Monthly State Let Maintenance Report For Dallas District As Of Aug 11, 2017 Page 3 Of 5

Last Update: Friday, August 11, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDALLAS
HighwayIH0035E
FromVARIOUS ROADWAYS IN
ToTHE DALLAS DISTRICT
CSJ6300-68-001
Proj IDRMC - 630068001
Work TypeNONSITE SPECIFIC RDWY ILLUMINATION MAINT
 
0.001776086.04231553.3529.8
Work Order01-09-17
Work Began01-16-17
Work Completed
Time Computed01-16-17
Contract Working Days730
Addl Days Granted0
Working Days Charged191
Percent Time Used26
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164208
Totals776086.0434634.95231553.3529.8

CountyDALLAS
HighwayIH0035E
FromVARIOUS ROADWAYS IN
ToTHE DALLAS DISTRICT
CSJ6300-69-001
Proj IDRMC - 630069001
Work TypeTRAFFIC SIGNAL MAINT & PREVENTATIVE MAIN
 
0.0011470000.00430812.0029.3
Work Order01-09-17
Work Began01-16-17
Work Completed
Time Computed01-16-17
Contract Working Days730
Addl Days Granted0
Working Days Charged191
Percent Time Used26
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164209
Totals1470000.0091408.00430812.0029.3

CountyELLIS
HighwayUS0077
FromVARIOUS ROADWAYS IN ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6300-81-001
Proj IDRMC - 630081001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.001761196.00706321.8892.7
Work Order10-05-16
Work Began10-05-16
Work Completed
Time Computed10-15-16
Contract Working Days365
Addl Days Granted365
Working Days Charged297
Percent Time Used40
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164011
Totals761196.00396307.78706321.8892.7

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6301-05-001
Proj IDRMC - 630105001
Work TypeSPECIALTY MARKINGS
 
0.001866995.07320158.0736.9
Work Order09-23-16
Work Began09-30-16
Work Completed
Time Computed09-30-16
Contract Working Days730
Addl Days Granted0
Working Days Charged301
Percent Time Used41
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164012
Totals866995.0748354.05320158.0736.9

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6301-07-001
Proj IDRMC - 630107001
Work TypeRETROREFLECTORIZED PAVEMENT MARKINGS
 
0.0012237672.94210994.639.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-21-16
Work Began11-28-16
Work Completed
Time Computed11-28-16
Contract Working Days365
Addl Days Granted0
Working Days Charged212
Percent Time Used58
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164209
Totals2237672.940.00210994.639.4

CountyNAVARRO
HighwayFM0055
FromVARIOUS ROADWAYS IN NAVARRO
ToCOUNTY MAINTENANCE SECTION
CSJ6301-11-001
Proj IDRMC - 630111001
Work TypeRETRO REFLECTORIZED PAVEMENT MARKING
 
0.001522254.740.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164014
Totals522254.740.000.000.0

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN THE
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6301-16-001
Proj IDRMC - 630116001
Work TypeSWEEPING & DEBRIS REMOVAL
 
0.001649458.60246444.2037.9
Work Order09-26-16
Work Began10-03-16
Work Completed
Time Computed10-11-16
Contract Working Days730
Addl Days Granted0
Working Days Charged299
Percent Time Used40
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164210
Totals649458.6035142.50246444.2037.9

CountyKAUFMAN
HighwayUS0080
FromVARIOUS ROADWAYS IN THE KAUFMAN-
ToROCKWALL MAINTENANCE SECTION
CSJ6301-39-001
Proj IDRMC - 630139001
Work TypeFLEXIBLE PAVE STRUCT RPR & OVERLAY
 
0.0012455120.303594142.2499.9
Work Order10-19-16
Work Began10-26-16
Work Completed
Time Computed10-26-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6301-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164211
Totals2455120.30219265.863594142.2499.9

CountyDALLAS
HighwaySH0078
FromVARIOUS ROADWAYS IN THE NORTHEAST DALLAS
ToCOUNTY MAINTENANCE SECTION
CSJ6301-90-001
Proj IDRMC - 630190001
Work TypeGUARD FENCE & CABLE REPAIR
 
0.0012144425.001905709.1988.8
Work Order11-02-16
Work Began11-09-16
Work Completed
Time Computed11-09-16
Contract Working Days730
Addl Days Granted0
Working Days Charged259
Percent Time Used35
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164212
Totals2144425.00155944.261905709.1988.8

CountyDALLAS
HighwaySL0012
FromVARIOUS HIGHWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6301-93-001
Proj IDRMC - 630193001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.001494875.00940952.0099.9
Work Order11-22-16
Work Began12-01-16
Work Completed
Time Computed12-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged237
Percent Time Used64
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164213
Totals494875.00487146.00940952.0099.9

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6301-99-001
Proj IDRMC - 630199001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001319047.00176175.6555.2
Work Order02-16-17
Work Began02-21-17
Work Completed
Time Computed02-23-17
Contract Working Days365
Addl Days Granted0
Working Days Charged154
Percent Time Used42
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164010
Totals319047.000.00176175.6555.2

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-01-001
Proj IDRMC - 630201001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001445740.00184924.8541.4
Work Order01-23-17
Work Began01-30-17
Work Completed
Time Computed01-30-17
Contract Working Days365
Addl Days Granted0
Working Days Charged177
Percent Time Used48
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164211
Totals445740.0012050.00184924.8541.4

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-06-001
Proj IDRMC - 630206001
Work TypeGUARD FENCE & CABLE REPAIR
 
0.0011179985.00536985.2645.5
Work Order10-21-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged267
Percent Time Used36
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164213
Totals1179985.0056982.26536985.2645.5

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-13-001
Proj IDRMC - 630213001
Work TypeSWEEPING & DEBRIS REMOVAL
 
0.0011346279.00358977.1526.6
Work Order10-21-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged267
Percent Time Used36
Contractor(s)
PANNELL INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164214
Totals1346279.0044606.30358977.1526.6

CountyDALLAS
HighwaySH0078
FromVARIOUS ROADWAYS IN THE NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-14-001
Proj IDRMC - 630214001
Work TypeSWEEPING & DEBRIS REMOVAL
 
0.0011672328.40504899.6230.1
Work Order10-21-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged267
Percent Time Used36
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6302-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164014
Totals1672328.4074989.42504899.6230.1

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-16-001
Proj IDRMC - 630216001
Work TypeSWEEPING & DEBRIS REMOVAL
 
0.0011773137.00562325.0031.7
Work Order10-21-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged267
Percent Time Used36
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164215
Totals1773137.0059462.00562325.0031.7

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-83-001
Proj IDRMC - 630283001
Work TypeFLEX PAVEMENT REPAIR
 
0.001429880.001283393.1099.9
Work Order11-22-16
Work Began12-01-16
Work Completed
Time Computed12-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged237
Percent Time Used64
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164015
Totals429880.00619283.551283393.1099.9

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-84-001
Proj IDRMC - 630284001
Work TypeFLEXIBLE PAVEMENT REPAIR
 
0.001486448.162220600.3499.9
Work Order01-06-17
Work Began01-09-17
Work Completed
Time Computed01-13-17
Contract Working Days365
Addl Days Granted0
Working Days Charged198
Percent Time Used54
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164212
Totals486448.161744836.582220600.3499.9

CountyDALLAS
HighwayUS0080
FromVARIOUS LOCATIONS IN DALLAS, KAUFMAN,
ToELLIS AND NAVARRO COUNTIES
CSJ6303-20-001
Proj IDBPM - 630320001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.001548901.00594669.3799.9
Work Order02-01-17
Work Began02-15-17
Work Completed
Time Computed02-15-17
Contract Working Days102
Addl Days Granted10
Working Days Charged101
Percent Time Used90
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12164015
Totals548901.0095909.70594669.3799.9

CountyKAUFMAN
HighwayIH0020
FromVARIOUS ROADWAYS IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6304-12-001
Proj IDRMC - 630412001
Work TypeGUARD FENCE & CABLE BARRIER REPAIR
 
0.001920608.00876182.5095.0
Work Order11-28-16
Work Began12-01-16
Work Completed
Time Computed12-05-16
Contract Working Days730
Addl Days Granted0
Working Days Charged238
Percent Time Used32
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164213
Totals920608.0083485.00876182.5095.0

page 1 | page 2 | page 3 | page 4 | page 5