Monthly Local Let Maintenance Report For Lufkin District As Of Jul 11, 2014 Page 2 Of 5

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySABINE
Highway SH0087
From VARIOUS LOCATIONS IN THE
To SABINE COUNTY MAINTENANCE AREA
CSJ 6261-85-001
Proj ID RMC - 626185001
Work Type GUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010 131851.10 2475.00 101916.00 77.2
Work Order 01-03-14
Work Began 01-15-14
Work Completed  
Time Computed 01-15-14
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 6
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09131102
Totals 131851.10 2475.00 101916.00 77.2

CountySAN AUGUSTINE
Highway US0096
From VARIOUS LOCATIONS IN
To SAN AUGUSTINE MAINTENANCE AREA
CSJ 6262-77-001
Proj ID RMC - 626277001
Work Type REMOVAL OF TREES
 
0.010 198100.00 41425.00 141750.00 71.5
Work Order 02-10-14
Work Began 02-18-14
Work Completed  
Time Computed 02-18-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 21
Contractor(s)
T.F.R. ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131103
Totals 198100.00 41425.00 141750.00 71.5

CountyANGELINA
Highway US0059
From VARIOUS IN
To ANGELINA COUNTY
CSJ 6262-78-001
Proj ID SUP - 626278001
Work Type WASHING & DETAILING VEHICLES - ANGELINA CO
 
0.010 7193.25 0.00 1626.72 23.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-01-13
Work Began 07-01-13
Work Completed  
Time Computed 07-01-13
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 14
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6262-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131130
Totals 7193.25 0.00 1626.72 23.2

CountySHELBY
Highway SH0087
From VARIOUS LOCATIONS IN
To SHELBY COUNTY
CSJ 6262-96-001
Proj ID RMC - 626296001
Work Type TREE REMOVAL
 
0.100 334250.00 0.00 100870.00 30.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-06-14
Work Began 05-05-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 9
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6262-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09131103
Totals 334250.00 0.00 100870.00 30.1

CountyANGELINA
Highway US0059
From LUFKIN DIST OFFICE AND
To NACOGDOCHES MAINT/AREA OFFICE
CSJ 6263-40-001
Proj ID SUP - 626340001
Work Type JANITORIAL MAINTENANCE
 
0.010 49288.32 4107.36 41073.60 83.3
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6263-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131139
Totals 49288.32 4107.36 41073.60 83.3

CountyTRINITY
Highway SH0094
From SH 94 AT TRINITY
To COUNTY MAINT OFFICE
CSJ 6263-43-001
Proj ID SUP - 626343001
Work Type JANITORIAL MAINTENANCE
 
0.010 13427.52 1118.96 11189.60 83.3
Work Order 08-31-13
Work Began 09-03-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6263-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131132
Totals 13427.52 1118.96 11189.60 83.3

CountyPOLK
Highway US0059
From US 59 AT POLK COUNTY
To MAINTENANCE OFFICE
CSJ 6263-44-001
Proj ID SUP - 626344001
Work Type JANITORIAL MAINTENANCE
 
0.010 8190.00 682.50 6825.00 83.3
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 83
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6263-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131136
Totals 8190.00 682.50 6825.00 83.3

CountyANGELINA
Highway US0059
From JANITORIAL - ANGELINA
To MAINTENANCE OFFICE
CSJ 6263-45-001
Proj ID SUP - 626345001
Work Type JANITORIAL MAINTENANCE
 
0.010 7402.00 585.00 5850.00 79.0
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 85
Percent Time Used 34
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6263-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131133
Totals 7402.00 585.00 5850.00 79.0

CountySAN JACINTO
Highway SH0150
From SH150 AT SAN JACINTO
To MAINTENANCE OFFICE
CSJ 6263-46-001
Proj ID SUP - 626346001
Work Type JANITORIAL MAINTENANCE
 
0.010 7314.00 551.25 5512.50 75.3
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6263-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131134
Totals 7314.00 551.25 5512.50 75.3

CountyTRINITY
Highway SH0019
From SH 19 & VARIOUS LOCATIONS
To IN TRINITY COUNTY
CSJ 6265-02-001
Proj ID RMC - 626502001
Work Type TREE TRIM & REM / DISP OF TREES & LIMBS
 
0.100 225150.02 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-04-14
Work Began 06-04-14
Work Completed  
Time Computed 06-04-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLORES TREE SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6265-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04141106
Totals 225150.02 0.00 0.00 0.0

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS WITHIN
To LUFKIN DISTRICT
CSJ 6265-93-001
Proj ID RMC - 626593001
Work Type INSTALLATION OF SPOT PAINT / BEAD STRIPING
 
0.001 277751.00 12339.28 17344.36 6.2
Work Order 05-20-14
Work Began 05-21-14
Work Completed  
Time Computed 05-21-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 11
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6265-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141114
Totals 277751.00 12339.28 17344.36 6.2

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS WITHIN
To LUFKIN DISTRICT (9 COUNTIES)
CSJ 6266-07-001
Proj ID RMC - 626607001
Work Type INSTALLATION OF THERMOPLASTIC STRIPING
 
0.001 228126.00 0.00 88542.10 38.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-20-14
Work Began 06-12-14
Work Completed  
Time Computed 05-27-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 5
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6266-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141115
Totals 228126.00 0.00 88542.10 38.8

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS WITHIN
To LUFKIN DISTRICT (9 COUNTIES)
CSJ 6266-08-001
Proj ID RMC - 626608001
Work Type INSTALLATION OF WATERBASE STRIPING
 
0.001 230501.00 0.00 46649.40 20.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-20-14
Work Began 06-02-14
Work Completed  
Time Computed 05-27-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6266-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141116
Totals 230501.00 0.00 46649.40 20.2

CountySAN AUGUSTINE
Highway FM0705
From VARIOUS LOCATIONS IN
To SAN AUGUSTINE
CSJ 6266-68-001
Proj ID RMC - 626668001
Work Type CULVERT REPLACEMENT
 
0.010 263747.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-24-14
Work Began 07-07-14
Work Completed  
Time Computed 07-07-14
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6266-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141107
Totals 263747.16 0.00 0.00 0.0

CountySABINE
Highway FM0083
From VARIOUS LOCATIONS IN
To SABINE COUNTY
CSJ 6266-70-001
Proj ID RMC - 626670001
Work Type CULVERT REPLACEMENT
 
0.010 179810.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-01-14
Work Began 00-00-00
Work Completed  
Time Computed 07-01-14
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6266-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141108
Totals 179810.00 0.00 0.00 0.0

CountySHELBY
Highway FM0947
From NELSON & SHIP CREEK
To IN SHELBY COUNTY
CSJ 6266-71-001
Proj ID RMC - 626671001
Work Type BRIDGE RAIL UPGRADE
 
0.010 128950.72 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-20-14
Work Began 00-00-00
Work Completed  
Time Computed 07-14-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ODUM SERVICES, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6266-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01141114
Totals 128950.72 0.00 0.00 0.0

CountyANGELINA
Highway US0059
From VARIOUS ROADS IN
To ANGELINA COUNTY
CSJ 6267-75-001
Proj ID RMC - 626775001
Work Type CLEAN DITCHES AND CULVERTS
 
0.100 90734.69 0.00 111457.90 99.9
Work Order 02-18-14
Work Began 02-24-14
Work Completed  
Time Computed 02-24-14
Contract Working Days 40
Addl Days Granted 20
Working Days Charged 25
Percent Time Used 41
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01141101
Totals 90734.69 0.00 111457.90 99.9

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS IN
To ANGELINA COUNTY
CSJ 6267-78-001
Proj ID RMC - 626778001
Work Type TREE TRIM & REM / DISP OF TREES & LIMBS
 
0.100 234355.00 18423.00 117274.00 50.0
Work Order 03-07-14
Work Began 03-17-14
Work Completed  
Time Computed 03-17-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 37
Contractor(s)
REGINA CRAWFORD
SUBCONTRACTOR(S) FOR CCSJ: 6267-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01141102
Totals 234355.00 18423.00 117274.00 50.0

CountySAN AUGUSTINE
Highway US0096
From VARIOUS LOCATIONS IN THE
To SAN AUGUSTINE MAINTENANCE AREA
CSJ 6267-79-001
Proj ID RMC - 626779001
Work Type GUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010 118339.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 07-03-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141103
Totals 118339.00 0.00 0.00 0.0

CountyTRINITY
Highway SH0019
From VARIOUS HIGHWAYS IN
To TRINITY COUNTY
CSJ 6267-80-001
Proj ID RMC - 626780001
Work Type CLEAN DITCHES AND CULVERTS
 
0.100 224450.00 94447.09 195137.10 86.9
Work Order 04-10-14
Work Began 04-21-14
Work Completed  
Time Computed 04-21-14
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 42
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01141104
Totals 224450.00 94447.09 195137.10 86.9