Monthly State Let Construction Report For El Paso District As Of Nov 9, 2016 Page 2 Of 2

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEL PASO
Highway CS
From SOCORRO CITY LIMITS
To .
CSJ 0924-06-520
Proj ID STP 2016(796)TP
Work Type SOCORRO SAFE ROUTES TO SCHOOL
 
2.830 373864.65 0.00 369865.22 98.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-28-16
Work Began 08-24-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 48
Percent Time Used 32
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-520
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163018
Totals 373864.65 0.00 369865.22 98.9

CountyBREWSTER
Highway VA
From VARIOUS LOCATIONS IN ALPINE AREA
To .
CSJ 0924-35-022
Proj ID NH 1602(501)
Work Type ALPINE BEAUTIFICATION PROJECT
 
1.000 202104.08 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KEGLEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-35-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163015
Totals 202104.08 0.00 0.00 0.0

CountyPRESIDIO
Highway FM 170
From 220 FT E OF BU 67A
To 0.718 MI E OF BU 67A
CSJ 0957-08-027
Proj ID STP 1602(291)
Work Type REHAB EXISTING ROAD
 
0.751 1271914.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0957-08-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11163020
Totals 1271914.40 0.00 0.00 0.0

CountyHUDSPETH
Highway RM 1111
From 0.5 MI N OF RM 1111/BI-10 INTERSEC
To RM 1111/BI-10 INTERSECTION
CSJ 1282-02-018
Proj ID BR 1502(393)
Work Type REPLACE STRUCTURE
 
0.621 1291694.00 0.00 1298626.12 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-05-15
Work Began 11-03-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 155
Percent Time Used 96
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1282-02-018
C & C ROAD CONSTRUCTION, INC.( 14.41%)
NATIONWIDE REBAR INC (3.68%)
HARDY HOLE DRILLING(7.32%)
SOUTHWESTERN INDUSTRIAL CONTRACTORS(0.61%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.48%)
V.C. HUFF, L.L.C.(0.44%)
Contract # 07153041
Totals 1291694.00 0.00 1298626.12 99.9

CountyHUDSPETH
Highway RM 1111 ETC
From US 62/180
To 0.3 MI N OF IH 10
CSJ 1282-02-025
Proj ID STP 2016(395)
Work Type PREVENTATIVE MAINTENANCE
 
151.746 4749629.99 18407.70 4708993.63 99.1
Work Order 04-18-16
Work Began 00-00-00
Work Completed  
Time Computed 04-18-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 50
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1282-02-025
FLASHER EQUIPMENT COMPANY(2.05%)
DOUBLE A CONTRACTING, L.P. (6.28%)
Contract # 12153218
Totals 4749629.99 18407.70 4708993.63 99.1

CountyEL PASO
Highway IH 10
From @ MESA
To .
CSJ 2121-01-087
Proj ID STP 2015(221)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.313 458248.26 0.00 4442.02 0.9
CountyEL PASO
Highway IH 10
From 0.48 MI E OF SUNLAND PARK DR
To 0.45 MI E OF EXECUTIVE CENTER
CSJ 2121-02-132
Proj ID NH 2015(335)
Work Type REHABILITATION
 
2.836 2487085.09 0.00 1107.04 0.0
CountyEL PASO
Highway IH 10
From MESA STREET
To EXECUTIVE CENTER
CSJ 2121-02-137
Proj ID CBI 2015(220)
Work Type COLLECTOR DISTRIBUTOR LANES
 
5.164 151231706.19 0.00 56702801.38 32.2
CountyEL PASO
Highway IH 10
From MESA STREET
To EXECUTIVE CENTER
CSJ 2121-02-154
Proj ID ROW 2121-2-154
Work Type ACQUISITION AND UTILITIES
 
7.854 4601364.66 0.00 2226242.22 48.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-19-14
Work Began 04-06-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 1,211
Addl Days Granted 51
Working Days Charged 439
Percent Time Used 34
Contractor(s)
TRADECO INFRAESTRUCTURA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-137
ZTEX CONSTRUCTION, INC.(9.00%)
TRAFFIC CONTROL SPECIALIST SALES & RENTALS (0.09%)
HARDY HOLE DRILLING(0.69%)
TRI STATE ELECTRIC, LTD. (1.25%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.69%)
SOUTHWESTERN INDUSTRIAL CONTRACTORS(0.21%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.02%)
HENRY TRUJILLO, INC. (0.01%)
A BROTHERS (OLD PRIME) (0.13%)
SUNDT CONSTRUCTION, INC. (0.00%)
TRI STATE ELECTRIC, LTD. ( 12.29%)
HARDY HOLE DRILLING(0.46%)
HARDY HOLE DRILLING(3.12%)
D"AMBRA CONSTRUCTION CORPORATION (0.10%)
PMI PAVEMENT MARKING, INC. (0.36%)
DH UNDERGROUND, INC. (0.63%)
ANTIGO CONSTRUCTION, INC.(0.04%)
ADVANCED CONCRETE SAWING & SEALING, LLC(0.34%)
ALLIED PAVING CO.(0.64%)
REBAR REINFORCEMENT PLACERS(6.83%)
EARTH REINFORCEMENT SPECIALISTS(0.99%)
CHOCTAW ERECTORS, INC. (2.49%)
SCOTT DERR PAINTING CO, LLC(0.42%)
LEEDSMAN CONSTRUCTION, INC.(1.19%)
HENRY TRUJILLO, INC. (1.14%)
BORDER DRILLING LLC(0.06%)
CRANE SERVICES, INC. (0.01%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.84%)
CANO STRUCTURES, LLC (0.81%)
KEN"S PORTABLE WELDING (0.01%)
PENHALL COMPANY(0.25%)
HERNANDEZ CONCRETE PUMPING (0.13%)
A BROTHERS MILLING, LLC(0.05%)
Contract # 10143001
Totals 158778404.20 0.00 58934592.66 32.1

CountyEL PASO
Highway IH 10
From WESTWAY
To LP 375
CSJ 2121-01-092
Proj ID C 2121-1-92
Work Type REHAB AND OPERATIONAL IMPROVEMENTS
 
3.400 12757146.91 1093763.21 12816773.19 99.9
Work Order 11-02-15
Work Began 11-30-15
Work Completed  
Time Computed 11-30-15
Contract Working Days 206
Addl Days Granted 60
Working Days Charged 221
Percent Time Used 83
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2121-01-092
BOWEN INDUSTRIAL CONTRACTORS, INC. (1.77%)
TRAFFIC BARRICADE SERVICE, INC.(0.88%)
SANCHEZ CONSTRUCTION & LANDSCAPING (5.85%)
HAWK CONSTRUCTION(1.56%)
FALC ENTERPRISES, LLC(0.94%)
SATARAIN CONSTRUCTION, INC.(7.67%)
PMI PAVEMENT MARKING, INC. (0.53%)
TRI STATE ELECTRIC, LTD. ( 12.99%)
EARTH REINFORCEMENTS LLC (0.75%)
HARDY HOLE DRILLING(1.05%)
HAWK CONSTRUCTION(0.11%)
GREATER EL PASO SANDBLASTING (0.11%)
D"AMBRA CONSTRUCTION CORPORATION (2.55%)
HDW CONSTRUCTION & DRILLING, LLC.(0.21%)
BELT CON CONSTRUCTION, INC.(0.14%)
BORDER DRILLING LLC(0.19%)
Contract # 08153207
Totals 12757146.91 1093763.21 12816773.19 99.9

CountyEL PASO
Highway IH 10
From COPIA ST (LP 478)
To CHELSEA ST
CSJ 2121-02-146
Proj ID NH 2017(025)
Work Type INSTALL HIGH MAST LIGHTING
 
1.486 1399520.76 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-21-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-146
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09163212
Totals 1399520.76 0.00 0.00 0.0

CountyEL PASO
Highway IH 10
From COPIA ST (LP 478)
To CHELSEA ST
CSJ 2121-02-151
Proj ID STP 2014(127)TE
Work Type ENHANCEMENT PROJECT
 
1.309 7584729.54 8773.00 9044268.46 99.9
Work Order 02-25-14
Work Began 04-01-14
Work Completed  
Time Computed 03-13-14
Contract Working Days 161
Addl Days Granted 100
Working Days Charged 261
Percent Time Used 100
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-151
HAWK CONSTRUCTION( 11.81%)
HARDY HOLE DRILLING(3.96%)
QUARRY HILLS, LTD. (0.13%)
HOWE PRECAST (0.40%)
EARTH REINFORCEMENT SPECIALISTS(2.79%)
HENRY TRUJILLO, INC. (1.44%)
APACHE BARRICADE & SIGN(2.33%)
BEAVER TREE SERVICE, INC.(0.22%)
NATIONWIDE REBAR INC (3.96%)
TRI STATE ELECTRIC, LTD. (1.60%)
VENEGAS ENGINEERING MANAGEMENT AND CONSTRUCTION, INC.( 31.84%)
KEN"S PORTABLE WELDING (0.06%)
VENEGAS ENGINEERING MANAGEMENT AND CONSTRUCTION, INC.(0.09%)
GREATER EL PASO SANDBLASTING ( 22.61%)
PEREZ ROCKWALL ( 16.66%)
MARQUEZ WROUGHT IRON (4.38%)
EL PASO CONCRETE CUTTERS, INC(0.14%)
Contract # 12133026
Totals 7584729.54 8773.00 9044268.46 99.9

CountyEL PASO
Highway IH 10
From PORFIRIO DIAZ ST
To MISSOURI AVE
CSJ 2121-02-152
Proj ID CC 2121-2-152
Work Type BRIDGE ENHANCEMENT
 
8.000 4677712.44 -25100.49 5738236.29 99.9
CountyEL PASO
Highway IH 10
From COPIA ST (LP 478)
To CHELSEA ST
CSJ 2121-02-155
Proj ID CC 2121-2-155
Work Type ENHANCEMENT PROJECT
 
1.309 4151891.90 250600.21 5927278.55 99.9
Work Order 05-22-14
Work Began 05-22-14
Work Completed  
Time Computed 06-07-14
Contract Working Days 218
Addl Days Granted 300
Working Days Charged 514
Percent Time Used 99
Contractor(s)
VENEGAS ENGINEERING MANAGEMENT AND CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-152
TRAFFIC BARRICADE SERVICE, INC.(0.20%)
GREATER EL PASO SANDBLASTING ( 10.88%)
HAWK CONSTRUCTION(1.04%)
TRI STATE ELECTRIC, LTD. (9.33%)
WESTSIDE WELDING INC.( 27.11%)
S. ROBERT"S IRON WORKS, INC. (0.29%)
THOMAS INDUSTRIAL COATINGS, INC. (0.96%)
EL PASO CONCRETE CUTTERS, INC(0.67%)
UNIQUE CUSTOM DRYWALL AND PAINTING DBA LUIS SIMENTAL (1.55%)
G&G ENTERPRISE (1.49%)
KASCO(4.98%)
HARDY HOLE DRILLING(7.48%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.64%)
RIVERBEND CRANE & RIGGING(3.39%)
CANYON GLASS CO. (0.53%)
HERNANDEZ CONCRETE PUMPING (0.06%)
ELIAS CONCRETE (0.07%)
GORMAN MOISTURE PROTECTION (0.07%)
PEREZ ROCKWALL (1.18%)
MANNY CARRIZAL PAINTING CO., INC.(0.09%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.12%)
Contract # 04143208
Totals 8829604.34 225499.72 11665514.84 99.9

CountyEL PASO
Highway IH 10
From IH 10 @ LP 375
To .
CSJ 2121-04-093
Proj ID C 2121-4-93
Work Type INTCHG IMPRV INCL CONSTR DIRECT CON
 
1.399 31027042.95 0.00 31183967.42 99.9
CountyEL PASO
Highway IH 10
From IH 10 @ LP 375
To .
CSJ 2121-04-103
Proj ID ROW 2121-4-103
Work Type UTILITY ONLY
 
1.399 462325.00 0.00 462477.74 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-14-14
Work Began 04-15-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 519
Addl Days Granted 0
Working Days Charged 415
Percent Time Used 79
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 2121-04-093
CHOCTAW ERECTORS, INC. ( 13.81%)
TRI STATE ELECTRIC, LTD. (8.96%)
A BROTHERS MILLING, LLC(0.18%)
HARDY HOLE DRILLING(4.67%)
NATIONWIDE REBAR INC (0.28%)
TRAFFIC CONTROL SPECIALIST SALES & RENTALS (0.98%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.99%)
PENHALL COMPANY(0.15%)
ACCURATE CORING, INC.(0.01%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.44%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.62%)
BORDER DRILLING LLC(0.09%)
ALLIED PAVING CO.(0.71%)
X GOMEZ TRANSPORTATION (0.43%)
CONCRETE PLACEMENT, INC. (0.33%)
PMI PAVEMENT MARKING, INC. (0.44%)
ER HAWKINS, LLC(0.19%)
SCOTT DERR PAINTING CO, LLC(0.49%)
GORMAN MOISTURE PROTECTION (0.04%)
Contract # 08143054
Totals 31489367.95 0.00 31646445.16 99.9

CountyEL PASO
Highway IH 10
From FM 659 (ZARAGOZA)
To EASTLAKE
CSJ 2121-04-098
Proj ID C 2121-4-98
Work Type WIDEN ROADWAY
 
3.220 12915901.72 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-02-16
Work Began 11-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 271
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2121-04-098
TRI STATE ELECTRIC, LTD. ( 10.25%)
INTERNATIONAL EAGLE ENTERPRISES, INC.( 28.09%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(6.79%)
PAVEMENT MARKINGS INC. (2.10%)
HARDY HOLE DRILLING(1.89%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.99%)
PRIME IRRIGATION & LANDSCAPE, INC. (0.59%)
Contract # 07163003
Totals 12915901.72 0.00 0.00 0.0

CountyEL PASO
Highway SL 375
From 0.5 MI W OF FMSP ENTRANCE
To 1.05 MI E OF FMSP ENTRANCE
CSJ 2552-01-054
Proj ID NH 2016(343)
Work Type IMPROVE CONNECTIVITY AT FMSP
 
2.616 3200881.70 192968.72 3060716.35 95.6
Work Order 12-21-15
Work Began 01-04-16
Work Completed  
Time Computed 01-04-16
Contract Working Days 252
Addl Days Granted 0
Working Days Charged 210
Percent Time Used 83
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2552-01-054
BOWEN INDUSTRIAL CONTRACTORS, INC. (8.33%)
HARDY HOLE DRILLING(9.67%)
EARTH REINFORCEMENTS LLC (8.49%)
NATIONWIDE REBAR INC (0.32%)
ABRI TRANSPORTATION SERVICES, LLC(0.09%)
Contract # 11153032
Totals 3200881.70 192968.72 3060716.35 95.6

CountyEL PASO
Highway SL 375
From US 62/180 (MONTANA AVE)
To BOB HOPE DR
CSJ 2552-03-054
Proj ID NH 2013(631)
Work Type WIDEN TO 6 LANES
 
7.789 21784387.32 0.00 8782618.39 40.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-10-16
Work Began 03-28-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 452
Addl Days Granted 0
Working Days Charged 149
Percent Time Used 32
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2552-03-054
TRI STATE ELECTRIC, LTD. ( 38.64%)
BORDER DRILLING LLC(0.96%)
HARDY HOLE DRILLING(1.51%)
A BROTHERS MILLING, LLC(0.14%)
PMI PAVEMENT MARKING, INC. (3.12%)
VERTEX CONTRACTORS, LLC(2.68%)
LEEDSMAN CONSTRUCTION, INC.(0.88%)
FALC ENTERPRISES, LLC(0.08%)
E. G. L. CONSTRUCTION, INC.(1.82%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(5.04%)
H.B. WELDING (0.01%)
SOUTH TEXAS PAINTING COMPANY (0.94%)
HARDY HOLE DRILLING(4.59%)
FALC ENTERPRISES, LLC(0.02%)
CRANE SERVICES, INC. (0.01%)
Contract # 12153002
Totals 21784387.32 0.00 8782618.39 40.3

CountyEL PASO
Highway SL 375
From 1.85 MI S OF FM 659
To 0.22 MI N OF FM 76
CSJ 2552-03-057
Proj ID BR 1602(072)
Work Type BRIDGE CLASS CULVERT RAIL UPGRADE
 
11.875 323840.10 0.00 336869.82 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-27-16
Work Began 07-27-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 68
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2552-03-057
HENRY TRUJILLO, INC. (2.37%)
BOWEN INDUSTRIAL CONTRACTORS, INC. ( 42.49%)
Contract # 05163012
Totals 323840.10 0.00 336869.82 99.9

CountyBREWSTER
Highway FM 1703
From 3.92 MI N OF US 67
To US 67
CSJ 2694-01-008
Proj ID STP 1502(394)HES
Work Type WIDEN PAVED SURFACE
 
37.119 1323354.80 0.00 1269373.21 95.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-20-15
Work Began 02-02-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 100
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2694-01-008
PAVEMENT MARKINGS INC. (3.41%)
HJC FARMS, INC.(3.63%)
BUYER BARRICADES (2.45%)
JARRATT DIRT WORK AND PAVING, INC. (0.00%)
HAT CONSTRUCTION, LLC(3.23%)
Contract # 08153018
Totals 1323354.80 0.00 1269373.21 95.9

CountyEL PASO
Highway SS 6
From SH 20 (DONIPHAN DR)
To DESERT SAGE ST
CSJ 3572-01-003
Proj ID STP 2014(134)TE
Work Type COMMUNITY LIGHTING AND SIDEWALK
 
0.510 242881.39 0.00 265188.69 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-21-15
Work Began 05-16-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 100
Contractor(s)
SYNERGY PROJECT CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3572-01-003
G. C. ELECTRIC ( 53.93%)
GARCOM, INC. (2.79%)
Contract # 08153019
Totals 242881.39 0.00 265188.69 99.9

CountyEL PASO
Highway SS 6
From SH 20 (MAIN ST)
To FM 1905 (ANTONIO ST)
CSJ 3572-01-004
Proj ID STP 1502(614)TP
Work Type PEDESTRIAN ENHANCEMENTS
 
1.487 1734404.30 0.00 2024405.65 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 01-19-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 40
Working Days Charged 119
Percent Time Used 99
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3572-01-004
TRAFFIC BARRICADE SERVICE, INC.(0.69%)
TRI STATE ELECTRIC, LTD. ( 28.69%)
ALLEN CONCRETE, INC. (3.48%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.36%)
BORDER DRILLING LLC(2.15%)
HARDY HOLE DRILLING(1.72%)
HENRY TRUJILLO, INC. (0.06%)
BRAVO EL PASO LANDSCAPING AND IRRIGATION (2.43%)
Contract # 08153218
Totals 1734404.30 0.00 2024405.65 99.9

CountyEL PASO
Highway SS 6
From 4TH STREET
To EAST OF DESERT SAGE STREET
CSJ 3572-01-005
Proj ID STP 1602(502)MM
Work Type CONST OF CROSSWALKS / SCHL ZONE FLSH
 
0.360 198745.08 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-15-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3572-01-005
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163020
Totals 198745.08 0.00 0.00 0.0

page 1 | page 2