Monthly Local Let Maintenance Report For Lufkin District As Of Nov 9, 2016 Page 2 Of 6

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyANGELINA
Highway US0059
From US 59 AT
To SB DIRECTO CONNECTOR
CSJ 6280-65-001
Proj ID BPM - 628065001
Work Type BEARING REPAIRS
 
0.010 95950.00 0.00 91800.00 95.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-27-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 10
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 40
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06151102
Totals 95950.00 0.00 91800.00 95.6

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS IN
To ANGELINA COUNTY
CSJ 6282-01-001
Proj ID RMC - 628201001
Work Type TREE REMOVAL / TREE & BRUSH TRIMMING
 
0.010 248800.00 29880.00 273764.00 99.9
Work Order 00-00-00
Work Began 02-23-15
Work Completed  
Time Computed 02-23-15
Contract Working Days 200
Addl Days Granted 60
Working Days Charged 108
Percent Time Used 41
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6282-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151116
Totals 248800.00 29880.00 273764.00 99.9

CountyHOUSTON
Highway US0287
From VARIOUS LOCATIONS IN
To HOUSTON COUNTY
CSJ 6282-70-001
Proj ID RMC - 628270001
Work Type GUARD FENCE, ATTENUATOR & MTL RAIL REPAI
 
0.010 232925.00 0.00 34995.00 15.0
Work Order 04-27-15
Work Began 08-17-15
Work Completed  
Time Computed 05-01-15
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 5
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6282-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03151117
Totals 232925.00 0.00 34995.00 15.0

CountyHOUSTON
Highway US0287
From VARIOUS LOCATIONS IN THE
To HOUSTON COUNTY MAINTENANCE AREA
CSJ 6283-69-001
Proj ID RMC - 628369001
Work Type TREE REMOVAL / TREE TRIMMING / BRUSH CONTROL
 
0.010 167011.00 0.00 167151.00 99.9
Work Order 09-10-15
Work Began 09-01-15
Work Completed  
Time Computed 09-10-15
Contract Working Days 120
Addl Days Granted 200
Working Days Charged 53
Percent Time Used 16
Contractor(s)
L & M CLEANING SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6283-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05151103
Totals 167011.00 0.00 167151.00 99.9

CountyTRINITY
Highway FM0358
From LOCATIONS ALONG FM 358, FM 2262 AND
To FM 2501 IN THE TRINITY MAINTENANCE SECT
CSJ 6286-69-001
Proj ID RMC - 628669001
Work Type CLEAN DITCHES AND CULVERTS
 
0.010 217560.00 22880.79 200894.79 92.3
Work Order 09-17-15
Work Began 09-01-15
Work Completed  
Time Computed 09-21-15
Contract Working Days 40
Addl Days Granted 30
Working Days Charged 34
Percent Time Used 48
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05151101
Totals 217560.00 22880.79 200894.79 92.3

CountyPOLK
Highway US0059
From VARIOUS LOCATIONS IN
To POLK COUNTY
CSJ 6288-65-001
Proj ID RMC - 628865001
Work Type GUARD FENCE, ATTENUATOR & MTL RAIL REPR
 
0.010 199473.00 8280.00 53769.00 26.9
Work Order 05-09-16
Work Began 05-16-16
Work Completed  
Time Computed 05-16-16
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 10
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6288-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03161101
Totals 199473.00 8280.00 53769.00 26.9

CountySAN AUGUSTINE
Highway US0096
From VARIOUS LOCATIONS WITHIN
To SAN AUGUSTINE COUNTY
CSJ 6288-67-001
Proj ID SUP - 628867001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 64079.08 3768.22 44270.68 69.0
Work Order 09-01-15
Work Began 09-01-15
Work Completed  
Time Computed 09-01-15
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 67
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6288-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151136
Totals 64079.08 3768.22 44270.68 69.0

CountySAN JACINTO
Highway US0059
From VARIOUS LOCATIONS WITHIN
To SAN JACINTO COUNTY
CSJ 6289-62-001
Proj ID SUP - 628962001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 71869.24 5767.58 75007.11 99.9
Work Order 09-01-15
Work Began 09-08-15
Work Completed  
Time Computed 09-01-15
Contract Working Days 190
Addl Days Granted 30
Working Days Charged 211
Percent Time Used 95
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6289-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151137
Totals 71869.24 5767.58 75007.11 99.9

CountyTRINITY
Highway US0287
From VARIOUS LOCATIONS IN
To IN TRINITY COUNTY
CSJ 6290-02-001
Proj ID RMC - 629002001
Work Type GUARD FENCE, ATTENUATOR & MTL RAIL REPR
 
0.010 142795.00 0.00 37650.00 26.3
Work Order 00-00-00
Work Began 10-28-15
Work Completed  
Time Computed 10-28-15
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 5
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6290-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09151106
Totals 142795.00 0.00 37650.00 26.3

CountySAN JACINTO
Highway US0059
From VARIOUS LOCATIONS IN
To SAN JACINTO COUNTY
CSJ 6290-78-001
Proj ID SUP - 629078001
Work Type LANDSCAPE, PICNIC & GROUNDS MAINTENANCE
 
0.010 76022.25 7668.75 70391.25 92.5
Work Order 12-07-15
Work Began 12-08-15
Work Completed  
Time Computed 12-07-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 330
Percent Time Used 90
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6290-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11151130
Totals 76022.25 7668.75 70391.25 92.5

CountyHOUSTON
Highway US0287
From VARIOUS LOCATIONS IN
To HOUSTON COUNTY
CSJ 6290-89-001
Proj ID SUP - 629089001
Work Type PICNIC, GROUNDS & TRAF ISLAND MAINT
 
0.010 80230.80 4427.29 57159.00 71.2
Work Order 12-02-15
Work Began 12-03-15
Work Completed  
Time Computed 12-02-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 334
Percent Time Used 91
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6290-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11151131
Totals 80230.80 4427.29 57159.00 71.2

CountyANGELINA
Highway US0069
From VARIOUS LOCATIONS IN THE
To ANGELINA COUNTY MAINTENANCE SECTION
CSJ 6291-44-001
Proj ID RMC - 629144001
Work Type TREE TRIM & BRUSH REMOVAL / TREE REMOVAL
 
0.010 188111.32 0.00 7000.00 3.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-29-16
Work Began 10-04-16
Work Completed  
Time Computed 10-04-16
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 37
Contractor(s)
DRC EMERGENCY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12151101
Totals 188111.32 0.00 7000.00 3.7

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS IN
To ANGELINA COUNTY
CSJ 6292-77-001
Proj ID RMC - 629277001
Work Type HIGH EDGE REMOVAL
 
0.010 188000.00 0.00 73700.00 39.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-06-16
Work Began 09-19-16
Work Completed  
Time Computed 09-15-16
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 70
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03161102
Totals 188000.00 0.00 73700.00 39.2

CountyANGELINA
Highway US0069
From VARIOUS LOCATIONS IN
To ANGELINA COUNTY
CSJ 6293-19-001
Proj ID RMC - 629319001
Work Type CLEAN DITCHES AND CULVERTS
 
0.010 212807.00 157031.03 198689.33 93.3
Work Order 12-22-15
Work Began 09-23-16
Work Completed  
Time Computed 09-23-16
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 67
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12151103
Totals 212807.00 157031.03 198689.33 93.3

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS IN
To LUFKIN DISTRICT
CSJ 6293-21-001
Proj ID RMC - 629321001
Work Type DISTRICT WIDE THERMOPLASTIC STRIPING
 
0.001 245685.00 110466.44 348890.23 99.9
Work Order 00-00-00
Work Began 04-25-16
Work Completed  
Time Computed 04-25-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 190
Percent Time Used 52
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6293-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10151102
Totals 245685.00 110466.44 348890.23 99.9

CountyANGELINA
Highway US0059
From DISTRICT WIDE IN
To LUFKIN DISTRICT
CSJ 6293-23-001
Proj ID RMC - 629323001
Work Type DIST WIDE TRAFFIC SIGNAL MAINT
 
0.001 359657.60 8057.56 17663.99 4.9
Work Order 03-22-16
Work Began 04-12-16
Work Completed  
Time Computed 04-12-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 214
Percent Time Used 58
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10151104
Totals 359657.60 8057.56 17663.99 4.9

CountyNACOGDOCHES
Highway US0059
From VARIOUS LOCATIONS WITHIN
To NACOGDOCHES COUNTY
CSJ 6293-53-001
Proj ID SUP - 629353001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 91371.15 8504.05 70680.41 77.3
Work Order 09-01-15
Work Began 09-01-15
Work Completed  
Time Computed 09-01-15
Contract Working Days 190
Addl Days Granted 30
Working Days Charged 144
Percent Time Used 65
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6293-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151133
Totals 91371.15 8504.05 70680.41 77.3

CountySAN JACINTO
Highway US0059
From SAN JACINTO COUNTY
To MAINTENANCE OFFICE
CSJ 6294-12-001
Proj ID SUP - 629412001
Work Type JANITORIAL MAINTENANCE
 
0.010 10858.41 0.00 10858.41 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-15
Work Began 09-01-15
Work Completed  
Time Computed 09-01-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 357
Percent Time Used 97
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6294-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09151136
Totals 10858.41 0.00 10858.41 99.9

CountySABINE
Highway US0096
From VARIOUS LOCATIONS IN
To SABINE COUNTY MAINTENANCE AREA
CSJ 6294-37-001
Proj ID RMC - 629437001
Work Type ROW MOWING AND LITTER CONTROL
 
0.010 144435.63 39896.93 111439.24 77.1
Work Order 05-27-16
Work Began 06-01-16
Work Completed  
Time Computed 06-01-16
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 153
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6294-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05161102
Totals 144435.63 39896.93 111439.24 77.1

CountySHELBY
Highway US0059
From VARIOUS LOCATIONS IN THE SHELBY COUNTY
To MAINTENANCE AREA
CSJ 6294-38-001
Proj ID RMC - 629438001
Work Type MOWING OF ROW AND LITTER REMOVAL
 
0.010 164306.04 0.00 162825.35 99.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-15-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 1
Working Days Charged 55
Percent Time Used 177
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6294-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05161103
Totals 164306.04 0.00 162825.35 99.0