRMC - 631375001
Work TypeDISTRICT WIDE TRAFFIC SIGNAL MAINTENANCE
 
0.001327765.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-02-17
Work Began00-00-00
Work Completed
Time Computed05-09-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BAY CITY TRAFFIC
SUBCONTRACTOR(S) FOR CCSJ: 6313-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171101
Totals327765.000.000.000.0

CountySHELBY
HighwaySH0007
FromVARIOUS LOCATIONS IN THE SHELBY COUNTY
ToMAINTENANCE SECTION
CSJ6314-24-001
Proj IDRMC - 631424001
Work TypeDITCH AND CULVERT CLEANING
 
0.010169650.000.000.0
Work Order04-17-17
Work Began04-20-17
Work Completed
Time Computed04-20-17
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171106
Totals169650.000.000.000.0

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN THE POLK COUNTY
ToMAINTENANCE SECTION
CSJ6314-74-001
Proj IDRMC - 631474001
Work TypeDITCH AND CULVERT CLEANING
 
0.010204889.0513470.006.5
Work Order04-19-17
Work Began04-20-17
Work Completed
Time Computed04-20-17
Contract Working Days45
Addl Days Granted0
Working Days Charged6
Percent Time Used13
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171108
Totals204889.0513470.0013470.006.5

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN THE SAN JACINTO
ToMAINTENANCE SECTION
CSJ6314-75-001
Proj IDRMC - 631475001
Work TypeDITCH AND CULVERT CLEANING
 
0.010166612.5093335.0056.0
Work Order04-12-17
Work Began04-12-17
Work Completed
Time Computed04-12-17
Contract Working Days45
Addl Days Granted0
Working Days Charged11
Percent Time Used24
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171109
Totals166612.5093335.0093335.0056.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6