Monthly State Let Construction Report For El Paso District As Of May 15, 2013 Page 1 Of 2

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEL PASO
Highway SH 20
From BOONE STREET
To 600 FT E OF CONCEPCION ST
CSJ 0002-01-074
Proj ID NH 2011(327)
Work Type INTERSECTION IMPROVEMENTS AND REHAB
 
0.875 5607003.00 509414.09 5481320.26 97.7
CountyEL PASO
Highway SH 20
From BOONE STREET
To 600 FT E OF CONCEPCION ST
CSJ 0002-01-082
Proj ID RW 2-1-82
Work Type ROW ACQUISITION
 
1.472 1053076.70 6300.00 1191024.69 99.9
Work Order 10-24-11
Work Began 01-23-12
Work Completed  
Time Computed 01-23-12
Contract Working Days 240
Addl Days Granted 98
Working Days Charged 336
Percent Time Used 99
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0002-01-074
TRI STATE ELECTRIC, LTD. ( 12.27%)
A BROTHERS (1.06%)
ROAD MARKINGS INC. (0.90%)
THREE C"S CONTRACTORS, INC.(0.42%)
DH UNDERGROUND, INC. (0.30%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(6.50%)
RNJ CONCRETE, INC. (2.70%)
Contract # 09113026
Totals 6660079.70 515714.09 6672344.95 99.9

CountyEL PASO
Highway SH 20
From 0.06 MI N OF HORIZON BLVD
To 0.07 MI S OF HORIZON BLDV
CSJ 0002-02-050
Proj ID STP 2013(147)
Work Type RECONSTRUCT INTERSECTION
 
0.229 1129305.88 0.00 0.00 0.0
CountyEL PASO
Highway MH
From 0.09 MI W OF SH 20 (ALAMEDA)
To 0.06 MI W OF FM 76 (NORTH LOOP)
CSJ 8056-24-001
Proj ID STP 2009(791)
Work Type RECONSTRUCTING AND WIDENING
 
1.190 4596242.98 0.00 0.00 0.0
CountyEL PASO
Highway MH
From 0.09 MI W OF SH 20 (ALAMEDA)
To 0.06 MI W OF FM 76 (NORTH LOOP)
CSJ 8056-24-003
Proj ID RW 8056-24-3
Work Type ROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
1.190 1779757.14 0.00 0.00 0.0
Work Order 11-09-12
Work Began 00-00-00
Work Completed  
Time Computed 11-25-12
Contract Working Days 290
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 8056-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09123021
Totals 7505306.00 0.00 0.00 0.0

CountyHUDSPETH
Highway IH 10
From APPROX 4.1 MI W OF LASCA RD
To 0.689 MI W OF I-10 AND LASCA RD
CSJ 0002-06-050
Proj ID C 2-6-50
Work Type CONSTRUCT CLIMBING LANE
 
3.000 2840928.35 455937.95 2548813.25 89.7
CountyHUDSPETH
Highway IH 10
From 0.3 MI W OF I-10/LASCA INTERSECTION
To 1.7 MI E OF I-10/LASCA INTERSECTION
CSJ 0002-07-043
Proj ID BR 2012(645)
Work Type BRIDGE REPLACEMENT
 
2.759 2778636.20 385859.20 2148452.84 77.3
Work Order 08-28-12
Work Began 09-13-12
Work Completed  
Time Computed 09-13-12
Contract Working Days 200
Addl Days Granted 25
Working Days Charged 167
Percent Time Used 74
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0002-07-043
TRI STATE ELECTRIC, LTD. (0.90%)
HARDY HOLE DRILLING(2.12%)
A BROTHERS MILLING, LLC(0.00%)
DUSTROL, INC.(0.02%)
ROAD SAFE(1.63%)
Contract # 07123020
Totals 5619564.55 841797.15 4697266.09 83.5

CountyEL PASO
Highway FM 258
From LP 375 (AMERICAS)
To WINN
CSJ 0002-14-037
Proj ID STP 1102(015)HES
Work Type CONTINUOUS LIGHTING
 
4.000 1613265.95 0.00 1692940.60 99.9
Work Order 07-27-11
Work Began 09-06-11
Work Completed  
Time Computed 08-12-11
Contract Working Days 100
Addl Days Granted 7
Working Days Charged 99
Percent Time Used 92
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0002-14-037
GARCOM, INC. ( 11.58%)
SUPERIOR SIGN AND LIGHTING (2.72%)
HIGHWAY TECHNOLOGIES, INC. (0.84%)
Contract # 05113011
Totals 1613265.95 0.00 1692940.60 99.9

CountyHUDSPETH
Highway BI 10-C ETC
From IH 10 WEST OF SIERRA BLANCA
To IH 10 EAST OF SIERRA BLANCA
CSJ 0002-19-009
Proj ID STP 2013(267)
Work Type SEAL COAT
 
51.717 2294382.94 0.00 28523.17 1.2
Work Order 02-22-13
Work Began 00-00-00
Work Completed  
Time Computed 03-10-13
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COX PAVING COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0002-19-009
BLACKTOPPER TECHNOLOGY, INC. ( 28.36%)
FLASHER EQUIPMENT COMPANY(0.94%)
DOUBLE A CONTRACTING, L.P. (3.19%)
Contract # 12123222
Totals 2294382.94 0.00 28523.17 1.2

CountyEL PASO
Highway US 54
From AT LP 375
To .
CSJ 0167-01-106
Proj ID STP 1102(033)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.100 359618.50 0.00 314669.16 87.5
CountyEL PASO
Highway LP 375
From US 54 (GATEWAY BLVD SOUTH)
To BU 54 (DYER ST)
CSJ 2552-01-036
Proj ID STP 1102(031)
Work Type CONSTRUCT MAIN LANES AND INTERCHANG
 
1.875 36214322.88 2246928.56 30352301.79 83.8
CountyEL PASO
Highway LP 375
From 1 M WEST OF US 54
To US 54 (GATEWAY BLVD SOUTH)
CSJ 2552-01-038
Proj ID NH 1102(032)
Work Type CONSTRUCTION OF UNDERPASS MAINLANES
 
0.846 11122609.24 217581.99 5587160.18 50.2
CountyEL PASO
Highway LP 375
From US 54 (GATEWAY BLVD SOUTH)
To BU 54 (DYER STREET)
CSJ 2552-01-040
Proj ID NH 2011(936)
Work Type ROW ACQ & UTL ADJ
 
3.220 1970294.50 0.00 1467690.91 74.4
Work Order 05-25-11
Work Began 12-12-11
Work Completed  
Time Computed 06-10-11
Contract Working Days 504
Addl Days Granted 80
Working Days Charged 341
Percent Time Used 58
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2552-01-036
A BROTHERS MILLING, LLC(0.25%)
DANRIDGE CONSTRUCTION, LLC.(0.51%)
UNINTECH CONSULTING ENGINEERS, INC.(0.08%)
SATARAIN CONSTRUCTION, INC.(0.92%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.36%)
THREE C"S CONTRACTORS, INC.(0.16%)
HARDY HOLE DRILLING(1.40%)
HENRY TRUJILLO, INC. (0.32%)
SOUTH TEXAS PAINTING COMPANY (0.37%)
RIVER CITIES SAWING LLC(0.20%)
ROAD MARKINGS INC. (0.35%)
TRI STATE ELECTRIC, LTD. ( 10.22%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(4.42%)
STEEL EFFECTS(0.64%)
FORET COMPANIES(0.07%)
ACCURATE CORING, INC.(0.03%)
EARTH REINFORCEMENT SPECIALISTS(1.75%)
STAR CITY SEALANTS (0.01%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.31%)
Contract # 04113201
Totals 49666845.12 2464510.55 37721822.04 75.9

CountyEL PASO
Highway US 54
From SH 20 (ALAMEDA)
To 1 M N OF FM 2529 (MCCOMBS)
CSJ 0167-01-107
Proj ID STP 2013(044)MM
Work Type DYNAMIC MESSAGE SYS BOARDS INSTALLA
 
13.810 619752.75 150730.00 261390.00 42.1
Work Order 10-12-12
Work Began 02-18-13
Work Completed  
Time Computed 02-18-13
Contract Working Days 295
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 17
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-107
HARDY HOLE DRILLING(7.28%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (4.82%)
Contract # 09123023
Totals 619752.75 150730.00 261390.00 42.1

CountyEL PASO
Highway US 54
From IH 10
To BOTA POE
CSJ 0167-01-109
Proj ID NH 2012(701)
Work Type SIGNING / PAVEMENT MARKINGS
 
3.243 677583.35 61909.80 678136.90 99.9
Work Order 09-24-12
Work Began 01-14-13
Work Completed  
Time Computed 10-10-12
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 100
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-109
HARDY HOLE DRILLING(5.82%)
ROADSAFE TRAFFIC SYSTEMS, INC. (7.52%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.98%)
Contract # 08123014
Totals 677583.35 61909.80 678136.90 99.9

CountyCULBERSON
Highway US 62
From 10 MI E OF SH 54
To 20 MI E OF SH 54
CSJ 0233-01-043
Proj ID STP 2013(770)
Work Type SEAL COAT
 
10.000 609719.91 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COX PAVING COMPANY OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0233-01-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133233
Totals 609719.91 0.00 0.00 0.0

CountyEL PASO
Highway US 62
From 0.633 MI E OF FM 659
To 2.640 MI W OF RM 2775
CSJ 0374-02-098
Proj ID NH 2013(558)
Work Type MILL AND INLAY
 
5.558 1672455.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0374-02-098
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133009
Totals 1672455.60 0.00 0.00 0.0

CountyJEFF DAVIS
Highway SH 118
From SH 166
To 0.6 MI NE OF EPPENAUER (W)
CSJ 0415-02-024
Proj ID STP 2012(016)HES
Work Type PROVIDE ADD PAVED SURFACE WIDTH
 
12.706 836423.40 0.00 820748.45 98.1
CountyJEFF DAVIS
Highway SH 118
From SH 166
To 0.6 MI NE OF EPPENAUER (W)
CSJ 0415-02-025
Proj ID STP 2012(017)
Work Type SEAL COAT
 
12.706 523195.10 0.00 548273.60 99.9
CountyEL PASO
Highway VA
From JEFF DAVIS AND PRESIDIO COUNTIES
To .
CSJ 0924-00-071
Proj ID STP 2012(017)
Work Type IMPROVE GUARDRAIL
 
18.088 1221869.50 12021.00 1204021.46 99.9
Work Order 10-13-11
Work Began 02-20-12
Work Completed  
Time Computed 11-17-11
Contract Working Days 180
Addl Days Granted 11
Working Days Charged 217
Percent Time Used 113
Contractor(s)
DANNY SANDER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-071
K-CONTRACTING, INC.( 32.81%)
TEX OP CONSTRUCTION, LP( 13.44%)
RONALD R. WAGNER & CO., LP ( 10.61%)
FLASHER EQUIPMENT COMPANY(4.22%)
RPV CONSTRUCTION (1.34%)
Contract # 09113206
Totals 2581488.00 12021.00 2573043.51 99.9

CountyEL PASO
Highway SP 276
From SH 20, 0.168 MI N OF BORDERLAND RD
To SOUTH DESERT BLVD
CSJ 0608-01-001
Proj ID STP 2012(390)MM
Work Type GR, STRS, ACP, SIGN & DEL
 
2.198 12311210.24 1190808.02 3828690.85 31.0
CountyEL PASO
Highway SP 276
From SH 20, 0.168 MI N OF BORDERLAND RD
To SOUTH DESERT BLVD
CSJ 0608-01-002
Proj ID STP 1102(539)MM
Work Type ROW ACQ. & UTIL ADJUST.
 
1.608 660927.00 173133.30 631572.14 95.5
Work Order 10-18-12
Work Began 01-02-13
Work Completed  
Time Computed 01-02-13
Contract Working Days 576
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 17
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0608-01-001
SATARAIN CONSTRUCTION, INC.(4.87%)
HARDY HOLE DRILLING(0.61%)
TRI STATE ELECTRIC, LTD. ( 16.69%)
ACCENT LANDSCAPE CONTRACTORS, INC. (3.41%)
A BROTHERS (0.16%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.15%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.18%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.30%)
HENRY TRUJILLO, INC. (1.29%)
BORDER DRILLING LLC(0.02%)
Contract # 08123205
Totals 12972137.24 1363941.32 4460262.99 34.3

CountyEL PASO
Highway FM 76
From 0.3 MI W OF THE CITY LIMITS
To 0.28 MI E OF FM 1281 (HORIZON BLVD)
CSJ 0674-01-037
Proj ID STP 2012(183)
Work Type GR, STRS & SURF
 
2.850 17477183.46 6200.00 2655472.91 15.1
CountyEL PASO
Highway FM 76
From 0.3 MILES WEST OF THE CITY LIMITS
To 0.28 MILES E. OF FM 1281 (HORIZON B
CSJ 0674-01-058
Proj ID RW 674-1-58
Work Type ACQUISITION, UTILITIES AND RELOCATI
 
0.001 1317086.00 0.00 0.00 0.0
Work Order 01-31-12
Work Began 07-02-12
Work Completed  
Time Computed 02-01-12
Contract Working Days 510
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 25
Contractor(s)
CF JORDAN CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0674-01-037
D"AMBRA STEEL SERVICES, INC. (HUB) (8.20%)
A BROTHERS (0.24%)
PRIME IRRIGATION & LANDSCAPE, INC. (0.89%)
SANCHEZ CONSTRUCTION & LANDSCAPING (1.98%)
TRI STATE ELECTRIC, LTD. ( 11.87%)
RNJ CONCRETE, INC. (5.82%)
PALO VERDE CONSTRUCTORS(3.03%)
C & C ROAD CONSTRUCTION, INC.(1.19%)
TRAFFIC BARRICADE SERVICE, INC.(0.69%)
Contract # 12113202
Totals 18794269.46 6200.00 2655472.91 14.1

CountyEL PASO
Highway VA
From TRI-COUNTY WIDE
To .
CSJ 0924-00-072
Proj ID STP 2012(329)
Work Type RURAL SIGNING PROJECT
 
1.000 824253.00 87180.95 719236.91 87.2
CountyEL PASO
Highway VA
From TRI-COUNTY WIDE
To .
CSJ 0924-00-087
Proj ID C 924-00-87
Work Type RURAL SIGNING PROJECT
 
1.000 124695.00 8955.00 80853.76 64.8
Work Order 03-12-12
Work Began 09-17-12
Work Completed  
Time Computed 06-12-12
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 139
Percent Time Used 99
Contractor(s)
DANNY SANDER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02123013
Totals 948948.00 96135.95 800090.67 84.3

CountyEL PASO
Highway VA
From DISTRICTWIDE
To .
CSJ 0924-00-077
Proj ID STP 2012(473)
Work Type REP SPALDG, SCOUR, JT REP, CL & SEAL
 
1.000 1045324.50 0.00 1139211.88 99.9
Work Order 05-10-12
Work Began 07-10-12
Work Completed  
Time Computed 06-26-12
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 115
Percent Time Used 106
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-077
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04123013
Totals 1045324.50 0.00 1139211.88 99.9

CountyEL PASO
Highway VA
From DISTRICTWIDE
To .
CSJ 0924-00-078
Proj ID STP 2013(188)
Work Type BRIDGE MAINTENANCE PROGRAM
 
1.000 536822.00 64704.00 137308.00 25.5
Work Order 11-30-12
Work Began 02-04-13
Work Completed  
Time Computed 12-16-12
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 41
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-078
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11123210
Totals 536822.00 64704.00 137308.00 25.5

CountyEL PASO
Highway VA
From DISTRICTWIDE
To .
CSJ 0924-00-085
Proj ID STP 2012(658)
Work Type METAL BEAM GUARD FENCE / SGT UPGRADES
 
1.000 932967.50 29632.08 921018.00 99.5
Work Order 08-21-12
Work Began 10-01-12
Work Completed  
Time Computed 09-06-12
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 112
Percent Time Used 112
Contractor(s)
MARTINEZ BROS. CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07123213
Totals 932967.50 29632.08 921018.00 99.5

CountyEL PASO
Highway VA
From CITYWIDE
To .
CSJ 0924-06-377
Proj ID NH 2013(045)
Work Type HIGHWAY ADVISORY RADIO SYSTEM
 
0.100 340789.00 0.00 0.00 0.0
Work Order 10-12-12
Work Began 00-00-00
Work Completed  
Time Computed 10-28-12
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-377
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09123218
Totals 340789.00 0.00 0.00 0.0

CountyEL PASO
Highway VA
From CAMPESTRE ELEMENTARY
To (CITY OF SOCORRO)
CSJ 0924-06-389
Proj ID STP 2012(244)SRS
Work Type SRTS INFRASTRUCTURE PROJECT
 
8.000 2069631.03 181141.87 846915.65 40.9
Work Order 11-30-12
Work Began 01-10-13
Work Completed  
Time Computed 12-16-12
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 47
Contractor(s)
GARCOM, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-389
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11123010
Totals 2069631.03 181141.87 846915.65 40.9

CountyEL PASO
Highway VA
From CITYWIDE
To .
CSJ 0924-06-409
Proj ID STP 1102(174)
Work Type CITYWIDE SIGN UPGRADE PROJECT
 
1.000 404813.62 21509.67 417792.41 99.9
Work Order 08-15-11
Work Began 03-25-13
Work Completed  
Time Computed 08-31-11
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 85
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-409
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07113208
Totals 404813.62 21509.67 417792.41 99.9

page 1 | page 2