Monthly State Let Maintenance Report For Dallas District As Of Feb 10, 2017 Page 2 Of 5

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKAUFMAN
HighwayIH0020
FromVARIOUS ROADWAYS IN THE KAUFMAN-
ToROCKWALL MAINTENANCE SECTION
CSJ6292-16-001
Proj IDRMC - 629216001
Work TypeRETROREFLECT PAVEMENT MARKINGS
 
0.001760061.0461009.268.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-16
Work Began12-08-16
Work Completed
Time Computed12-08-16
Contract Working Days365
Addl Days Granted0
Working Days Charged49
Percent Time Used13
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164209
Totals760061.040.0061009.268.0

CountyDALLAS
HighwaySH0078
FromVARIOUS ROADWAYS IN THE DALLAS COUNTY
ToMAINTENANCE SECTIONS
CSJ6292-51-001
Proj IDRMC - 629251001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001874836.10145470.5116.6
Work Order06-08-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged209
Percent Time Used57
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6292-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164011
Totals874836.1054223.46145470.5116.6

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE
ToDALLAS DISTRICT
CSJ6292-93-001
Proj IDRMC - 629293001
Work TypeNON-SITE SPEC SIGN REPLACEMENT &
 
0.001628889.9957427.199.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-27-16
Work Began09-01-16
Work Completed
Time Computed08-03-16
Contract Working Days730
Addl Days Granted0
Working Days Charged176
Percent Time Used24
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164013
Totals628889.990.0057427.199.1

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6293-56-001
Proj IDRMC - 629356001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001425785.7043888.4010.3
Work Order05-26-16
Work Began05-31-16
Work Completed
Time Computed06-02-16
Contract Working Days365
Addl Days Granted0
Working Days Charged242
Percent Time Used66
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6293-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164012
Totals425785.700.0043888.4010.3

CountyCOLLIN
HighwayFM1827
FromVARIOUS LOCATIONS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6293-57-001
Proj IDRMC - 629357001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0011434042.50326043.3622.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-09-16
Work Began09-16-16
Work Completed
Time Computed09-16-16
Contract Working Days365
Addl Days Granted0
Working Days Charged137
Percent Time Used37
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6293-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164212
Totals1434042.500.00326043.3622.7

CountyDENTON
HighwayFM1385
FromMUSTANG ROAD
ToFM 455
CSJ6294-69-001
Proj IDRMC - 629469001
Work TypeCULVERT EXTENSION/REPLACING
 
0.100402160.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-08-17
Work Began00-00-00
Work Completed
Time Computed02-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6294-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164206
Totals402160.000.000.000.0

CountyNAVARRO
HighwayFM3096
FromVARIOUS ROADWAYS IN NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6295-03-001
Proj IDRMC - 629503001
Work TypeFLEXIBLE PAV STRUCTURE RPR AND
 
0.0012767250.001917809.7969.3
Work Order03-29-16
Work Began04-04-16
Work Completed
Time Computed04-04-16
Contract Working Days365
Addl Days Granted0
Working Days Charged295
Percent Time Used80
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6295-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164014
Totals2767250.000.001917809.7969.3

CountyKAUFMAN
HighwayIH0020
FromVARIOUS ROADWAYS IN THE KAUFMAN-
ToROCKWALL MAINTENANCE SECTION
CSJ6295-33-001
Proj IDRMC - 629533001
Work TypeSPECIALTY MARKINGS
 
0.001423373.3012949.603.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-16
Work Began12-08-16
Work Completed
Time Computed12-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged49
Percent Time Used6
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6295-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164213
Totals423373.300.0012949.603.0

CountyKAUFMAN
HighwayIH0020
FromVAIOUS ROADWAYS IN THE KAUFMAN AND
ToROCKWALL MAINTENANCE SECTION
CSJ6296-21-001
Proj IDRMC - 629621001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001547600.00247012.8445.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-02-16
Work Began05-09-16
Work Completed
Time Computed05-09-16
Contract Working Days730
Addl Days Granted0
Working Days Charged262
Percent Time Used35
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164209
Totals547600.000.00247012.8445.1

CountyDALLAS
HighwayIH0030
FromVARIOUS HOV LANES IN DALLAS AND TARRANT
ToCOUNTIES
CSJ6296-73-001
Proj IDRMC - 629673001
Work TypePERF BASED O & M OF HOV-EXPRESS
 
0.0012375000.00420533.4917.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-13-16
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged178
Percent Time Used24
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164210
Totals2375000.000.00420533.4917.7

CountyELLIS
HighwayUS0077
FromVARIOUS ROADWAYS IN ELLIS
ToCOUNTY MAINTENANCE
CSJ6296-85-001
Proj IDRMC - 629685001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.001915032.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164211
Totals915032.000.000.000.0

CountyNAVARRO
HighwaySH0031
FromVARIOUS ROADWAYS IN NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6297-52-001
Proj IDRMC - 629752001
Work TypeGUARD FENCE & CABLE BARRIER REPAIR
 
0.001354169.0087012.0024.5
Work Order08-02-16
Work Began08-08-16
Work Completed
Time Computed08-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged172
Percent Time Used23
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05164204
Totals354169.0015032.0087012.0024.5

CountyELLIS
HighwayIH0045
FromIH45 FROM DALLAS COUNTY LINE
ToTO NAVARRO COUNTY LINE
CSJ6297-75-001
Proj IDRMC - 629775001
Work TypeCABLE_MEDIAN BARRIER SYSTEM REPAIR
 
0.001216800.0041940.0019.3
Work Order07-01-16
Work Began07-08-16
Work Completed
Time Computed07-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged202
Percent Time Used27
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05164005
Totals216800.0013640.0041940.0019.3

CountyCOLLIN
HighwayUS0075
FromVARIOUS LOCATIONS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6298-90-001
Proj IDRMC - 629890001
Work TypePOTHOLE REPAIR & EDGE REPAIR
 
0.001780000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164010
Totals780000.000.000.000.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS LOCATIONS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6299-00-001
Proj IDRMC - 629900001
Work TypeMETAL BEAM GUARD FENCE &
 
0.001897796.00211091.0023.5
Work Order10-13-16
Work Began10-20-16
Work Completed
Time Computed10-19-16
Contract Working Days730
Addl Days Granted0
Working Days Charged98
Percent Time Used13
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164011
Totals897796.0053908.00211091.0023.5

CountyNAVARRO
HighwayIH0045
FromVARIOUS LOCATIONS ON IH45 AND SH31 IN
ToNAVARRO COUNTY MAINTENANCE SECTION
CSJ6299-03-001
Proj IDRMC - 629903001
Work TypeFULL-DEPTH CONCRETE REPAIR
 
0.001436000.00447819.3099.9
Work Order07-26-16
Work Began07-26-16
Work Completed
Time Computed08-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged190
Percent Time Used26
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164006
Totals436000.00104521.69447819.3099.9

CountyDALLAS
HighwayUS0080
FromVARIOUS HIGHWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6299-08-001
Proj IDRMC - 629908001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0012060755.000.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed08-15-16
Time Computed00-00-00
Contract Working Days548
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164012
Totals2060755.000.000.00100.0

CountyROCKWALL
HighwayIH0030
FromVARIOUS ROADWAYS IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6299-09-001
Proj IDRMC - 629909001
Work TypeFULL DEPTH CONRETE & SPALLING
 
0.001587100.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-16
Work Began12-08-16
Work Completed
Time Computed12-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged49
Percent Time Used6
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164208
Totals587100.000.000.000.0

CountyELLIS
HighwayFM1182
FromVARIOUS LOCATIONS IN DALLAS DISTRICT
ToEXCLUDING DALLAS & ROCKWALL COUNTY
CSJ6299-29-001
Proj IDRMC - 629929001
Work TypeFOR THE CONST OF SEAL COAT & PVMT
 
0.0012123083.5593150.004.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164207
Totals2123083.550.0093150.004.3

CountyDENTON
HighwayIH0035W
FromVARIOUS ROADWAYS IN THE DENTON
ToMAINTENANCE SECTION
CSJ6299-33-001
Proj IDRMC - 629933001
Work TypeGUARDRAIL, CABLE & HEADLIGHT
 
0.1001785538.00231263.7512.9
Work Order08-25-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged149
Percent Time Used20
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164009
Totals1785538.0047059.25231263.7512.9

page 1 | page 2 | page 3 | page 4 | page 5