Monthly State Let Maintenance Report For Lubbock District As Of May 15, 2013 Page 1 Of 1

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLUBBOCK
Highway IH0027
From LUBBOCK COUNTY
To SWISHER COUNTY
CSJ 6192-17-001
Proj ID RMC - 619217001
Work Type STREET SWEEPING
 
0.001 373646.56 18377.80 693115.78 99.9
Work Order 12-04-09
Work Began 12-11-09
Work Completed  
Time Computed 12-11-09
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 299
Percent Time Used 40
Contractor(s)
MIJELUM
SUBCONTRACTOR(S) FOR CCSJ: 6192-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10094010
Totals 373646.56 18377.80 693115.78 99.9

CountyLUBBOCK
Highway IH0027
From LOOP 289
To IH 0027
CSJ 6195-87-001
Proj ID RMC - 619587001
Work Type ROADSIDE MAINTENANCE
 
0.001 328264.00 0.00 240231.00 73.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-15-09
Work Began 01-19-10
Work Completed  
Time Computed 12-22-09
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 709
Percent Time Used 97
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6195-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10094003
Totals 328264.00 0.00 240231.00 73.4

CountyCASTRO
Highway US0060
From CASTRO COUNTY
To PARMER COUNTY
CSJ 6210-74-001
Proj ID RMC - 621074001
Work Type MOWING THE RIGHT OF WAY
 
0.001 252973.60 0.00 189730.20 75.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-28-11
Work Began 11-28-11
Work Completed  
Time Computed 12-05-11
Contract Working Days 104
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 10
Contractor(s)
JAMESON MOWING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6210-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08104002
Totals 252973.60 0.00 189730.20 75.0

CountyHALE
Highway IH0027
From HALE COUNTY
To SWISHER COUNTY
CSJ 6210-75-001
Proj ID RMC - 621075001
Work Type MOWING THE RIGHT OF WAY
 
0.001 471641.28 0.00 352779.69 75.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-20-11
Work Began 11-01-11
Work Completed  
Time Computed 11-01-11
Contract Working Days 161
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 36
Contractor(s)
BILLY BENSON
SUBCONTRACTOR(S) FOR CCSJ: 6210-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08104003
Totals 471641.28 0.00 352779.69 75.0

CountyBAILEY
Highway SH0214
From BAILEY COUNTY
To COCHRAN COUNTY
CSJ 6210-76-001
Proj ID RMC - 621076001
Work Type PLANS ARE REQUIRED FOR THIS PROJECT
 
0.001 283389.60 0.00 216919.62 76.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-23-11
Work Began 09-26-11
Work Completed  
Time Computed 10-03-11
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 21
Contractor(s)
BILLY BENSON
SUBCONTRACTOR(S) FOR CCSJ: 6210-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08104004
Totals 283389.60 0.00 216919.62 76.5

CountyHOCKLEY
Highway US0385
From HOCKLEY COUNTY
To LAMB COUNTY
CSJ 6210-77-001
Proj ID RMC - 621077001
Work Type MOWING THE RIGHT OF WAY
 
0.001 270403.84 0.00 207944.64 76.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-11-11
Work Began 10-12-11
Work Completed  
Time Computed 10-19-11
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 48
Percent Time Used 44
Contractor(s)
LUBBOCK LAWN SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6210-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08104005
Totals 270403.84 0.00 207944.64 76.9

CountyCROSBY
Highway US0062
From CROSBY COUNTY
To FLOYD COUNTY
CSJ 6210-78-001
Proj ID RMC - 621078001
Work Type MOWING THE RIGHT OF WAY
 
0.001 287320.40 0.00 215490.30 75.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-10-11
Work Began 10-17-11
Work Completed  
Time Computed 10-17-11
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 26
Contractor(s)
BILLY BENSON
SUBCONTRACTOR(S) FOR CCSJ: 6210-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08104010
Totals 287320.40 0.00 215490.30 75.0

CountyTERRY
Highway US0380
From TERRY COUNTY
To YOAKUM COUNTY
CSJ 6210-80-001
Proj ID RMC - 621080001
Work Type MOWING THE RIGHT OF WAY
 
0.001 220080.93 0.00 165226.41 75.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-27-11
Work Began 11-07-11
Work Completed  
Time Computed 11-07-11
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 43
Contractor(s)
LUBBOCK LAWN SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6210-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08104012
Totals 220080.93 0.00 165226.41 75.0

CountyDAWSON
Highway US0180
From DAWSON COUNTY
To GAINES COUNTY
CSJ 6210-81-001
Proj ID RMC - 621081001
Work Type MOWING THE RIGHT OF WAY
 
0.001 290043.66 0.00 221306.03 76.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-27-11
Work Began 11-09-11
Work Completed  
Time Computed 11-09-11
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 25
Contractor(s)
JAMESON MOWING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6210-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08104013
Totals 290043.66 0.00 221306.03 76.3

CountyGARZA
Highway US0380
From DAWSON COUNTY
To LYNN COUNTY
CSJ 6210-82-001
Proj ID RMC - 621082001
Work Type MOWING THE RIGHT OF WAY
 
0.001 244768.04 0.00 183644.52 75.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-31-11
Work Began 11-14-11
Work Completed  
Time Computed 11-14-11
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 31
Contractor(s)
BILLY BENSON
SUBCONTRACTOR(S) FOR CCSJ: 6210-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08104014
Totals 244768.04 0.00 183644.52 75.0

CountyLUBBOCK
Highway LP0289
From VARIOUS
To VARIOUS
CSJ 6218-22-001
Proj ID RMC - 621822001
Work Type GUARDRAIL INSTALL, REPAIR, REPLACEMENT
 
0.001 490795.00 22209.00 672709.00 99.9
Work Order 01-31-11
Work Began 02-07-11
Work Completed  
Time Computed 02-07-11
Contract Working Days 730
Addl Days Granted 730
Working Days Charged 814
Percent Time Used 55
Contractor(s)
T & L CLEANING SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6218-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12104003
Totals 490795.00 22209.00 672709.00 99.9

CountyLUBBOCK
Highway US0084
From VARIOUS LOCATIONS
To LUBBOCK DISTRICT
CSJ 6230-53-001
Proj ID RMC - 623053001
Work Type REMOVE AND REPLACE SPEED LIMIT SIGNS
 
0.010 321410.00 0.00 101550.00 31.5
CountyLUBBOCK
Highway US0084
From VARIOUS LOCATIONS
To AMARILLO DISTRICT
CSJ 6230-53-002
Proj ID RMC - 623053002
Work Type REMOVE AND REPLACE SPEED LIMIT SIGNS
 
0.010 101251.00 0.00 56920.00 56.2
CountyLUBBOCK
Highway US0084
From VARIOUS LOCATIONS
To CHILDRESS DISTRICT
CSJ 6230-53-003
Proj ID RMC - 623053003
Work Type REMOVE AND REPLACE SPEED LIMIT SIGNS
 
0.010 111020.00 0.00 81045.00 73.0
CountyLUBBOCK
Highway US0084
From VARIOUS LOCATIONS
To ODESSA DISTRICT
CSJ 6230-53-004
Proj ID RMC - 623053004
Work Type REMOVE AND REPLACE SPEED LIMIT SIGNS
 
0.010 179752.00 0.00 103800.00 57.7
CountyLUBBOCK
Highway US0084
From VARIOUS LOCATIONS
To ABILENE DISTRICT
CSJ 6230-53-005
Proj ID RMC - 623053005
Work Type REMOVE AND REPLACE SPEED LIMIT SIGNS
 
0.010 95870.00 0.00 78369.00 81.7
CountyLUBBOCK
Highway US0084
From VARIOUS LOCATIONS
To EL PASO DISTRICT
CSJ 6230-53-006
Proj ID RMC - 623053006
Work Type REMOVE AND REPLACE SPEED LIMIT SIGNS
 
0.010 72039.00 0.00 27190.00 37.7
CountyLUBBOCK
Highway US0084
From VARIOUS LOCATIONS
To SAN ANGELO DISTRICT
CSJ 6230-53-007
Proj ID RMC - 623053007
Work Type REMOVE AND REPLACE SPEED LIMIT SIGNS
 
0.010 195970.00 0.00 47810.00 24.3
Work Order 10-03-11
Work Began 10-10-11
Work Completed  
Time Computed 10-10-11
Contract Working Days 273
Addl Days Granted 0
Working Days Charged 204
Percent Time Used 74
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6230-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08114028
Totals 1077312.00 0.00 496684.00 46.1

CountyGAINES
Highway FM3306
From VARIOUS
To VARIOUS
CSJ 6250-90-001
Proj ID RMC - 625090001
Work Type DIST. SEAL COAT
 
40.214 1180052.26 69700.00 131010.00 11.1
Work Order 03-14-13
Work Began 03-14-13
Work Completed  
Time Computed 05-15-13
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6250-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12124002
Totals 1180052.26 69700.00 131010.00 11.1

CountyPARMER
Highway SH0086
From VARIOUS LOCATIONS IN PARMER
To AND SWISHER COUNTIES
CSJ 6252-75-001
Proj ID BPM - 625275001
Work Type BRIDGE PREVENTIVE MAINTENANCE
 
0.451 773396.63 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6252-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05134011
Totals 773396.63 0.00 0.00 0.0

CountyLUBBOCK
Highway IH0027
From KUEKA ST IN LUBBOCK
To RANDALL COUNTY LINE
CSJ 6253-46-001
Proj ID RMC - 625346001
Work Type ELECTRICAL WORK, LUMINAIRES AND LUMINAIR
 
0.001 424144.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 609
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05134021
Totals 424144.00 0.00 0.00 0.0

CountyLUBBOCK
Highway FM2255
From VARIOUS LOCATIONS IN LUBBOCK AND
To HOCKLEY COUNTIES
CSJ 6253-47-001
Proj ID RMC - 625347001
Work Type MILLING, SEAL COAT, HOT MIX INLAY
 
1.400 887213.45 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04134002
Totals 887213.45 0.00 0.00 0.0

CountyLUBBOCK
Highway FM0789
From VARIOUS LOCATIONS IN THE LUBBOCK
To DISTRICT
CSJ 6254-43-001
Proj ID RMC - 625443001
Work Type STRIPING AND SPECIALTY MARKINGS
 
0.001 561832.14 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6254-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04134019
Totals 561832.14 0.00 0.00 0.0