Monthly Local Let Maintenance Report For Lufkin District As Of Jul 14, 2017 Page 4 Of 6

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToNACOGDOCHES COUNTY
CSJ6306-69-001
Proj IDSUP - 630669001
Work TypeCURB & GUTTER MAINTENANCE
 
0.01046744.3217623.4837.7
Work Order08-31-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged256
Percent Time Used70
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6306-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161140
Totals46744.320.0017623.4837.7

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY
ToMAINTENANCE OFFICE
CSJ6306-71-001
Proj IDSUP - 630671001
Work TypeJANITORIAL MAINTENANCE
 
0.0107402.005850.0079.0
Work Order08-15-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6306-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161137
Totals7402.00585.005850.0079.0

CountyTRINITY
HighwayUS0287
FromTRINITY COUNTY
ToMAINTENANCE OFFICE
CSJ6306-72-001
Proj IDSUP - 630672001
Work TypeJANITORIAL MAINTENANCE
 
0.01013713.0012441.9090.7
Work Order08-18-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6306-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161139
Totals13713.001142.7512441.9090.7

CountyHOUSTON
HighwaySL0304
FromHOUSTON COUNTY
ToMAINTENANCE OFFICE
CSJ6306-73-001
Proj IDSUP - 630673001
Work TypeJANITORIAL MAINTENANCE
 
0.01011232.009512.0084.6
Work Order08-15-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6306-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161136
Totals11232.00860.009512.0084.6

CountyANGELINA
HighwayUS0059
FromLUFKIN DISTRICT OFFICE AND
ToNACOGDOCHES MAINT/AREA OFFICE
CSJ6306-74-001
Proj IDSUP - 630674001
Work TypeJANITORIAL MAINTENANCE
 
0.01049288.3241073.6083.3
Work Order08-10-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6306-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161132
Totals49288.324107.3641073.6083.3

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO COUNTY
ToMAINTENANCE OFFICE
CSJ6306-75-001
Proj IDSUP - 630675001
Work TypeJANITORIAL MAINTENANCE
 
0.0108013.0012189.1899.9
Work Order08-18-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6306-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161138
Totals8013.001142.7512189.1899.9

CountyANGELINA
HighwayUS0059
FromLUFKIN DISTRICT
ToOFFICE
CSJ6306-76-001
Proj IDSUP - 630676001
Work TypeWASHING AND DETAILING VEHICLES
 
0.0107193.251182.9716.4
Work Order08-10-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6306-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161133
Totals7193.25384.641182.9716.4

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToIN ANGELINA COUNTY
CSJ6306-78-001
Proj IDSUP - 630678001
Work TypeDELINEATOR, OBJ MRK, MAILBOX & SIGN STR
 
0.010100000.0053920.0053.9
Work Order08-30-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161141
Totals100000.004943.0053920.0053.9

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToPOLK COUNTY
CSJ6306-79-001
Proj IDSUP - 630679001
Work TypeDELINEATOR, OBJ MRKR, MAILBOX & SIGN
 
0.010200000.0040491.0020.2
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161131
Totals200000.000.0040491.0020.2

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSAN JACINTO COUNTY
CSJ6306-80-001
Proj IDSUP - 630680001
Work TypeDELINEATOR, OBJ MARKER & MAILBOX MAINT
 
0.01050000.0073158.0099.9
Work Order08-11-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161134
Totals50000.007044.0073158.0099.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6307-44-001
Proj IDRMC - 630744001
Work TypeILLUMINATION
 
0.001388546.00395533.5099.9
Work Order10-19-16
Work Began10-26-06
Work Completed
Time Computed10-26-16
Contract Working Days365
Addl Days Granted0
Working Days Charged250
Percent Time Used68
Contractor(s)
LUDCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161108
Totals388546.0079335.75395533.5099.9

CountySABINE
HighwaySH0184
FromVARIOUS LOCATIONS IN SABINE & SAN AUGUST
ToINE COUNTY MAINTENANCE SECTION
CSJ6307-60-001
Proj IDRMC - 630760001
Work TypeDRAINAGE REPAIR
 
0.010149008.0089275.0059.9
Work Order05-04-17
Work Began06-07-17
Work Completed
Time Computed06-01-17
Contract Working Days60
Addl Days Granted0
Working Days Charged16
Percent Time Used26
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6307-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04171101
Totals149008.0089275.0089275.0059.9

CountySABINE
HighwaySH0087
FromVARIOUS LOCATIONS WITHIN THE
ToSABINE COUNTY MAINTENANCE SECTION
CSJ6308-42-001
Proj IDRMC - 630842001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010172470.0013488.007.8
Work Order01-12-17
Work Began01-12-17
Work Completed
Time Computed01-12-17
Contract Working Days200
Addl Days Granted0
Working Days Charged6
Percent Time Used3
Contractor(s)
T & L CLEANING SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6308-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161107
Totals172470.001490.0013488.007.8

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6308-73-001
Proj IDRMC - 630873001
Work TypeINSTALLATION OF WATERBASE STRIPING
 
0.001294400.000.000.0
Work Order12-08-16
Work Began12-15-16
Work Completed
Time Computed12-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged198
Percent Time Used54
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6308-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161103
Totals294400.000.000.000.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6308-74-001
Proj IDRMC - 630874001
Work TypeINSTALLATION OF THERMOPLASTIC STRIPING
 
0.001274570.00366835.4099.9
Work Order12-08-16
Work Began12-15-16
Work Completed
Time Computed12-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged198
Percent Time Used54
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6308-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161104
Totals274570.0052074.60366835.4099.9

CountySHELBY
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN THE
ToSHELBY COUNTY MAINTENANCE SECTION
CSJ6309-67-001
Proj IDRMC - 630967001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010142140.0023535.0016.5
Work Order01-12-17
Work Began01-12-17
Work Completed
Time Computed01-12-17
Contract Working Days200
Addl Days Granted0
Working Days Charged8
Percent Time Used4
Contractor(s)
T & L CLEANING SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6309-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161110
Totals142140.005180.0023535.0016.5

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN THE
ToSAN AUGUSTINE COUNTY MAINTENANCE SECTION
CSJ6309-68-001
Proj IDRMC - 630968001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010146806.0030025.0020.4
Work Order00-00-00
Work Began01-26-17
Work Completed
Time Computed01-26-17
Contract Working Days200
Addl Days Granted0
Working Days Charged6
Percent Time Used3
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161109
Totals146806.009100.0030025.0020.4

CountySHELBY
HighwayUS0096
FromVARIOUS LOCATIONS IN
ToSHELBY COUNTY
CSJ6310-07-001
Proj IDSUP - 631007001
Work TypePICNIC, GROUNDS AND ISLAND MAINTENANCE
 
0.01083397.5042632.0051.1
Work Order09-27-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged242
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161115
Totals83397.507343.5042632.0051.1

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS WITHIN
ToLUFKIN DISTRICT
CSJ6310-18-001
Proj IDRMC - 631018001
Work TypeINSTALLATION OF SPECIALTY PVMNT MARKINGS
 
0.001179448.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-17
Work Began00-00-00
Work Completed
Time Computed01-17-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6310-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161108
Totals179448.000.000.000.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToANGELINA COUNTY
CSJ6310-20-001
Proj IDSUP - 631020001
Work TypePICNIC AREA, HIST MRK & TRAF ISL MAINT
 
0.01037988.9222310.6358.7
Work Order10-15-16
Work Began10-15-16
Work Completed
Time Computed10-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged259
Percent Time Used70
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161106
Totals37988.922976.4222310.6358.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6