Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySHELBY
Highway FM0138
From FM 138 & VARIOUS LOCATIONS WITHIN
To SHELBY & NACOGDOCHES SECTIONS
CSJ 6186-72-001
Proj ID EMC - 618672001
Work Type RELOCATE, REINSTALL, STRAIGHTEN SMALL SIGN
 
0.010 5575.00 33595.00 33595.00 99.9
Work Order 09-26-08
Work Began 10-01-08
Work Completed  
Time Computed 09-26-08
Contract Working Days 26
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 69
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6186-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09081114
Totals 5575.00 33595.00 33595.00 99.9

CountyPOLK
Highway FM0062
From FM 62 & VARIOUS LOCATIONS WITHIN
To POLK & SAN JACINTO SECTIONS
CSJ 6186-73-001
Proj ID EMC - 618673001
Work Type RELOCATE, REINSTALL, STRAIGHTEN SMALL SIGN
 
0.010 7350.00 48355.00 48805.00 99.9
Work Order 09-29-08
Work Began 09-30-08
Work Completed  
Time Computed 09-30-08
Contract Working Days 26
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 107
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD
SUBCONTRACTOR(S) FOR CCSJ: 6186-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09081115
Totals 7350.00 48355.00 48805.00 99.9

CountyANGELINA
Highway LP0287
From LP 287 & VARIOUS LOCATIONS WTIHIN
To ANGELINA & POLK MAINT SECTIONS
CSJ 6187-17-001
Proj ID EMC - 618717001
Work Type RELOCATE LARGE ROADSIDE SIGN ASSEMBLIES
 
0.010 26096.00 0.00 26096.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-02-08
Work Began 10-03-08
Work Completed 10-24-08
Time Computed 10-03-08
Contract Working Days 21
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 104
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6187-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09081116
Totals 26096.00 0.00 26096.00 100.0