Monthly State Let Construction Report For Houston District As Of Apr 7, 2016 Page 15 Of 15

Last Update: Thursday, April 7, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14 | page 15

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway BW 8
From AT MYKAWA AND SFRR
To .
CSJ 3256-04-061
Proj ID NH 1402(198)
Work Type STRS, GR, BASE AND PAVEMENT
 
1.040 10329185.50 634585.16 7226833.45 69.9
Work Order 10-17-14
Work Began 03-17-15
Work Completed  
Time Computed 11-02-14
Contract Working Days 282
Addl Days Granted 0
Working Days Charged 221
Percent Time Used 78
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3256-04-061
LONE STAR TRAFFIC SERVICE, INC.(0.16%)
BELL BOTTOM FOUNDATION CO. (4.88%)
SCOTT DERR PAINTING CO, LLC(0.39%)
A-1 EROSION CONTROL, LLC (0.66%)
MESA ROD BUSTERS, INC. (3.41%)
FOSTER FENCE, LTD. (0.41%)
PRIMATE CONSTRUCTION, INC. (0.34%)
WILLOW CITY SIGN & RAIL, INC.(1.67%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (3.97%)
STORM WATER SOLUTIONS, LP(0.01%)
PROFESSIONAL TRAFFIC CONTROL, LLC(0.42%)
GMJ PAVING CO. (0.65%)
DORAN STEEL, INC.(0.47%)
Contract # 08143037
Totals 10329185.50 634585.16 7226833.45 69.9

CountyHARRIS
Highway FM 270
From HENDERSON ST
To HARRIS COUNTY LINE
CSJ 3312-01-008
Proj ID CM 2013(571)
Work Type BICYCLE / PEDESTRIAN IMPROVEMENTS
 
1.136 3845442.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-08-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 3312-01-008
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153027
Totals 3845442.26 0.00 0.00 0.0

CountyHARRIS
Highway SH 99
From 0.490 MI N OF KINGSLAND BLVD
To 0.120 MI S OF COLONIAL PKWY
CSJ 3510-05-010
Proj ID C 3510-5-10
Work Type GR, STRS, BASE AND PAVEMENT
 
0.896 17265149.66 0.00 17484591.85 100.0
CountyHARRIS
Highway SH 99
From AT IH 10 (W)
To N OF COLONIAL PKWY
CSJ 3510-05-018
Proj ID NH 1102(439)
Work Type CONSTRUCT 2 DIRECT CONNECTORS
 
0.436 32174192.92 0.00 32222210.51 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-15-11
Work Began 09-23-11
Work Completed 11-10-14
Time Computed 10-01-11
Contract Working Days 598
Addl Days Granted 0
Working Days Charged 598
Percent Time Used 100
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 3510-05-018
SCOTT DERR PAINTING CO, LLC(0.84%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.54%)
BASE CONSTRUCTION, L.L.P.(3.00%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.18%)
AMERICAN DRAINAGE SYSTEM, INC. (0.16%)
WILLOW CITY SIGN & RAIL, INC.(0.56%)
MESA ROD BUSTERS, INC. ( 13.52%)
BORTUNCO (0.16%)
BATTERSON,LLP(0.34%)
CREACOM, INC.(4.96%)
MAGNUM TUNNELING, LLC(0.11%)
SPECIALTY DRILLING, LTD. (0.19%)
URETEK USA, INC. (0.06%)
BONDED LIGHTNING PROTECTION(0.07%)
QUALITY TURF GRASS (0.15%)
Contract # 08113001
Totals 49439342.58 0.00 49706802.36 100.0

CountyHARRIS
Highway SH 99
From IH 10 (W)
To .
CSJ 3510-05-017
Proj ID NH 2012(647)
Work Type CONSTRUCT 4 DIRECT CONNECTORS
 
0.250 31203249.82 0.00 33364196.48 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-24-12
Work Began 10-22-12
Work Completed 12-09-14
Time Computed 10-10-12
Contract Working Days 362
Addl Days Granted 78
Working Days Charged 432
Percent Time Used 98
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3510-05-017
HOUSTON SAWING & DRILLING(0.06%)
BORTUNCO (0.00%)
ENVIRONMENTAL ALLIES, L.P. (0.07%)
EROSION CONTROL, INC.(0.38%)
SCOTT DERR PAINTING CO, LLC(0.90%)
GMJ PAVING CO. (0.09%)
WILLOW CITY SIGN & RAIL, INC.(0.14%)
HIGHWAY TECHNOLOGIES, INC. (0.10%)
MAGNOLIA SKIDROW MULCHING, LLC (0.00%)
MESA ROD BUSTERS, INC. (6.83%)
W. W. FOUNDATION DRILLING, LTD.(7.24%)
CREACOM, INC.(1.00%)
BATTERSON,LLP(0.12%)
CURB PLANET INC. (0.00%)
CHOCTAW ERECTORS, INC. (4.32%)
A-1 EROSION CONTROL, LLC (0.47%)
Contract # 07123203
Totals 31203249.82 0.00 33364196.48 100.0

CountyHARRIS
Highway SH 99
From S OF US 290
To US 290
CSJ 3510-05-019
Proj ID C 3510-5-19
Work Type 4 DCS
 
3.140 115670596.33 0.00 116735140.86 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-14-11
Work Began 10-03-11
Work Completed 02-18-15
Time Computed 09-30-11
Contract Working Days 691
Addl Days Granted 8
Working Days Charged 699
Percent Time Used 100
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3510-05-019
DORAN STEEL, INC.(1.09%)
KELLYSTONE, INC(0.14%)
ALLSTATE SIGNAL & CONSTRUCTION, LLC(4.41%)
RDI FOUNDATION DRILLING(4.34%)
EROSION CONTROL, INC.(0.45%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.18%)
GMJ PAVING CO. (1.32%)
WILLOW CITY SIGN & RAIL, INC.(0.79%)
HIGHWAY TECHNOLOGIES, INC. (0.22%)
ENVIRONMENTAL ALLIES, L.P. (0.03%)
WEBBER BARRIER SERVICES, INC.(1.13%)
FINE CURBS (0.01%)
CHOCTAW ERECTORS, INC. (1.54%)
BATTERSON,LLP(0.20%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.30%)
PRIMATE CONSTRUCTION, INC. (0.03%)
Contract # 07113011
Totals 115670596.33 0.00 116735140.86 100.0

CountyHARRIS
Highway SH 99
From N OF COLONIAL PKWY
To N OF MORTON RD (SEG E)
CSJ 3510-05-022
Proj ID C 3510-5-22
Work Type GR, STRS, BASE & PAV
 
1.950 32334777.01 0.00 33688969.44 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-30-11
Work Began 10-17-11
Work Completed 10-06-14
Time Computed 10-16-11
Contract Working Days 602
Addl Days Granted 0
Working Days Charged 602
Percent Time Used 100
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3510-05-022
GMJ PAVING CO. (3.09%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.23%)
BREDA COMPANY, INC.(0.56%)
GULF COAST PAVERS, INC.(0.52%)
H & H CURB COMPANY (0.04%)
CHAMPIONS HYDRO-LAWN (0.59%)
LONE STAR ROAD CONSTRUCTION, LTD.( 31.94%)
VAQUERO CONSTRUCTION, INC. (3.26%)
BATTERSON,LLP(0.65%)
CREACOM, INC.(6.17%)
LINDSEY CONSTRUCTION, INC. (7.65%)
RDI FOUNDATION DRILLING(2.21%)
VALLEY PLACERS, LLC(0.12%)
DORAN STEEL, INC.(0.26%)
SPECIALTY DRILLING, LTD. (0.38%)
MESA ROD BUSTERS, INC. (0.12%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(0.21%)
WILLOW CITY SIGN & RAIL, INC.(0.80%)
SCOTT DERR PAINTING CO, LLC(0.26%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.28%)
HOUSTON SAWING & DRILLING(0.02%)
NBG CONSTRUCTORS, INC. (0.02%)
TOM-MAC, INC.(0.29%)
ALL-TEXAS FENCE(0.06%)
Contract # 07113233
Totals 32334777.01 0.00 33688969.44 100.0

CountyHARRIS
Highway SH 99
From N OF MORTON RD
To S OF FM 529 (SEG E)
CSJ 3510-05-023
Proj ID C 3510-5-23
Work Type GR, STRS, BASE & PAV
 
8.903 122892918.02 0.00 126278551.34 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-13-11
Work Began 09-19-11
Work Completed 09-16-14
Time Computed 09-29-11
Contract Working Days 650
Addl Days Granted 1
Working Days Charged 651
Percent Time Used 100
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 3510-05-023
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.21%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.42%)
REPUBLIC TRAFFIC SAFETY, INC.(0.09%)
CUT"N SHOOT, INC.(0.13%)
BELL BOTTOM FOUNDATION CO. (3.44%)
DORAN STEEL, INC.(0.23%)
EGGEMEYER LAND CLEARING, LLC (0.12%)
ESSARY, HART & MACWILIAM,INC.(0.88%)
VAQUERO CONSTRUCTION, INC. (3.34%)
CREACOM, INC.(5.08%)
SPECIALTY DRILLING, LTD. (0.08%)
MAGNUM TUNNELING, LLC(0.08%)
EROSION CONTROL, INC.(0.90%)
SILVA CONTRACTING COMPANY, INC.(2.70%)
SOUTHERN CRUSHED CONCRETE LLC(0.07%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25%)
APCON SERVICES, LLC(0.21%)
SCOTT DERR PAINTING CO, LLC(0.27%)
CURB PLANET INC. (0.01%)
HIGHWAY TECHNOLOGIES, INC. (0.40%)
BONDED LIGHTNING PROTECTION(0.07%)
BEDO CONSTRUCTION PRODUCTS, INC. (5.51%)
PROFESSIONAL TRAFFIC CONTROL, LLC(0.36%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.34%)
KELLYSTONE, INC(0.16%)
Contract # 07113222
Totals 122892918.02 0.00 126278551.34 100.0

CountyMONTGOMERY
Highway SH 242
From EAST OF THE SAN JACINTO RIVER BR
To HICKORY ROAD
CSJ 3538-01-041
Proj ID STP 2016(963)
Work Type PLANING, BASE REP, SEAL AND ACP
 
6.360 3635039.14 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 87
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 3538-01-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163027
Totals 3635039.14 0.00 0.00 0.0

CountyMONTGOMERY
Highway SH 242
From AT FM 1485
To .
CSJ 3538-01-044
Proj ID STP 2016(722)HES
Work Type TS IMPRVMTS
 
0.500 275772.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-08-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 3538-01-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163036
Totals 275772.88 0.00 0.00 0.0

CountyHARRIS
Highway MH
From HEMPSTEAD RD AT UPRR
To WHITE OAK BAYOU
CSJ 8170-12-002
Proj ID RW 8170-12-2
Work Type ROW UTL. ADJ.; RELOC. ASSIST.
 
1.439 668395.50 0.00 1207198.54 100.0
CountyHARRIS
Highway MH
From ON WASHINGTON/HEMPSTEAD
To WASHINGTON-KATY SPLIT TO IH 10
CSJ 8170-12-006
Proj ID HP 2008(049)
Work Type GR, STRS & SURF
 
2.151 10729927.24 0.00 11444774.37 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-09-11
Work Began 07-23-12
Work Completed 04-21-15
Time Computed 04-07-12
Contract Working Days 407
Addl Days Granted 0
Working Days Charged 421
Percent Time Used 103
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 8170-12-006
KELLYSTONE, INC(0.59%)
AZTEC REMODELING AND LANDSCAPING COMPANY (0.98%)
MAGNUM TUNNELING, LLC(4.07%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(3.54%)
PRV SERVICES, INC. (5.35%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.23%)
SEMARCK LANDSCAPE SERVICES, INC. (5.37%)
PFEIFFER & SON LTD.(3.70%)
R & A BORING COMPANY (0.00%)
W. W. FOUNDATION DRILLING, LTD.(3.63%)
CURB PLANET INC. (0.04%)
C & C FENCE CORPORATION(0.75%)
MAIN LANE INDUSTRIES, LTD. (0.52%)
Contract # 10113205
Totals 11398322.74 0.00 12651972.91 100.0