Monthly Local Let Maintenance Report For Lufkin District As Of Jul 14, 2017 Page 5 Of 6

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToNACOGDOCHES COUNTY
CSJ6310-21-001
Proj IDSUP - 631021001
Work TypePICNIC, GRNDS, TRAF ISLAND MAINT
 
0.01048820.0016913.5034.6
Work Order10-15-16
Work Began10-15-16
Work Completed
Time Computed10-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged259
Percent Time Used70
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6310-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161107
Totals48820.001921.5016913.5034.6

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONA IN
ToSAN JACINTO COUNTY
CSJ6311-14-001
Proj IDSUP - 631114001
Work TypeLANDSCAPE, PICNIC & GROUNDS MAINT
 
0.010109370.0940685.6237.1
Work Order12-12-16
Work Began01-01-17
Work Completed
Time Computed01-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged181
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161101
Totals109370.099051.5740685.6237.1

CountySABINE
HighwayUS0096
FromVARIOUS LOCATIONS IN THE SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6312-50-001
Proj IDRMC - 631250001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010218711.96108405.9849.5
Work Order05-04-17
Work Began06-07-17
Work Completed
Time Computed06-01-17
Contract Working Days61
Addl Days Granted0
Working Days Charged13
Percent Time Used21
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171102
Totals218711.96108405.98108405.9849.5

CountySHELBY
HighwayUS0096
FromVARIOUS LOCATIONS IN THE SHELBY COUNTY
ToMAINTENANCE SECTION
CSJ6312-51-001
Proj IDRMC - 631251001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010155717.9275582.7448.5
Work Order04-17-17
Work Began05-25-17
Work Completed
Time Computed05-25-17
Contract Working Days68
Addl Days Granted0
Working Days Charged19
Percent Time Used27
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6312-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171103
Totals155717.9260342.3775582.7448.5

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN THE HOUSTON COUNTY
ToMAINTENANCE SECTION
CSJ6312-52-001
Proj IDRMC - 631252001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010165108.109675.005.8
Work Order05-23-17
Work Began06-20-17
Work Completed
Time Computed06-20-17
Contract Working Days72
Addl Days Granted0
Working Days Charged4
Percent Time Used5
Contractor(s)
DON YATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171104
Totals165108.109675.009675.005.8

CountyTRINITY
HighwaySH0094
FromVARIOUS ROADWAYS IN THE TRINITY COUNTY
ToMAINTENANCE SECTION
CSJ6312-53-001
Proj IDRMC - 631253001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010101948.6833042.8532.4
Work Order05-15-17
Work Began06-01-17
Work Completed
Time Computed06-01-17
Contract Working Days45
Addl Days Granted0
Working Days Charged15
Percent Time Used33
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6312-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171102
Totals101948.6833042.8533042.8532.4

CountyPOLK
HighwayUS0059
FromVARIOUS ROADWAYS IN THE POLK COUNTY
ToMAINTENANCE SECTION
CSJ6312-54-001
Proj IDRMC - 631254001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010244709.270.000.0
Work Order00-00-00
Work Began06-12-17
Work Completed
Time Computed06-01-17
Contract Working Days99
Addl Days Granted0
Working Days Charged8
Percent Time Used8
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6312-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171103
Totals244709.270.000.000.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN THE ANGELINA COUNTY
ToMAINTENANCE SECTION
CSJ6312-55-001
Proj IDRMC - 631255001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010189582.9431591.5216.6
Work Order04-24-17
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days65
Addl Days Granted0
Working Days Charged17
Percent Time Used26
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6312-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171105
Totals189582.9430158.9231591.5216.6

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS ROADWAYS IN THE NACOGDOCHES
ToCOUNTY MAINTENANCE SECTION
CSJ6312-56-001
Proj IDRMC - 631256001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010204371.8029970.6014.6
Work Order04-12-17
Work Began04-25-17
Work Completed
Time Computed04-25-17
Contract Working Days76
Addl Days Granted0
Working Days Charged14
Percent Time Used18
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171104
Totals204371.8029591.1029970.6014.6

CountySAN AUGUSTINE
HighwaySH0147
FromVARIOUS ROADWAYS IN THE SAN AUGUSTINE
ToMAINTENANCE SECTION
CSJ6312-57-001
Proj IDRMC - 631257001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010176801.6188966.1250.3
Work Order05-04-17
Work Began06-01-17
Work Completed
Time Computed06-01-17
Contract Working Days49
Addl Days Granted0
Working Days Charged12
Percent Time Used24
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171105
Totals176801.6188966.1288966.1250.3

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN THE SAN JACINTO
ToMAINTENANCE SECTION
CSJ6312-58-001
Proj IDRMC - 631258001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010132231.7710730.948.1
Work Order06-01-17
Work Began06-01-17
Work Completed
Time Computed06-01-17
Contract Working Days54
Addl Days Granted0
Working Days Charged11
Percent Time Used20
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6312-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171106
Totals132231.7710730.9410730.948.1

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN_HOUSTON COUNTY
ToMAINTENANCE SECTION
CSJ6312-81-001
Proj IDRMC - 631281001
Work TypeHIGH EDGE REMOVAL
 
0.010181500.00148915.0082.0
Work Order03-16-17
Work Began03-20-17
Work Completed
Time Computed03-20-17
Contract Working Days100
Addl Days Granted0
Working Days Charged10
Percent Time Used10
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171102
Totals181500.000.00148915.0082.0

CountySABINE
HighwaySH0087
FromVARIOUS ROADWAYS IN THE SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6313-49-001
Proj IDRMC - 631349001
Work TypeDITCH AND CULVERT CLEANING
 
0.010177929.00117475.4066.0
Work Order03-08-17
Work Began03-22-07
Work Completed
Time Computed03-22-17
Contract Working Days64
Addl Days Granted0
Working Days Charged31
Percent Time Used48
Contractor(s)
L&S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6313-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171101
Totals177929.0056963.60117475.4066.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIIONS IN
ToLUFKIN DISTRICT
CSJ6313-75-001
Proj IDRMC - 631375001
Work TypeDISTRICT WIDE TRAFFIC SIGNAL MAINTENANCE
 
0.001327765.0035860.0010.9
Work Order05-02-17
Work Began05-09-17
Work Completed
Time Computed05-09-17
Contract Working Days365
Addl Days Granted0
Working Days Charged53
Percent Time Used14
Contractor(s)
BAY CITY TRAFFIC
SUBCONTRACTOR(S) FOR CCSJ: 6313-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171101
Totals327765.004210.0035860.0010.9

CountySHELBY
HighwaySH0007
FromVARIOUS LOCATIONS IN THE SHELBY COUNTY
ToMAINTENANCE SECTION
CSJ6314-24-001
Proj IDRMC - 631424001
Work TypeDITCH AND CULVERT CLEANING
 
0.010169650.000.000.0
Work Order04-17-17
Work Began04-20-17
Work Completed
Time Computed04-20-17
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171106
Totals169650.000.000.000.0

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN THE POLK COUNTY
ToMAINTENANCE SECTION
CSJ6314-74-001
Proj IDRMC - 631474001
Work TypeDITCH AND CULVERT CLEANING
 
0.010204889.05182314.0588.9
Work Order04-19-17
Work Began04-21-17
Work Completed
Time Computed04-21-17
Contract Working Days45
Addl Days Granted0
Working Days Charged31
Percent Time Used68
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171108
Totals204889.0595023.80182314.0588.9

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN THE SAN JACINTO
ToMAINTENANCE SECTION
CSJ6314-75-001
Proj IDRMC - 631475001
Work TypeDITCH AND CULVERT CLEANING
 
0.010166612.50182672.0099.9
Work Order04-12-17
Work Began04-12-17
Work Completed
Time Computed04-12-17
Contract Working Days45
Addl Days Granted0
Working Days Charged21
Percent Time Used46
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171109
Totals166612.501623.75182672.0099.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS ON US59 AND US259
ToWITHIN THE LUFKIN DISTRICT
CSJ6315-23-001
Proj IDSUP - 631523001
Work TypeLARGE DEBRIS PICKUP AND REMOVAL
 
0.010293400.0063570.0021.6
Work Order03-16-17
Work Began04-01-17
Work Completed
Time Computed04-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged91
Percent Time Used24
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6315-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171130
Totals293400.0019560.0063570.0021.6

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN THE_HOUSTON_COUNTY
ToMAINTENANCE SECTION
CSJ6317-63-001
Proj IDRMC - 631763001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010356050.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171101
Totals356050.000.000.000.0

CountySABINE
HighwaySH0087
FromVARIOUS LOCATIONS IN THE SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6317-92-001
Proj IDSUP - 631792001
Work TypePICNIC AREA GRNDS & C&G MAINTENANCE
 
0.01082720.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171111
Totals82720.220.000.000.0