| Item No |
Description |
Units |
May 31, 2013 |
Twelve Month Moving |
Usage |
| Quantity |
Avg Bid |
Quantity |
Avg Bid |
| 500 2001 |
MOBILIZATION |
LS |
4.000 |
27,750.00000 |
23.000 |
34,071.82609 |
23 |
| 502 2001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING |
MO |
11.000 |
1,595.45455 |
76.000 |
1,826.28947 |
24 |
| 506 2001 |
ROCK FILTER DAMS (INSTALL) (TY 1) |
LF |
|
|
1,050.000 |
19.04762 |
3 |
| 506 2002 |
ROCK FILTER DAMS (INSTALL) (TY 2) |
LF |
|
|
250.000 |
20.00000 |
1 |
| 506 2009 |
ROCK FILTER DAMS (REMOVE) |
LF |
|
|
1,300.000 |
6.00000 |
3 |
| 506 2034 |
TEMPORARY SEDIMENT CONTROL FENCE |
LF |
395.000 |
3.00000 |
1,290.000 |
2.80620 |
3 |
| 512 2002 |
PORT CTB (FUR & INST) (SAFETY SH) (TY 2) |
LF |
|
|
300.000 |
45.00000 |
1 |
| 512 2010 |
PORT CTB (DES SOURCE) (SAFETY SH) (TY 1) |
LF |
|
|
200.000 |
1.00000 |
1 |
| 512 2011 |
PORT CTB (DES SOURCE) (SAFETY SH) (TY 2) |
LF |
|
|
1,757.000 |
1.40979 |
6 |
| 512 2019 |
PORT CTB (MOVE) (SAFETY SH) (TY 1) |
LF |
|
|
1,440.000 |
6.00000 |
1 |
| 512 2020 |
PORT CTB (MOVE) (SAFETY SH) (TY 2) |
LF |
|
|
30,492.000 |
3.33468 |
9 |
| 512 2022 |
PORT CTB (MOVE) (SNGL SLP) (TY 1) |
LF |
|
|
675.000 |
1.00000 |
2 |
| 512 2023 |
PORT CTB (MOVE) (SNGL SLP) (TY 2) |
LF |
|
|
600.000 |
1.00000 |
2 |
| 512 2025 |
PORT CTB (MOVE) (SNGL SLP) (TY 4) |
LF |
|
|
150.000 |
1.00000 |
1 |
| 512 2028 |
PORT CTB (STKPL) (SAFETY SH) (TY 1) |
LF |
|
|
100.000 |
4.00000 |
1 |
| 512 2029 |
PORT CTB (STKPL) (SAFETY SH) (TY 2) |
LF |
|
|
932.000 |
2.64163 |
6 |
| 512 2038 |
PORT CTB (REMOVE) (SAFETY SH) (TY 2) |
LF |
|
|
795.000 |
2.50943 |
4 |
| 512 2047 |
PORT CTB (STKPL) (SAFETY SH) (TY P & P) |
LF |
|
|
120.000 |
45.00000 |
1 |
| 512 2055 |
PORT CTB (MOVE) (F - SHAPE) (TY 4) |
LF |
|
|
2,000.000 |
4.00000 |
1 |
| 512 2061 |
PORT CTB (STKPL) (SNGL SLP) (TY J - J) |
LF |
|
|
150.000 |
45.00000 |
1 |
| 514 2014 |
PERM CONC TRF BARR (SGL SLP) (TY 2) (36") |
LF |
|
|
20,821.000 |
43.00000 |
1 |
| 514 2020 |
PERM CONC TRF BARR (SGL SLP) TY 2 (36") SP |
LF |
|
|
1,220.000 |
96.00000 |
1 |
| 529 2002 |
CONC CURB (TY II) |
LF |
|
|
100.000 |
36.00000 |
1 |
| 529 2004 |
CONC CURB & GUTTER (TY II) |
LF |
|
|
1,400.000 |
37.00000 |
1 |
| 529 2005 |
CONC CURB (MONO) (TY I) |
LF |
|
|
750.000 |
3.60000 |
3 |
| 529 2006 |
CONC CURB (MONO) (TY II) |
LF |
|
|
750.000 |
4.20000 |
3 |
| 529 2007 |
CONC CURB (DOWEL) |
LF |
|
|
5,095.000 |
10.54956 |
11 |
| 530 2011 |
DRIVEWAYS (ACP) |
SY |
|
|
8,703.000 |
3.00000 |
1 |
| 531 2004 |
CONC SIDEWALKS (6") |
SY |
|
|
50.000 |
36.00000 |
1 |
| 531 2005 |
CURB RAMPS (TY 1) |
EA |
|
|
10.000 |
995.00000 |
5 |
| 531 2010 |
CURB RAMPS (TY 7) |
EA |
|
|
8.000 |
1,043.75000 |
5 |
| 531 2015 |
CONC SIDEWLKS (4") |
SY |
|
|
590.000 |
39.61017 |
5 |
| 533 2006 |
SHOULDER TEXTURING (MILLED) (ASPHALT) |
LF |
|
|
26,400.000 |
0.28000 |
1 |
| 540 2001 |
MTL W - BEAM GD FEN (TIM POST) |
LF |
475.000 |
24.00000 |
1,500.000 |
22.00000 |
4 |
| 540 2002 |
MTL W - BEAM GD FEN (STEEL POST) |
LF |
|
|
500.000 |
21.00000 |
1 |
| 540 2005 |
TERMINAL ANCHOR SECTION |
EA |
|
|
21.000 |
289.61905 |
3 |
| 540 2007 |
MTL W - BEAM GD FEN ADJUSTMENT |
LF |
|
|
100.000 |
2.00000 |
1 |
| 540 2011 |
MTL BEAM GD FEN TRANS (THRIE - BEAM) |
EA |
5.000 |
1,800.00000 |
71.000 |
1,386.14085 |
11 |
| 540 2015 |
MTL W - BEAM GD FEN (TIM POST) RADIUS RAIL |
LF |
|
|
1,200.000 |
16.00000 |
2 |
| 542 2001 |
REMOVING METAL BEAM GUARD FENCE |
LF |
560.000 |
4.00000 |
2,420.000 |
2.38843 |
8 |
| 542 2002 |
REMOVING TERMINAL ANCHOR SECTION |
EA |
1.000 |
275.00000 |
37.000 |
15.81081 |
10 |
| 544 2001 |
GUARDRAIL END TREATMENT (INSTALL) |
EA |
5.000 |
2,700.00000 |
21.000 |
2,452.38095 |
5 |
| 544 2002 |
GUARDRAIL END TREATMENT (MOVE & RESET) |
EA |
|
|
15.000 |
300.00000 |
3 |
| 544 2003 |
GUARDRAIL END TREATMENT (REMOVE) |
EA |
4.000 |
200.00000 |
18.000 |
144.44444 |
4 |
| 544 2006 |
GDRAIL END TRT (INST) (WOOD POST) (TY III |
EA |
|
|
5.000 |
2,350.00000 |
2 |
| 545 2003 |
CRASH CUSH ATTEN (REMOVE) |
EA |
|
|
2.000 |
300.00000 |
1 |
| 545 2007 |
CRASH CUSH ATTEN (INSTL) (TRACC) |
EA |
|
|
2.000 |
7,500.00000 |
1 |
| 545 2022 |
CRASH CUSH ATTEN (INSTL) (REACT) (N) |
EA |
|
|
1.000 |
20,000.00000 |
1 |
| 545 2026 |
CRASH CUSH ATTEN (MOVE & RESET) (REACT) (W |
EA |
|
|
16.000 |
506.25000 |
2 |
| 545 2033 |
CRASH CUSH ATTEN (REMOVE) (QUAD) (W) |
EA |
|
|
5.000 |
140.00000 |
2 |
| 545 2064 |
CRASH CUSH ATTEN (MOVE & RESET) (SMTC) (N |
EA |
|
|
2.000 |
450.00000 |
2 |
| 545 2065 |
CRASH CUSH ATTEN (REMOVE) (SMTC) (N) |
EA |
|
|
2.000 |
650.00000 |
2 |
| 550 2001 |
CHAIN LINK FENCE (INSTALL) (6') |
LF |
|
|
637.000 |
13.41287 |
3 |
| 550 2002 |
CHAIN LINK FENCE (REPAIR) (6') |
LF |
|
|
962.000 |
12.20790 |
4 |
| 550 2003 |
CHAIN LINK FENCE (REMOVE) |
LF |
|
|
1,162.000 |
1.00000 |
3 |
| 550 2004 |
GATE (INSTALL) (DOUBLE) (6' X 14') |
EA |
|
|
2.000 |
380.00000 |
2 |
| 550 2005 |
GATE (REPAIR) (DOUBLE) (6' X 14') |
EA |
|
|
2.000 |
380.00000 |
2 |
| 550 2006 |
GATE (REMOVE) |
EA |
|
|
2.000 |
88.00000 |
2 |
| 550 2007 |
GATE (INSTALL) (SINGLE) (6' X 24') |
EA |
|
|
2.000 |
505.00000 |
2 |
| 550 2013 |
GATE (INSTALL) (DOUBLE) (6'X16') |
EA |
|
|
1.000 |
10.00000 |
1 |