Monthly Local Let Maintenance Report For Lufkin District As Of Mar 13, 2024 Page 5 Of 6

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySABINE
HighwayUS0096
FromSABINE COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6450-51-001
Proj IDSUP - 645051001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.01097466.2536344.7037.2
Work Order08-01-23
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6450-51-001
OAK CREEK DAY HABILITATION/VOCATION CENTER (0.00)
Contract #07231134
Totals97466.255393.8536344.7037.2

CountySAN AUGUSTINE
HighwayUS0096
FromSAN AUGUSTINE COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6450-53-001
Proj IDSUP - 645053001
Work TypeGROUNDS MAINTENANCE
 
0.01024522.355132.9820.9
Work Order00-00-00
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6450-53-001
OAK CREEK DAY HABILITATION/VOCATION CENTER (0.00)
Contract #07231135
Totals24522.35563.225132.9820.9

CountyANGELINA
HighwayBU0069J
FromANGELINA COUNTY
ToANGELINA COUNTY
CSJ6451-22-001
Proj IDSUP - 645122001
Work TypeLITTER REMOVAL
 
0.01058189.5232680.5156.1
Work Order00-00-00
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
SAUMYA, INC
SUBCONTRACTOR(S) FOR CCSJ: 6451-22-001
SAUMYA, INC (0.00)
Contract #07231136
Totals58189.5220350.2032680.5156.1

CountyTRINITY
HighwaySH0019
FromTRINITY COUNTY
ToVARIOUS LOCATIONS
CSJ6452-97-001
Proj IDSUP - 645297001
Work TypeSTATE USE CONTRACT
 
0.01053509.8219417.7736.2
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6452-97-001
BURKE CENTER (0.00)
Contract #08231132
Totals53509.822257.5319417.7736.2

CountyPOLK
HighwayUS0059
FromPOLK COUNTY MAINTENANCE YARD
ToPOLK COUNTY MAINTENANCE YARD
CSJ6452-99-001
Proj IDSUP - 645299001
Work TypeLITTER REMOVAL
 
0.010105969.2256647.0453.4
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6452-99-001
BURKE CENTER (0.00)
Contract #08231133
Totals105969.2212326.6256647.0453.4

CountySAN JACINTO
HighwaySH0150
FromSAN JACINTO COUNTY MAINTENANCE YARD
ToSAN JACINTO COUNTY MAINTENANCE YARD
CSJ6453-07-001
Proj IDMMC - 645307001
Work TypeHOT MIX
 
0.010234454.004160.931.7
Work Order00-00-00
Work Began10-23-23
Work Completed
Time Computed10-23-23
Contract Working Days120
Addl Days Granted120
Working Days Charged130
Percent Time Used54
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6453-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231160
Totals234454.000.004160.931.7

CountyTRINITY
HighwaySH0094
FromTRINITY COUNTY MAINTENANCE YARD
ToTRINITY COUNTY MAINTENANCE YARD
CSJ6453-34-001
Proj IDMMC - 645334001
Work TypeHOT MIX
 
0.010244450.000.000.0
Work Order10-04-23
Work Began10-16-23
Work Completed
Time Computed10-16-23
Contract Working Days120
Addl Days Granted120
Working Days Charged137
Percent Time Used57
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6453-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231161
Totals244450.000.000.000.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATION IN THE HOUSTON COUNTY
ToMAINTENANCE SECTION
CSJ6453-70-001
Proj IDRMC - 645370001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010165200.0024485.0014.8
Work Order00-00-00
Work Began12-07-23
Work Completed
Time Computed12-07-23
Contract Working Days365
Addl Days Granted0
Working Days Charged91
Percent Time Used24
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6453-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231103
Totals165200.000.0024485.0014.8

CountyTRINITY
HighwayUS0287
FromSHELBY COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6453-93-001
Proj IDRMC - 645393001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010272670.0028600.0010.4
Work Order01-30-24
Work Began02-01-24
Work Completed
Time Computed02-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged29
Percent Time Used7
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6453-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231104
Totals272670.0028600.0028600.0010.4

CountyNACOGDOCHES
HighwayFM0343
FromNACOGDOCHES COUNTY
ToNACOGDOCHES COUNTY
CSJ6456-53-001
Proj IDSUP - 645653001
Work TypeLITTER REMOVAL
 
0.01055970.6116726.4229.8
Work Order00-00-00
Work Began10-01-23
Work Completed
Time Computed10-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged152
Percent Time Used41
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6456-53-001
BURKE CENTER (0.00)
Contract #09231130
Totals55970.614535.7716726.4229.8

CountySABINE
HighwayFM0083
FromSABINE COUNTY
ToSABINE COUNTY
CSJ6456-58-001
Proj IDSUP - 645658001
Work TypeLITTER REMOVAL
 
0.01046721.608473.4018.1
Work Order00-00-00
Work Began10-01-23
Work Completed
Time Computed10-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged152
Percent Time Used41
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6456-58-001
BURKE CENTER (0.00)
Contract #09231131
Totals46721.601287.988473.4018.1

CountySAN AUGUSTINE
HighwaySH0021
FromSAN AUGUSTINE COUNTY
ToSAN AUGUSTINE COUNTY
CSJ6456-60-001
Proj IDSUP - 645660001
Work TypeLITTER REMOVAL
 
0.01068258.90853.121.2
Work Order00-00-00
Work Began10-01-23
Work Completed
Time Computed10-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged152
Percent Time Used41
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6456-60-001
BURKE CENTER (0.00)
Contract #09231132
Totals68258.90853.12853.121.2

CountySAN JACINTO
HighwaySH0150
FromSAN JACINTO COUNTY
ToSAN JACINTO COUNTY
CSJ6456-63-001
Proj IDSUP - 645663001
Work TypeLITTER REMOVAL
 
0.01053213.9924925.8346.8
Work Order00-00-00
Work Began10-01-23
Work Completed
Time Computed10-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged152
Percent Time Used41
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6456-63-001
BURKE CENTER (0.00)
Contract #09231133
Totals53213.996116.1324925.8346.8

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6456-99-001
Proj IDRMC - 645699001
Work TypeRAISED PAVEMENT MARKERS
 
0.010288179.000.000.0
Work Order12-11-23
Work Began12-18-23
Work Completed
Time Computed12-18-23
Contract Working Days365
Addl Days Granted0
Working Days Charged74
Percent Time Used20
Contractor(s)
BRYDL CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6456-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231105
Totals288179.000.000.000.0

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO COUNTY MAINTENANCE SECTION
ToVARIOUS ROADWAYS
CSJ6457-91-001
Proj IDRMC - 645791001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010173170.0018100.0010.4
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed02-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged29
Percent Time Used7
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6457-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12231103
Totals173170.0018100.0018100.0010.4

CountyHOUSTON
HighwayUS0287
FromHOUSTON COUNTY
ToVARIOUS LOCATIONS
CSJ6457-95-001
Proj IDRMC - 645795001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010175000.0015040.008.5
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed02-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged29
Percent Time Used7
Contractor(s)
WAYLON BOYLES
SUBCONTRACTOR(S) FOR CCSJ: 6457-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12231102
Totals175000.0015040.0015040.008.5

CountySAN AUGUSTINE
HighwayUS0096
FromSAN AUGUSTINE COUNTY MAINTENANCE SECTION
ToVARIOUS ROADWAYS
CSJ6457-99-001
Proj IDRMC - 645799001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010116118.070.000.0
Work Order00-00-00
Work Began02-07-24
Work Completed
Time Computed02-07-24
Contract Working Days365
Addl Days Granted0
Working Days Charged23
Percent Time Used6
Contractor(s)
JCW CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6457-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12231104
Totals116118.070.000.000.0

CountyPOLK
HighwayUS0059
FromPOLK COUNTY
ToVARIOUS LOCATIONS
CSJ6458-05-001
Proj IDRMC - 645805001
Work TypeTREE REMOVAL
 
0.010170832.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6458-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12231101
Totals170832.000.000.000.0

CountySHELBY
HighwaySH0007
FromSHELBY COUNTY
ToSABINE COUNTY
CSJ6458-34-001
Proj IDMMC - 645834001
Work TypeEMULSION
 
0.010252800.000.000.0
Work Order12-08-23
Work Began12-11-23
Work Completed
Time Computed12-11-23
Contract Working Days120
Addl Days Granted0
Working Days Charged81
Percent Time Used67
Contractor(s)
CLEVELAND ASPHALT PRODUCTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6458-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231161
Totals252800.000.000.000.0

CountyNACOGDOCHES
HighwayFM0343
FromNACOGDOCHES COUNTY
ToSAN AUGUSTINE COUNTY
CSJ6458-85-001
Proj IDMMC - 645885001
Work TypeEMULSION
 
0.010251700.0014517.755.7
Work Order00-00-00
Work Began12-14-23
Work Completed
Time Computed12-14-23
Contract Working Days120
Addl Days Granted0
Working Days Charged78
Percent Time Used65
Contractor(s)
CLEVELAND ASPHALT PRODUCTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6458-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231162
Totals251700.000.0014517.755.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6