Monthly Local Let Maintenance Report For Lufkin District As Of Jan 11, 2017 Page 3 Of 6

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN POLK,
ToSAN JACINTO AND TRINITY COUNTIES
CSJ6299-78-001
Proj IDRMC - 629978001
Work TypeINSTALL RAISED REFL PAVEMENT
 
0.001210952.009119.184.3
Work Order06-08-16
Work Began06-14-16
Work Completed
Time Computed06-15-16
Contract Working Days730
Addl Days Granted0
Working Days Charged201
Percent Time Used27
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6299-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161110
Totals210952.000.009119.184.3

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToANGELINA COUNTY MAINTENANCE SECTION
CSJ6300-07-001
Proj IDRMC - 630007001
Work TypeTREE REMOVAL AND TREE AND BRUSH
 
0.010258400.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6300-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161105
Totals258400.000.000.000.0

CountyTRINITY
HighwaySH0019
FromVARIOUS LOCATIONS THROUGHOUT
ToTRINITY COUNTY
CSJ6300-98-001
Proj IDRMC - 630098001
Work TypeTREE REMOVAL AND TREE TRIM
 
0.010271080.0058297.6821.5
Work Order08-24-16
Work Began09-19-16
Work Completed
Time Computed09-19-16
Contract Working Days175
Addl Days Granted0
Working Days Charged63
Percent Time Used36
Contractor(s)
DEVTEX INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161115
Totals271080.0020798.2858297.6821.5

CountyTRINITY
HighwayFM2781
FromVARIOUS LOCATIONS IN TRINITY & ANGELINA
ToMAINTENANCE SECTIONS
CSJ6301-20-001
Proj IDRMC - 630120001
Work TypeDRAINAGE REPAIR
 
0.010205367.940.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GREEN SOURCE ENVIRONMENTAL SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171101
Totals205367.940.000.000.0

CountySHELBY
HighwayFM0414
From0.89 MILES NORTHEAST OF SH 87 ON THE
ToSOUTH SIDE OF FM 414
CSJ6301-55-001
Proj IDRMC - 630155001
Work TypeCULVERT INSTALLATION
 
0.010109175.00120789.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-16
Work Began07-26-16
Work Completed
Time Computed07-18-16
Contract Working Days25
Addl Days Granted0
Working Days Charged25
Percent Time Used100
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161101
Totals109175.000.00120789.0099.9

CountyNACOGDOCHES
HighwaySH0007
FromVARIOUS LOCATIONS WITHIN_THE
ToNACOGDOCHES COUNTY MAINTENANCE SECTION
CSJ6301-57-001
Proj IDRMC - 630157001
Work TypeGUARD FENCE, ATTENUATOR & METAL
 
0.010190750.0014215.007.4
Work Order11-30-16
Work Began12-02-16
Work Completed
Time Computed12-02-16
Contract Working Days200
Addl Days Granted0
Working Days Charged2
Percent Time Used1
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161106
Totals190750.0014215.0014215.007.4

CountySHELBY
HighwaySH0007
From1.16 MILES WEST OF FM 711
To2.90 MILES WEST OF FM 711
CSJ6302-08-001
Proj IDEMC - 630208001
Work TypeEXCAVATION, TEMP SPCL SHORING,
 
0.0102640798.752660568.2599.9
Work Order07-11-16
Work Began07-19-16
Work Completed
Time Computed07-12-16
Contract Working Days72
Addl Days Granted16
Working Days Charged88
Percent Time Used100
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6302-08-001
AR DANIEL CONSTRUCTION SERVICES, INC. (2.70)
DREWERY & WHEATON, LLC (3.61)
FREDONIA CONSTRUCTION SERVICES (0.37)
PANOLA SIGN & BARRICADE, INC. (0.49)
STRIPING TECHNOLOGY, L.P. (2.00)
OSCAR ORDUNO, INC. (8.62)
Contract #06161152
Totals2640798.7511537.612660568.2599.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS ON US59 AND US259
ToWITHIN THE LUFKIN DISTRICT
CSJ6302-22-001
Proj IDSUP - 630222001
Work TypeLARGE DEBRIS PICKUP AND REMOVAL
 
0.010293400.00228630.0077.9
Work Order00-00-00
Work Began04-01-16
Work Completed
Time Computed04-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged275
Percent Time Used75
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161133
Totals293400.0016215.00228630.0077.9

CountySHELBY
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSHELBY COUNTY
CSJ6302-27-001
Proj IDSUP - 630227001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON
 
0.010101849.3922505.1022.0
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161135
Totals101849.396464.6522505.1022.0

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToPOLK COUNTY
CSJ6302-28-001
Proj IDSUP - 630228001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON
 
0.010103351.3216458.3915.9
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged67
Percent Time Used18
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161114
Totals103351.326919.0016458.3915.9

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS WITHIN
ToHOUSTON COUNTY
CSJ6302-29-001
Proj IDSUP - 630229001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON
 
0.01058420.6311153.6419.0
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161111
Totals58420.634054.9911153.6419.0

CountyTRINITY
HighwaySH0019
FromVARIOUS LOCATION IN
ToTRINITY COUNTY
CSJ6302-30-001
Proj IDSUP - 630230001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON
 
0.01043866.9011373.9125.9
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161118
Totals43866.904931.9611373.9125.9

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSAN JACINTO COUNTY
CSJ6302-31-001
Proj IDSUP - 630231001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON
 
0.01080384.1118845.9323.4
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161117
Totals80384.116950.8218845.9323.4

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToNACOGDOCHES COUNTY
CSJ6302-32-001
Proj IDSUP - 630232001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON
 
0.010101283.8221588.5021.3
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161113
Totals101283.829040.7421588.5021.3

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS IN
ToSAN AUGUSTINE COUNTY
CSJ6302-33-001
Proj IDSUP - 630233001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON
 
0.01086182.2610398.2212.0
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161119
Totals86182.263991.6410398.2212.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToANGELINA COUNTY
CSJ6302-34-001
Proj IDSUP - 630234001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON
 
0.010100797.8833899.8433.6
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161116
Totals100797.8811739.2833899.8433.6

CountySABINE
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN
ToSABINE COUNTY
CSJ6302-35-001
Proj IDSUP - 630235001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON
 
0.01041609.7910234.2424.5
Work Order00-00-00
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161110
Totals41609.793381.3010234.2424.5

CountyANGELINA
HighwayUS0069
FromUS 69 @ SH 7
ToBRIDGE OVERPASS
CSJ6302-39-001
Proj IDEMC - 630239001
Work TypeBRIDGE BEAM REPAIR
 
0.01039500.0039500.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-12-16
Work Completed04-29-16
Time Computed00-00-00
Contract Working Days10
Addl Days Granted0
Working Days Charged5
Percent Time Used50
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6302-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161116
Totals39500.000.0039500.00100.0

CountyANGELINA
HighwayUS0069
FromWITHIN THE LIMITS
ToOF THE LSSLC
CSJ6302-61-001
Proj IDRMC - 630261001
Work TypePARKING LOT CONSTRUCTION AT LSSLC
 
0.010229591.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-05-17
Work Began00-00-00
Work Completed
Time Computed01-09-17
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROCKETT CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161106
Totals229591.500.000.000.0

CountySABINE
HighwaySH0021
FromVARIOUS LOCATIONS THROUGHOUT
ToSABINE COUNTY
CSJ6302-70-001
Proj IDRMC - 630270001
Work TypeTREE REMOVAL AND TREE TRIM
 
0.010246250.0070525.0028.6
Work Order10-04-16
Work Began10-17-16
Work Completed
Time Computed10-17-16
Contract Working Days175
Addl Days Granted0
Working Days Charged23
Percent Time Used13
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6302-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161109
Totals246250.0021375.0070525.0028.6