| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | EL PASO |
| Highway |
VA |
| From |
CITYWIDE |
| To |
. |
| CSJ |
0924-06-413 |
| Proj ID |
STP 2012(285) |
| Work Type |
CONSTRUCTION / REHAB SIDEWALKS FY2012 |
| |
|
1.000 |
192509.02 |
864.78 |
234232.20 |
99.9 |
| Work Order |
05-15-12 |
| Work Began |
06-18-12 |
| Work Completed |
|
| Time Computed |
05-31-12 |
| Contract Working Days |
60 |
| Addl Days Granted |
13 |
| Working Days Charged |
73 |
| Percent Time Used |
100 |
| Contractor(s) |
| INTEGRATED SOLUTIONS AGGREGATE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-413 TEXAS BARRICADE SERVICE(7.79%)
|
| Contract # |
04123207 |
|
Totals |
192509.02 |
864.78 |
234232.20 |
99.9 |
|
| County | EL PASO |
| Highway |
VA |
| From |
VARIOUS LOCATIONS IN EL PASO |
| To |
. |
| CSJ |
0924-06-415 |
| Proj ID |
STP 2013(046) |
| Work Type |
CONST CURB RAMPS FOR ADA COMPLIANCE |
| |
|
1.000 |
1245534.75 |
239806.50 |
1239267.07 |
99.4 |
| Work Order |
10-18-12 |
| Work Began |
11-05-12 |
| Work Completed |
|
| Time Computed |
11-03-12 |
| Contract Working Days |
150 |
| Addl Days Granted |
0 |
| Working Days Charged |
107 |
| Percent Time Used |
71 |
| Contractor(s) |
| LESNA CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-415 C & C ROAD CONSTRUCTION, INC.( 26.78%) TEXAS BARRICADE SERVICE(3.53%) TRI STATE ELECTRIC, LTD. ( 14.44%)
|
| Contract # |
09123224 |
|
Totals |
1245534.75 |
239806.50 |
1239267.07 |
99.4 |
|
| County | EL PASO |
| Highway |
VA |
| From |
VARIOUS LOCATIONS |
| To |
(ON BU 54A AND FM 1281) |
| CSJ |
0924-06-426 |
| Proj ID |
STP 2012(582) |
| Work Type |
VEGETATIVE LANDSCAPING |
| |
|
1.000 |
539330.78 |
4900.00 |
311977.47 |
57.8 |
| Work Order |
08-10-12 |
| Work Began |
10-01-12 |
| Work Completed |
|
| Time Computed |
08-26-12 |
| Contract Working Days |
80 |
| Addl Days Granted |
23 |
| Working Days Charged |
43 |
| Percent Time Used |
41 |
| Contractor(s) |
| GARCOM, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-426 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07123013 |
|
Totals |
539330.78 |
4900.00 |
311977.47 |
57.8 |
|
| County | EL PASO |
| Highway |
PW |
| From |
INSIDE HUECO TANKS STATE PARK |
| To |
. |
| CSJ |
0924-06-428 |
| Proj ID |
C 924-6-428 |
| Work Type |
RESURFACE EXISTING ROADS |
| |
|
2.611 |
219185.33 |
0.00 |
0.00 |
0.0 |
| Work Order |
02-08-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
02-24-13 |
| Contract Working Days |
37 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| SOUTHWEST G.C.E.P., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-428 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12123216 |
|
Totals |
219185.33 |
0.00 |
0.00 |
0.0 |
|
| County | PRESIDIO |
| Highway |
FM 170 |
| From |
BIG BEND RANCH STATE RD (E) |
| To |
BREWSTER COUNTY LINE |
| CSJ |
0957-09-017 |
| Proj ID |
STP 2013(480)HES |
| Work Type |
PROVIDE ADD PAVED SURFACE WIDTH |
| |
|
28.004 |
3149302.71 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-13-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
240 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| KIEWIT INFRASTRUCTURE SOUTH CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0957-09-017 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03133228 |
|
Totals |
3149302.71 |
0.00 |
0.00 |
0.0 |
|
| County | EL PASO |
| Highway |
FM 659 |
| From |
PICASSO DR |
| To |
NEW WORLD DR |
| CSJ |
1046-01-029 |
| Proj ID |
NH 2013(559) |
| Work Type |
SIDEWALK INSTALLATION |
| |
|
0.826 |
273306.60 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ALLEN CONCRETE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1046-01-029 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04133211 |
|
Totals |
273306.60 |
0.00 |
0.00 |
0.0 |
|
| County | EL PASO |
| Highway |
IH 10 |
| From |
NEW MEXICO STATE LINE |
| To |
0.25 MI W OF VINTON INTERCHANGE |
| CSJ |
2121-01-085 |
| Proj ID |
C 2121-1-85 |
| Work Type |
CONSTRUCT RAMPS ON I - 10 NORTH |
| |
|
2.000 |
1213345.38 |
20562.22 |
1238097.98 |
99.9 |
| Work Order |
09-05-12 |
| Work Began |
09-25-12 |
| Work Completed |
|
| Time Computed |
09-21-12 |
| Contract Working Days |
120 |
| Addl Days Granted |
0 |
| Working Days Charged |
113 |
| Percent Time Used |
94 |
| Contractor(s) |
| DAN WILLIAMS COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 2121-01-085 TRI STATE ELECTRIC, LTD. ( 29.35%) RNJ CONCRETE, INC. (9.73%) A BROTHERS (0.86%) ROADSAFE TRAFFIC SYSTEMS, INC. (1.21%) HENRY TRUJILLO, INC. (0.31%)
|
| Contract # |
08123023 |
|
Totals |
1213345.38 |
20562.22 |
1238097.98 |
99.9 |
|
| County | EL PASO |
| Highway |
IH 10 |
| From |
COPIA ST (LP 478) |
| To |
CHELSEA STREET |
| CSJ |
2121-02-138 |
| Proj ID |
C 2121-2-138 |
| Work Type |
AESTHETIC DEVELOPMENT, PHASE I |
| |
|
2.046 |
8187649.10 |
742208.83 |
857919.43 |
10.4 |
| Work Order |
01-23-13 |
| Work Began |
04-15-13 |
| Work Completed |
|
| Time Computed |
02-08-13 |
| Contract Working Days |
120 |
| Addl Days Granted |
0 |
| Working Days Charged |
9 |
| Percent Time Used |
7 |
| Contractor(s) |
| CF JORDAN CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-138 GORDON"S SPECIALTIES, INC. (2.93%) TRAFFIC BARRICADE SERVICE, INC.(0.67%) HAWK CONSTRUCTION(1.74%) TRI STATE ELECTRIC, LTD. ( 42.28%) GREATER EL PASO SANDBLASTING ( 14.66%) MFH ENVIRONMENTAL CORP.( 10.74%) MOUNTAIN ELECTRIC CORPORATION(1.75%)
|
| Contract # |
12123003 |
|
Totals |
8187649.10 |
742208.83 |
857919.43 |
10.4 |
|
| County | EL PASO |
| Highway |
IH 10 |
| From |
SH 20 (MESA) |
| To |
RAYNOLDS |
| CSJ |
2121-02-141 |
| Proj ID |
CM 1102(435) |
| Work Type |
COASTCOM RING A |
| |
|
11.900 |
406328.75 |
0.00 |
219155.02 |
53.9 |
| Work Order |
03-19-12 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
04-04-12 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| TRI STATE ELECTRIC, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-141 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02123008 |
|
Totals |
406328.75 |
0.00 |
219155.02 |
53.9 |
|
| County | EL PASO |
| Highway |
IH 10 |
| From |
(ON GATEWAY) I-10/COPIA INTERCHANGE |
| To |
725' E OF IH-10/TROWBRIDGE INTERCHG |
| CSJ |
2121-02-143 |
| Proj ID |
IM 0101(259) |
| Work Type |
VEGETATIVE LANDSCAPING |
| |
|
2.800 |
178759.53 |
781.56 |
170524.89 |
95.3 |
| Work Order |
09-14-11 |
| Work Began |
10-24-11 |
| Work Completed |
|
| Time Computed |
09-30-11 |
| Contract Working Days |
20 |
| Addl Days Granted |
0 |
| Working Days Charged |
20 |
| Percent Time Used |
100 |
| Contractor(s) |
| SOUTHWEST G.C.E.P., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-143 TRAFFIC CONTROL SPECIALIST SALES AND RENTALS (0.67%) PRIME IRRIGATION & LANDSCAPE, INC. ( 50.98%)
|
| Contract # |
08113263 |
|
Totals |
178759.53 |
781.56 |
170524.89 |
95.3 |
|
| County | EL PASO |
| Highway |
IH 10 |
| From |
1.047 MILES EAST OF US 54 |
| To |
0.5 MILES EAST OF FM 659 |
| CSJ |
2121-03-142 |
| Proj ID |
IM 0101(263) |
| Work Type |
REHABILITATION |
| |
|
11.261 |
2227563.35 |
857573.76 |
935094.48 |
41.9 |
| Work Order |
10-12-12 |
| Work Began |
03-14-13 |
| Work Completed |
|
| Time Computed |
10-28-12 |
| Contract Working Days |
100 |
| Addl Days Granted |
0 |
| Working Days Charged |
34 |
| Percent Time Used |
34 |
| Contractor(s) |
| DAN WILLIAMS COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 2121-03-142 PMI PAVEMENT MARKING, INC. (3.99%) A BROTHERS MILLING, LLC(7.00%)
|
| Contract # |
09123211 |
|
Totals |
2227563.35 |
857573.76 |
935094.48 |
41.9 |
|
| County | EL PASO |
| Highway |
IH 10 |
| From |
FM 659 (ZARAGOZA RD.) |
| To |
0.19 MILES WEST OF EASTLAKE BLVD |
| CSJ |
2121-04-078 |
| Proj ID |
NH 2009(630) |
| Work Type |
ROW ACQ, UTIL ADJ, RELOC ASSIST |
| |
|
3.259 |
210532.00 |
0.00 |
0.00 |
0.0 |
| County | EL PASO |
| Highway |
IH 10 |
| From |
IH 10 @ LP 375 |
| To |
. |
| CSJ |
2121-04-088 |
| Proj ID |
IM 0101(262) |
| Work Type |
INTCHG IMPRV INCL CONSTR DIRECT CON |
| |
|
0.750 |
17898469.60 |
0.00 |
141459.40 |
0.7 |
| County | EL PASO |
| Highway |
IH 10 |
| From |
IH 10 @ LP 375 |
| To |
. |
| CSJ |
2121-04-089 |
| Proj ID |
C 2121-4-89 |
| Work Type |
INTCHG IMPRV INCL CONSTR DIRECT CON |
| |
|
0.750 |
18362784.99 |
0.00 |
80180.00 |
0.4 |
| County | EL PASO |
| Highway |
IH 10 |
| From |
IH 10 @ LP 375 |
| To |
. |
| CSJ |
2121-04-091 |
| Proj ID |
C 2121-4-91 |
| Work Type |
INTCHG IMPRV INCL CONSTR DIRECT CON |
| |
|
0.750 |
6079188.24 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
12-20-12 |
| Work Began |
04-15-13 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
460 |
| Addl Days Granted |
0 |
| Working Days Charged |
12 |
| Percent Time Used |
2 |
| Contractor(s) |
| J.D. ABRAMS, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 2121-04-088 BOWEN INDUSTRIAL CONTRACTORS, INC. (1.03%) CHOCTAW ERECTORS, INC. (1.62%) HARDY HOLE DRILLING(6.78%) PRIMATE CONSTRUCTION, INC. (0.12%) SCOTT DERR PAINTING CO (0.95%) TFW, INC.(1.64%) TRI STATE ELECTRIC, LTD. (4.66%) HENRY TRUJILLO, INC. (0.39%) HARDY HOLE DRILLING(0.15%)
|
| Contract # |
10123201 |
|
Totals |
42550974.83 |
0.00 |
221639.40 |
0.5 |
|
| County | EL PASO |
| Highway |
LP 375 |
| From |
0.038 MI W OF IH 10 AT LOOP 375 |
| To |
0.479 MI E OF FRANKLIN MT STATE PRK |
| CSJ |
2552-01-033 |
| Proj ID |
C 2552-1-33 |
| Work Type |
CONVERT NON - FREEWAY TO FREEWAY |
| |
|
3.624 |
61272749.71 |
3505556.10 |
39800778.53 |
64.9 |
| Work Order |
10-27-11 |
| Work Began |
02-06-12 |
| Work Completed |
|
| Time Computed |
02-06-12 |
| Contract Working Days |
696 |
| Addl Days Granted |
25 |
| Working Days Charged |
374 |
| Percent Time Used |
51 |
| Contractor(s) |
| SUNDT CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2552-01-033 ROADSAFE TRAFFIC SYSTEMS, INC. (0.81%) TRI STATE ELECTRIC, LTD. (9.99%) HARDY HOLE DRILLING(2.23%) TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.13%) HOWE PRECAST (0.08%) BOWNEN MACHINE & FABRICATING, INC. (0.68%) CONTECH CONSTRUCTION PRODUCTS INC. (EL PASO) (0.59%) HILL COUNTRY CULVERTS(0.10%) CMC REBAR(2.20%) TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.70%) CONCRETE PLACEMENT, INC. (0.20%) HERNANDEZ CONCRETE PUMPING (0.20%) DUSTROL, INC.(0.14%) HENRY TRUJILLO, INC. (0.25%) ASPHALT PAVERS, INC. (0.09%) COMBS CONSTRUCTION COMPANY, INC. (0.56%) ALLEN CONCRETE, INC. (1.84%) THREE C"S CONTRACTORS, INC.(1.84%) HAWK CONSTRUCTION(0.03%) CHOCTAW ERECTORS, INC. (1.43%)
|
| Contract # |
09113201 |
|
Totals |
61272749.71 |
3505556.10 |
39800778.53 |
64.9 |
|
| County | EL PASO |
| Highway |
LP 375 |
| From |
0.61 MI NE OF LP 375(ON FM 659) |
| To |
0.63 M S OF FM 659(ON LP 375) |
| CSJ |
2552-03-034 |
| Proj ID |
STP 1102(034) |
| Work Type |
CONSTRUCT INTERCHANGE |
| |
|
1.240 |
24824079.27 |
1859197.75 |
18359859.79 |
73.9 |
| County | EL PASO |
| Highway |
LP 375 |
| From |
0.61 MI NE OF LP 375(ON FM 659) |
| To |
0.63 M S OF FM 659(ON LP 375) |
| CSJ |
2552-03-046 |
| Proj ID |
NH 2011(937) |
| Work Type |
ROW ACQ. & UTIL ADJ |
| |
|
1.240 |
344793.00 |
18788.00 |
112358.00 |
32.5 |
| County | EL PASO |
| Highway |
LP 375 |
| From |
0.63 MI S OF FM 659 |
| To |
1.002 MI N OF LP 375/I-10 INTERCH |
| CSJ |
2552-03-050 |
| Proj ID |
STP 1102(035) |
| Work Type |
REMOVE / INSTALL OVERHEAD SIGNS |
| |
|
2.991 |
323677.80 |
0.00 |
13050.00 |
4.0 |
| Work Order |
06-03-11 |
| Work Began |
01-03-12 |
| Work Completed |
|
| Time Computed |
06-19-11 |
| Contract Working Days |
619 |
| Addl Days Granted |
15 |
| Working Days Charged |
397 |
| Percent Time Used |
62 |
| Contractor(s) |
| A.S. HORNER, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2552-03-034 ACCENT LANDSCAPE CONTRACTORS, INC. (0.74%) SOUTH TEXAS PAINTING COMPANY (0.75%) RIVER CITIES SAWING, LLC (0.23%) ROADSAFE, INC. (0.10%) BOWEN INDUSTRIAL CONTRACTORS, INC. (0.60%) TRI STATE ELECTRIC, LTD. (9.13%) TEXAS FAR WEST CONSTRUCTION & ENGINEERING(5.44%) SCHNABEL FOUNDATION CO. (HOUSTON)(3.69%) V.C. HUFF, L.L.C.(3.47%) HARDY HOLE DRILLING(0.26%) PAVEMENT MARKINGS INC. (0.41%) CHOCTAW ERECTORS, INC. (2.25%)
|
| Contract # |
04113202 |
|
Totals |
25492550.07 |
1877985.75 |
18485267.79 |
72.5 |
|
| County | EL PASO |
| Highway |
LP 375 |
| From |
APPROX .43 MI E OF US 54 |
| To |
APPROX .23 MI W OF ZARAGOZA RD |
| CSJ |
2552-04-029 |
| Proj ID |
HP 2011(752) |
| Work Type |
ADD TWO INSIDE TRAVEL LANES |
| |
|
8.769 |
54265535.00 |
2141157.91 |
51075025.69 |
94.1 |
| Work Order |
05-25-11 |
| Work Began |
07-07-11 |
| Work Completed |
|
| Time Computed |
06-10-11 |
| Contract Working Days |
696 |
| Addl Days Granted |
70 |
| Working Days Charged |
537 |
| Percent Time Used |
85 |
| Contractor(s) |
| J.D. ABRAMS, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 2552-04-029 TEXAS FAR WEST CONSTRUCTION & ENGINEERING( 13.69%) HARDY HOLE DRILLING(1.05%) TRI STATE ELECTRIC, LTD. ( 16.03%) CAIN FENCE (0.01%) BOWEN INDUSTRIAL CONTRACTORS, INC. (2.18%) JAVALINA CONSTRUCTION SOUTH, INC.(0.52%) ROADSAFE TRAFFIC SYSTEMS, INC. (0.96%) SOUTH TEXAS PAINTING COMPANY (0.39%) RIVER CITIES SAWING LLC(0.56%) HENRY TRUJILLO, INC. (1.24%) HARDY HOLE DRILLING(0.90%) YUCCA CONTRACTING(0.02%) DUSTROL, INC.(0.07%) SATARAIN CONSTRUCTION, INC.(0.27%) HAWK CONSTRUCTION(0.04%)
|
| Contract # |
04113204 |
|
Totals |
54265535.00 |
2141157.91 |
51075025.69 |
94.1 |
|
| County | EL PASO |
| Highway |
LP 375 |
| From |
1.0 MI E OF SANTA FE STREET |
| To |
SANTA FE STREET |
| CSJ |
2552-04-040 |
| Proj ID |
NH 2013(268) |
| Work Type |
MILL AND INLAY |
| |
|
2.000 |
842568.16 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
01-18-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
40 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| DAN WILLIAMS COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 2552-04-040 A BROTHERS MILLING, LLC(4.97%) PMI PAVEMENT MARKING, INC. (2.14%)
|
| Contract # |
12123015 |
|
Totals |
842568.16 |
0.00 |
0.00 |
0.0 |
|
| County | EL PASO |
| Highway |
SH 178 |
| From |
NEW MEXICO STATE LINE |
| To |
IH 10 |
| CSJ |
3592-01-006 |
| Proj ID |
CM 2013(048) |
| Work Type |
INTELLIGENT TRANSPORTATION SYS EXP |
| |
|
2.860 |
1102510.45 |
184098.90 |
585791.65 |
53.1 |
| Work Order |
10-12-12 |
| Work Began |
11-05-12 |
| Work Completed |
|
| Time Computed |
10-28-12 |
| Contract Working Days |
220 |
| Addl Days Granted |
0 |
| Working Days Charged |
109 |
| Percent Time Used |
49 |
| Contractor(s) |
| TRI STATE ELECTRIC, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 3592-01-006 BORDER DRILLING LLC(2.86%) BOWEN INDUSTRIAL CONTRACTORS, INC. (1.17%) HARDY HOLE DRILLING(2.59%)
|
| Contract # |
09123209 |
|
Totals |
1102510.45 |
184098.90 |
585791.65 |
53.1 |
|
| County | EL PASO |
| Highway |
SS 1966 |
| From |
US 85 (PAISANO DR) |
| To |
SCHUSTER AVE |
| CSJ |
3628-01-001 |
| Proj ID |
C 3628-1-1 |
| Work Type |
CONSTRUCTION OF SPUR |
| |
|
0.650 |
29259577.28 |
0.00 |
0.00 |
0.0 |
| County | EL PASO |
| Highway |
SS 1966 |
| From |
US 85 (PAISANO DR) |
| To |
SCHUSTER AVE |
| CSJ |
3628-01-002 |
| Proj ID |
RW 3628-1-2 |
| Work Type |
ACQ, RELOC, ASST, & UTIL ADJ |
| |
|
0.650 |
1699305.05 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-13-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
518 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| HAYDON BUILDING CORP. |
SUBCONTRACTOR(S) FOR CCSJ: 3628-01-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02133001 |
|
Totals |
30958882.33 |
0.00 |
0.00 |
0.0 |
|