Monthly Local Let Maintenance Report For Lubbock District As Of May 10, 2023 Page 3 Of 3
Last Update: Tuesday, June 13, 2023
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | LUBBOCK |
Highway | IH0027 |
From | VARIOUS LOCATIONS |
To | VARIOUS LOCATIONS |
CSJ | 6422-87-001 |
Proj ID | SUP - 642287001 |
Work Type | LITTER REMOVAL |
|
| 0.010 | 507834.00 | | 162652.00 | 32.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-14-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 224 |
Percent Time Used | 61 |
Contractor(s) |
WORKQUEST MARIAN MOSS ENTERPRISES |
SUBCONTRACTOR(S) FOR CCSJ: 6422-87-001 MARIAN MOSS ENTERPRISES (0.00)
|
Contract # | 09220531 |
| Totals | 507834.00 | 10091.00 | 162652.00 | 32.0 |
|