| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | EL PASO |
| Highway |
SH 20 |
| From |
BALTIMORE ST. |
| To |
CINCINNATI AVE. |
| CSJ |
0001-02-049 |
| Proj ID |
STP 2008(668) |
| Work Type |
FY 06 SUPPLEMENTAL REHABILITATION |
| |
|
0.068 |
146154.65 |
0.00 |
0.00 |
0.0 |
| County | EL PASO |
| Highway |
SH 20 |
| From |
CINCINNATI AVE. |
| To |
0.023 MI SOUTH OF E YANDELL ST. |
| CSJ |
0001-03-053 |
| Proj ID |
STP 2008(668) |
| Work Type |
FY 06 SUPPLEMENTAL REHABILITATION |
| |
|
1.279 |
1971378.50 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
09-12-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
04-01-09 |
| Contract Working Days |
86 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| C.F. JORDAN, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0001-02-049 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08083028 |
|
Totals |
2117533.15 |
0.00 |
0.00 |
0.0 |
|
| County | EL PASO |
| Highway |
SH 20 |
| From |
SH 20 (MESA ST) @ SUN BOWL |
| To |
SH 20 (MESA ST) @ EXECUTIVE CENTER |
| CSJ |
0001-02-050 |
| Proj ID |
NH 2007(464) |
| Work Type |
LANDSCAPE MEDIANS |
| |
|
0.750 |
200437.45 |
1850.00 |
192047.45 |
95.8 |
| County | EL PASO |
| Highway |
VA |
| From |
HAWKINS BLVD @ IH - 10 WEST |
| To |
HAWKINS BLVD @ US 62/180(MONTANA AV |
| CSJ |
0924-06-243 |
| Proj ID |
STP 2007(076)MM |
| Work Type |
MEDIAN IMPROVEMENTS |
| |
|
1.750 |
549473.40 |
1850.00 |
566275.90 |
99.9 |
| Work Order |
06-05-07 |
| Work Began |
07-09-07 |
| Work Completed |
|
| Time Computed |
06-21-07 |
| Contract Working Days |
80 |
| Addl Days Granted |
11 |
| Working Days Charged |
91 |
| Percent Time Used |
100 |
| Contractor(s) |
| C & C ROAD CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-243 THREE C'S CONTRACTORS( 33.39%) HARDY HOLE DRILLING(3.46%) XPERT ROAD CONSTRUCTION INC. (2.84%)
|
| Contract # |
04073222 |
|
Totals |
749910.85 |
3700.00 |
758323.35 |
99.9 |
|
| County | EL PASO |
| Highway |
SH 20 ETC |
| From |
@ SH 20 AND SCHUSTER |
| To |
. |
| CSJ |
0001-03-054 |
| Proj ID |
STP 2007(419)HES |
| Work Type |
IMPROVE TRAFFIC SIGNAL |
| |
|
3.000 |
1549583.75 |
6000.00 |
1661350.76 |
99.9 |
| Work Order |
05-15-07 |
| Work Began |
01-08-08 |
| Work Completed |
|
| Time Computed |
05-31-07 |
| Contract Working Days |
100 |
| Addl Days Granted |
0 |
| Working Days Charged |
213 |
| Percent Time Used |
213 |
| Contractor(s) |
| TRI STATE ELECTRIC, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0001-03-054 MOUNTAIN STAR CONSTRUCTION (6.55%) HARDY HOLE DRILLING(0.89%) ROAD MARKINGS INC. (3.11%)
|
| Contract # |
04073018 |
|
Totals |
1549583.75 |
6000.00 |
1661350.76 |
99.9 |
|
| County | EL PASO |
| Highway |
SH 20 |
| From |
DELTA |
| To |
LOOP 375 |
| CSJ |
0002-01-080 |
| Proj ID |
CM 2008(825) |
| Work Type |
ALAMEDA TRAFFIC SIGNAL INTERCONNECT |
| |
|
10.000 |
1634478.50 |
0.00 |
0.00 |
0.0 |
| Work Order |
09-16-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
10-02-08 |
| Contract Working Days |
220 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| TRI STATE ELECTRIC, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0002-01-080 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08083213 |
|
Totals |
1634478.50 |
0.00 |
0.00 |
0.0 |
|
| County | EL PASO |
| Highway |
SH 20 |
| From |
LOOP 375 |
| To |
FABENS |
| CSJ |
0002-02-046 |
| Proj ID |
MG 2005(694) |
| Work Type |
GDRL PLMT AT EXIS IRR STRUC LOC |
| |
|
15.200 |
236939.10 |
0.00 |
267903.37 |
99.9 |
| County | EL PASO |
| Highway |
FM 258 |
| From |
16.2 MILES EAST ON FM 258 |
| To |
FABENS |
| CSJ |
0002-14-025 |
| Proj ID |
STP 2005(695)SFT |
| Work Type |
GDRL PLMT AT EXIS IRR STRUC LOC |
| |
|
16.200 |
355702.00 |
0.00 |
274482.48 |
77.1 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
11-29-06 |
| Work Began |
01-04-07 |
| Work Completed |
|
| Time Computed |
12-15-06 |
| Contract Working Days |
120 |
| Addl Days Granted |
0 |
| Working Days Charged |
153 |
| Percent Time Used |
127 |
| Contractor(s) |
| C & C ROAD CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0002-02-046 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10063227 |
|
Totals |
592641.10 |
0.00 |
542385.85 |
94.8 |
|
| County | HUDSPETH |
| Highway |
IH 10 |
| From |
@ THE BORDER CHECKPOINT STATION |
| To |
. |
| CSJ |
0002-07-041 |
| Proj ID |
IM 0101(241) |
| Work Type |
GR, STR EXTS, EMBK, ACP, CRCP, COSS, SIGN |
| |
|
3.000 |
3330288.09 |
240055.52 |
2692518.44 |
80.8 |
| Work Order |
07-24-07 |
| Work Began |
03-17-08 |
| Work Completed |
|
| Time Computed |
08-09-07 |
| Contract Working Days |
120 |
| Addl Days Granted |
0 |
| Working Days Charged |
120 |
| Percent Time Used |
100 |
| Contractor(s) |
| C & C ROAD CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0002-07-041 TRI STATE ELECTRIC, LTD. ( 27.85%)
|
| Contract # |
06073024 |
|
Totals |
3330288.09 |
240055.52 |
2692518.44 |
80.8 |
|
| County | EL PASO |
| Highway |
FM 258 ETC |
| From |
FM 258 (SOCORRO) AT ZEBU |
| To |
. |
| CSJ |
0002-14-030 |
| Proj ID |
C 2-14-30 |
| Work Type |
TRAFFIC SIGNAL INSTALLATION |
| |
|
0.500 |
840475.90 |
0.00 |
726299.99 |
90.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
08-15-07 |
| Work Began |
02-13-08 |
| Work Completed |
|
| Time Computed |
08-31-07 |
| Contract Working Days |
160 |
| Addl Days Granted |
0 |
| Working Days Charged |
160 |
| Percent Time Used |
100 |
| Contractor(s) |
| TRI STATE ELECTRIC, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0002-14-030 MOUNTAIN STAR CONSTRUCTION ( 10.36%) ROAD MARKINGS INC. ( 10.13%)
|
| Contract # |
07073214 |
|
Totals |
840475.90 |
0.00 |
726299.99 |
90.9 |
|
| County | CULBERSON |
| Highway |
IH 10 |
| From |
12.56 MI W CULBERSON/JEFF DAVIS C L |
| To |
0.04 MI W CULBERSON/JEFF DAVIS C L |
| CSJ |
0003-03-041 |
| Proj ID |
IM 0101(244) |
| Work Type |
MILL AND OVERLAY |
| |
|
12.520 |
9306863.92 |
1748705.59 |
6292860.82 |
67.6 |
| Work Order |
04-14-08 |
| Work Began |
06-03-08 |
| Work Completed |
|
| Time Computed |
04-30-08 |
| Contract Working Days |
120 |
| Addl Days Granted |
0 |
| Working Days Charged |
105 |
| Percent Time Used |
87 |
| Contractor(s) |
| C & C ROAD CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0003-03-041 HIGHWAY TECHNOLOGIES (0.51%) TEX OP CONSTRUCTION, LP(3.83%) ROAD MARKINGS INC. (2.26%) XPERT ROAD CONSTRUCTION INC. ( 10.88%) TEXAS HIGHWAY BARRICADES & SIGNS INC (0.51%)
|
| Contract # |
03083229 |
|
Totals |
9306863.92 |
1748705.59 |
6292860.82 |
67.6 |
|
| County | PRESIDIO |
| Highway |
US 67 |
| From |
.8 MI S OF US 90 |
| To |
3.645 MILES N OF PEDIZ CREEK |
| CSJ |
0104-06-022 |
| Proj ID |
STP 2008(705)HES |
| Work Type |
SAFETY TREAT FIXED OBJECTS |
| |
|
12.247 |
2025091.55 |
0.00 |
0.00 |
0.0 |
| County | PRESIDIO |
| Highway |
US 67 |
| From |
.1 MI N OF PERDIZ CREEK |
| To |
.1 MI S OF PERDIZ CREEK |
| CSJ |
0104-07-019 |
| Proj ID |
STP 2008(705)HES |
| Work Type |
SAFETY TREAT FIXED OBJECTS |
| |
|
0.200 |
52044.80 |
0.00 |
0.00 |
0.0 |
| Work Order |
10-09-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
10-25-08 |
| Contract Working Days |
180 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| MANN CONTRACTORS, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0104-06-022 ROAD MARKINGS INC. (0.82%) W.S. CONSTRUCTION COMPANY(6.19%) W. W. FOUNDATION DRILLING, LTD.(8.66%)
|
| Contract # |
08083017 |
|
Totals |
2077136.35 |
0.00 |
0.00 |
0.0 |
|
| County | EL PASO |
| Highway |
US 54 |
| From |
YANDELL DRIVE OVERPASS |
| To |
APPROX. 1200 FT N OF HONDO PASS DR |
| CSJ |
0167-01-081 |
| Proj ID |
STP 2006(434)MM |
| Work Type |
GR, BA, CPCR, SURF & STRUC |
| |
|
6.347 |
32478827.58 |
338596.80 |
27634838.33 |
85.4 |
| Work Order |
06-05-06 |
| Work Began |
07-21-06 |
| Work Completed |
|
| Time Computed |
06-21-06 |
| Contract Working Days |
549 |
| Addl Days Granted |
0 |
| Working Days Charged |
605 |
| Percent Time Used |
110 |
| Contractor(s) |
| J.D. ABRAMS, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-081 HARDY HOLE DRILLING(1.12%) TRI STATE ELECTRIC, LTD. ( 21.42%) RAMIREZ BROTHERS CONCRETE CONSTRUCTION COMPANY (0.63%) MOUNTAIN ELECTRIC CORPORATION(5.55%) RUTHERFORD DIVERSIFIED INDUSTRIES, INC.(0.31%) TEX OP CONSTRUCTION, LP(0.27%) ROAD MARKINGS INC. (2.07%) SCOTT DERR PAINTING CO (0.20%) J.L. STEEL, L.P. (0.87%) HARDY HOLE DRILLING(0.28%) TRUJILLO TRUCKING(0.43%) HOUSTON SAWING & DRILLING(0.06%)
|
| Contract # |
04063217 |
|
Totals |
32478827.58 |
338596.80 |
27634838.33 |
85.4 |
|
| County | EL PASO |
| Highway |
US 54 ETC |
| From |
ZARAGOSA ROAD (FM 659) |
| To |
HORIZON BLVD (FM 1281) |
| CSJ |
0167-01-092 |
| Proj ID |
CM 2005(338) |
| Work Type |
UPGRADING LOOP DETECTORS: PHASE I |
| |
|
47.829 |
2165361.50 |
0.00 |
2005317.32 |
97.4 |
| Work Order |
08-04-05 |
| Work Began |
01-02-07 |
| Work Completed |
|
| Time Computed |
08-20-05 |
| Contract Working Days |
180 |
| Addl Days Granted |
65 |
| Working Days Charged |
245 |
| Percent Time Used |
100 |
| Contractor(s) |
| TRI STATE ELECTRIC, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-092 TEXAS FAR WEST CONSTRUCTION & ENGINEERING(5.97%) ROAD MARKINGS INC. (1.44%) HARDY HOLE DRILLING(0.08%)
|
| Contract # |
06053057 |
|
Totals |
2165361.50 |
0.00 |
2005317.32 |
97.4 |
|
| County | JEFF DAVIS |
| Highway |
SH 118 |
| From |
6.507 MILES SOUTH OF FORT DAVIS |
| To |
BREWSTER/JEFF DAVIS COUNTY LINE |
| CSJ |
0358-01-024 |
| Proj ID |
STP 2007(026) |
| Work Type |
MILL AND INLAY OF EXISTING ROADWAY |
| |
|
8.653 |
3602686.86 |
36161.05 |
1571172.78 |
43.6 |
| Work Order |
08-15-07 |
| Work Began |
07-07-08 |
| Work Completed |
|
| Time Computed |
08-31-07 |
| Contract Working Days |
110 |
| Addl Days Granted |
0 |
| Working Days Charged |
31 |
| Percent Time Used |
28 |
| Contractor(s) |
| REECE ALBERT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0358-01-024 NITE LITE, INC.(2.06%) CHEROKEE SERVICES(3.87%) 76 MILLING, INC. (1.11%)
|
| Contract # |
07073009 |
|
Totals |
3602686.86 |
36161.05 |
1571172.78 |
43.6 |
|
| County | EL PASO |
| Highway |
US 62 |
| From |
1.473MI(2.731)E OF FM659 (ZARAGOZA) |
| To |
3.262MI(5.250KM)W OF FM2775(HUECO T |
| CSJ |
0374-02-072 |
| Proj ID |
NH 2007(743) |
| Work Type |
MISCELLANEOUS WORK |
| |
|
4.035 |
1719655.40 |
12811.67 |
1727211.13 |
99.9 |
| Work Order |
09-14-07 |
| Work Began |
11-26-07 |
| Work Completed |
|
| Time Computed |
09-30-07 |
| Contract Working Days |
100 |
| Addl Days Granted |
25 |
| Working Days Charged |
124 |
| Percent Time Used |
99 |
| Contractor(s) |
| DAN WILLIAMS COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0374-02-072 AR DANIEL SERVICES ( 15.34%) TEXAS FAR WEST CONSTRUCTION & ENGINEERING( 10.65%) HENRY TRUJILLO, INC. (1.64%)
|
| Contract # |
08073022 |
|
Totals |
1719655.40 |
12811.67 |
1727211.13 |
99.9 |
|
| County | EL PASO |
| Highway |
FM 76 |
| From |
APPROX. 4 MI. NW OF FM 1109 |
| To |
FM 1109 |
| CSJ |
0674-02-013 |
| Proj ID |
STP 2008(462) |
| Work Type |
MILL, SPOT BASE REPAIR, OVERLAY |
| |
|
4.073 |
796068.30 |
0.00 |
348190.96 |
43.7 |
| Work Order |
04-16-08 |
| Work Began |
05-02-08 |
| Work Completed |
|
| Time Computed |
05-02-08 |
| Contract Working Days |
42 |
| Addl Days Granted |
88 |
| Working Days Charged |
115 |
| Percent Time Used |
88 |
| Contractor(s) |
| J.A.R. CONCRETE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0674-02-013 DUSTROL, INC.(3.88%) ROAD MARKINGS INC. (3.82%)
|
| Contract # |
03083030 |
|
Totals |
796068.30 |
0.00 |
348190.96 |
43.7 |
|
| County | ECTOR |
| Highway |
VA |
| From |
ON IH 10 AND IH 20 |
| To |
. |
| CSJ |
0906-00-115 |
| Proj ID |
ITS 2004(802) |
| Work Type |
INSTALL AMBER ALERT SIGNS |
| |
|
0.001 |
770430.00 |
0.00 |
717940.65 |
98.0 |
| County | EL PASO |
| Highway |
VA |
| From |
DISTRICTWIDE |
| To |
. |
| CSJ |
0924-06-257 |
| Proj ID |
ITS 2004(802) |
| Work Type |
AMBER PLAN IMPLEMENTATION ASSISTANC |
| |
|
0.100 |
318025.00 |
0.00 |
299007.75 |
98.9 |
| Work Order |
01-04-06 |
| Work Began |
07-12-07 |
| Work Completed |
|
| Time Computed |
01-20-06 |
| Contract Working Days |
100 |
| Addl Days Granted |
0 |
| Working Days Charged |
100 |
| Percent Time Used |
100 |
| Contractor(s) |
| TRI STATE ELECTRIC, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-257 HARDY HOLE DRILLING(1.42%) TEXAS FAR WEST CONSTRUCTION & ENGINEERING(3.08%)
|
| Contract # |
12053011 |
|
Totals |
1088455.00 |
0.00 |
1016948.40 |
98.3 |
|
| County | EL PASO |
| Highway |
VA |
| From |
DISTRICTWIDE |
| To |
. |
| CSJ |
0924-00-059 |
| Proj ID |
STP 2007(395) |
| Work Type |
SIGNING UPGRADE |
| |
|
85.000 |
969648.25 |
0.00 |
971750.96 |
99.9 |
| County | EL PASO |
| Highway |
IH 10 |
| From |
US 54 |
| To |
FM 659 |
| CSJ |
2121-03-136 |
| Proj ID |
IM 0101(242) |
| Work Type |
OVERHEAD SIGN BRIDGE SIGN REPLACEMT |
| |
|
8.000 |
229045.30 |
0.00 |
191345.21 |
83.5 |
| Work Order |
06-01-07 |
| Work Began |
08-27-07 |
| Work Completed |
|
| Time Computed |
06-17-07 |
| Contract Working Days |
112 |
| Addl Days Granted |
0 |
| Working Days Charged |
119 |
| Percent Time Used |
106 |
| Contractor(s) |
| TEXAS CONCRETE AND ASPHALT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-059 HARDY HOLE DRILLING(1.18%)
|
| Contract # |
04073213 |
|
Totals |
1198693.55 |
0.00 |
1163096.17 |
97.4 |
|
| County | EL PASO |
| Highway |
CS |
| From |
FM 1281 & ASHFORD ST INTERSECTION |
| To |
RYDERWOOD AV & DARRINGTON RD INTERS |
| CSJ |
0924-06-181 |
| Proj ID |
STP 2003(312)MM |
| Work Type |
RECONSTRUCT ASHFORD / RYDERWOOD |
| |
|
1.490 |
1518140.40 |
312747.05 |
635885.81 |
41.8 |
| County | EL PASO |
| Highway |
FM 1281 |
| From |
ASHFORD/HORIZON BLVD INTERSECTION |
| To |
. |
| CSJ |
3451-01-025 |
| Proj ID |
STP 2008(412) |
| Work Type |
UPGRADING INTERSECTION AT ASHFORD |
| |
|
0.040 |
281221.95 |
2290.00 |
2290.00 |
0.8 |
| Work Order |
07-25-08 |
| Work Began |
08-11-08 |
| Work Completed |
|
| Time Computed |
08-10-08 |
| Contract Working Days |
120 |
| Addl Days Granted |
0 |
| Working Days Charged |
56 |
| Percent Time Used |
46 |
| Contractor(s) |
| C & C ROAD CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-181 TRI STATE ELECTRIC, LTD. ( 12.28%) ROAD MARKINGS INC. (1.81%) TEX OP CONSTRUCTION, LP(1.32%)
|
| Contract # |
06083028 |
|
Totals |
1799362.35 |
315037.05 |
638175.81 |
35.4 |
|
| County | EL PASO |
| Highway |
CS |
| From |
SH 20 (DONIPHAN DRIVE) |
| To |
IH 10 |
| CSJ |
0924-06-199 |
| Proj ID |
STP 2007(686)MM |
| Work Type |
A NON - FREEWAY FACILITY |
| |
|
1.111 |
5239435.30 |
206629.92 |
1505847.40 |
28.7 |
| County | EL PASO |
| Highway |
CS |
| From |
SH 20 (DONIPHAN DRIVE) |
| To |
IH 10 |
| CSJ |
0924-06-293 |
| Proj ID |
CC 924-6-293 |
| Work Type |
WATER AND SEWER FACILITIES |
| |
|
1.111 |
1676163.25 |
136878.83 |
1204664.08 |
71.8 |
| Work Order |
03-24-08 |
| Work Began |
05-12-08 |
| Work Completed |
|
| Time Computed |
04-09-08 |
| Contract Working Days |
300 |
| Addl Days Granted |
0 |
| Working Days Charged |
111 |
| Percent Time Used |
37 |
| Contractor(s) |
| C & C ROAD CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-199 TRI STATE ELECTRIC, LTD. ( 13.39%) ROAD MARKINGS INC. (0.64%) THREE C'S CONTRACTORS(1.33%) TEX OP CONSTRUCTION, LP(0.32%) SAAB DEVELOPMENT ( 24.35%) XPERT ROAD CONSTRUCTION INC. (2.65%) DH UNDERGROUND, INC. (7.35%)
|
| Contract # |
01083206 |
|
Totals |
6915598.55 |
343508.75 |
2710511.48 |
39.1 |
|
| County | EL PASO |
| Highway |
VA |
| From |
VARIOUS LOCATIONS (ON SYSTEM) |
| To |
. |
| CSJ |
0924-06-244 |
| Proj ID |
CM 2007(579) |
| Work Type |
MISCELLANEOUS: ALTERNATE ROUTES |
| |
|
1.000 |
3492312.50 |
0.00 |
0.00 |
0.0 |
| Work Order |
02-11-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
02-27-08 |
| Contract Working Days |
380 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| TRI STATE ELECTRIC, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-244 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09073011 |
|
Totals |
3492312.50 |
0.00 |
0.00 |
0.0 |
|
| County | EL PASO |
| Highway |
CS |
| From |
LEE BLVD; FROM MONTANA AVE_(PHASEII |
| To |
PRATT AVE |
| CSJ |
0924-06-251 |
| Proj ID |
STP 2006(069)MM |
| Work Type |
NEW LOCATION NON - FREEWAY |
| |
|
1.000 |
2693136.85 |
126687.92 |
1132784.57 |
42.0 |
| Work Order |
11-30-07 |
| Work Began |
03-17-08 |
| Work Completed |
|
| Time Computed |
12-16-07 |
| Contract Working Days |
160 |
| Addl Days Granted |
0 |
| Working Days Charged |
151 |
| Percent Time Used |
94 |
| Contractor(s) |
| TEXAS CONCRETE AND ASPHALT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-251 HENRY TRUJILLO, INC. (2.20%) NOE TAPIA CONCRETE ( 14.81%) ROAD MARKINGS INC. (2.59%) TRI STATE ELECTRIC, LTD. ( 11.81%) PABLO GOMEZ TRUCKING (0.32%) MEDELLIN TRUCKING(0.12%) JAT TRUCKING (0.12%) ALONSO TRUCKING(0.12%)
|
| Contract # |
07073218 |
|
Totals |
2693136.85 |
126687.92 |
1132784.57 |
42.0 |
|