Monthly Local Let Maintenance Report For Lufkin District As Of Mar 10, 2014 Page 5 Of 5

Last Update: Monday, March 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySAN AUGUSTINE
Highway US0096
From VARIOUS LOCATIONS WITHIN
To SAN AUGUSTINE COUNTY
CSJ 6267-99-001
Proj ID RMC - 626799001
Work Type MOWING HIGHWAY R.O.W. & LITTER REMOVAL
 
0.010 125954.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6267-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141112
Totals 125954.50 0.00 0.00 0.0

CountySAN JACINTO
Highway US0059
From VARIOUS LOCATIONS WITHIN
To SAN JACINTO COUNTY
CSJ 6268-00-001
Proj ID RMC - 626800001
Work Type MOWING HIGHWAY R.O.W. & LITTER REMOVAL
 
0.010 99945.03 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6268-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141113
Totals 99945.03 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5