Monthly State Let Construction Report For El Paso District As Of May 15, 2013 Page 2 Of 2

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEL PASO
Highway VA
From CITYWIDE
To .
CSJ 0924-06-413
Proj ID STP 2012(285)
Work Type CONSTRUCTION / REHAB SIDEWALKS FY2012
 
1.000 192509.02 864.78 234232.20 99.9
Work Order 05-15-12
Work Began 06-18-12
Work Completed  
Time Computed 05-31-12
Contract Working Days 60
Addl Days Granted 13
Working Days Charged 73
Percent Time Used 100
Contractor(s)
INTEGRATED SOLUTIONS AGGREGATE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-413
TEXAS BARRICADE SERVICE(7.79%)
Contract # 04123207
Totals 192509.02 864.78 234232.20 99.9

CountyEL PASO
Highway VA
From VARIOUS LOCATIONS IN EL PASO
To .
CSJ 0924-06-415
Proj ID STP 2013(046)
Work Type CONST CURB RAMPS FOR ADA COMPLIANCE
 
1.000 1245534.75 239806.50 1239267.07 99.4
Work Order 10-18-12
Work Began 11-05-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 71
Contractor(s)
LESNA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-415
C & C ROAD CONSTRUCTION, INC.( 26.78%)
TEXAS BARRICADE SERVICE(3.53%)
TRI STATE ELECTRIC, LTD. ( 14.44%)
Contract # 09123224
Totals 1245534.75 239806.50 1239267.07 99.4

CountyEL PASO
Highway VA
From VARIOUS LOCATIONS
To (ON BU 54A AND FM 1281)
CSJ 0924-06-426
Proj ID STP 2012(582)
Work Type VEGETATIVE LANDSCAPING
 
1.000 539330.78 4900.00 311977.47 57.8
Work Order 08-10-12
Work Began 10-01-12
Work Completed  
Time Computed 08-26-12
Contract Working Days 80
Addl Days Granted 23
Working Days Charged 43
Percent Time Used 41
Contractor(s)
GARCOM, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-426
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07123013
Totals 539330.78 4900.00 311977.47 57.8

CountyEL PASO
Highway PW
From INSIDE HUECO TANKS STATE PARK
To .
CSJ 0924-06-428
Proj ID C 924-6-428
Work Type RESURFACE EXISTING ROADS
 
2.611 219185.33 0.00 0.00 0.0
Work Order 02-08-13
Work Began 00-00-00
Work Completed  
Time Computed 02-24-13
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SOUTHWEST G.C.E.P., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-428
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12123216
Totals 219185.33 0.00 0.00 0.0

CountyPRESIDIO
Highway FM 170
From BIG BEND RANCH STATE RD (E)
To BREWSTER COUNTY LINE
CSJ 0957-09-017
Proj ID STP 2013(480)HES
Work Type PROVIDE ADD PAVED SURFACE WIDTH
 
28.004 3149302.71 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0957-09-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133228
Totals 3149302.71 0.00 0.00 0.0

CountyEL PASO
Highway FM 659
From PICASSO DR
To NEW WORLD DR
CSJ 1046-01-029
Proj ID NH 2013(559)
Work Type SIDEWALK INSTALLATION
 
0.826 273306.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ALLEN CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1046-01-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133211
Totals 273306.60 0.00 0.00 0.0

CountyEL PASO
Highway IH 10
From NEW MEXICO STATE LINE
To 0.25 MI W OF VINTON INTERCHANGE
CSJ 2121-01-085
Proj ID C 2121-1-85
Work Type CONSTRUCT RAMPS ON I - 10 NORTH
 
2.000 1213345.38 20562.22 1238097.98 99.9
Work Order 09-05-12
Work Began 09-25-12
Work Completed  
Time Computed 09-21-12
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 113
Percent Time Used 94
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2121-01-085
TRI STATE ELECTRIC, LTD. ( 29.35%)
RNJ CONCRETE, INC. (9.73%)
A BROTHERS (0.86%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.21%)
HENRY TRUJILLO, INC. (0.31%)
Contract # 08123023
Totals 1213345.38 20562.22 1238097.98 99.9

CountyEL PASO
Highway IH 10
From COPIA ST (LP 478)
To CHELSEA STREET
CSJ 2121-02-138
Proj ID C 2121-2-138
Work Type AESTHETIC DEVELOPMENT, PHASE I
 
2.046 8187649.10 742208.83 857919.43 10.4
Work Order 01-23-13
Work Began 04-15-13
Work Completed  
Time Computed 02-08-13
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 7
Contractor(s)
CF JORDAN CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-138
GORDON"S SPECIALTIES, INC. (2.93%)
TRAFFIC BARRICADE SERVICE, INC.(0.67%)
HAWK CONSTRUCTION(1.74%)
TRI STATE ELECTRIC, LTD. ( 42.28%)
GREATER EL PASO SANDBLASTING ( 14.66%)
MFH ENVIRONMENTAL CORP.( 10.74%)
MOUNTAIN ELECTRIC CORPORATION(1.75%)
Contract # 12123003
Totals 8187649.10 742208.83 857919.43 10.4

CountyEL PASO
Highway IH 10
From SH 20 (MESA)
To RAYNOLDS
CSJ 2121-02-141
Proj ID CM 1102(435)
Work Type COASTCOM RING A
 
11.900 406328.75 0.00 219155.02 53.9
Work Order 03-19-12
Work Began 00-00-00
Work Completed  
Time Computed 04-04-12
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-141
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02123008
Totals 406328.75 0.00 219155.02 53.9

CountyEL PASO
Highway IH 10
From (ON GATEWAY) I-10/COPIA INTERCHANGE
To 725' E OF IH-10/TROWBRIDGE INTERCHG
CSJ 2121-02-143
Proj ID IM 0101(259)
Work Type VEGETATIVE LANDSCAPING
 
2.800 178759.53 781.56 170524.89 95.3
Work Order 09-14-11
Work Began 10-24-11
Work Completed  
Time Computed 09-30-11
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 100
Contractor(s)
SOUTHWEST G.C.E.P., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-143
TRAFFIC CONTROL SPECIALIST SALES AND RENTALS (0.67%)
PRIME IRRIGATION & LANDSCAPE, INC. ( 50.98%)
Contract # 08113263
Totals 178759.53 781.56 170524.89 95.3

CountyEL PASO
Highway IH 10
From 1.047 MILES EAST OF US 54
To 0.5 MILES EAST OF FM 659
CSJ 2121-03-142
Proj ID IM 0101(263)
Work Type REHABILITATION
 
11.261 2227563.35 857573.76 935094.48 41.9
Work Order 10-12-12
Work Began 03-14-13
Work Completed  
Time Computed 10-28-12
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 34
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2121-03-142
PMI PAVEMENT MARKING, INC. (3.99%)
A BROTHERS MILLING, LLC(7.00%)
Contract # 09123211
Totals 2227563.35 857573.76 935094.48 41.9

CountyEL PASO
Highway IH 10
From FM 659 (ZARAGOZA RD.)
To 0.19 MILES WEST OF EASTLAKE BLVD
CSJ 2121-04-078
Proj ID NH 2009(630)
Work Type ROW ACQ, UTIL ADJ, RELOC ASSIST
 
3.259 210532.00 0.00 0.00 0.0
CountyEL PASO
Highway IH 10
From IH 10 @ LP 375
To .
CSJ 2121-04-088
Proj ID IM 0101(262)
Work Type INTCHG IMPRV INCL CONSTR DIRECT CON
 
0.750 17898469.60 0.00 141459.40 0.7
CountyEL PASO
Highway IH 10
From IH 10 @ LP 375
To .
CSJ 2121-04-089
Proj ID C 2121-4-89
Work Type INTCHG IMPRV INCL CONSTR DIRECT CON
 
0.750 18362784.99 0.00 80180.00 0.4
CountyEL PASO
Highway IH 10
From IH 10 @ LP 375
To .
CSJ 2121-04-091
Proj ID C 2121-4-91
Work Type INTCHG IMPRV INCL CONSTR DIRECT CON
 
0.750 6079188.24 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-20-12
Work Began 04-15-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 460
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 2
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2121-04-088
BOWEN INDUSTRIAL CONTRACTORS, INC. (1.03%)
CHOCTAW ERECTORS, INC. (1.62%)
HARDY HOLE DRILLING(6.78%)
PRIMATE CONSTRUCTION, INC. (0.12%)
SCOTT DERR PAINTING CO (0.95%)
TFW, INC.(1.64%)
TRI STATE ELECTRIC, LTD. (4.66%)
HENRY TRUJILLO, INC. (0.39%)
HARDY HOLE DRILLING(0.15%)
Contract # 10123201
Totals 42550974.83 0.00 221639.40 0.5

CountyEL PASO
Highway LP 375
From 0.038 MI W OF IH 10 AT LOOP 375
To 0.479 MI E OF FRANKLIN MT STATE PRK
CSJ 2552-01-033
Proj ID C 2552-1-33
Work Type CONVERT NON - FREEWAY TO FREEWAY
 
3.624 61272749.71 3505556.10 39800778.53 64.9
Work Order 10-27-11
Work Began 02-06-12
Work Completed  
Time Computed 02-06-12
Contract Working Days 696
Addl Days Granted 25
Working Days Charged 374
Percent Time Used 51
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2552-01-033
ROADSAFE TRAFFIC SYSTEMS, INC. (0.81%)
TRI STATE ELECTRIC, LTD. (9.99%)
HARDY HOLE DRILLING(2.23%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.13%)
HOWE PRECAST (0.08%)
BOWNEN MACHINE & FABRICATING, INC. (0.68%)
CONTECH CONSTRUCTION PRODUCTS INC. (EL PASO) (0.59%)
HILL COUNTRY CULVERTS(0.10%)
CMC REBAR(2.20%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.70%)
CONCRETE PLACEMENT, INC. (0.20%)
HERNANDEZ CONCRETE PUMPING (0.20%)
DUSTROL, INC.(0.14%)
HENRY TRUJILLO, INC. (0.25%)
ASPHALT PAVERS, INC. (0.09%)
COMBS CONSTRUCTION COMPANY, INC. (0.56%)
ALLEN CONCRETE, INC. (1.84%)
THREE C"S CONTRACTORS, INC.(1.84%)
HAWK CONSTRUCTION(0.03%)
CHOCTAW ERECTORS, INC. (1.43%)
Contract # 09113201
Totals 61272749.71 3505556.10 39800778.53 64.9

CountyEL PASO
Highway LP 375
From 0.61 MI NE OF LP 375(ON FM 659)
To 0.63 M S OF FM 659(ON LP 375)
CSJ 2552-03-034
Proj ID STP 1102(034)
Work Type CONSTRUCT INTERCHANGE
 
1.240 24824079.27 1859197.75 18359859.79 73.9
CountyEL PASO
Highway LP 375
From 0.61 MI NE OF LP 375(ON FM 659)
To 0.63 M S OF FM 659(ON LP 375)
CSJ 2552-03-046
Proj ID NH 2011(937)
Work Type ROW ACQ. & UTIL ADJ
 
1.240 344793.00 18788.00 112358.00 32.5
CountyEL PASO
Highway LP 375
From 0.63 MI S OF FM 659
To 1.002 MI N OF LP 375/I-10 INTERCH
CSJ 2552-03-050
Proj ID STP 1102(035)
Work Type REMOVE / INSTALL OVERHEAD SIGNS
 
2.991 323677.80 0.00 13050.00 4.0
Work Order 06-03-11
Work Began 01-03-12
Work Completed  
Time Computed 06-19-11
Contract Working Days 619
Addl Days Granted 15
Working Days Charged 397
Percent Time Used 62
Contractor(s)
A.S. HORNER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2552-03-034
ACCENT LANDSCAPE CONTRACTORS, INC. (0.74%)
SOUTH TEXAS PAINTING COMPANY (0.75%)
RIVER CITIES SAWING, LLC (0.23%)
ROADSAFE, INC. (0.10%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.60%)
TRI STATE ELECTRIC, LTD. (9.13%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(5.44%)
SCHNABEL FOUNDATION CO. (HOUSTON)(3.69%)
V.C. HUFF, L.L.C.(3.47%)
HARDY HOLE DRILLING(0.26%)
PAVEMENT MARKINGS INC. (0.41%)
CHOCTAW ERECTORS, INC. (2.25%)
Contract # 04113202
Totals 25492550.07 1877985.75 18485267.79 72.5

CountyEL PASO
Highway LP 375
From APPROX .43 MI E OF US 54
To APPROX .23 MI W OF ZARAGOZA RD
CSJ 2552-04-029
Proj ID HP 2011(752)
Work Type ADD TWO INSIDE TRAVEL LANES
 
8.769 54265535.00 2141157.91 51075025.69 94.1
Work Order 05-25-11
Work Began 07-07-11
Work Completed  
Time Computed 06-10-11
Contract Working Days 696
Addl Days Granted 70
Working Days Charged 537
Percent Time Used 85
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2552-04-029
TEXAS FAR WEST CONSTRUCTION & ENGINEERING( 13.69%)
HARDY HOLE DRILLING(1.05%)
TRI STATE ELECTRIC, LTD. ( 16.03%)
CAIN FENCE (0.01%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (2.18%)
JAVALINA CONSTRUCTION SOUTH, INC.(0.52%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.96%)
SOUTH TEXAS PAINTING COMPANY (0.39%)
RIVER CITIES SAWING LLC(0.56%)
HENRY TRUJILLO, INC. (1.24%)
HARDY HOLE DRILLING(0.90%)
YUCCA CONTRACTING(0.02%)
DUSTROL, INC.(0.07%)
SATARAIN CONSTRUCTION, INC.(0.27%)
HAWK CONSTRUCTION(0.04%)
Contract # 04113204
Totals 54265535.00 2141157.91 51075025.69 94.1

CountyEL PASO
Highway LP 375
From 1.0 MI E OF SANTA FE STREET
To SANTA FE STREET
CSJ 2552-04-040
Proj ID NH 2013(268)
Work Type MILL AND INLAY
 
2.000 842568.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-18-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2552-04-040
A BROTHERS MILLING, LLC(4.97%)
PMI PAVEMENT MARKING, INC. (2.14%)
Contract # 12123015
Totals 842568.16 0.00 0.00 0.0

CountyEL PASO
Highway SH 178
From NEW MEXICO STATE LINE
To IH 10
CSJ 3592-01-006
Proj ID CM 2013(048)
Work Type INTELLIGENT TRANSPORTATION SYS EXP
 
2.860 1102510.45 184098.90 585791.65 53.1
Work Order 10-12-12
Work Began 11-05-12
Work Completed  
Time Computed 10-28-12
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 109
Percent Time Used 49
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3592-01-006
BORDER DRILLING LLC(2.86%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (1.17%)
HARDY HOLE DRILLING(2.59%)
Contract # 09123209
Totals 1102510.45 184098.90 585791.65 53.1

CountyEL PASO
Highway SS 1966
From US 85 (PAISANO DR)
To SCHUSTER AVE
CSJ 3628-01-001
Proj ID C 3628-1-1
Work Type CONSTRUCTION OF SPUR
 
0.650 29259577.28 0.00 0.00 0.0
CountyEL PASO
Highway SS 1966
From US 85 (PAISANO DR)
To SCHUSTER AVE
CSJ 3628-01-002
Proj ID RW 3628-1-2
Work Type ACQ, RELOC, ASST, & UTIL ADJ
 
0.650 1699305.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 518
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 3628-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133001
Totals 30958882.33 0.00 0.00 0.0