TxDOT Expressway
Search:
   Home   |    Contact Us   |    Tools & Plug-Ins  
 
 
Last Update: Monday, November 17, 2008
FTP Icon Text Version
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEL PASO
Highway SH 20
From BALTIMORE ST.
To CINCINNATI AVE.
CSJ 0001-02-049
Proj ID STP 2008(668)
Work Type FY 06 SUPPLEMENTAL REHABILITATION
 
0.068 146154.65 0.00 0.00 0.0
CountyEL PASO
Highway SH 20
From CINCINNATI AVE.
To 0.023 MI SOUTH OF E YANDELL ST.
CSJ 0001-03-053
Proj ID STP 2008(668)
Work Type FY 06 SUPPLEMENTAL REHABILITATION
 
1.279 1971378.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-12-08
Work Began 00-00-00
Work Completed  
Time Computed 04-01-09
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
C.F. JORDAN, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0001-02-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08083028
Totals 2117533.15 0.00 0.00 0.0

CountyEL PASO
Highway SH 20
From SH 20 (MESA ST) @ SUN BOWL
To SH 20 (MESA ST) @ EXECUTIVE CENTER
CSJ 0001-02-050
Proj ID NH 2007(464)
Work Type LANDSCAPE MEDIANS
 
0.750 200437.45 1850.00 192047.45 95.8
CountyEL PASO
Highway VA
From HAWKINS BLVD @ IH - 10 WEST
To HAWKINS BLVD @ US 62/180(MONTANA AV
CSJ 0924-06-243
Proj ID STP 2007(076)MM
Work Type MEDIAN IMPROVEMENTS
 
1.750 549473.40 1850.00 566275.90 99.9
Work Order 06-05-07
Work Began 07-09-07
Work Completed  
Time Computed 06-21-07
Contract Working Days 80
Addl Days Granted 11
Working Days Charged 91
Percent Time Used 100
Contractor(s)
C & C ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-243
THREE C'S CONTRACTORS( 33.39%)
HARDY HOLE DRILLING(3.46%)
XPERT ROAD CONSTRUCTION INC. (2.84%)
Contract # 04073222
Totals 749910.85 3700.00 758323.35 99.9

CountyEL PASO
Highway SH 20 ETC
From @ SH 20 AND SCHUSTER
To .
CSJ 0001-03-054
Proj ID STP 2007(419)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
3.000 1549583.75 6000.00 1661350.76 99.9
Work Order 05-15-07
Work Began 01-08-08
Work Completed  
Time Computed 05-31-07
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 213
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0001-03-054
MOUNTAIN STAR CONSTRUCTION (6.55%)
HARDY HOLE DRILLING(0.89%)
ROAD MARKINGS INC. (3.11%)
Contract # 04073018
Totals 1549583.75 6000.00 1661350.76 99.9

CountyEL PASO
Highway SH 20
From DELTA
To LOOP 375
CSJ 0002-01-080
Proj ID CM 2008(825)
Work Type ALAMEDA TRAFFIC SIGNAL INTERCONNECT
 
10.000 1634478.50 0.00 0.00 0.0
Work Order 09-16-08
Work Began 00-00-00
Work Completed  
Time Computed 10-02-08
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0002-01-080
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08083213
Totals 1634478.50 0.00 0.00 0.0

CountyEL PASO
Highway SH 20
From LOOP 375
To FABENS
CSJ 0002-02-046
Proj ID MG 2005(694)
Work Type GDRL PLMT AT EXIS IRR STRUC LOC
 
15.200 236939.10 0.00 267903.37 99.9
CountyEL PASO
Highway FM 258
From 16.2 MILES EAST ON FM 258
To FABENS
CSJ 0002-14-025
Proj ID STP 2005(695)SFT
Work Type GDRL PLMT AT EXIS IRR STRUC LOC
 
16.200 355702.00 0.00 274482.48 77.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-29-06
Work Began 01-04-07
Work Completed  
Time Computed 12-15-06
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 127
Contractor(s)
C & C ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-02-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10063227
Totals 592641.10 0.00 542385.85 94.8

CountyHUDSPETH
Highway IH 10
From @ THE BORDER CHECKPOINT STATION
To .
CSJ 0002-07-041
Proj ID IM 0101(241)
Work Type GR, STR EXTS, EMBK, ACP, CRCP, COSS, SIGN
 
3.000 3330288.09 240055.52 2692518.44 80.8
Work Order 07-24-07
Work Began 03-17-08
Work Completed  
Time Computed 08-09-07
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 100
Contractor(s)
C & C ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-07-041
TRI STATE ELECTRIC, LTD. ( 27.85%)
Contract # 06073024
Totals 3330288.09 240055.52 2692518.44 80.8

CountyEL PASO
Highway FM 258 ETC
From FM 258 (SOCORRO) AT ZEBU
To .
CSJ 0002-14-030
Proj ID C 2-14-30
Work Type TRAFFIC SIGNAL INSTALLATION
 
0.500 840475.90 0.00 726299.99 90.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-15-07
Work Began 02-13-08
Work Completed  
Time Computed 08-31-07
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 160
Percent Time Used 100
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0002-14-030
MOUNTAIN STAR CONSTRUCTION ( 10.36%)
ROAD MARKINGS INC. ( 10.13%)
Contract # 07073214
Totals 840475.90 0.00 726299.99 90.9

CountyCULBERSON
Highway IH 10
From 12.56 MI W CULBERSON/JEFF DAVIS C L
To 0.04 MI W CULBERSON/JEFF DAVIS C L
CSJ 0003-03-041
Proj ID IM 0101(244)
Work Type MILL AND OVERLAY
 
12.520 9306863.92 1748705.59 6292860.82 67.6
Work Order 04-14-08
Work Began 06-03-08
Work Completed  
Time Computed 04-30-08
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 87
Contractor(s)
C & C ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0003-03-041
HIGHWAY TECHNOLOGIES (0.51%)
TEX OP CONSTRUCTION, LP(3.83%)
ROAD MARKINGS INC. (2.26%)
XPERT ROAD CONSTRUCTION INC. ( 10.88%)
TEXAS HIGHWAY BARRICADES & SIGNS INC (0.51%)
Contract # 03083229
Totals 9306863.92 1748705.59 6292860.82 67.6

CountyPRESIDIO
Highway US 67
From .8 MI S OF US 90
To 3.645 MILES N OF PEDIZ CREEK
CSJ 0104-06-022
Proj ID STP 2008(705)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
12.247 2025091.55 0.00 0.00 0.0
CountyPRESIDIO
Highway US 67
From .1 MI N OF PERDIZ CREEK
To .1 MI S OF PERDIZ CREEK
CSJ 0104-07-019
Proj ID STP 2008(705)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
0.200 52044.80 0.00 0.00 0.0
Work Order 10-09-08
Work Began 00-00-00
Work Completed  
Time Computed 10-25-08
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MANN CONTRACTORS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0104-06-022
ROAD MARKINGS INC. (0.82%)
W.S. CONSTRUCTION COMPANY(6.19%)
W. W. FOUNDATION DRILLING, LTD.(8.66%)
Contract # 08083017
Totals 2077136.35 0.00 0.00 0.0

CountyEL PASO
Highway US 54
From YANDELL DRIVE OVERPASS
To APPROX. 1200 FT N OF HONDO PASS DR
CSJ 0167-01-081
Proj ID STP 2006(434)MM
Work Type GR, BA, CPCR, SURF & STRUC
 
6.347 32478827.58 338596.80 27634838.33 85.4
Work Order 06-05-06
Work Began 07-21-06
Work Completed  
Time Computed 06-21-06
Contract Working Days 549
Addl Days Granted 0
Working Days Charged 605
Percent Time Used 110
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-081
HARDY HOLE DRILLING(1.12%)
TRI STATE ELECTRIC, LTD. ( 21.42%)
RAMIREZ BROTHERS CONCRETE CONSTRUCTION COMPANY (0.63%)
MOUNTAIN ELECTRIC CORPORATION(5.55%)
RUTHERFORD DIVERSIFIED INDUSTRIES, INC.(0.31%)
TEX OP CONSTRUCTION, LP(0.27%)
ROAD MARKINGS INC. (2.07%)
SCOTT DERR PAINTING CO (0.20%)
J.L. STEEL, L.P. (0.87%)
HARDY HOLE DRILLING(0.28%)
TRUJILLO TRUCKING(0.43%)
HOUSTON SAWING & DRILLING(0.06%)
Contract # 04063217
Totals 32478827.58 338596.80 27634838.33 85.4

CountyEL PASO
Highway US 54 ETC
From ZARAGOSA ROAD (FM 659)
To HORIZON BLVD (FM 1281)
CSJ 0167-01-092
Proj ID CM 2005(338)
Work Type UPGRADING LOOP DETECTORS: PHASE I
 
47.829 2165361.50 0.00 2005317.32 97.4
Work Order 08-04-05
Work Began 01-02-07
Work Completed  
Time Computed 08-20-05
Contract Working Days 180
Addl Days Granted 65
Working Days Charged 245
Percent Time Used 100
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-092
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(5.97%)
ROAD MARKINGS INC. (1.44%)
HARDY HOLE DRILLING(0.08%)
Contract # 06053057
Totals 2165361.50 0.00 2005317.32 97.4

CountyJEFF DAVIS
Highway SH 118
From 6.507 MILES SOUTH OF FORT DAVIS
To BREWSTER/JEFF DAVIS COUNTY LINE
CSJ 0358-01-024
Proj ID STP 2007(026)
Work Type MILL AND INLAY OF EXISTING ROADWAY
 
8.653 3602686.86 36161.05 1571172.78 43.6
Work Order 08-15-07
Work Began 07-07-08
Work Completed  
Time Computed 08-31-07
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 28
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0358-01-024
NITE LITE, INC.(2.06%)
CHEROKEE SERVICES(3.87%)
76 MILLING, INC. (1.11%)
Contract # 07073009
Totals 3602686.86 36161.05 1571172.78 43.6

CountyEL PASO
Highway US 62
From 1.473MI(2.731)E OF FM659 (ZARAGOZA)
To 3.262MI(5.250KM)W OF FM2775(HUECO T
CSJ 0374-02-072
Proj ID NH 2007(743)
Work Type MISCELLANEOUS WORK
 
4.035 1719655.40 12811.67 1727211.13 99.9
Work Order 09-14-07
Work Began 11-26-07
Work Completed  
Time Computed 09-30-07
Contract Working Days 100
Addl Days Granted 25
Working Days Charged 124
Percent Time Used 99
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0374-02-072
AR DANIEL SERVICES ( 15.34%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING( 10.65%)
HENRY TRUJILLO, INC. (1.64%)
Contract # 08073022
Totals 1719655.40 12811.67 1727211.13 99.9

CountyEL PASO
Highway FM 76
From APPROX. 4 MI. NW OF FM 1109
To FM 1109
CSJ 0674-02-013
Proj ID STP 2008(462)
Work Type MILL, SPOT BASE REPAIR, OVERLAY
 
4.073 796068.30 0.00 348190.96 43.7
Work Order 04-16-08
Work Began 05-02-08
Work Completed  
Time Computed 05-02-08
Contract Working Days 42
Addl Days Granted 88
Working Days Charged 115
Percent Time Used 88
Contractor(s)
J.A.R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0674-02-013
DUSTROL, INC.(3.88%)
ROAD MARKINGS INC. (3.82%)
Contract # 03083030
Totals 796068.30 0.00 348190.96 43.7

CountyECTOR
Highway VA
From ON IH 10 AND IH 20
To .
CSJ 0906-00-115
Proj ID ITS 2004(802)
Work Type INSTALL AMBER ALERT SIGNS
 
0.001 770430.00 0.00 717940.65 98.0
CountyEL PASO
Highway VA
From DISTRICTWIDE
To .
CSJ 0924-06-257
Proj ID ITS 2004(802)
Work Type AMBER PLAN IMPLEMENTATION ASSISTANC
 
0.100 318025.00 0.00 299007.75 98.9
Work Order 01-04-06
Work Began 07-12-07
Work Completed  
Time Computed 01-20-06
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 100
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-257
HARDY HOLE DRILLING(1.42%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(3.08%)
Contract # 12053011
Totals 1088455.00 0.00 1016948.40 98.3

CountyEL PASO
Highway VA
From DISTRICTWIDE
To .
CSJ 0924-00-059
Proj ID STP 2007(395)
Work Type SIGNING UPGRADE
 
85.000 969648.25 0.00 971750.96 99.9
CountyEL PASO
Highway IH 10
From US 54
To FM 659
CSJ 2121-03-136
Proj ID IM 0101(242)
Work Type OVERHEAD SIGN BRIDGE SIGN REPLACEMT
 
8.000 229045.30 0.00 191345.21 83.5
Work Order 06-01-07
Work Began 08-27-07
Work Completed  
Time Computed 06-17-07
Contract Working Days 112
Addl Days Granted 0
Working Days Charged 119
Percent Time Used 106
Contractor(s)
TEXAS CONCRETE AND ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-059
HARDY HOLE DRILLING(1.18%)
Contract # 04073213
Totals 1198693.55 0.00 1163096.17 97.4

CountyEL PASO
Highway CS
From FM 1281 & ASHFORD ST INTERSECTION
To RYDERWOOD AV & DARRINGTON RD INTERS
CSJ 0924-06-181
Proj ID STP 2003(312)MM
Work Type RECONSTRUCT ASHFORD / RYDERWOOD
 
1.490 1518140.40 312747.05 635885.81 41.8
CountyEL PASO
Highway FM 1281
From ASHFORD/HORIZON BLVD INTERSECTION
To .
CSJ 3451-01-025
Proj ID STP 2008(412)
Work Type UPGRADING INTERSECTION AT ASHFORD
 
0.040 281221.95 2290.00 2290.00 0.8
Work Order 07-25-08
Work Began 08-11-08
Work Completed  
Time Computed 08-10-08
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 46
Contractor(s)
C & C ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-181
TRI STATE ELECTRIC, LTD. ( 12.28%)
ROAD MARKINGS INC. (1.81%)
TEX OP CONSTRUCTION, LP(1.32%)
Contract # 06083028
Totals 1799362.35 315037.05 638175.81 35.4

CountyEL PASO
Highway CS
From SH 20 (DONIPHAN DRIVE)
To IH 10
CSJ 0924-06-199
Proj ID STP 2007(686)MM
Work Type A NON - FREEWAY FACILITY
 
1.111 5239435.30 206629.92 1505847.40 28.7
CountyEL PASO
Highway CS
From SH 20 (DONIPHAN DRIVE)
To IH 10
CSJ 0924-06-293
Proj ID CC 924-6-293
Work Type WATER AND SEWER FACILITIES
 
1.111 1676163.25 136878.83 1204664.08 71.8
Work Order 03-24-08
Work Began 05-12-08
Work Completed  
Time Computed 04-09-08
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 111
Percent Time Used 37
Contractor(s)
C & C ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-199
TRI STATE ELECTRIC, LTD. ( 13.39%)
ROAD MARKINGS INC. (0.64%)
THREE C'S CONTRACTORS(1.33%)
TEX OP CONSTRUCTION, LP(0.32%)
SAAB DEVELOPMENT ( 24.35%)
XPERT ROAD CONSTRUCTION INC. (2.65%)
DH UNDERGROUND, INC. (7.35%)
Contract # 01083206
Totals 6915598.55 343508.75 2710511.48 39.1

CountyEL PASO
Highway VA
From VARIOUS LOCATIONS (ON SYSTEM)
To .
CSJ 0924-06-244
Proj ID CM 2007(579)
Work Type MISCELLANEOUS: ALTERNATE ROUTES
 
1.000 3492312.50 0.00 0.00 0.0
Work Order 02-11-08
Work Began 00-00-00
Work Completed  
Time Computed 02-27-08
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-244
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09073011
Totals 3492312.50 0.00 0.00 0.0

CountyEL PASO
Highway CS
From LEE BLVD; FROM MONTANA AVE_(PHASEII
To PRATT AVE
CSJ 0924-06-251
Proj ID STP 2006(069)MM
Work Type NEW LOCATION NON - FREEWAY
 
1.000 2693136.85 126687.92 1132784.57 42.0
Work Order 11-30-07
Work Began 03-17-08
Work Completed  
Time Computed 12-16-07
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 151
Percent Time Used 94
Contractor(s)
TEXAS CONCRETE AND ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-251
HENRY TRUJILLO, INC. (2.20%)
NOE TAPIA CONCRETE ( 14.81%)
ROAD MARKINGS INC. (2.59%)
TRI STATE ELECTRIC, LTD. ( 11.81%)
PABLO GOMEZ TRUCKING (0.32%)
MEDELLIN TRUCKING(0.12%)
JAT TRUCKING (0.12%)
ALONSO TRUCKING(0.12%)
Contract # 07073218
Totals 2693136.85 126687.92 1132784.57 42.0

page 1 | page 2
 
spacer spacer
Disclaimer | Accessibility Policy | Privacy and Security Policy | Open Records | TxDOT Contacts