Monthly Local Let Maintenance Report For Lufkin District As Of Jan 11, 2017 Page 2 Of 6

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyANGELINA
HighwayUS0059
FromUS 59 AT
ToSB DIRECTO CONNECTOR
CSJ6280-65-001
Proj IDBPM - 628065001
Work TypeBEARING REPAIRS
 
0.01095950.0091800.0095.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-27-15
Work Completed
Time Computed00-00-00
Contract Working Days10
Addl Days Granted0
Working Days Charged4
Percent Time Used40
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151102
Totals95950.000.0091800.0095.6

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN
ToHOUSTON COUNTY
CSJ6282-70-001
Proj IDRMC - 628270001
Work TypeGUARD FENCE, ATTENUATOR & MTL RAIL
 
0.010232925.0034995.0015.0
Work Order04-27-15
Work Began08-17-15
Work Completed
Time Computed05-01-15
Contract Working Days200
Addl Days Granted0
Working Days Charged10
Percent Time Used5
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6282-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03151117
Totals232925.000.0034995.0015.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN THE
ToHOUSTON COUNTY MAINTENANCE AREA
CSJ6283-69-001
Proj IDRMC - 628369001
Work TypeTREE REMOVAL/TREE TRIMMING/BRUSH
 
0.010167011.00184051.0099.9
Work Order09-10-15
Work Began09-01-15
Work Completed
Time Computed09-10-15
Contract Working Days120
Addl Days Granted200
Working Days Charged59
Percent Time Used18
Contractor(s)
L & M CLEANING SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6283-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05151103
Totals167011.0016900.00184051.0099.9

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToPOLK COUNTY
CSJ6288-65-001
Proj IDRMC - 628865001
Work TypeGUARD FENCE, ATTENUATOR & MTL RAIL
 
0.010199473.0077012.0038.6
Work Order05-09-16
Work Began05-16-16
Work Completed
Time Computed05-16-16
Contract Working Days200
Addl Days Granted0
Working Days Charged27
Percent Time Used13
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6288-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161101
Totals199473.0010220.0077012.0038.6

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN
ToSAN AUGUSTINE COUNTY
CSJ6288-67-001
Proj IDSUP - 628867001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON
 
0.01064079.0844270.6869.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days190
Addl Days Granted0
Working Days Charged129
Percent Time Used67
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6288-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151136
Totals64079.080.0044270.6869.0

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS WITHIN
ToSAN JACINTO COUNTY
CSJ6289-62-001
Proj IDSUP - 628962001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON
 
0.01071869.2475007.1199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began09-08-15
Work Completed
Time Computed09-01-15
Contract Working Days190
Addl Days Granted30
Working Days Charged211
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6289-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151137
Totals71869.240.0075007.1199.9

CountyTRINITY
HighwayUS0287
FromVARIOUS LOCATIONS IN
ToIN TRINITY COUNTY
CSJ6290-02-001
Proj IDRMC - 629002001
Work TypeGUARD FENCE, ATTENUATOR & MTL RAIL
 
0.010142795.0041125.0028.8
Work Order00-00-00
Work Began10-28-15
Work Completed
Time Computed10-28-15
Contract Working Days200
Addl Days Granted0
Working Days Charged11
Percent Time Used5
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6290-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151106
Totals142795.000.0041125.0028.8

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSAN JACINTO COUNTY
CSJ6290-78-001
Proj IDSUP - 629078001
Work TypeLANDSCAPE, PICNIC & GROUNDS
 
0.01076022.2576131.2599.9
Work Order12-07-15
Work Began12-08-15
Work Completed
Time Computed12-07-15
Contract Working Days365
Addl Days Granted31
Working Days Charged391
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6290-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11151130
Totals76022.25457.0076131.2599.9

CountyANGELINA
HighwayUS0069
FromVARIOUS LOCATIONS IN THE
ToANGELINA COUNTY MAINTENANCE SECTION
CSJ6291-44-001
Proj IDRMC - 629144001
Work TypeTREE TRIM & BRUSH REMOVAL/TREE
 
0.010188111.3266890.0035.5
Work Order07-29-16
Work Began10-04-16
Work Completed
Time Computed10-04-16
Contract Working Days45
Addl Days Granted155
Working Days Charged45
Percent Time Used22
Contractor(s)
DRC EMERGENCY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151101
Totals188111.3230075.0066890.0035.5

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToLUFKIN DISTRICT
CSJ6293-21-001
Proj IDRMC - 629321001
Work TypeDISTRICT WIDE THERMOPLASTIC
 
0.001245685.00348890.2399.9
Work Order00-00-00
Work Began04-25-16
Work Completed
Time Computed04-25-16
Contract Working Days365
Addl Days Granted0
Working Days Charged251
Percent Time Used68
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6293-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10151102
Totals245685.000.00348890.2399.9

CountyANGELINA
HighwayUS0059
FromDISTRICT WIDE IN
ToLUFKIN DISTRICT
CSJ6293-23-001
Proj IDRMC - 629323001
Work TypeDIST WIDE TRAFFIC SIGNAL MAINT
 
0.001359657.6022657.486.2
Work Order03-22-16
Work Began04-12-16
Work Completed
Time Computed04-12-16
Contract Working Days365
Addl Days Granted0
Working Days Charged275
Percent Time Used75
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10151104
Totals359657.604993.4922657.486.2

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS WITHIN
ToNACOGDOCHES COUNTY
CSJ6293-53-001
Proj IDSUP - 629353001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON
 
0.01091371.1570680.4177.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days190
Addl Days Granted30
Working Days Charged144
Percent Time Used65
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6293-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151133
Totals91371.150.0070680.4177.3

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO COUNTY
ToMAINTENANCE OFFICE
CSJ6294-12-001
Proj IDSUP - 629412001
Work TypeJANITORIAL MAINTENANCE
 
0.01010858.4110858.4199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged357
Percent Time Used97
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6294-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151136
Totals10858.410.0010858.4199.9

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSAN JACINTO COUNTY
CSJ6296-20-001
Proj IDRMC - 629620001
Work TypeGUARD FENCE, ATTENUATOR & METAL
 
0.010102832.5015503.7515.0
Work Order01-29-16
Work Began02-01-16
Work Completed
Time Computed02-01-16
Contract Working Days200
Addl Days Granted0
Working Days Charged4
Percent Time Used2
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151104
Totals102832.503378.7515503.7515.0

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS WITHIN
ToPOLK COUNTY
CSJ6297-00-001
Proj IDRMC - 629700001
Work TypeTREE & BRUSH TRIMMING/REMOVAL OF
 
0.010267850.01134620.0050.2
Work Order05-09-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days200
Addl Days Granted0
Working Days Charged72
Percent Time Used36
Contractor(s)
FLORES TREE SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161104
Totals267850.010.00134620.0050.2

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToANGELINA COUNTY
CSJ6297-73-001
Proj IDRMC - 629773001
Work TypeLARGE SIGN MAINTENANCE
 
0.001183683.85103237.9756.2
Work Order08-01-16
Work Began11-03-16
Work Completed
Time Computed11-01-16
Contract Working Days30
Addl Days Granted0
Working Days Charged15
Percent Time Used50
Contractor(s)
SOUTH RANGER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161111
Totals183683.8556078.49103237.9756.2

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS WITHIN
ToLUFKIN DISTRICT
CSJ6297-74-001
Proj IDRMC - 629774001
Work TypeINSTALL SPOT PAINT AND BEAD
 
0.001296250.00263314.1088.8
Work Order05-12-16
Work Began05-24-16
Work Completed
Time Computed05-24-16
Contract Working Days365
Addl Days Granted0
Working Days Charged222
Percent Time Used60
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6297-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161107
Totals296250.0018806.60263314.1088.8

CountyPOLK
HighwayUS0190
FromVARIOUS LOCATIONS IN SOUTHERN COUNTIES
ToOF THE LUFKIN DISTRICT
CSJ6299-50-001
Proj IDRMC - 629950001
Work TypeDISTRICT WIDE CRACK SEAL
 
106.759136741.93119168.0787.1
Work Order10-28-16
Work Began11-14-16
Work Completed
Time Computed12-01-16
Contract Working Days40
Addl Days Granted0
Working Days Charged12
Percent Time Used30
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6299-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161104
Totals136741.9362612.64119168.0787.1

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN ANGELINA,
ToHOUSTON AND NACOGDOCHES COUNTIES
CSJ6299-76-001
Proj IDRMC - 629976001
Work TypeINSTALL RAISED REFL PAVEMENT
 
0.001210952.0031824.0815.0
Work Order06-08-16
Work Began06-14-16
Work Completed
Time Computed06-15-16
Contract Working Days730
Addl Days Granted0
Working Days Charged201
Percent Time Used27
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6299-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161108
Totals210952.000.0031824.0815.0

CountySHELBY
HighwayUS0059
FromVARIOUS LOCATIONS IN SHELBY,
ToSAN AUGUSTINE AND SABINE COUNTIES
CSJ6299-77-001
Proj IDRMC - 629977001
Work TypeINSTALL RAISED REFL PAVEMENT
 
0.001210952.0032104.6715.2
Work Order06-08-16
Work Began06-14-16
Work Completed
Time Computed06-15-16
Contract Working Days730
Addl Days Granted0
Working Days Charged201
Percent Time Used27
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6299-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161109
Totals210952.000.0032104.6715.2