Monthly State Let Maintenance Report For Dallas District As Of Mar 13, 2017 Page 2 Of 5

Last Update: Monday, March 13, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6293-56-001
Proj IDRMC - 629356001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001425785.7044530.6810.4
Work Order05-26-16
Work Began05-31-16
Work Completed
Time Computed06-02-16
Contract Working Days365
Addl Days Granted0
Working Days Charged271
Percent Time Used74
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6293-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164012
Totals425785.70642.2844530.6810.4

CountyCOLLIN
HighwayFM1827
FromVARIOUS LOCATIONS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6293-57-001
Proj IDRMC - 629357001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0011434042.50738187.6751.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-09-16
Work Began09-16-16
Work Completed
Time Computed09-16-16
Contract Working Days365
Addl Days Granted0
Working Days Charged165
Percent Time Used45
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6293-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164212
Totals1434042.500.00738187.6751.4

CountyDENTON
HighwayFM1385
FromMUSTANG ROAD
ToFM 455
CSJ6294-69-001
Proj IDRMC - 629469001
Work TypeCULVERT EXTENSION/REPLACING
 
0.100402160.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-08-17
Work Began00-00-00
Work Completed
Time Computed02-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged14
Percent Time Used3
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6294-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164206
Totals402160.000.000.000.0

CountyNAVARRO
HighwayFM3096
FromVARIOUS ROADWAYS IN NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6295-03-001
Proj IDRMC - 629503001
Work TypeFLEXIBLE PAV STRUCTURE RPR AND OVERLAY
 
0.0012767250.001917809.7969.3
Work Order03-29-16
Work Began04-04-16
Work Completed
Time Computed04-04-16
Contract Working Days365
Addl Days Granted0
Working Days Charged329
Percent Time Used90
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6295-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164014
Totals2767250.000.001917809.7969.3

CountyKAUFMAN
HighwayIH0020
FromVARIOUS ROADWAYS IN THE KAUFMAN-
ToROCKWALL MAINTENANCE SECTION
CSJ6295-33-001
Proj IDRMC - 629533001
Work TypeSPECIALTY MARKINGS
 
0.001423373.30105256.5524.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-16
Work Began12-08-16
Work Completed
Time Computed12-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged79
Percent Time Used10
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6295-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164213
Totals423373.300.00105256.5524.8

CountyKAUFMAN
HighwayIH0020
FromVAIOUS ROADWAYS IN THE KAUFMAN AND
ToROCKWALL MAINTENANCE SECTION
CSJ6296-21-001
Proj IDRMC - 629621001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001547600.00328593.7760.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-02-16
Work Began05-09-16
Work Completed
Time Computed05-09-16
Contract Working Days730
Addl Days Granted0
Working Days Charged292
Percent Time Used40
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164209
Totals547600.000.00328593.7760.0

CountyDALLAS
HighwayIH0030
FromVARIOUS HOV LANES IN DALLAS AND TARRANT
ToCOUNTIES
CSJ6296-73-001
Proj IDRMC - 629673001
Work TypePERF BASED O & M OF HOV-EXPRESS LANES
 
0.0012375000.00474023.4919.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-13-16
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged209
Percent Time Used28
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164210
Totals2375000.000.00474023.4919.9

CountyELLIS
HighwayUS0077
FromVARIOUS ROADWAYS IN ELLIS
ToCOUNTY MAINTENANCE
CSJ6296-85-001
Proj IDRMC - 629685001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.001915032.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164211
Totals915032.000.000.000.0

CountyNAVARRO
HighwaySH0031
FromVARIOUS ROADWAYS IN NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6297-52-001
Proj IDRMC - 629752001
Work TypeGUARD FENCE & CABLE BARRIER REPAIR
 
0.001354169.0099449.0028.0
Work Order08-02-16
Work Began08-08-16
Work Completed
Time Computed08-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged204
Percent Time Used27
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05164204
Totals354169.0012437.0099449.0028.0

CountyELLIS
HighwayIH0045
FromIH45 FROM DALLAS COUNTY LINE
ToTO NAVARRO COUNTY LINE
CSJ6297-75-001
Proj IDRMC - 629775001
Work TypeCABLE_MEDIAN BARRIER SYSTEM REPAIR
 
0.001216800.0088370.0040.7
Work Order07-01-16
Work Began07-08-16
Work Completed
Time Computed07-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged233
Percent Time Used31
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05164005
Totals216800.0046430.0088370.0040.7

CountyCOLLIN
HighwayUS0075
FromVARIOUS LOCATIONS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6298-90-001
Proj IDRMC - 629890001
Work TypePOTHOLE REPAIR & EDGE REPAIR
 
0.001780000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164010
Totals780000.000.000.000.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS LOCATIONS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6299-00-001
Proj IDRMC - 629900001
Work TypeMETAL BEAM GUARD FENCE & DELINEATION
 
0.001897796.00296849.0033.0
Work Order10-13-16
Work Began10-20-16
Work Completed
Time Computed10-19-16
Contract Working Days730
Addl Days Granted0
Working Days Charged129
Percent Time Used17
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164011
Totals897796.0085758.00296849.0033.0

CountyNAVARRO
HighwayIH0045
FromVARIOUS LOCATIONS ON IH45 AND SH31 IN
ToNAVARRO COUNTY MAINTENANCE SECTION
CSJ6299-03-001
Proj IDRMC - 629903001
Work TypeFULL-DEPTH CONCRETE REPAIR
 
0.001436000.00447819.3099.9
Work Order07-26-16
Work Began07-26-16
Work Completed
Time Computed08-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged214
Percent Time Used29
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164006
Totals436000.000.00447819.3099.9

CountyDALLAS
HighwayUS0080
FromVARIOUS HIGHWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6299-08-001
Proj IDRMC - 629908001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0012060755.000.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed08-15-16
Time Computed00-00-00
Contract Working Days548
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164012
Totals2060755.000.000.00100.0

CountyROCKWALL
HighwayIH0030
FromVARIOUS ROADWAYS IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6299-09-001
Proj IDRMC - 629909001
Work TypeFULL DEPTH CONRETE & SPALLING REPAIR
 
0.001587100.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-16
Work Began12-08-16
Work Completed
Time Computed12-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged78
Percent Time Used10
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164208
Totals587100.000.000.000.0

CountyELLIS
HighwayFM1182
FromVARIOUS LOCATIONS IN DALLAS DISTRICT
ToEXCLUDING DALLAS & ROCKWALL COUNTY
CSJ6299-29-001
Proj IDRMC - 629929001
Work TypeFOR THE CONST OF SEAL COAT & PVMT MRKGS
 
0.0012123083.55249335.1911.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-24-17
Work Began00-00-00
Work Completed
Time Computed03-06-17
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164207
Totals2123083.550.00249335.1911.7

CountyDENTON
HighwayIH0035W
FromVARIOUS ROADWAYS IN THE DENTON
ToMAINTENANCE SECTION
CSJ6299-33-001
Proj IDRMC - 629933001
Work TypeGUARDRAIL, CABLE & HEADLIGHT BARRIER REP
 
0.1001785538.00274579.2515.3
Work Order08-25-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged176
Percent Time Used24
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164009
Totals1785538.0043315.50274579.2515.3

CountyNAVARRO
HighwaySH0031
FromVARIOUS ROADWAYS IN NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6299-34-001
Proj IDRMC - 629934001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.001752679.20148906.0419.7
Work Order08-24-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged180
Percent Time Used24
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164210
Totals752679.2018056.34148906.0419.7

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE SOUTHEAST DALLAS
ToCOUNTY MAINTENANCE SECTION
CSJ6299-44-001
Proj IDRMC - 629944001
Work TypeGUARD FENCE & CABLE REPAIR
 
0.0011102913.00435570.0039.4
Work Order11-02-16
Work Began11-02-16
Work Completed
Time Computed11-09-16
Contract Working Days730
Addl Days Granted0
Working Days Charged117
Percent Time Used16
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164012
Totals1102913.00138016.00435570.0039.4

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE SOUTHWEST DALLAS
ToCOUNTY MAINTENANCE SECTION
CSJ6299-47-001
Proj IDRMC - 629947001
Work TypeFLEXIBLE PAVEMENT REPAIR
 
0.001425446.1046063.8610.8
Work Order11-10-16
Work Began12-04-16
Work Completed
Time Computed12-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged87
Percent Time Used23
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6299-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164210
Totals425446.1046063.8646063.8610.8

page 1 | page 2 | page 3 | page 4 | page 5