Monthly State Let Construction Report For El Paso District As Of May 10, 2016 Page 1 Of 2

Last Update: Tuesday, May 10, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEL PASO
Highway SH 20
From NM STATE LINE
To SH 20 MESA
CSJ 0001-01-058
Proj ID CM 2014(902)
Work Type TRAFFIC OPERATION
 
11.100 1133585.95 14803.21 1124431.20 99.1
Work Order 09-30-14
Work Began 01-12-15
Work Completed  
Time Computed 10-16-14
Contract Working Days 60
Addl Days Granted 40
Working Days Charged 140
Percent Time Used 140
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0001-01-058
TRAFFIC BARRICADE SERVICE, INC.(3.52%)
TRI STATE ELECTRIC, LTD. ( 31.02%)
HARDY HOLE DRILLING(0.23%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (2.44%)
ALLEN CONCRETE, INC. (0.00%)
Contract # 07143219
Totals 1133585.95 14803.21 1124431.20 99.1

CountyEL PASO
Highway US 62
From 650 FT W OF EUCALYPTUS ST
To BARCELONA DR
CSJ 0001-04-094
Proj ID NH 1502(154)
Work Type VEGETATION LANDSCAPE
 
3.618 682967.00 182790.00 182790.00 26.7
Work Order 08-04-15
Work Began 04-04-16
Work Completed  
Time Computed 04-04-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 33
Contractor(s)
DOUBLE H CONTRACTING INC.
SUBCONTRACTOR(S) FOR CCSJ: 0001-04-094
APACHE BARRICADE & SIGN(1.53%)
BRAVO EL PASO LANDSCAPING AND IRRIGATION (3.66%)
SATARAIN CONSTRUCTION, INC.(8.45%)
TEXAS CONCRETE AND ASPHALT, INC. ( 10.24%)
Contract # 05153020
Totals 682967.00 182790.00 182790.00 26.7

CountyEL PASO
Highway SH 20
From BOONE STREET
To 600 FT E OF CONCEPCION ST
CSJ 0002-01-074
Proj ID NH 2011(327)
Work Type INTERSECTION IMPROVEMENTS AND REHAB
 
0.875 5607003.00 0.00 6826648.27 99.9
CountyEL PASO
Highway SH 20
From BOONE STREET
To 600 FT E OF CONCEPCION ST
CSJ 0002-01-082
Proj ID RW 2-1-82
Work Type ROW ACQUISITION
 
1.472 1053076.70 0.00 1228957.67 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-24-11
Work Began 01-23-12
Work Completed  
Time Computed 01-23-12
Contract Working Days 240
Addl Days Granted 128
Working Days Charged 368
Percent Time Used 100
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0002-01-074
TRI STATE ELECTRIC, LTD. ( 12.27%)
A BROTHERS (1.06%)
ROAD MARKINGS INC. (0.90%)
THREE C"S CONTRACTORS, INC.(0.42%)
DH UNDERGROUND, INC. (0.30%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(6.50%)
RNJ CONCRETE, INC. (2.70%)
PMI PAVEMENT MARKING, INC. (0.92%)
Contract # 09113026
Totals 6660079.70 0.00 8055605.94 99.9

CountyEL PASO
Highway SH 20
From CONCEPCION ST
To GLENWOOD ST
CSJ 0002-01-090
Proj ID C 2-1-90
Work Type ROADWAY IMPROVEMENTS
 
0.700 9768518.24 0.00 10697399.72 99.9
CountyEL PASO
Highway SH 20
From CONCEPCION ST
To GLENWOOD ST
CSJ 0002-01-092
Proj ID RW 2-1-92
Work Type ADJUSTMENT OF UTILITIES
 
0.700 706816.30 0.00 653296.30 92.4
Work Order 01-06-14
Work Began 01-20-14
Work Completed  
Time Computed 01-20-14
Contract Working Days 280
Addl Days Granted 80
Working Days Charged 357
Percent Time Used 99
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0002-01-090
A BROTHERS (OLD PRIME) (0.90%)
BORDER DEMOLITION & ENVIRONMENTAL INC. (1.06%)
D"AMBRA STEEL SERVICES, INC. (HUB) (3.74%)
FALC ENTERPRISES, LLC(0.00%)
PALO VERDE CONSTRUCTORS(1.13%)
PRIME IRRIGATION & LANDSCAPE, INC. (2.72%)
QUARRY HILLS, LTD. (0.57%)
SANCHEZ CONSTRUCTION & LANDSCAPING (2.83%)
SATARAIN CONSTRUCTION, INC.(4.66%)
TRAFFIC BARRICADE SERVICE, INC.(0.83%)
TRI STATE ELECTRIC, LTD. ( 15.64%)
HARDY HOLE DRILLING(0.36%)
PMI PAVEMENT MARKING, INC. (0.56%)
D"AMBRA CONSTRUCTION CORPORATION (3.74%)
Contract # 08133020
Totals 10475334.54 0.00 11350696.02 99.9

CountyEL PASO
Highway SH 20
From 0.06 MI N OF HORIZON BLVD
To 0.07 MI S OF HORIZON BLDV
CSJ 0002-02-050
Proj ID STP 2013(147)
Work Type RECONSTRUCT INTERSECTION
 
0.229 1129305.88 120114.63 1230874.05 99.9
CountyEL PASO
Highway MH
From 0.09 MI W OF SH 20 (ALAMEDA)
To 0.06 MI W OF FM 76 (NORTH LOOP)
CSJ 8056-24-001
Proj ID STP 2009(791)
Work Type RECONSTRUCTING AND WIDENING
 
1.190 4596242.98 379407.27 4572328.85 99.4
CountyEL PASO
Highway MH
From 0.09 MI W OF SH 20 (ALAMEDA)
To 0.06 MI W OF FM 76 (NORTH LOOP)
CSJ 8056-24-003
Proj ID RW 8056-24-3
Work Type ROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
1.190 1779757.14 93501.08 1802268.39 99.9
Work Order 11-09-12
Work Began 07-08-13
Work Completed  
Time Computed 11-25-12
Contract Working Days 290
Addl Days Granted 111
Working Days Charged 394
Percent Time Used 98
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 8056-24-001
HAWK CONSTRUCTION(5.97%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.59%)
TRI STATE ELECTRIC, LTD. (6.42%)
ALLIED PAVING CO.(0.10%)
PRIME IRRIGATION & LANDSCAPE, INC. (4.38%)
A BROTHERS MILLING, LLC(0.43%)
GREATER EL PASO SANDBLASTING (0.28%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.49%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.13%)
DH UNDERGROUND, INC. (2.04%)
ACCURATE CORING, INC.(0.01%)
HARDY HOLE DRILLING(0.02%)
HENRY TRUJILLO, INC. (0.21%)
BORDER DEMOLITION & ENVIRONMENTAL INC. (0.25%)
STAR CITY SEALANTS (0.10%)
WALL & FENCES(0.40%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (1.82%)
Contract # 09123021
Totals 7505306.00 593022.98 7605471.29 99.9

CountyHUDSPETH
Highway IH 10 ETC
From 0.117 MI S OF SH 20
To 0.8 MI E OF FM 34
CSJ 0002-05-044
Proj ID STP 2016(638)HES
Work Type TEXTURIZE SHOULDERS
 
205.104 3057663.63 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0002-05-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163217
Totals 3057663.63 0.00 0.00 0.0

CountyHUDSPETH
Highway IH 10
From 0.194 MI W OF FM 34
To 2.573 MI E OF FM 34
CSJ 0002-06-049
Proj ID NH 2016(464)
Work Type MILL AND INLAY
 
3.686 3107215.26 0.00 75961.46 2.4
CountyCULBERSON
Highway IH 10
From 24.04 MI W CULBERSON/JEFF DAVIS C L
To 13.2 MI W CULBERSON/JEFF DAVIS C L
CSJ 0003-02-039
Proj ID NH 2016(464)
Work Type MILL AND INLAY
 
10.838 9482866.31 0.00 523150.88 5.5
CountyCULBERSON
Highway IH 10
From EVERGREEN RD
To 0.3 MI W OF BORACHO STATION
CSJ 0003-02-044
Proj ID STP 2016(647)HES
Work Type TEXTURIZE SHOULDERS
 
12.754 284617.58 0.00 0.00 0.0
CountyZERO COUNTIES
Highway  
From  
To  
CSJ 0003-03-045
Proj ID  
Work Type  
 
  0.00 0.00 4463.36 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 04-14-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 9
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0003-02-039
A BROTHERS MILLING, LLC(1.54%)
ANTIGO CONSTRUCTION, INC.(0.14%)
PAVEMENT MARKINGS INC. (3.14%)
HENRY TRUJILLO, INC. (0.43%)
TX TINMAN ENTERPRISES, LLC.(2.22%)
FALC ENTERPRISES, LLC(1.02%)
Contract # 01163002
Totals 12874699.15 0.00 603575.70 4.6

CountyHUDSPETH
Highway IH 10
From 0.20 MI W OF JCT IH 10/RM 1111
To 0.20 MI E OF JCT IH 10/RM 1111
CSJ 0002-07-046
Proj ID BR 1502(391)
Work Type BRIDGE MAINTENANCE
 
0.756 727181.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-24-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-07-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153039
Totals 727181.00 0.00 0.00 0.0

CountyEL PASO
Highway FM 258
From 2.52 MI W OF FM 258/SH 20 INTERSECT
To 2.39 MI W OF FM 258/SH 20 INTERSECT
CSJ 0002-14-042
Proj ID BR 1502(392)
Work Type REPLACE STRUCTURE
 
0.528 457012.00 85884.77 590817.30 99.9
Work Order 10-22-15
Work Began 11-30-15
Work Completed  
Time Computed 11-30-15
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 89
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-14-042
TRAFFIC BARRICADE SERVICE, INC.( 10.50%)
Contract # 07153030
Totals 457012.00 85884.77 590817.30 99.9

CountyBREWSTER
Highway US 90
From 6.89 MI E OF US 67
To 0.43 MI W OF US 385
CSJ 0021-02-024
Proj ID NH 2016(900)
Work Type HOT MIX SHOULDER LEVEL UP AND SC
 
51.338 5614637.07 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-06-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0021-02-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163207
Totals 5614637.07 0.00 0.00 0.0

CountyEL PASO
Highway US 54
From LP 375 (BORDER HIGHWAY)
To MCCOMBS
CSJ 0167-01-108
Proj ID CM 2014(024)
Work Type ALTERNATE ROUTES, PHASE II
 
14.000 1898217.38 0.00 1634857.92 86.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-14
Work Began 04-20-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 76
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-108
HARDY HOLE DRILLING(0.23%)
BORDER DRILLING LLC(3.26%)
HAWK CONSTRUCTION(0.26%)
Contract # 11133221
Totals 1898217.38 0.00 1634857.92 86.1

CountyCULBERSON
Highway US 62
From 8.683 MI E OF SH 54 JUNCTION
To 19.302 MI E OF SH 54 JUNCTION
CSJ 0233-01-045
Proj ID NH 2014(850)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
33.019 6441134.87 99953.43 8947190.75 99.9
Work Order 09-09-14
Work Began 05-11-15
Work Completed  
Time Computed 10-30-15
Contract Working Days 60
Addl Days Granted 118
Working Days Charged 152
Percent Time Used 85
Contractor(s)
ALLIED PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0233-01-045
FALC ENTERPRISES, LLC(2.26%)
COX PAVING COMPANY, L.P. ( 10.71%)
DOUBLE A CONTRACTING, L.P. (2.73%)
TRAFFIC BARRICADE SERVICE, INC.(0.69%)
WEST TEXAS RUMBLE STRIP(0.16%)
DUSTROL, INC.(0.83%)
Contract # 07143044
Totals 6441134.87 99953.43 8947190.75 99.9

CountyHUDSPETH
Highway US 62
From 17.705 MI W OF RM 2317
To 2.916 MI W OF RM 2317
CSJ 0374-05-025
Proj ID STP 1502(370)HES
Work Type ADD PASSING LANES
 
30.791 3121216.06 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0374-05-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153238
Totals 3121216.06 0.00 0.00 0.0

CountyEL PASO
Highway FM 76
From 0.3 MI W OF THE CITY LIMITS
To 0.28 MI E OF FM 1281 (HORIZON BLVD)
CSJ 0674-01-037
Proj ID STP 2012(183)
Work Type GR, STRS & SURF
 
2.850 17477183.46 885634.32 10302281.64 58.9
CountyEL PASO
Highway FM 76
From 0.3 MILES WEST OF THE CITY LIMITS
To 0.28 MILES E. OF FM 1281 (HORIZON B
CSJ 0674-01-058
Proj ID RW 674-1-58
Work Type ACQUISITION, UTILITIES AND RELOCATI
 
0.001 1317086.00 191151.71 490675.53 37.2
Work Order 00-00-00
Work Began 07-02-12
Work Completed  
Time Computed 02-01-12
Contract Working Days 510
Addl Days Granted 129
Working Days Charged 317
Percent Time Used 49
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0674-01-037
PRIME IRRIGATION & LANDSCAPE, INC. (0.89%)
SANCHEZ CONSTRUCTION & LANDSCAPING (1.98%)
TRI STATE ELECTRIC, LTD. ( 11.87%)
RNJ CONCRETE, INC. (5.82%)
PALO VERDE CONSTRUCTORS(3.03%)
C & C ROAD CONSTRUCTION, INC.(0.20%)
TRAFFIC BARRICADE SERVICE, INC.(0.69%)
HENRY TRUJILLO, INC. (1.33%)
A BROTHERS MILLING, LLC(0.24%)
PMI PAVEMENT MARKING, INC. (0.86%)
MFH ENVIRONMENTAL CORP.(0.01%)
SATARAIN CONSTRUCTION, INC.(6.32%)
D"AMBRA CONSTRUCTION CORPORATION (8.20%)
VENEGAS ENGINEERING MANAGEMENT AND CONSTRUCTION, INC.(0.27%)
HARDY HOLE DRILLING(0.04%)
Contract # 12113202
Totals 18794269.46 1076786.03 10792957.17 57.4

CountyEL PASO
Highway VA
From DISTRICTWIDE
To .
CSJ 0924-00-086
Proj ID STP 2013(863)
Work Type METAL BEAM GUARD FENCE / SGT UPGRADES
 
3.282 1408923.00 0.00 573860.78 40.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-24-13
Work Began 11-14-13
Work Completed  
Time Computed 11-09-13
Contract Working Days 188
Addl Days Granted 0
Working Days Charged 233
Percent Time Used 123
Contractor(s)
SURETEC INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07133012
Totals 1408923.00 0.00 573860.78 40.7

CountyEL PASO
Highway CS
From SH 20 (ALAMEDA AVENUE)
To STILES/FRANKLIN DRIVE
CSJ 0924-06-154
Proj ID BR 2008(321)
Work Type OFF - SYSTEM BRIDGE REPLACEMENT
 
0.267 7490552.40 0.00 0.00 0.0
CountyEL PASO
Highway CS
From SH 20 (ALAMEDA AVENUE)
To STILES/FRANKLIN DRIVE
CSJ 0924-06-521
Proj ID ROW 924-6-521
Work Type UTILITY ADJUSTMENT
 
0.267 357978.91 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 218
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-154
ALLEN CONCRETE, INC. (9.18%)
DH UNDERGROUND, INC. (0.64%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.11%)
HARDY HOLE DRILLING(3.65%)
TRI STATE ELECTRIC, LTD. (6.31%)
TRAFFIC BARRICADE SERVICE, INC.(1.10%)
O.D. CONSTRUCTION(3.32%)
Contract # 01163230
Totals 7848531.31 0.00 0.00 0.0

CountyEL PASO
Highway CS
From 0.35 MI S OF SH 20
To IH 10
CSJ 0924-06-311
Proj ID CBI 2012(231)
Work Type NEW LOCATION NON FREEWAY
 
3.880 15520544.41 834762.51 5799460.70 37.3
Work Order 10-06-15
Work Began 01-04-16
Work Completed  
Time Computed 01-04-16
Contract Working Days 280
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 31
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-311
ZTEX CONSTRUCTION, INC.( 22.55%)
HARDY HOLE DRILLING(7.42%)
PAVEMENT MARKINGS INC. (0.35%)
PENHALL COMPANY(0.19%)
SATARAIN CONSTRUCTION, INC.(0.95%)
HAWK CONSTRUCTION(2.43%)
A BROTHERS MILLING, LLC(0.16%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.24%)
SCOTT DERR PAINTING CO, LLC(0.23%)
EL PASO FENCE CO (0.77%)
NATIONWIDE REBAR INC (0.13%)
FALC ENTERPRISES, LLC(0.00%)
NATIONWIDE REBAR INC (0.51%)
Contract # 07153264
Totals 15520544.41 834762.51 5799460.70 37.3

CountyEL PASO
Highway VA
From AT VARIOUS LOCATIONS IN EL PASO CO
To .
CSJ 0924-06-449
Proj ID STP 2015(042)
Work Type CONSTRUCT CURB RAMPS
 
1.000 1991412.68 157149.36 2025482.04 99.9
Work Order 11-03-14
Work Began 01-05-15
Work Completed  
Time Computed 11-19-14
Contract Working Days 226
Addl Days Granted 95
Working Days Charged 313
Percent Time Used 97
Contractor(s)
GARCOM, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-449
BOWEN INDUSTRIAL CONTRACTORS, INC. (4.01%)
TRAFFIC CONTROL SPECIALIST SALES & RENTALS (5.42%)
TRI STATE ELECTRIC, LTD. ( 16.69%)
HENRY TRUJILLO, INC. (1.25%)
Contract # 09143023
Totals 1991412.68 157149.36 2025482.04 99.9

CountyEL PASO
Highway SS 601
From AT LP 375 / SPUR 601
To .
CSJ 1046-03-006
Proj ID CM 1402(076)
Work Type INTERSECTION IMPROVEMENTS
 
0.500 879924.05 0.00 929121.85 99.9
Work Order 11-19-14
Work Began 04-20-15
Work Completed  
Time Computed 12-05-14
Contract Working Days 120
Addl Days Granted 26
Working Days Charged 136
Percent Time Used 93
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1046-03-006
C & C ROAD CONSTRUCTION, INC.( 42.50%)
TRI STATE ELECTRIC, LTD. (1.60%)
HORIZONE CONSTRUCTION I, LTD (2.75%)
NATIONWIDE REBAR INC (0.81%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (2.90%)
Contract # 09143039
Totals 879924.05 0.00 929121.85 99.9

CountyEL PASO
Highway FM 1110
From AT IH 10
To .
CSJ 1281-02-006
Proj ID BR 2013(630)
Work Type REPLACE BRIDGE
 
0.339 9449138.14 491051.34 8072809.36 85.4
Work Order 09-30-14
Work Began 10-23-14
Work Completed  
Time Computed 10-16-14
Contract Working Days 278
Addl Days Granted 100
Working Days Charged 357
Percent Time Used 94
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1281-02-006
PAVEMENT MARKINGS INC. (1.28%)
TRI STATE ELECTRIC, LTD. (7.72%)
HARDY HOLE DRILLING(0.03%)
HAWK CONSTRUCTION(3.84%)
HARDY HOLE DRILLING(3.69%)
SATARAIN CONSTRUCTION, INC.(3.21%)
HENRY TRUJILLO, INC. (0.17%)
HORIZONE CONSTRUCTION I, LTD ( 20.01%)
NATIONWIDE REBAR INC (0.17%)
A BROTHERS MILLING, LLC(0.49%)
CRANE SERVICES, INC. (0.39%)
FALC ENTERPRISES, LLC(0.01%)
PENHALL COMPANY(0.03%)
SCOTT DERR PAINTING CO (0.16%)
SATARAIN CONSTRUCTION, INC.(5.07%)
DUSTROL, INC.(0.04%)
Contract # 07143207
Totals 9449138.14 491051.34 8072809.36 85.4

page 1 | page 2