Monthly Local Let Maintenance Report For Lufkin District As Of Jul 13, 2015 Page 3 Of 7

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyANGELINA
Highway US0069
From LOCATED WITHIN THE LUFKIN STATE
To SUPPORTED LIVING CENTER ON US 69
CSJ 6273-13-001
Proj ID RMC - 627313001
Work Type SEAL COAT, REHAB & MISC. CONSTRUCTION
 
0.010 164328.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05151104
Totals 164328.00 0.00 0.00 0.0

CountySHELBY
Highway SH0007
From VARIOUS LOCATIONS WITHIN
To SHELBY COUNTY
CSJ 6273-29-001
Proj ID SUP - 627329001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 150166.20 5624.57 103325.43 68.8
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 143
Percent Time Used 75
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141135
Totals 150166.20 5624.57 103325.43 68.8

CountyPOLK
Highway US0059
From VARIOUS LOCATION IN
To POLK COUNTY
CSJ 6273-30-001
Proj ID SUP - 627330001
Work Type REMOVAL AND DISPOSAL OF LITTER FROM ROW
 
0.010 100617.11 5025.94 106620.93 99.9
Work Order 05-30-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 145
Percent Time Used 76
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141130
Totals 100617.11 5025.94 106620.93 99.9

CountyHOUSTON
Highway US0287
From VARIOUS LOCATIONS WITHIN
To HOUSTON COUNTY
CSJ 6273-31-001
Proj ID SUP - 627331001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 53966.10 3835.66 37660.08 69.7
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 64
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141136
Totals 53966.10 3835.66 37660.08 69.7

CountyTRINITY
Highway SH0019
From VARIOUS LOCATIONS WITHIN
To TRINITY COUNTY
CSJ 6273-32-001
Proj ID SUP - 627332001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 30679.43 4541.40 31448.76 99.9
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141134
Totals 30679.43 4541.40 31448.76 99.9

CountySAN JACINTO
Highway US0059
From VARIOUS LOCATIONS WITHIN
To SAN JACINTO COUNTY
CSJ 6273-33-001
Proj ID SUP - 627333001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 103857.18 7933.58 104942.66 99.9
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 142
Percent Time Used 74
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141137
Totals 103857.18 7933.58 104942.66 99.9

CountyNACOGDOCHES
Highway US0059
From VARIOUS LOCATIONS WITHIN
To NACOGDOCHES COUNTY
CSJ 6273-34-001
Proj ID SUP - 627334001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 91651.16 1825.99 61994.18 67.6
Work Order 05-30-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 136
Percent Time Used 71
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141132
Totals 91651.16 1825.99 61994.18 67.6

CountySAN AUGUSTINE
Highway US0096
From VARIOUS LOCATIONS WITHIN
To SAN AUGUSTINE COUNTY
CSJ 6273-35-001
Proj ID SUP - 627335001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 78790.92 3500.24 55287.92 70.1
Work Order 05-30-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 56
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141131
Totals 78790.92 3500.24 55287.92 70.1

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS WITHIN
To ANGELINA COUNTY
CSJ 6273-36-001
Proj ID SUP - 627336001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 145010.45 5877.48 81278.16 56.0
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 140
Percent Time Used 73
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141133
Totals 145010.45 5877.48 81278.16 56.0

CountySABINE
Highway US0096
From VARIOUS LOCATIONS WITHIN
To SABINE COUNTY
CSJ 6273-37-001
Proj ID SUP - 627337001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 60374.52 2207.29 32845.40 54.4
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 18
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141138
Totals 60374.52 2207.29 32845.40 54.4

CountySAN JACINTO
Highway US0190
From VARIOUS LOCATIONS IN THE
To SAN JACINTO MAINTENANCE AREA
CSJ 6273-40-001
Proj ID RMC - 627340001
Work Type HIGH EDGE REMOVAL
 
0.010 63250.00 0.00 61250.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-08-14
Work Began 08-18-14
Work Completed 08-22-14
Time Computed 08-12-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 26
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141107
Totals 63250.00 0.00 61250.00 100.0

CountyPOLK
Highway US0059
From VARIOUS LOCATIONS WITHIN
To POLK COUNTY
CSJ 6273-59-001
Proj ID SUP - 627359001
Work Type PICNIC AND GROUNDS MAINTENANCE
 
0.010 36967.12 1931.90 24347.77 65.8
Work Order 06-27-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 335
Percent Time Used 91
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141131
Totals 36967.12 1931.90 24347.77 65.8

CountySAN JACINTO
Highway SH0150
From VARIOUS LOCATIONS IN
To SAN JACINTO COUNTY
CSJ 6273-82-001
Proj ID RMC - 627382001
Work Type CROSS CULVERT REPAIR
 
0.010 64244.14 0.00 64244.14 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-22-15
Work Began 02-13-15
Work Completed 02-27-15
Time Computed 02-02-15
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 6
Contractor(s)
KEGLEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10141101
Totals 64244.14 0.00 64244.14 100.0

CountyNACOGDOCHES
Highway FM1638
From VARIOUS LOCATIONS IN
To NACOGDOCHES COUNTY
CSJ 6274-08-001
Proj ID RMC - 627408001
Work Type DITCH AND CULVERT CLEANING
 
0.010 111960.00 0.00 107996.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-16-14
Work Began 09-24-14
Work Completed 01-31-15
Time Computed 09-22-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 37
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141106
Totals 111960.00 0.00 107996.00 100.0

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS IN
To THE LUFKIN DISTRICT
CSJ 6274-24-001
Proj ID RMC - 627424001
Work Type LARGE SIGN MAINTENANCE DISTRICT WIDE
 
0.010 175373.40 0.00 6511.95 3.7
Work Order 12-05-14
Work Began 12-16-14
Work Completed  
Time Computed 12-16-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 197
Percent Time Used 53
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141103
Totals 175373.40 0.00 6511.95 3.7

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS WITHIN
To LUFKIN DISTRICT
CSJ 6274-25-001
Proj ID RMC - 627425001
Work Type INSTALLATION OF THERMOPLASTIC STRIPING
 
0.010 234861.00 51793.30 145186.67 61.8
Work Order 11-12-14
Work Began 00-00-00
Work Completed  
Time Computed 11-19-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6274-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141110
Totals 234861.00 51793.30 145186.67 61.8

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS WITHIN
To LUFKIN DISTRICT
CSJ 6274-26-001
Proj ID RMC - 627426001
Work Type INSTALLATION OF WATERBASE STRIPING
 
0.010 244706.00 0.00 99322.07 40.5
Work Order 11-12-14
Work Began 01-20-15
Work Completed  
Time Computed 11-19-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6274-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141111
Totals 244706.00 0.00 99322.07 40.5

CountySHELBY
Highway US0096
From VARIOUS LOCATIONS IN THE
To SHELBY COUNTY MAINTENANCE AREA
CSJ 6274-68-001
Proj ID RMC - 627468001
Work Type GUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010 184237.00 7480.00 74907.50 100.0
Work Order 11-04-14
Work Began 00-00-00
Work Completed 02-27-15
Time Computed 11-10-14
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 4
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141109
Totals 184237.00 7480.00 74907.50 100.0

CountySABINE
Highway SH0087
From VARIOUS LOCATIONS WITHIN
To SABINE COUNTY
CSJ 6275-13-001
Proj ID SUP - 627513001
Work Type PICNIC, GROUNDS, CURB & GUTTER MAINT
 
0.010 71757.41 8479.90 60821.00 85.0
Work Order 06-27-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 354
Percent Time Used 96
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141130
Totals 71757.41 8479.90 60821.00 85.0

CountySABINE
Highway US0096
From VARIOUS LOCTIONS WITHIN
To SABINE COUNTY
CSJ 6275-15-001
Proj ID SUP - 627515001
Work Type MAILBOX AND DELINEATOR MAINTENANCE
 
0.010 100000.00 15278.00 76396.00 76.3
Work Order 06-27-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141132
Totals 100000.00 15278.00 76396.00 76.3