Monthly State Let Construction Report For Fort Worth District As Of Apr 7, 2016 Page 8 Of 9

Last Update: Thursday, April 7, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPARKER
Highway FM 1886
From FM 730
To TARRANT COUNTY LINE
CSJ 1605-01-014
Proj ID STP 2014(478)
Work Type GR.BS, DR, STRUC AND PAVEMENT
 
5.748 4834822.79 185813.74 3459101.52 72.8
Work Order 05-07-14
Work Began 06-12-14
Work Completed  
Time Computed 05-23-14
Contract Working Days 256
Addl Days Granted 2
Working Days Charged 321
Percent Time Used 124
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1605-01-014
RAMBO CONTRACTING, INC.(4.85%)
BICK"S CONSTRUCTION, INC.( 16.34%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.93%)
MARCOM"S MOWING SERVICE, LLC (0.53%)
WEST TEXAS RUMBLE STRIP(0.08%)
AAA DRILLING FOUNDATION CO., INC.(0.36%)
LIRA ELECTRIC(1.57%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.79%)
ELLIS-MCGINNIS CONSTRUCTION CO.(1.86%)
Contract # 03143221
Totals 4834822.79 185813.74 3459101.52 72.8

CountyWISE
Highway FM 2123
From AT SALT CREEK
To AND AT COTTONWOOD CREEK
CSJ 1606-02-013
Proj ID BR 1102(297)
Work Type REPL BRIDGES
 
0.099 1968338.24 0.00 1872221.52 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-14-11
Work Began 12-08-11
Work Completed 03-27-15
Time Computed 09-30-11
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 380
Percent Time Used 253
Contractor(s)
DOUGHTIE CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-013
COWTOWN TRAFFIC CONTROL, INC.(0.36%)
BROCK ENVIRONMENTAL, LLC (0.39%)
DUSTIN ALLEN, INC. (1.70%)
GORRONDONA & ASSOCIATES, INC.(0.50%)
HIGHWAY TECHNOLOGIES, INC. (1.28%)
RG PAINTING(0.19%)
TEXAS ALTERNATIVE GRASSER, INC.(0.20%)
PRIMATE CONSTRUCTION, INC. (0.54%)
TEX OP CONSTRUCTION, LP(0.78%)
PEACHTREE CONSTRUCTION, LTD. (8.23%)
EW WELLS GROUP LLC (2.13%)
W. W. FOUNDATION DRILLING, LTD.(8.30%)
J.L. STEEL REINFORCING, LLC(0.33%)
ENVIRONMENTAL SAFETY SERVICES, INC.(8.95%)
JUST GROOVING, LTD.(0.29%)
JTM MATERIALS, INC.(0.17%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.42%)
KYLE ERWIN CONSTRUCTION, LLC (0.13%)
Contract # 08113260
Totals 1968338.24 0.00 1872221.52 100.0

CountyWISE
Highway FM 2123
From SH 114
To C.R. 3355
CSJ 1606-02-018
Proj ID STP 2012(736)HES
Work Type GRADING, BASE, DRAINAGE, STRUCTURE, PAV
 
12.330 4939000.01 72807.69 5575694.49 100.0
Work Order 12-03-12
Work Began 01-29-13
Work Completed 04-29-15
Time Computed 12-19-12
Contract Working Days 224
Addl Days Granted 30
Working Days Charged 257
Percent Time Used 101
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-018
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.47%)
BUYERS BARRICADES, INC.(0.39%)
W.S. CONSTRUCTION COMPANY( 13.29%)
PEACHTREE CONSTRUCTION, LTD. ( 20.15%)
HIGHWAY TECHNOLOGIES, INC. (2.13%)
HJC FARMS, INC.(2.96%)
STRIPING TECHNOLOGY, L.P.(2.21%)
W.O.E. CONSTRUCTION(0.03%)
Contract # 11123224
Totals 4939000.01 72807.69 5575694.49 100.0

CountyWISE
Highway FM 2123
From FM 51
To CR 3585
CSJ 1606-02-019
Proj ID STP 2014(884)
Work Type GRADING, BASE, DRAIN.STRUCT. AND PAVE
 
3.078 2779919.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-28-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163020
Totals 2779919.35 0.00 0.00 0.0

CountyTARRANT
Highway FM 1938
From 0.2 MILE SOUTH OF FM 1709
To RANDOL MILL RD/WESTLAKE C/L
CSJ 1978-01-050
Proj ID STP 1402(039)MM
Work Type GR, BS, DR, STRUCTURES & PAVEMENT
 
1.743 20575236.87 596306.74 9693241.10 47.1
Work Order 01-16-15
Work Began 03-23-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 554
Addl Days Granted 6
Working Days Charged 266
Percent Time Used 47
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-050
DALLAS LITE AND BARRICADE INC. (0.38%)
GJ SEEDING, LLC(0.59%)
THELIN RECYCLING COMPANY, L.P. (0.25%)
AUSTCO, INC. (0.05%)
NORTH TEXAS CONTRACTING, INC.( 20.99%)
LIRA ELECTRIC(2.47%)
FARR FOUNDATION, INC.(0.60%)
BREDA COMPANY, INC.(0.50%)
W.O.E. CONSTRUCTION(8.79%)
TEXAS SHAFTS, INC. (0.76%)
CROSSROADS DECORATIVE PAVEMENT (0.09%)
USA SWPPP INSPECTIONS, INC.(2.75%)
SCOTT DERR PAINTING CO, LLC(0.06%)
TRP CONSTRUCTION GROUP, LLC(0.67%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (5.68%)
A & A CONSTRUCTION (0.06%)
MARCOM"S MOWING SERVICE, LLC (0.32%)
BRENDA PRICE TRUCKING(0.68%)
INLET STRUCTURE SPECIALTIES LTD. (3.12%)
JM MATERIALS, INC. (0.50%)
KLP COMMERCIAL, LLC(8.05%)
Contract # 08143005
Totals 20575236.87 596306.74 9693241.10 47.1

CountyTARRANT
Highway FM 1938
From SH 114
To RANDOL MILL ROAD
CSJ 1978-01-055
Proj ID STP 2012(570)
Work Type LANDSCAPE ENHANCEMENT
 
2.205 856000.00 0.00 856832.28 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 12-14-12
Work Completed 10-28-15
Time Computed 07-28-12
Contract Working Days 128
Addl Days Granted 50
Working Days Charged 178
Percent Time Used 100
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-055
HIGHWAY TECHNOLOGIES, INC. (0.36%)
Contract # 05123245
Totals 856000.00 0.00 856832.28 100.0

CountyPALO PINTO
Highway FM 2201
From FM 4
To US 281
CSJ 1993-01-015
Proj ID STP 1502(334)
Work Type GR, BS, DR, STRUC & PAVEMENT
 
6.427 4655964.11 0.00 0.00 0.0
Work Order 08-20-15
Work Began 00-00-00
Work Completed  
Time Computed 09-19-15
Contract Working Days 277
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1993-01-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153024
Totals 4655964.11 0.00 0.00 0.0

CountyTARRANT
Highway FM 1220
From EAGLE MOUNTAIN ELEM SCHOOL
To 1,100 FT. NORTH OF BAILEY BOSWELL
CSJ 2079-01-041
Proj ID STP 2013(901)
Work Type GRADING, BASE AND PAVEMENT
 
2.879 5878132.94 0.00 114642.11 1.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-13
Work Began 00-00-00
Work Completed  
Time Computed 06-09-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2079-01-041
BRENDA PRICE TRUCKING(0.72%)
DALLAS LITE AND BARRICADE INC. (0.31%)
FARR FOUNDATION, INC.(1.36%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(0.46%)
LAYFIELD CONSTRUCTION, INC (4.47%)
J. E. GUZMAN CONSTRUCTION, INC.(5.59%)
TEX OP CONSTRUCTION, LP(2.07%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.13%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.43%)
W.O.E. CONSTRUCTION(4.76%)
NORTH TEXAS CONTRACTING, INC.( 14.65%)
STRIPING TECHNOLOGY, L.P.(1.26%)
Contract # 08133064
Totals 5878132.94 0.00 114642.11 1.9

CountyTARRANT
Highway FM 1220
From EAGLE MOUNTAIN ELEM SCHOOL
To 1,100 FT. NORTH OF BAILEY BOSWELL
CSJ 2079-01-043
Proj ID STP 2013(901)
Work Type GRADING, BASE AND PAVEMENT
 
2.879 8350775.03 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-31-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 278
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 2079-01-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163037
Totals 8350775.03 0.00 0.00 0.0

CountyTARRANT
Highway SP 303
From WEST C/L (SHADY VALLEY DR)
To EAST C/L (W CORNERSTONE LN)
CSJ 2208-01-063
Proj ID NH 2013(289)
Work Type LANDSCAPE ENHANCEMENT
 
1.647 197430.50 0.00 194799.90 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-13
Work Began 09-25-13
Work Completed 05-11-15
Time Computed 07-24-13
Contract Working Days 81
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 93
Contractor(s)
GREY CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 2208-01-063
BUYERS BARRICADES, INC.(1.41%)
UNLIMITED UTILITY CONSTRUCTION (3.62%)
L.E.D. CONCRETE, LLC (5.54%)
BOWDEN"S GUARANTEED HYDORMULCH, INC. (0.63%)
Contract # 05133037
Totals 197430.50 0.00 194799.90 100.0

CountyJOHNSON
Highway FM 2331
From SH 171
To FM 4 (NORTH)
CSJ 2213-01-013
Proj ID STP 2014(007)HES
Work Type ADDITIONAL PAVED SURFACE WIDTH
 
10.092 4289114.81 0.00 4910475.11 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-22-13
Work Began 01-08-14
Work Completed 09-11-15
Time Computed 12-08-13
Contract Working Days 214
Addl Days Granted 52
Working Days Charged 373
Percent Time Used 140
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2213-01-013
RAMBO CONTRACTING, INC.(9.51%)
TEXAS ALTERNATIVE GRASSER, INC.(0.48%)
NORTHEASTERN PAVERS, INC.( 62.69%)
FORTSON CONTRACTING, INC.(2.11%)
D. I. J. CONSTRUCTION, INC.(1.25%)
BUYER BARRICADES (0.44%)
Contract # 09133023
Totals 4289114.81 0.00 4910475.11 100.0

CountyTARRANT
Highway SH 360
From AT SH 180 (DIVISION STREET)
To AND UPRR; IN ARLINGTON
CSJ 2266-02-127
Proj ID NH 2007(806)
Work Type GR, STRS & PAVEMENT
 
0.854 55975100.62 0.00 59587176.17 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-07-08
Work Began 03-07-09
Work Completed 08-12-14
Time Computed 10-05-08
Contract Working Days 555
Addl Days Granted 509
Working Days Charged 1,064
Percent Time Used 100
Contractor(s)
W.W. WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2266-02-127
COWTOWN TRAFFIC CONTROL, INC.(0.20%)
EVANS ENVIRONMENTAL CONTRACTING, LLC.(0.43%)
CAPROCK SPECIALITY CONTRACTORS (0.01%)
CRAIG OLDEN, INC.(1.53%)
FOUNDATION DRILLERS, INC.(1.00%)
HAYWARD BAKER, INC.(1.52%)
HIGHWAY TECHNOLOGIES, INC. (0.68%)
MAGNUM TUNNELING, LLC(0.32%)
MICA CORPORATION (3.87%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(7.49%)
TEX OP CONSTRUCTION, LP(0.33%)
DURABLE SPECIALTIES, INC.(0.67%)
LAYFIELD CONSTRUCTION, INC (0.07%)
BRENDA PRICE TRUCKING(4.11%)
SCOTT DERR PAINTING CO (0.06%)
INDUS CONSTRUCTION, L.P. (2.51%)
GREAT WESTERN ERECTORS (0.05%)
RAILWORKS TRACK SYSTEMS TEXAS, INC.( 11.20%)
SOUTHWEST CONSTRUCTION SERVICES(0.11%)
ERWIN STEEL WORKS, LLC (0.29%)
MOBILE ENTERPRISES, INC. (0.39%)
STOMPER DEMOLITION COMPANY, INC. (0.27%)
RIVER CITIES SAWING LLC(0.01%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.41%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.00%)
Contract # 02083001
Totals 55975100.62 0.00 59587176.17 100.0

CountyTARRANT
Highway SH 360
From SOUTH OF MIDWAY
To TRINITY RIVER
CSJ 2266-02-138
Proj ID NH 2016(594)
Work Type MILL AND OVERLAY
 
2.106 2126639.61 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 61
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DIAMOND SURFACE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2266-02-138
PEACHTREE CONSTRUCTION, LTD. ( 12.85%)
STRIPING TECHNOLOGY, L.P.(6.54%)
ALTUS TRAFFIC MANAGEMENT LLC (5.00%)
DUSTROL, INC.(1.88%)
Contract # 01163205
Totals 2126639.61 0.00 0.00 0.0

CountyPALO PINTO
Highway FM 2353
From SH-16
To PR-36
CSJ 2290-01-009
Proj ID STP 1502(335)
Work Type GR, BS, STRUCTURE AND PAVEMENTS
 
5.880 5278946.23 187854.58 2011596.18 38.1
Work Order 07-31-15
Work Began 10-12-15
Work Completed  
Time Computed 08-29-15
Contract Working Days 299
Addl Days Granted 2
Working Days Charged 83
Percent Time Used 27
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2290-01-009
LUZ LERMA CONSTRUCTION, INC. ( 16.74%)
HJC FARMS, INC.(1.98%)
ALTUS TRAFFIC MANAGEMENT LLC (0.59%)
STRIPING TECHNOLOGY, L.P.(1.83%)
Contract # 06153243
Totals 5278946.23 187854.58 2011596.18 38.1

CountyPARKER
Highway FM 1187
From FM 5
To TARRANT COUNTY LINE
CSJ 2291-01-013
Proj ID STP 2014(772)
Work Type GR, BS, STR, SURFACE, SIGNING & MARKING
 
7.204 6785848.59 3000.00 1694720.79 24.9
Work Order 08-08-14
Work Began 12-10-14
Work Completed  
Time Computed 08-24-14
Contract Working Days 374
Addl Days Granted 0
Working Days Charged 111
Percent Time Used 29
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2291-01-013
RAMBO CONTRACTING, INC.( 20.05%)
TEXAS ALTERNATIVE GRASSER, INC.(0.90%)
NORTHEASTERN PAVERS, INC.( 14.31%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(0.49%)
HJC FARMS, INC.(0.77%)
WEST TEXAS RUMBLE STRIP(0.07%)
TRP CONSTRUCTION GROUP, LLC(1.08%)
Contract # 06143231
Totals 6785848.59 3000.00 1694720.79 24.9

CountyTARRANT
Highway IH 635
From SH-121
To TARRANT / DALLAS COUNTY LINE
CSJ 2374-06-005
Proj ID NH 2015(255)
Work Type MILL AND OVERLAY
 
0.575 1773525.11 0.00 1579309.57 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-17-14
Work Began 06-08-15
Work Completed 10-06-15
Time Computed 01-19-15
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 42
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2374-06-005
CROSSROADS, L.P. (1.27%)
TEX OP CONSTRUCTION, LP( 10.59%)
O. TREVINO CONSTRUCTION, LLC (6.88%)
TRP CONSTRUCTION GROUP, LLC(2.66%)
WOLFE CONSTRUCTION GROUP, INC. (0.06%)
W.O.E. CONSTRUCTION(0.06%)
W.O.E. CONSTRUCTION(0.10%)
Contract # 10143013
Totals 1773525.11 0.00 1579309.57 100.0

CountyJOHNSON
Highway FM 2415
From FM 4
To C.R. 401
CSJ 2464-01-014
Proj ID STP 2014(665)HES
Work Type GRADING, BASE AND PAVEMENT
 
6.253 2913097.88 0.00 2968277.56 100.0
Work Order 07-25-14
Work Began 08-18-14
Work Completed 03-01-16
Time Computed 08-10-14
Contract Working Days 150
Addl Days Granted 67
Working Days Charged 237
Percent Time Used 109
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2464-01-014
SAN-ANN-CO., INC.(0.90%)
STRIPING TECHNOLOGY, L.P.(1.49%)
W.S. CONSTRUCTION COMPANY( 11.84%)
D & M CONTRACTORS, LLC (1.22%)
Contract # 05143019
Totals 2913097.88 0.00 2968277.56 100.0

CountyJOHNSON
Highway FM 2738
From FM 2738 AT MOUNTAIN CREEK
To .
CSJ 2762-01-014
Proj ID BR 2012(572)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.307 1319000.00 0.00 1344227.38 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-16-12
Work Began 04-29-13
Work Completed 07-23-14
Time Computed 08-01-12
Contract Working Days 192
Addl Days Granted 31
Working Days Charged 234
Percent Time Used 104
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2762-01-014
T-BAR FENCE, INC.(0.73%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.71%)
HIGHWAY TECHNOLOGIES, INC. (1.21%)
FORTSON CONTRACTING, INC.(1.49%)
ATS DRILLING, L.P. (2.91%)
GJ SEEDING, LLC(1.43%)
MCL CONTRACTING, LLC (0.49%)
TEX OP CONSTRUCTION, LP(1.27%)
HOUSTON SAWING & DRILLING(0.31%)
SCOTT DERR PAINTING CO (0.21%)
ROAD MASTER STRIPING LLC (0.79%)
SOUTHEAST GRINDING & GROOVING, LLC (0.15%)
BRENDA PRICE TRUCKING(0.89%)
Contract # 05123231
Totals 1319000.00 0.00 1344227.38 100.0

CountyTARRANT
Highway RM 2871
From RM 2871 OVER MARY'S CREEK
To .
CSJ 2855-01-016
Proj ID BR 1102(208)
Work Type REHABILITATE BRIDGE AND APPROACHES
 
0.291 1796479.01 0.00 1899350.83 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-06-11
Work Began 04-02-12
Work Completed 07-02-14
Time Computed 03-15-12
Contract Working Days 299
Addl Days Granted 27
Working Days Charged 326
Percent Time Used 100
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 2855-01-016
STRIPING TECHNOLOGY, L.P.(1.61%)
USA SWPPP INSPECTIONS, INC.(1.79%)
PEACHTREE CONSTRUCTION, LTD. (8.58%)
A.M.S. COMPANY, INC. ( 12.08%)
RICE ENVIRONMENTAL SERVICES(6.83%)
FOUNDATION DRILLERS, INC.(1.50%)
DUSTROL, INC.(0.78%)
HIGHWAY TECHNOLOGIES, INC. (0.59%)
M-CO CONSTRUCTION, INC.(0.38%)
T & R EXCAVATION, INC. (0.51%)
Contract # 08113066
Totals 1796479.01 0.00 1899350.83 100.0

CountyTARRANT
Highway RM 2871
From SOUTH OF RR CROSSING
To US-377
CSJ 2855-01-021
Proj ID STP 2014(319)
Work Type OVERLAY
 
1.387 2072283.33 0.00 1759883.11 85.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-19-14
Work Began 04-28-14
Work Completed  
Time Computed 03-07-14
Contract Working Days 167
Addl Days Granted 15
Working Days Charged 184
Percent Time Used 101
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2855-01-021
PEACHTREE CONSTRUCTION, LTD. ( 38.67%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.53%)
FORTSON CONTRACTING, INC.(1.20%)
ENVIRONMENTAL STANDARDS(1.13%)
DURABLE SPECIALTIES, INC.(0.48%)
MARCOM"S MOWING SERVICE, LLC (0.30%)
TEXAS ALTERNATIVE GRASSER, INC.(0.33%)
Contract # 01143023
Totals 2072283.33 0.00 1759883.11 85.1

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9