Monthly Local Let Maintenance Report For Lufkin District As Of Nov 9, 2016 Page 3 Of 6

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOUSTON
Highway US0287
From VARIOUS LOCATIONS IN THE HOUSTON COUNTY
To MAINTENANCE AREA
CSJ 6294-39-001
Proj ID RMC - 629439001
Work Type MOWING OF THE ROW AND LITTER REMOVAL
 
0.010 173249.00 57449.00 144091.00 83.1
Work Order 05-26-16
Work Began 06-07-16
Work Completed  
Time Computed 06-01-16
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 166
Contractor(s)
DON YATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6294-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05161104
Totals 173249.00 57449.00 144091.00 83.1

CountyPOLK
Highway US0059
From VARIOUS LOCATIONS IN
To POLK COUNTY MAINTENANCE AREA
CSJ 6294-41-001
Proj ID RMC - 629441001
Work Type ROW MOWING AND LITTER CONTROL
 
0.010 252232.22 0.00 109044.70 43.2
Work Order 05-26-16
Work Began 06-02-16
Work Completed  
Time Computed 06-02-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 90
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05161106
Totals 252232.22 0.00 109044.70 43.2

CountySAN AUGUSTINE
Highway US0096
From VARIOUS RAODS IN SAN AUGUSTINE
To MAINTENANCE AREA
CSJ 6294-44-001
Proj ID RMC - 629444001
Work Type MOWING OF THE ROW AND LITTER REMOVAL
 
0.010 147214.96 25188.66 99418.54 67.5
Work Order 00-00-00
Work Began 06-01-16
Work Completed  
Time Computed 06-01-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 50
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6294-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05161109
Totals 147214.96 25188.66 99418.54 67.5

CountySAN JACINTO
Highway US0059
From VARIOUS ROADS SAN JACINTO COUNTY
To MAINTENANCE AREA
CSJ 6294-45-001
Proj ID RMC - 629445001
Work Type MOWING OF THE ROW AND LITTER REMOVAL
 
0.010 135346.38 55777.06 113209.02 88.8
Work Order 05-26-16
Work Began 06-02-16
Work Completed  
Time Computed 06-02-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 88
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05161110
Totals 135346.38 55777.06 113209.02 88.8

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS IN
To THE LUFKIN DISTRICT
CSJ 6295-05-001
Proj ID RMC - 629505001
Work Type DISTRICT WIDE CRACK SEAL
 
409.220 190732.68 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-21-16
Work Began 00-00-00
Work Completed  
Time Computed 11-01-16
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6295-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09161103
Totals 190732.68 0.00 0.00 0.0

CountySAN JACINTO
Highway US0059
From VARIOUS LOCATIONS IN
To SAN JACINTO COUNTY
CSJ 6296-20-001
Proj ID RMC - 629620001
Work Type GUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010 102832.50 0.00 12125.00 11.7
Work Order 01-29-16
Work Began 02-01-16
Work Completed  
Time Computed 02-01-16
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 1
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12151104
Totals 102832.50 0.00 12125.00 11.7

CountyPOLK
Highway US0059
From VARIOUS LOCATIONS WITHIN
To POLK COUNTY
CSJ 6297-00-001
Proj ID RMC - 629700001
Work Type TREE & BRUSH TRIMMING / REMOVAL OF TREES
 
0.010 267850.01 0.00 123320.00 46.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-09-16
Work Began 06-01-16
Work Completed  
Time Computed 06-01-16
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 33
Contractor(s)
FLORES TREE SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01161104
Totals 267850.01 0.00 123320.00 46.0

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS IN
To ANGELINA COUNTY
CSJ 6297-73-001
Proj ID RMC - 629773001
Work Type LARGE SIGN MAINTENANCE
 
0.001 183683.85 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-01-16
Work Began 00-00-00
Work Completed  
Time Computed 11-01-16
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SOUTH RANGER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05161111
Totals 183683.85 0.00 0.00 0.0

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS WITHIN
To LUFKIN DISTRICT
CSJ 6297-74-001
Proj ID RMC - 629774001
Work Type INSTALL SPOT PAINT AND BEAD STRIPING
 
0.001 296250.00 98069.45 198426.00 66.9
Work Order 05-12-16
Work Began 05-24-16
Work Completed  
Time Computed 05-24-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 161
Percent Time Used 44
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6297-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04161107
Totals 296250.00 98069.45 198426.00 66.9

CountyPOLK
Highway US0190
From VARIOUS LOCATIONS IN SOUTHERN COUNTIES
To OF THE LUFKIN DISTRICT
CSJ 6299-50-001
Proj ID RMC - 629950001
Work Type DISTRICT WIDE CRACK SEAL
 
106.759 136741.93 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-28-16
Work Began 12-01-16
Work Completed  
Time Computed 12-01-16
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6299-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09161104
Totals 136741.93 0.00 0.00 0.0

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS IN ANGELINA,
To HOUSTON AND NACOGDOCHES COUNTIES
CSJ 6299-76-001
Proj ID RMC - 629976001
Work Type INSTALL RAISED REFL PAVEMENT MARKERS
 
0.001 210952.00 0.00 29097.78 13.7
Work Order 06-08-16
Work Began 06-14-16
Work Completed  
Time Computed 06-15-16
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 140
Percent Time Used 19
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6299-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04161108
Totals 210952.00 0.00 29097.78 13.7

CountySHELBY
Highway US0059
From VARIOUS LOCATIONS IN SHELBY,
To SAN AUGUSTINE AND SABINE COUNTIES
CSJ 6299-77-001
Proj ID RMC - 629977001
Work Type INSTALL RAISED REFL PAVEMENT MARKERS
 
0.001 210952.00 0.00 19716.92 9.3
Work Order 06-08-16
Work Began 06-14-16
Work Completed  
Time Computed 06-15-16
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 140
Percent Time Used 19
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6299-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04161109
Totals 210952.00 0.00 19716.92 9.3

CountyPOLK
Highway US0059
From VARIOUS LOCATIONS IN POLK,
To SAN JACINTO AND TRINITY COUNTIES
CSJ 6299-78-001
Proj ID RMC - 629978001
Work Type INSTALL RAISED REFL PAVEMENT MARKERS
 
0.001 210952.00 0.00 6924.21 3.2
Work Order 06-08-16
Work Began 06-14-16
Work Completed  
Time Computed 06-15-16
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 140
Percent Time Used 19
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6299-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04161110
Totals 210952.00 0.00 6924.21 3.2

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS IN
To ANGELINA COUNTY MAINTENANCE SECTION
CSJ 6300-07-001
Proj ID RMC - 630007001
Work Type TREE REMOVAL AND TREE AND BRUSH TRIMMING
 
0.010 258400.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6300-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10161105
Totals 258400.00 0.00 0.00 0.0

CountyTRINITY
Highway SH0019
From VARIOUS LOCATIONS THROUGHOUT
To TRINITY COUNTY
CSJ 6300-98-001
Proj ID RMC - 630098001
Work Type TREE REMOVAL AND TREE TRIM
 
0.010 271080.00 0.00 21451.50 7.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-24-16
Work Began 09-19-16
Work Completed  
Time Computed 09-19-16
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 17
Contractor(s)
DEVTEX INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04161115
Totals 271080.00 0.00 21451.50 7.9

CountySHELBY
Highway FM0414
From 0.89 MILES NORTHEAST OF SH 87 ON THE
To SOUTH SIDE OF FM 414
CSJ 6301-55-001
Proj ID RMC - 630155001
Work Type CULVERT INSTALLATION
 
0.010 109175.00 0.00 120789.00 99.9
Work Order 07-11-16
Work Began 07-26-16
Work Completed  
Time Computed 07-18-16
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 100
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06161101
Totals 109175.00 0.00 120789.00 99.9

CountyNACOGDOCHES
Highway SH0007
From VARIOUS LOCATIONS WITHIN_THE
To NACOGDOCHES COUNTY MAINTENANCE SECTION
CSJ 6301-57-001
Proj ID RMC - 630157001
Work Type GUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010 190750.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11161106
Totals 190750.00 0.00 0.00 0.0

CountySHELBY
Highway SH0007
From 1.16 MILES WEST OF FM 711
To 2.90 MILES WEST OF FM 711
CSJ 6302-08-001
Proj ID EMC - 630208001
Work Type EXCAVATION, TEMP SPCL SHORING, CULVERT
 
0.010 2640798.75 577127.84 2627612.72 99.5
Work Order 07-11-16
Work Began 07-19-16
Work Completed  
Time Computed 07-12-16
Contract Working Days 72
Addl Days Granted 16
Working Days Charged 86
Percent Time Used 97
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6302-08-001
AR DANIEL CONSTRUCTION SERVICES, INC.(2.70%)
DREWERY & WHEATON, LLC (3.61%)
FREDONIA CONSTRUCTION SERVICES (0.37%)
PANOLA SIGN & BARRICADE, INC.(0.49%)
STRIPING TECHNOLOGY, L.P.(2.00%)
OSCAR ORDUNO, INC. (8.62%)
Contract # 06161152
Totals 2640798.75 577127.84 2627612.72 99.5

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS ON US59 AND US259
To WITHIN THE LUFKIN DISTRICT
CSJ 6302-22-001
Proj ID SUP - 630222001
Work Type LARGE DEBRIS PICKUP AND REMOVAL
 
0.010 293400.00 21105.00 189930.00 64.7
Work Order 00-00-00
Work Began 04-01-16
Work Completed  
Time Computed 04-01-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 214
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03161133
Totals 293400.00 21105.00 189930.00 64.7

CountySHELBY
Highway US0059
From VARIOUS LOCATIONS IN
To SHELBY COUNTY
CSJ 6302-27-001
Proj ID SUP - 630227001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 101849.39 5868.43 5868.43 5.7
Work Order 10-01-16
Work Began 10-01-16
Work Completed  
Time Computed 10-01-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09161135
Totals 101849.39 5868.43 5868.43 5.7