Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHUDSPETH
Highway IH0010
From IH 10
To US 62/180
CSJ 6212-07-001
Proj ID BPM - 621207001
Work Type BRIDGE AND CULVERT REPAIRS
 
50.000 572460.00 103029.96 615101.53 99.9
Work Order 03-01-11
Work Began 03-01-11
Work Completed  
Time Computed 03-01-11
Contract Working Days 75
Addl Days Granted 25
Working Days Charged 103
Percent Time Used 103
Contractor(s)
TEXAS CONCRETE AND ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6212-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10104020
Totals 572460.00 103029.96 615101.53 99.9

CountyEL PASO
Highway IH0010
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6215-03-001
Proj ID RMC - 621503001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
600.000 315260.00 0.00 267748.05 84.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-22-10
Work Began 11-01-10
Work Completed  
Time Computed 11-01-10
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 357
Percent Time Used 97
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6215-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09104013
Totals 315260.00 0.00 267748.05 84.9

CountyEL PASO
Highway IH0010
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6226-86-001
Proj ID RMC - 622686001
Work Type MILL AND INLAY
 
100.000 616308.45 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ALLIED PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 6226-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05124011
Totals 616308.45 0.00 0.00 0.0

CountyEL PASO
Highway IH0010
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6229-05-001
Proj ID RMC - 622905001
Work Type CLEANING AND SWEEPING
 
600.000 475242.00 0.00 206009.50 50.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-01-11
Work Began 11-01-11
Work Completed  
Time Computed 11-01-11
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 49
Contractor(s)
MIJELUM
SUBCONTRACTOR(S) FOR CCSJ: 6229-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09114015
Totals 475242.00 0.00 206009.50 50.3

CountyEL PASO
Highway IH0010
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6230-73-001
Proj ID RMC - 623073001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
600.000 420741.60 0.00 99698.70 31.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-10-11
Work Began 11-17-11
Work Completed  
Time Computed 11-17-11
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 166
Percent Time Used 45
Contractor(s)
TEXAS CONCRETE AND ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6230-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09114007
Totals 420741.60 0.00 99698.70 31.5

CountyEL PASO
Highway US0054
From NEW MEXICO STATE LINE
To EL PASO DISTRICT LINE
CSJ 6232-26-001
Proj ID RMC - 623226001
Work Type TRAFFIC MANAGEMENT SYSTEM
 
200.000 1347980.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6232-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03124033
Totals 1347980.95 0.00 0.00 0.0

CountyEL PASO
Highway IH0010
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6235-91-001
Proj ID RMC - 623591001
Work Type REPAIR OF MAINT. MBGF AND POST & CABLE
 
300.000 351140.00 0.00 70334.40 27.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-23-12
Work Began 02-01-12
Work Completed  
Time Computed 02-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 24
Contractor(s)
MIJELUM
SUBCONTRACTOR(S) FOR CCSJ: 6235-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12114033
Totals 351140.00 0.00 70334.40 27.1

CountyEL PASO
Highway IH0010
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6236-50-001
Proj ID BPM - 623650001
Work Type CONST. & MAINT. OF BRIDGE JOINT REPAIR
 
50.000 489530.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6236-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05124012
Totals 489530.00 0.00 0.00 0.0

CountyEL PASO
Highway IH0010
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6236-99-001
Proj ID RMC - 623699001
Work Type DYNAMIC MESSAGE SIGN UPGRAD
 
200.000 385200.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6236-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05124024
Totals 385200.00 0.00 0.00 0.0

CountyEL PASO
Highway IH0010
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6237-49-001
Proj ID RMC - 623749001
Work Type POTHOLE REPAIR
 
100.000 302598.00 0.00 0.00 11.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-18-12
Work Began 04-22-12
Work Completed  
Time Computed 04-22-12
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 15
Contractor(s)
ALLEN CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6237-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02124015
Totals 302598.00 0.00 0.00 11.3

CountyEL PASO
Highway IH0010
From VARIOUS LOCATIONS IN EL PASO COUNTY
To VARIOUS LOCATIONS IN HUDSPETH COUNTY
CSJ 6237-54-001
Proj ID RMC - 623754001
Work Type MISCELLANOUS CONCRETE WORK
 
50.000 243012.50 0.00 0.00 16.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-04-12
Work Began 04-16-12
Work Completed  
Time Computed 04-16-12
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 15
Contractor(s)
GARCOM, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6237-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02124033
Totals 243012.50 0.00 0.00 16.7

CountyEL PASO
Highway IH0010
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6237-55-001
Proj ID RMC - 623755001
Work Type POTHOLE REPAIR
 
150.000 283500.00 0.00 0.00 40.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-08-12
Work Began 04-10-12
Work Completed  
Time Computed 04-10-12
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 21
Contractor(s)
LESNA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6237-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02124016
Totals 283500.00 0.00 0.00 40.1

CountyEL PASO
Highway IH0010
From VARIOUS HIGHWAYS
To VARIOUS HIGHWAYS
CSJ 6238-30-001
Proj ID RMC - 623830001
Work Type METAL BEAM GUARDRAIL REPAIR
 
100.000 493835.00 0.00 3616.50 8.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-27-12
Work Began 03-27-12
Work Completed  
Time Computed 03-27-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 9
Contractor(s)
BOWEN INDUSTRIAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6238-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02124034
Totals 493835.00 0.00 3616.50 8.9

CountyEL PASO
Highway RM2775
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6239-91-001
Proj ID RMC - 623991001
Work Type PAVEMENT REPAIR
 
5.000 1223992.38 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ALLIED PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 6239-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05124023
Totals 1223992.38 0.00 0.00 0.0