Monthly Local Let Maintenance Report For Lufkin District As Of Feb 09, 2018 Page 4 Of 5

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyANGELINA
HighwayUS0059
FromLUFKIN DISTRICT
ToOFFICE
CSJ6319-51-001
Proj IDSUP - 631951001
Work TypeWASHING AND DETAILING VEHICLES
 
0.0106573.251310.7319.9
Work Order08-28-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6319-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171103
Totals6573.25192.321310.7319.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATION IN ANGELINA COUNTY
ToMAINTENANCE SECTION
CSJ6319-52-001
Proj IDSUP - 631952001
Work TypeDELINEATOR, OBJ MRK, MAILBOX & SIGN STR
 
0.010100000.0015019.0015.0
Work Order08-30-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171109
Totals100000.002613.0015019.0015.0

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN POLK COUNTY
ToMAINTENANCE SECTION
CSJ6319-53-001
Proj IDSUP - 631953001
Work TypeDELINEATOR, OBJ MRKR, MAILBOX & SIGN
 
0.010200000.0014254.007.1
Work Order08-28-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171106
Totals200000.003766.0014254.007.1

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN SAN JACINTO
ToCOUNTY MAINTENANCE SECTION
CSJ6319-54-001
Proj IDSUP - 631954001
Work TypeDELINEATOR, OBJ MARKER & MAILBOX MAINT
 
0.01070000.0035348.0050.4
Work Order08-29-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171107
Totals70000.004456.0035348.0050.4

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS IN SAN AUGUSTINE
ToCOUNTY MAINTENANCE SECTION
CSJ6319-55-001
Proj IDSUP - 631955001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.010180000.0077472.0043.0
Work Order08-30-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171110
Totals180000.0010673.0077472.0043.0

CountySABINE
HighwayUS0096
FromVARIOUS LOCATION IN SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6319-56-001
Proj IDSUP - 631956001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.010182000.0040736.0022.3
Work Order08-28-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171108
Totals182000.004565.0040736.0022.3

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN NACOGDOCHES
ToCOUNTY
CSJ6319-57-001
Proj IDSUP - 631957001
Work TypeCURB AND GUTTER MAINTENANCE
 
0.01046744.3215080.9632.2
Work Order08-28-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171105
Totals46744.320.0015080.9632.2

CountySHELBY
HighwaySH0007
FromVARIOUS LOCATIONS IN SHELBY COUNTY
ToMAINTENANCE SECTION
CSJ6321-56-001
Proj IDRMC - 632156001
Work TypeTREE & BRUSH REMOVAL AND TREE TRIMMING
 
0.010257604.000.000.0
Work Order00-00-00
Work Began10-16-17
Work Completed
Time Computed10-16-17
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6321-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171110
Totals257604.000.000.000.0

CountyTRINITY
HighwaySH0019
FromVARIOUS LOCATIONS IN TRINITY COUNTY
ToMAINTENANCE SECTION
CSJ6321-57-001
Proj IDRMC - 632157001
Work TypeGUARD FENCE, ATTENUATOR, & MTL RAIL REP
 
0.010160600.2011105.006.9
Work Order00-00-00
Work Began10-16-17
Work Completed
Time Computed10-16-17
Contract Working Days200
Addl Days Granted0
Working Days Charged3
Percent Time Used1
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171111
Totals160600.204150.0011105.006.9

CountyTRINITY
HighwaySH0019
FromVARIOUS LOCATIONS IN TRINITY COUNTY
ToMAINTENANCE SECTION
CSJ6322-97-001
Proj IDRMC - 632297001
Work TypeCULVERT CLEANING AND REPLACEMENT
 
0.010134140.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6322-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01181108
Totals134140.000.000.000.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN HOUSTON, POLK,
ToSAN JACINTO, & TRINITY COUNTY MAINT SEC
CSJ6322-99-001
Proj IDRMC - 632299001
Work TypeCRACK SEALING
 
0.01093890.380.000.0
Work Order01-08-18
Work Began01-09-18
Work Completed
Time Computed01-09-18
Contract Working Days40
Addl Days Granted0
Working Days Charged12
Percent Time Used30
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6322-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10171111
Totals93890.380.000.000.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN HOUSTON COUNTY
ToMAINTENANCE SECTION
CSJ6323-16-001
Proj IDRMC - 632316001
Work TypeTREE TRIMMING
 
0.010150636.0087725.0058.2
Work Order12-07-17
Work Began12-11-17
Work Completed
Time Computed12-11-17
Contract Working Days40
Addl Days Granted0
Working Days Charged26
Percent Time Used65
Contractor(s)
ALARCON CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6323-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10171112
Totals150636.0055430.0087725.0058.2

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY MAINTENANCE
ToOFFICE
CSJ6323-23-001
Proj IDSUP - 632323001
Work TypeJANITORIAL MAINTENANCE
 
0.0107402.002925.0039.5
Work Order08-25-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6323-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171102
Totals7402.00585.002925.0039.5

CountySABINE
HighwaySH0087
FromVARIOUS LOCATIONS IN SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6323-36-001
Proj IDRMC - 632336001
Work TypeDITCH AND CULVERT CLEANING
 
0.010152028.8046818.1630.7
Work Order12-01-17
Work Began12-11-17
Work Completed
Time Computed12-04-17
Contract Working Days60
Addl Days Granted0
Working Days Charged10
Percent Time Used16
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10171113
Totals152028.800.0046818.1630.7

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6323-73-001
Proj IDRMC - 632373001
Work TypeINSTALLATION OF SPOT PAINT STRIPING
 
0.001262850.0019724.267.5
Work Order01-11-18
Work Began01-23-18
Work Completed
Time Computed01-18-18
Contract Working Days365
Addl Days Granted0
Working Days Charged14
Percent Time Used3
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6323-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171101
Totals262850.0019724.2619724.267.5

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6323-74-001
Proj IDRMC - 632374001
Work TypeILLUMINATION
 
0.001362700.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BAY CITY TRAFFIC
SUBCONTRACTOR(S) FOR CCSJ: 6323-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171102
Totals362700.000.000.000.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS WITHIN
ToHOUSTON COUNTY
CSJ6323-79-001
Proj IDSUP - 632379001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01076786.7511301.0714.7
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6323-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171131
Totals76786.755334.5211301.0714.7

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToANGELINA COUNTY
CSJ6323-80-001
Proj IDSUP - 632380001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01046667.836944.0914.8
Work Order11-30-17
Work Began00-00-00
Work Completed
Time Computed12-01-17
Contract Working Days304
Addl Days Granted0
Working Days Charged62
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171130
Totals46667.833738.866944.0914.8

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToNACOGDOCHES COUNTY
CSJ6323-81-001
Proj IDSUP - 632381001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010112955.4519018.0516.8
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6323-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171130
Totals112955.454914.8919018.0516.8

CountySABINE
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN
ToSABINE COUNTY
CSJ6323-82-001
Proj IDSUP - 632382001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01043881.5110713.8924.4
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6323-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171134
Totals43881.511678.7610713.8924.4