Monthly Local Let Maintenance Report For Lufkin District As Of Mar 13, 2017 Page 4 Of 6

Last Update: Monday, March 13, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySABINE
HighwaySH0087
FromVARIOUS LOCATIONS IN
ToSABINE COUNTY
CSJ6304-65-001
Proj IDSUP - 630465001
Work TypePICNIC AREA GRNDS & CURB & GUTTER MAINT
 
0.01071757.4142586.0459.3
Work Order06-28-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161132
Totals71757.413873.6742586.0459.3

CountySHELBY
HighwaySH0007
FromVARIOUS LOCATIONS IN
ToSHELBY COUNTY
CSJ6304-67-001
Proj IDSUP - 630467001
Work TypeDELINEATOR, MBOX & CURB & GUTTER MAINT
 
0.010128500.00110980.9986.3
Work Order06-27-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161139
Totals128500.0012905.00110980.9986.3

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN
ToHOUSTON COUNTY
CSJ6304-68-001
Proj IDSUP - 630468001
Work TypePICNIC, GROUNDS & TRAFFIC ISLAND MAINT
 
0.01082013.807493.799.1
Work Order12-30-16
Work Began01-01-17
Work Completed
Time Computed01-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged59
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161102
Totals82013.804173.297493.799.1

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN
ToHOUSTON COUNTY
CSJ6304-69-001
Proj IDSUP - 630469001
Work TypeCURB & GUTTER - HOUSTON COUNTY
 
0.01028500.0012826.8045.0
Work Order07-13-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161133
Totals28500.000.0012826.8045.0

CountyTRINITY
HighwayUS0287
FromVARIOUS LOCATIONS IN
ToTRINITY COUNTY
CSJ6304-70-001
Proj IDSUP - 630470001
Work TypePICNIC, GROUNDS, TRFC ISLD IN TRINITY CO
 
0.01076420.2528781.8137.6
Work Order00-00-00
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161138
Totals76420.252176.0028781.8137.6

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToANGELINA COUNTY
CSJ6304-71-001
Proj IDSUP - 630471001
Work TypeCURB & GUTTER MAINTENANCE FOR ANGELINA
 
0.01044000.0022807.9851.8
Work Order00-00-00
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161136
Totals44000.000.0022807.9851.8

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToNACOGDOCHES COUNTY
CSJ6304-72-001
Proj IDSUP - 630472001
Work TypeDELINEATOR, OBJ MRKR & MAILBOX MAINT
 
0.010120000.0040899.0034.0
Work Order07-01-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161135
Totals120000.000.0040899.0034.0

CountyANGELINA
HighwayBU0059G
From1805 NORTH TIMBERLAND DRIVE
ToLUFKIN, TEXAS 75901
CSJ6304-73-001
Proj IDSUP - 630473001
Work TypeGROUNDS MAINT AT DISTRICT COMPLEX
 
0.01025400.009525.0037.5
Work Order00-00-00
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161134
Totals25400.001270.009525.0037.5

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS IN
ToSAN AUGUSTINE COUNTY
CSJ6304-74-001
Proj IDSUP - 630474001
Work TypePICNIC AREA GRNDS & C&G MAINT
 
0.01086588.0014493.7216.7
Work Order00-00-00
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161137
Totals86588.001402.0014493.7216.7

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToPOLK COUNTY
CSJ6304-76-001
Proj IDSUP - 630476001
Work TypePICNIC & GROUNDS MAINT IN POLK COUNTY
 
0.01036967.1219010.1151.4
Work Order06-27-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161140
Totals36967.122146.7619010.1151.4

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS IN
ToSAN AUGUSTINE COUNTY
CSJ6305-25-001
Proj IDSUP - 630525001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.010100000.0093281.0093.2
Work Order08-25-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged181
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161142
Totals100000.008278.0093281.0093.2

CountySABINE
HighwayUS0096
FromVARIOUS LOCATIONS IN
ToSABINE COUNTY
CSJ6305-26-001
Proj IDSUP - 630526001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.010100000.0074174.0074.1
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged181
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161141
Totals100000.008237.0074174.0074.1

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToNACOGDOCHES COUNTY
CSJ6306-69-001
Proj IDSUP - 630669001
Work TypeCURB & GUTTER MAINTENANCE
 
0.01046744.3217623.4837.7
Work Order08-31-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged134
Percent Time Used36
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6306-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161140
Totals46744.320.0017623.4837.7

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY
ToMAINTENANCE OFFICE
CSJ6306-71-001
Proj IDSUP - 630671001
Work TypeJANITORIAL MAINTENANCE
 
0.0107402.003510.0047.4
Work Order08-15-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged181
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6306-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161137
Totals7402.00585.003510.0047.4

CountyTRINITY
HighwayUS0287
FromTRINITY COUNTY
ToMAINTENANCE OFFICE
CSJ6306-72-001
Proj IDSUP - 630672001
Work TypeJANITORIAL MAINTENANCE
 
0.01013713.007870.9057.3
Work Order08-18-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged181
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6306-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161139
Totals13713.001142.757870.9057.3

CountyHOUSTON
HighwaySL0304
FromHOUSTON COUNTY
ToMAINTENANCE OFFICE
CSJ6306-73-001
Proj IDSUP - 630673001
Work TypeJANITORIAL MAINTENANCE
 
0.01011232.006072.0054.0
Work Order08-15-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged181
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6306-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161136
Totals11232.00860.006072.0054.0

CountyANGELINA
HighwayUS0059
FromLUFKIN DISTRICT OFFICE AND
ToNACOGDOCHES MAINT/AREA OFFICE
CSJ6306-74-001
Proj IDSUP - 630674001
Work TypeJANITORIAL MAINTENANCE
 
0.01049288.3224644.1650.0
Work Order08-10-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged181
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6306-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161132
Totals49288.324107.3624644.1650.0

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO COUNTY
ToMAINTENANCE OFFICE
CSJ6306-75-001
Proj IDSUP - 630675001
Work TypeJANITORIAL MAINTENANCE
 
0.0108013.007618.1895.0
Work Order08-18-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged181
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6306-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161138
Totals8013.001089.047618.1895.0

CountyANGELINA
HighwayUS0059
FromLUFKIN DISTRICT
ToOFFICE
CSJ6306-76-001
Proj IDSUP - 630676001
Work TypeWASHING AND DETAILING VEHICLES
 
0.0107193.25389.655.4
Work Order08-10-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged181
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6306-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161133
Totals7193.250.00389.655.4

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToIN ANGELINA COUNTY
CSJ6306-78-001
Proj IDSUP - 630678001
Work TypeDELINEATOR, OBJ MRK, MAILBOX & SIGN STR
 
0.010100000.0029297.0029.2
Work Order08-30-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged181
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161141
Totals100000.007621.0029297.0029.2

page 1 | page 2 | page 3 | page 4 | page 5 | page 6