Monthly Local Let Maintenance Report For Lufkin District As Of Aug 11, 2017 Page 4 Of 6

Last Update: Friday, August 11, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyANGELINA
HighwayUS0059
FromLUFKIN DISTRICT
ToOFFICE
CSJ6306-76-001
Proj IDSUP - 630676001
Work TypeWASHING AND DETAILING VEHICLES
 
0.0107193.251524.5421.1
Work Order08-10-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6306-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161133
Totals7193.25341.571524.5421.1

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToIN ANGELINA COUNTY
CSJ6306-78-001
Proj IDSUP - 630678001
Work TypeDELINEATOR, OBJ MRK, MAILBOX & SIGN STR
 
0.010100000.0058807.0058.8
Work Order08-30-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161141
Totals100000.004887.0058807.0058.8

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToPOLK COUNTY
CSJ6306-79-001
Proj IDSUP - 630679001
Work TypeDELINEATOR, OBJ MRKR, MAILBOX & SIGN
 
0.010200000.0040491.0020.2
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161131
Totals200000.000.0040491.0020.2

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSAN JACINTO COUNTY
CSJ6306-80-001
Proj IDSUP - 630680001
Work TypeDELINEATOR, OBJ MARKER & MAILBOX MAINT
 
0.01050000.0078877.0099.9
Work Order08-11-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161134
Totals50000.005719.0078877.0099.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6307-44-001
Proj IDRMC - 630744001
Work TypeILLUMINATION
 
0.001388546.00507882.8599.9
Work Order10-19-16
Work Began10-26-06
Work Completed
Time Computed10-26-16
Contract Working Days365
Addl Days Granted0
Working Days Charged281
Percent Time Used76
Contractor(s)
LUDCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161108
Totals388546.00112349.35507882.8599.9

CountySABINE
HighwaySH0184
FromVARIOUS LOCATIONS IN SABINE & SAN AUGUST
ToINE COUNTY MAINTENANCE SECTION
CSJ6307-60-001
Proj IDRMC - 630760001
Work TypeDRAINAGE REPAIR
 
0.010149008.00131615.0088.3
Work Order05-04-17
Work Began06-07-17
Work Completed
Time Computed06-01-17
Contract Working Days60
Addl Days Granted0
Working Days Charged34
Percent Time Used56
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6307-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04171101
Totals149008.0042340.00131615.0088.3

CountySABINE
HighwaySH0087
FromVARIOUS LOCATIONS WITHIN THE
ToSABINE COUNTY MAINTENANCE SECTION
CSJ6308-42-001
Proj IDRMC - 630842001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010172470.0013488.007.8
Work Order01-12-17
Work Began01-12-17
Work Completed
Time Computed01-12-17
Contract Working Days200
Addl Days Granted0
Working Days Charged6
Percent Time Used3
Contractor(s)
T & L CLEANING SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6308-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161107
Totals172470.000.0013488.007.8

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6308-73-001
Proj IDRMC - 630873001
Work TypeINSTALLATION OF WATERBASE STRIPING
 
0.001294400.000.000.0
Work Order12-08-16
Work Began12-15-16
Work Completed
Time Computed12-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged229
Percent Time Used62
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6308-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161103
Totals294400.000.000.000.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6308-74-001
Proj IDRMC - 630874001
Work TypeINSTALLATION OF THERMOPLASTIC STRIPING
 
0.001274570.00366835.4099.9
Work Order12-08-16
Work Began12-15-16
Work Completed
Time Computed12-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged229
Percent Time Used62
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6308-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161104
Totals274570.000.00366835.4099.9

CountySHELBY
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN THE
ToSHELBY COUNTY MAINTENANCE SECTION
CSJ6309-67-001
Proj IDRMC - 630967001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010142140.0027915.0019.6
Work Order01-12-17
Work Began01-12-17
Work Completed
Time Computed01-12-17
Contract Working Days200
Addl Days Granted0
Working Days Charged9
Percent Time Used4
Contractor(s)
T & L CLEANING SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6309-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161110
Totals142140.004380.0027915.0019.6

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN THE
ToSAN AUGUSTINE COUNTY MAINTENANCE SECTION
CSJ6309-68-001
Proj IDRMC - 630968001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010146806.0030025.0020.4
Work Order00-00-00
Work Began01-26-17
Work Completed
Time Computed01-26-17
Contract Working Days200
Addl Days Granted0
Working Days Charged6
Percent Time Used3
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161109
Totals146806.000.0030025.0020.4

CountySHELBY
HighwayUS0096
FromVARIOUS LOCATIONS IN
ToSHELBY COUNTY
CSJ6310-07-001
Proj IDSUP - 631007001
Work TypePICNIC, GROUNDS AND ISLAND MAINTENANCE
 
0.01083397.5051049.0061.2
Work Order09-27-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161115
Totals83397.508417.0051049.0061.2

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS WITHIN
ToLUFKIN DISTRICT
CSJ6310-18-001
Proj IDRMC - 631018001
Work TypeINSTALLATION OF SPECIALTY PVMNT MARKINGS
 
0.001179448.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-09-17
Work Began00-00-00
Work Completed
Time Computed08-16-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6310-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161108
Totals179448.000.000.000.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToANGELINA COUNTY
CSJ6310-20-001
Proj IDSUP - 631020001
Work TypePICNIC AREA, HIST MRK & TRAF ISL MAINT
 
0.01037988.9225287.0566.5
Work Order10-15-16
Work Began10-15-16
Work Completed
Time Computed10-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged290
Percent Time Used79
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161106
Totals37988.922976.4225287.0566.5

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToNACOGDOCHES COUNTY
CSJ6310-21-001
Proj IDSUP - 631021001
Work TypePICNIC, GRNDS, TRAF ISLAND MAINT
 
0.01048820.0019610.0040.1
Work Order10-15-16
Work Began10-15-16
Work Completed
Time Computed10-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged290
Percent Time Used79
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6310-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161107
Totals48820.002696.5019610.0040.1

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONA IN
ToSAN JACINTO COUNTY
CSJ6311-14-001
Proj IDSUP - 631114001
Work TypeLANDSCAPE, PICNIC & GROUNDS MAINT
 
0.010109370.0947909.4443.8
Work Order12-12-16
Work Began01-01-17
Work Completed
Time Computed01-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged212
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161101
Totals109370.097223.8247909.4443.8

CountySABINE
HighwayUS0096
FromVARIOUS LOCATIONS IN THE SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6312-50-001
Proj IDRMC - 631250001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010218711.96108405.9849.5
Work Order05-04-17
Work Began06-07-17
Work Completed
Time Computed06-01-17
Contract Working Days61
Addl Days Granted0
Working Days Charged13
Percent Time Used21
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171102
Totals218711.960.00108405.9849.5

CountySHELBY
HighwayUS0096
FromVARIOUS LOCATIONS IN THE SHELBY COUNTY
ToMAINTENANCE SECTION
CSJ6312-51-001
Proj IDRMC - 631251001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010155717.9275582.7448.5
Work Order04-17-17
Work Began05-25-17
Work Completed
Time Computed05-25-17
Contract Working Days68
Addl Days Granted0
Working Days Charged19
Percent Time Used27
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6312-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171103
Totals155717.920.0075582.7448.5

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN THE HOUSTON COUNTY
ToMAINTENANCE SECTION
CSJ6312-52-001
Proj IDRMC - 631252001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010165108.1047083.0028.5
Work Order05-23-17
Work Began06-20-17
Work Completed
Time Computed06-20-17
Contract Working Days72
Addl Days Granted0
Working Days Charged20
Percent Time Used27
Contractor(s)
DON YATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171104
Totals165108.1037408.0047083.0028.5

CountyTRINITY
HighwaySH0094
FromVARIOUS ROADWAYS IN THE TRINITY COUNTY
ToMAINTENANCE SECTION
CSJ6312-53-001
Proj IDRMC - 631253001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010101948.6850814.6049.8
Work Order05-15-17
Work Began06-01-17
Work Completed
Time Computed06-01-17
Contract Working Days45
Addl Days Granted0
Working Days Charged19
Percent Time Used42
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6312-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171102
Totals101948.6817771.7550814.6049.8