| AVERAGE LOW BID UNIT PRICE - MAINTENANCE - LUFKIN DISTRICT | ||||
| Last Update: Thursday, October 8, 2009 |
| ITEMS 500 2001 TO 545 2003 |
| Items | Items | Bid Code Range |
|---|---|---|
| 0100 - 0169 0340 - 0340 0400 - 0496 0500 - 0545 0610 - 0690 0712 - 0788 |
6266 - 6266 7126 - 7210 |
500 2001 - 545 2003 |
| Item No | Description | Units | Septembe 30, 2009 | Twelve Month Moving | Usage | ||
|---|---|---|---|---|---|---|---|
| Quantity | Avg Bid | Quantity | Avg Bid | ||||
| 500 2001 | MOBILIZATION | LS | 7.000 | 10,432.80286 | 7 | ||
| 502 2001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 17.000 | 2,144.11765 | 6 | ||
| 506 2024 | BACKHOE WORK (EROSION & SEDM CONT) | HR | 2.000 | 35.00000 | 1 | ||
| 506 2034 | TEMPORARY SEDIMENT CONTROL FENCE | LF | 800.000 | 4.84375 | 4 | ||
| 529 2010 | CONC CURB AND GUTTER (TY II) (REINF) | LF | 450.000 | 29.00000 | 1 | ||
| 529 2037 | CONC CURB (TY II) (REINF) | LF | 150.000 | 20.00000 | 1 | ||
| 540 2001 | MTL W - BEAM GD FEN (TIM POST) | LF | 2,225.000 | 16.62921 | 3 | ||
| 540 2010 | TRANSITION ADJUSTMENT | EA | 1.000 | 500.00000 | 1 | ||
| 540 2011 | MTL BEAM GD FEN TRANS (THRIE - BEAM) | EA | 23.000 | 1,116.30435 | 5 | ||
| 540 2013 | MTL BEAM GD FEN TRANS (T101) | EA | 32.000 | 752.50000 | 3 | ||
| 540 2015 | MTL W - BEAM GD FEN (TIM POST) RADIUS RAIL | LF | 50.000 | 17.00000 | 1 | ||
| 540 2030 | MTL BEAM GD FEN (MOVE AND RESET) | LF | 325.000 | 6.15385 | 2 | ||
| 542 2001 | REMOVING METAL BEAM GUARD FENCE | LF | 4,523.000 | 1.93666 | 4 | ||
| 542 2002 | REMOVING TERMINAL ANCHOR SECTION | EA | 8.000 | 100.00000 | 1 | ||
| 544 2002 | GUARDRAIL END TREATMENT (MOVE & RESET) | EA | 5.000 | 580.00000 | 2 | ||
| 544 2006 | GDRAIL END TRT (INST) (WOOD POST) (TY III | EA | 33.000 | 2,000.00000 | 3 | ||
| 545 2001 | CRASH CUSH ATTEN (INSTL) | EA | 3.000 | 3,500.00000 | 2 | ||
| 545 2003 | CRASH CUSH ATTEN (REMOVE) | EA | 2.000 | 250.00000 | 2 | ||
| | ||||
|