| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | LUBBOCK |
| Highway |
US0084 |
| From |
LUBBOCK BUILDING MAINTENANCE |
| To |
LUBBOCK BUILDING MAINTENANCE |
| CSJ |
6180-75-001 |
| Proj ID |
SUP - 618075001 |
| Work Type |
GROUNDS MAINTENANCE |
| |
|
0.001 |
2970.00 |
50.00 |
638.00 |
21.4 |
| Work Order |
08-22-08 |
| Work Began |
09-01-08 |
| Work Completed |
|
| Time Computed |
09-01-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
91 |
| Percent Time Used |
24 |
| Contractor(s) |
TIBH INDUSTRIES, INC. MARIAN MOSS ENTERPRISES |
SUBCONTRACTOR(S) FOR CCSJ: 6180-75-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08080519 |
|
Totals |
2970.00 |
50.00 |
638.00 |
21.4 |
|
| County | LUBBOCK |
| Highway |
US0084 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6180-76-001 |
| Proj ID |
SUP - 618076001 |
| Work Type |
VEHICLE WASHING |
| |
|
0.001 |
16410.00 |
196.00 |
397.70 |
2.4 |
| Work Order |
08-22-08 |
| Work Began |
09-01-08 |
| Work Completed |
|
| Time Computed |
09-01-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
61 |
| Percent Time Used |
16 |
| Contractor(s) |
TIBH INDUSTRIES, INC. MARIAN MOSS ENTERPRISES |
SUBCONTRACTOR(S) FOR CCSJ: 6180-76-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08080520 |
|
Totals |
16410.00 |
196.00 |
397.70 |
2.4 |
|