Monthly State Let Construction Report For El Paso District As Of May 11, 2017 Page 2 Of 2

Last Update: Wednesday, May 17, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwayCS
FromALBERTON AVE
To200 FT S OF LTV RD
CSJ0924-06-457
Proj IDSTP 2015(455)MM
Work TypeWIDEN ROAD
 
1.2506591274.781230180.0418.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-03-16
Work Began02-01-17
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted0
Working Days Charged55
Percent Time Used22
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-457
INTERNATIONAL EAGLE ENTERPRISES, INC. (42.75)
TRI STATE ELECTRIC, LTD. (10.14)
PRIME IRRIGATION & LANDSCAPE, INC. (1.94)
ABRI TRANSPORTATION SERVICES, LLC (0.37)
PMI PAVEMENT MARKING, INC. (0.82)
Contract #08163204
Totals6591274.780.001230180.0418.6

CountyEL PASO
HighwayVA
FromEL PASO COUNTYWIDE
To.
CSJ0924-06-491
Proj IDCM 1602(500)
Work TypeREGIONAL BIKE IMPROVEMENTS (ON ST)
 
36.052324898.830.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-06-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-491
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163221
Totals324898.830.000.000.0

CountyEL PASO
HighwayCS
FromSOCORRO CITY LIMITS
To.
CSJ0924-06-520
Proj IDSTP 2016(796)TP
Work TypeSOCORRO SAFE ROUTES TO SCHOOL
 
2.830373864.65417813.8799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-28-16
Work Began08-24-16
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged110
Percent Time Used73
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-520
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06163018
Totals373864.650.00417813.8799.9

CountyBREWSTER
HighwayVA
FromVARIOUS LOCATIONS IN ALPINE AREA
To.
CSJ0924-35-022
Proj IDNH 1602(501)
Work TypeALPINE BEAUTIFICATION PROJECT
 
1.000202104.08192401.9795.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-22-16
Work Began03-20-17
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged27
Percent Time Used45
Contractor(s)
KEGLEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-35-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163015
Totals202104.080.00192401.9795.1

CountyPRESIDIO
HighwayFM 170
From220 FT E OF BU 67A
To0.718 MI E OF BU 67A
CSJ0957-08-027
Proj IDSTP 1602(291)
Work TypeREHAB EXISTING ROAD
 
0.7511271914.40106677.008.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-13-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted0
Working Days Charged16
Percent Time Used11
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0957-08-027
DELGADOS CONSTRUCTION, DBA ERNESTO A. DELGADO (29.25)
Contract #11163020
Totals1271914.400.00106677.008.3

CountyHUDSPETH
HighwayRM 1111
From0.5 MI N OF RM 1111/BI-10 INTERSEC
ToRM 1111/BI-10 INTERSECTION
CSJ1282-02-018
Proj IDBR 1502(393)
Work TypeREPLACE STRUCTURE
 
0.6211291694.001298626.1299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-05-15
Work Began11-02-15
Work Completed
Time Computed11-02-15
Contract Working Days160
Addl Days Granted0
Working Days Charged155
Percent Time Used96
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1282-02-018
C & C ROAD CONSTRUCTION, INC. (14.41)
NATIONWIDE REBAR INC (3.68)
HARDY HOLE DRILLING (7.32)
SOUTHWESTERN INDUSTRIAL CONTRACTORS (0.61)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.48)
V.C. HUFF, L.L.C. (0.44)
Contract #07153041
Totals1291694.000.001298626.1299.9

CountyHUDSPETH ETC
HighwayRM 1111 ETC
FromUS 62/180
To0.3 MI N OF IH 10
CSJ1282-02-025
Proj IDSTP 2016(395)
Work TypePREVENTATIVE MAINTENANCE
 
151.7464749629.994709198.1899.1
Work Order04-18-16
Work Began08-08-16
Work Completed
Time Computed04-18-16
Contract Working Days60
Addl Days Granted0
Working Days Charged30
Percent Time Used50
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1282-02-025
FLASHER EQUIPMENT COMPANY (2.05)
DOUBLE A CONTRACTING, L.P. (6.28)
Contract #12153218
Totals4749629.990.004709198.1899.1

CountyEL PASO
HighwayIH 10
From@ MESA
To.
CSJ2121-01-087
Proj IDSTP 2015(221)HES
Work TypeIMPROVE TRAFFIC SIGNAL
 
0.313458248.264442.020.9
CountyEL PASO
HighwayIH 10
From0.48 MI E OF SUNLAND PARK DR
To0.45 MI E OF EXECUTIVE CENTER
CSJ2121-02-132
Proj IDNH 2015(335)
Work TypeREHABILITATION
 
2.8362487085.091107.040.0
CountyEL PASO
HighwayIH 10
FromMESA STREET
ToEXECUTIVE CENTER
CSJ2121-02-137
Proj IDCBI 2015(220)
Work TypeCOLLECTOR DISTRIBUTOR LANES
 
5.164151231706.1985775664.0051.4
CountyEL PASO
HighwayIH 10
FromMESA STREET
ToEXECUTIVE CENTER
CSJ2121-02-154
Proj IDROW 2121-2-154
Work TypeACQUISITION AND UTILITIES
 
7.8544601364.663987171.5786.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-19-14
Work Began04-06-15
Work Completed
Time Computed00-00-00
Contract Working Days1,211
Addl Days Granted51
Working Days Charged582
Percent Time Used46
Contractor(s)
TRADECO INFRAESTRUCTURA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2121-01-087
ZTEX CONSTRUCTION, INC. (9.00)
TRAFFIC CONTROL SPECIALIST SALES & RENTALS (0.09)
HARDY HOLE DRILLING (0.69)
TRI STATE ELECTRIC, LTD. (1.25)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.69)
SOUTHWESTERN INDUSTRIAL CONTRACTORS (0.21)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.02)
HENRY TRUJILLO, INC. (0.01)
A BROTHERS (OLD PRIME) (0.13)
SUNDT CONSTRUCTION, INC. (0.00)
TRI STATE ELECTRIC, LTD. (12.29)
HARDY HOLE DRILLING (0.46)
HARDY HOLE DRILLING (3.12)
D"AMBRA CONSTRUCTION CORPORATION (0.10)
PMI PAVEMENT MARKING, INC. (0.36)
DH UNDERGROUND, INC. (0.63)
ANTIGO CONSTRUCTION, INC. (0.04)
ADVANCED CONCRETE SAWING & SEALING, LLC (0.34)
ALLIED PAVING CO. (0.64)
REBAR REINFORCEMENT PLACERS (6.83)
EARTH REINFORCEMENT SPECIALISTS (0.99)
CHOCTAW ERECTORS, INC. (2.49)
SCOTT DERR PAINTING CO, LLC (0.42)
LEEDSMAN CONSTRUCTION, INC. (1.19)
HENRY TRUJILLO, INC. (1.14)
BORDER DRILLING LLC (0.06)
CRANE SERVICES, INC. (0.01)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.84)
CANO STRUCTURES, LLC (0.82)
KEN"S PORTABLE WELDING (0.01)
PENHALL COMPANY (0.25)
HERNANDEZ CONCRETE PUMPING (0.13)
A BROTHERS MILLING, LLC (0.05)
MFH ENVIRONMENTAL CORP. (0.00)
Contract #10143001
Totals158778404.200.0089768384.6351.5

CountyEL PASO
HighwayIH 10
FromWESTWAY
ToLP 375
CSJ2121-01-092
Proj IDC 2121-1-92
Work TypeREHAB AND OPERATIONAL IMPROVEMENTS
 
3.40012757146.9113986236.7699.9
Work Order11-02-15
Work Began11-30-15
Work Completed
Time Computed11-30-15
Contract Working Days206
Addl Days Granted60
Working Days Charged264
Percent Time Used99
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2121-01-092
BOWEN INDUSTRIAL CONTRACTORS, INC. (1.77)
TRAFFIC BARRICADE SERVICE, INC. (0.88)
SANCHEZ CONSTRUCTION & LANDSCAPING (5.85)
HAWK CONSTRUCTION (1.56)
FALC ENTERPRISES, LLC (0.94)
SATARAIN CONSTRUCTION, INC. (7.67)
PMI PAVEMENT MARKING, INC. (0.53)
TRI STATE ELECTRIC, LTD. (12.99)
EARTH REINFORCEMENTS LLC (0.75)
HARDY HOLE DRILLING (1.05)
HAWK CONSTRUCTION (0.11)
GREATER EL PASO SANDBLASTING (0.11)
D"AMBRA CONSTRUCTION CORPORATION (2.55)
HDW CONSTRUCTION & DRILLING, LLC. (0.21)
BELT CON CONSTRUCTION, INC. (0.14)
BORDER DRILLING LLC (0.19)
Contract #08153207
Totals12757146.910.0013986236.7699.9

CountyEL PASO
HighwayIH 10
FromCOPIA ST (LP 478)
ToCHELSEA ST
CSJ2121-02-146
Proj IDNH 2017(025)
Work TypeINSTALL HIGH MAST LIGHTING
 
1.4861399520.76336717.0024.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-21-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-146
HAWK CONSTRUCTION (1.09)
HARDY HOLE DRILLING (6.73)
Contract #09163212
Totals1399520.760.00336717.0024.0

CountyEL PASO
HighwayIH 10
FromCOPIA ST (LP 478)
ToCHELSEA ST
CSJ2121-02-151
Proj IDSTP 2014(127)TE
Work TypeENHANCEMENT PROJECT
 
1.3097584729.549044268.4699.9
Work Order02-25-14
Work Began04-01-14
Work Completed
Time Computed03-13-14
Contract Working Days161
Addl Days Granted100
Working Days Charged261
Percent Time Used100
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-151
HAWK CONSTRUCTION (11.81)
HARDY HOLE DRILLING (3.96)
QUARRY HILLS, LTD. (0.13)
HOWE PRECAST (0.40)
EARTH REINFORCEMENT SPECIALISTS (2.79)
HENRY TRUJILLO, INC. (1.44)
APACHE BARRICADE & SIGN (2.33)
BEAVER TREE SERVICE, INC. (0.22)
NATIONWIDE REBAR INC (3.96)
TRI STATE ELECTRIC, LTD. (1.60)
VENEGAS ENGINEERING MANAGEMENT AND CONSTRUCTION, INC. (31.84)
KEN"S PORTABLE WELDING (0.06)
VENEGAS ENGINEERING MANAGEMENT AND CONSTRUCTION, INC. (0.09)
GREATER EL PASO SANDBLASTING (22.61)
PEREZ ROCKWALL (16.66)
MARQUEZ WROUGHT IRON (4.38)
EL PASO CONCRETE CUTTERS, INC (0.14)
Contract #12133026
Totals7584729.540.009044268.4699.9

CountyEL PASO
HighwayIH 10
FromPORFIRIO DIAZ ST
ToMISSOURI AVE
CSJ2121-02-152
Proj IDCC 2121-2-152
Work TypeBRIDGE ENHANCEMENT
 
8.0004677712.445798469.3799.9
CountyEL PASO
HighwayIH 10
FromCOPIA ST (LP 478)
ToCHELSEA ST
CSJ2121-02-155
Proj IDCC 2121-2-155
Work TypeENHANCEMENT PROJECT
 
1.3094151891.906259132.2399.9
Work Order05-22-14
Work Began05-22-14
Work Completed
Time Computed06-07-14
Contract Working Days218
Addl Days Granted310
Working Days Charged518
Percent Time Used98
Contractor(s)
VENEGAS ENGINEERING MANAGEMENT AND CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-152
TRAFFIC BARRICADE SERVICE, INC. (0.20)
GREATER EL PASO SANDBLASTING (10.88)
HAWK CONSTRUCTION (1.04)
TRI STATE ELECTRIC, LTD. (9.33)
WESTSIDE WELDING INC. (27.11)
S. ROBERT"S IRON WORKS, INC. (0.29)
THOMAS INDUSTRIAL COATINGS, INC. (0.96)
EL PASO CONCRETE CUTTERS, INC (0.67)
UNIQUE CUSTOM DRYWALL AND PAINTING DBA LUIS SIMENTAL (1.55)
G&G ENTERPRISE (1.49)
KASCO (4.98)
HARDY HOLE DRILLING (7.48)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING (0.64)
RIVERBEND CRANE & RIGGING (3.39)
CANYON GLASS CO. (0.53)
HERNANDEZ CONCRETE PUMPING (0.06)
ELIAS CONCRETE (0.07)
GORMAN MOISTURE PROTECTION (0.07)
PEREZ ROCKWALL (1.18)
MANNY CARRIZAL PAINTING CO., INC. (0.09)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.12)
PRIME IRRIGATION & LANDSCAPE, INC. (0.02)
BELT CON CONSTRUCTION, INC. (0.21)
Contract #04143208
Totals8829604.3446359.0712057601.6099.9

CountyEL PASO
HighwayIH 10
FromFM 659 (ZARAGOZA)
ToEASTLAKE
CSJ2121-04-098
Proj IDC 2121-4-98
Work TypeWIDEN ROADWAY
 
3.22012915901.724784562.5337.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-02-16
Work Began11-01-16
Work Completed
Time Computed00-00-00
Contract Working Days271
Addl Days Granted0
Working Days Charged127
Percent Time Used46
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2121-04-098
TRI STATE ELECTRIC, LTD. (10.25)
INTERNATIONAL EAGLE ENTERPRISES, INC. (29.93)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING (6.79)
HARDY HOLE DRILLING (1.89)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.99)
PRIME IRRIGATION & LANDSCAPE, INC. (0.59)
FALC ENTERPRISES, LLC (0.06)
NATIONWIDE REBAR INC (0.32)
HARDY HOLE DRILLING (0.41)
NATIONWIDE REBAR INC (0.04)
PMI PAVEMENT MARKING, INC. (2.10)
SOUTH TEXAS PAINTING COMPANY (0.43)
Contract #07163003
Totals12915901.720.004784562.5337.0

CountyEL PASO
HighwaySL 375
From0.5 MI W OF FMSP ENTRANCE
To1.05 MI E OF FMSP ENTRANCE
CSJ2552-01-054
Proj IDNH 2016(343)
Work TypeIMPROVE CONNECTIVITY AT FMSP
 
2.6163200881.703296410.9499.9
Work Order12-21-15
Work Began01-04-16
Work Completed
Time Computed01-04-16
Contract Working Days252
Addl Days Granted0
Working Days Charged252
Percent Time Used100
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2552-01-054
BOWEN INDUSTRIAL CONTRACTORS, INC. (8.33)
HARDY HOLE DRILLING (9.67)
EARTH REINFORCEMENTS LLC (8.49)
NATIONWIDE REBAR INC (0.32)
ABRI TRANSPORTATION SERVICES, LLC (0.09)
Contract #11153032
Totals3200881.700.003296410.9499.9

CountyEL PASO
HighwaySL 375
FromUS 62/180 (MONTANA AVE)
ToBOB HOPE DR
CSJ2552-03-054
Proj IDNH 2013(631)
Work TypeWIDEN TO 6 LANES
 
7.78921784387.3212302482.6756.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-10-16
Work Began03-28-16
Work Completed
Time Computed00-00-00
Contract Working Days452
Addl Days Granted0
Working Days Charged279
Percent Time Used61
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2552-03-054
TRI STATE ELECTRIC, LTD. (38.64)
BORDER DRILLING LLC (0.96)
HARDY HOLE DRILLING (1.51)
A BROTHERS MILLING, LLC (0.14)
PMI PAVEMENT MARKING, INC. (3.12)
VERTEX CONTRACTORS, LLC (2.68)
LEEDSMAN CONSTRUCTION, INC. (0.88)
FALC ENTERPRISES, LLC (0.08)
E. G. L. CONSTRUCTION, INC. (1.82)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING (5.04)
H.B. WELDING (0.01)
SOUTH TEXAS PAINTING COMPANY (0.94)
HARDY HOLE DRILLING (4.59)
FALC ENTERPRISES, LLC (0.02)
CRANE SERVICES, INC. (0.01)
Contract #12153002
Totals21784387.320.0012302482.6756.4

CountyEL PASO
HighwaySS 6
FromSH 20 (DONIPHAN DR)
ToDESERT SAGE ST
CSJ3572-01-003
Proj IDSTP 2014(134)TE
Work TypeCOMMUNITY LIGHTING AND SIDEWALK
 
0.510242881.39270205.8199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-21-15
Work Began05-16-16
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged40
Percent Time Used100
Contractor(s)
SYNERGY PROJECT CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3572-01-003
G. C. ELECTRIC (53.93)
GARCOM, INC. (2.79)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.62)
Contract #08153019
Totals242881.390.00270205.8199.9

CountyEL PASO
HighwaySS 6
FromSH 20 (MAIN ST)
ToFM 1905 (ANTONIO ST)
CSJ3572-01-004
Proj IDSTP 1502(614)TP
Work TypePEDESTRIAN ENHANCEMENTS
 
1.4871734404.302049082.6599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-19-16
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted40
Working Days Charged119
Percent Time Used99
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3572-01-004
TRAFFIC BARRICADE SERVICE, INC. (0.69)
TRI STATE ELECTRIC, LTD. (28.69)
ALLEN CONCRETE, INC. (3.48)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.36)
BORDER DRILLING LLC (2.15)
HARDY HOLE DRILLING (1.72)
HENRY TRUJILLO, INC. (0.06)
BRAVO EL PASO LANDSCAPING AND IRRIGATION (2.43)
Contract #08153218
Totals1734404.300.002049082.6599.9

CountyEL PASO
HighwaySS 6
From4TH STREET
ToEAST OF DESERT SAGE STREET
CSJ3572-01-005
Proj IDSTP 1602(502)MM
Work TypeCONST OF CROSSWALKS/SCHL ZONE FLSH
 
0.360198745.08157930.2379.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-16
Work Began02-06-17
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged40
Percent Time Used100
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3572-01-005
BOWEN INDUSTRIAL CONTRACTORS, INC. (2.57)
V.C. HUFF, L.L.C. (34.55)
Contract #08163020
Totals198745.080.00157930.2379.4