Monthly State Let Construction Report For El Paso District As Of Aug 11, 2017 Page 3 Of 3

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwaySS 6
From4TH STREET
ToEAST OF DESERT SAGE STREET
CSJ3572-01-005
Proj IDSTP 1602(502)MM
Work TypeCONST OF CROSSWALKS/SCHL ZONE FLSH
 
0.360198745.08213206.1799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-16
Work Began02-06-17
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged40
Percent Time Used100
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3572-01-005
BOWEN INDUSTRIAL CONTRACTORS, INC. (2.57)
V.C. HUFF, L.L.C. (34.55)
Contract #08163020
Totals198745.088507.40213206.1799.9