AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - LUFKIN DISTRICT
ITEMS 100 6002 TO 192 6006 |
Items | Items | Bid Code Range |
---|---|---|
0100 - 0192 0204 - 0276 0310 - 0354 0400 - 0496 0500 - 0560 0610 - 0688 | 3002 - 3002 4108 - 4108 5001 - 5093 6001 - 6185 7179 - 7180 | 100 6002 - 192 6006 |
Item No | Description | Units | March 31, 2019 | Twelve-Month-Moving | Usage | ||
---|---|---|---|---|---|---|---|
Quantity | Avg Bid | Quantity | Avg Bid | ||||
100 6002 | PREPARING ROW | STA | 416.600 | 343.35094 | 2,909.590 | 542.86231 | 15 |
103 6001 | DISPOSAL OF WATER WELLS | EA | 1.000 | 4,914.86000 | 1 | ||
104 6001 | REMOVING CONC (PAV) | SY | 24,046.000 | 20.16368 | 4 | ||
104 6009 | REMOVING CONC (RIPRAP) | SY | 266.000 | 13.48421 | 4 | ||
104 6011 | REMOVING CONC (MEDIANS) | SY | 408.000 | 20.00000 | 1 | ||
104 6015 | REMOVING CONC (SIDEWALKS) | SY | 87.000 | 15.00000 | 1 | ||
104 6017 | REMOVING CONC (DRIVEWAYS) | SY | 4,442.000 | 14.13637 | 6 | ||
104 6021 | REMOVING CONC (CURB) | LF | 2,124.000 | 12.50000 | 2,124.000 | 12.50000 | 1 |
104 6022 | REMOVING CONC (CURB AND GUTTER) | LF | 282.000 | 9.29362 | 2 | ||
104 6023 | REMOVING CONC (CTB) | LF | 60.000 | 10.00000 | 1 | ||
104 6024 | REMOVING CONC (RETAINING WALLS) | SY | 4.000 | 100.00000 | 1 | ||
104 6025 | REMOVE CONC (WINGWALL) | CY | 2.000 | 500.00000 | 1 | ||
104 6028 | REMOVING CONC (MISC) | SY | 94.000 | 20.00000 | 1 | ||
104 6032 | REMOVING CONC (WHEELCHAIR RAMP) | SY | 79.000 | 15.00000 | 1 | ||
104 6036 | REMOVING CONC (SIDEWALK OR RAMP) | SY | 1,217.000 | 12.01972 | 2 | ||
104 6040 | REMOVING CONC (PAVERS) | SY | 74.000 | 19.21622 | 2 | ||
104 6041 | REMOVING CONC (GND BOX W/ APRON) | EA | 2.000 | 230.00000 | 1 | ||
104 6054 | REMOVING CONCRETE(MOW STRIP) | LF | 101.000 | 5.00000 | 1 | ||
105 6008 | REMOVING STAB BASE AND ASPH PAV (6") | SY | 2,222.000 | 4.28000 | 1 | ||
105 6011 | REMOVING STAB BASE AND ASPH PAV (2"-6" | SY | 973.000 | 8.00000 | 1 | ||
105 6016 | REMOVING STAB BASE & ASPH PAV(16") | SY | 4,002.000 | 10.75000 | 4,002.000 | 10.75000 | 1 |
105 6020 | REMOVING STAB BASE & ASPH PAV (12") | SY | 9,457.000 | 3.10000 | 1 | ||
105 6045 | REMOVING STAB BASE AND ASPH PAV (2"-8" | SY | 1,108.000 | 3.75000 | 1 | ||
105 6046 | REMOVING STAB BASE & ASPH PAV (0"-10") | SY | 1,200.000 | 15.00000 | 1 | ||
106 6002 | OBLITERATING ABANDONED ROAD | SY | 412.000 | 36.00000 | 412.000 | 36.00000 | 1 |
110 6001 | EXCAVATION (ROADWAY) | CY | 568,348.000 | 4.59802 | 7 | ||
112 6001 | SUBGRADE WIDENING (ORD COMP) | STA | 28.100 | 860.00000 | 1,190.300 | 270.17979 | 6 |
132 6002 | EMBANKMENT (FINAL)(DENS CONT)(TY A) | CY | 56,965.000 | 9.80000 | 1 | ||
132 6003 | EMBANKMENT (FINAL)(ORD COMP)(TY B) | CY | 36,428.000 | 4.98969 | 4 | ||
132 6004 | EMBANKMENT (FINAL)(DENS CONT)(TY B) | CY | 613,686.000 | 5.00254 | 2 | ||
132 6019 | EMBANKMENT (VEHICLE)(ORD COMP)(TY B) | CY | 717.000 | 19.92469 | 38,829.000 | 10.76279 | 16 |
134 6002 | BACKFILL (TY B) | STA | 1,433.900 | 183.64772 | 4 | ||
150 6001 | BLADING | STA | 2.500 | 1,025.00000 | 1,336.260 | 83.71794 | 6 |
158 6003 | SPEC EXCAV WORK (HYD EXCAVATOR) | HR | 45.000 | 147.33333 | 1,565.000 | 128.22684 | 15 |
160 6003 | FURNISHING AND PLACING TOPSOIL (4") | SY | 940,863.000 | 1.03077 | 6 | ||
161 6017 | COMPOST MANUF TOPSOIL (4") | SY | 184,657.000 | 1.05000 | 1 | ||
162 6002 | BLOCK SODDING | SY | 3,230.000 | 4.33100 | 61,278.000 | 4.73562 | 19 |
164 6001 | BROADCAST SEED (PERM) (RURAL) (SANDY) | SY | 76,015.000 | .16533 | 2 | ||
164 6003 | BROADCAST SEED (PERM) (RURAL) (CLAY) | SY | 2,025.000 | 1.59506 | 2 | ||
164 6009 | BROADCAST SEED (TEMP) (WARM) | SY | 10,716.000 | .27627 | 453,481.000 | .11094 | 17 |
164 6011 | BROADCAST SEED (TEMP) (COOL) | SY | 10,716.000 | .27627 | 453,480.000 | .11108 | 17 |
164 6021 | CELL FBR MLCH SEED(PERM)(RURAL)(SANDY) | SY | 4,000.000 | .57000 | 2,720,626.000 | .28276 | 17 |
164 6023 | CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) | SY | 103,300.000 | .29000 | 1 | ||
164 6025 | CELL FBR MLCH SEED(PERM)(URBAN)(SANDY) | SY | 17,432.000 | .31000 | 17,432.000 | .31000 | 1 |
164 6029 | CELL FBR MLCH SEED(TEMP)(WARM) | SY | 917,694.000 | .26464 | 3 | ||
164 6031 | CELL FBR MLCH SEED(TEMP)(COOL) | SY | 917,694.000 | .26464 | 3 | ||
164 6071 | BROADCAST SEED (TEMP)(WARM OR COOL) | SY | 4,891.000 | .30000 | 1 | ||
168 6001 | VEGETATIVE WATERING | MG | 917.500 | 8.70096 | 60,008.400 | 12.50483 | 26 |
169 6001 | SOIL RETENTION BLANKETS (CL 1) (TY A) | SY | 40,749.000 | 1.19211 | 5 | ||
169 6002 | SOIL RETENTION BLANKETS (CL 1) (TY B) | SY | 1,634.000 | 1.40000 | 31,992.000 | 1.39763 | 7 |
169 6003 | SOIL RETENTION BLANKETS (CL 1) (TY C) | SY | 9,221.000 | 1.11584 | 2 | ||
169 6004 | SOIL RETENTION BLANKETS (CL 1) (TY D) | SY | 7,304.000 | 1.83472 | 4 | ||
169 6006 | SOIL RETENTION BLANKETS (CL 2) (TY F) | SY | 90.000 | 10.00000 | 1 | ||
170 6003 | IRRIGATION SYSTEM (TY II) | LS | 1.000 | 230,000.00000 | 1 | ||
180 6001 | WILDFLOWER SEEDING | AC | 293.030 | 795.00000 | 1 | ||
192 6002 | PLANT MATERIAL (1-GAL) | EA | 107.000 | 15.25000 | 1 | ||
192 6004 | PLANT MATERIAL (5-GAL) | EA | 45.000 | 56.00000 | 1 | ||
192 6005 | PLANT MATERIAL (15-GAL) | EA | 75.000 | 450.00000 | 1 | ||
192 6006 | PLANT MATERIAL (30-GAL) | EA | 17.000 | 1,300.00000 | 1 |