Monthly State Let Construction Report For Corpus Christi District As Of Jun 10, 2015 Page 3 Of 4

Last Update: Wednesday, June 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLIVE OAK
Highway US 59 ETC
From US 281
To MCMULLEN C/L
CSJ 0542-06-047
Proj ID STP 2015(376)HES
Work Type TEXTURIZE SHOULDERS AND CENTERLINE
 
77.329 742929.98 11476.25 873902.82 100.0
Work Order 01-05-15
Work Began 01-26-15
Work Completed 05-06-15
Time Computed 01-21-15
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 51
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0542-06-047
D. I. J. CONSTRUCTION, INC.( 49.75%)
Contract # 12143223
Totals 742929.98 11476.25 873902.82 100.0

CountyNUECES
Highway SH 358
From .2 MI W OF FM 43
To .2 MI E OF FM 43
CSJ 0617-01-185
Proj ID STP 2014(982)HES
Work Type IMPORVE TRAFFIC SIGNAL
 
0.400 281111.29 0.00 0.00 0.0
CountyNUECES
Highway SH 358
From .2 MI W OF EVERHART
To .2 MI E OF EVERHART
CSJ 0617-01-186
Proj ID STP 2014(990)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.400 280827.44 0.00 81529.30 29.0
CountyNUECES
Highway SH 358
From .4 MI W OF SS3
To .4 MI E OF SS3
CSJ 0617-01-187
Proj ID STP 2014(991)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.600 373871.92 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-24-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 3
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0617-01-185
HIGHWAY BARRICADES AND SERVICES, LLC (1.75%)
Contract # 06143057
Totals 935810.65 0.00 81529.30 8.7

CountyNUECES
Highway VA
From AT VARIOUS LOCATIONS IN NUECES CO.
To .
CSJ 0916-00-069
Proj ID ITS 99(714)
Work Type ITS INTERGRATION
 
0.100 946694.00 0.00 1048424.90 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-28-13
Work Began 07-29-13
Work Completed 09-29-14
Time Computed 07-14-13
Contract Working Days 204
Addl Days Granted 14
Working Days Charged 218
Percent Time Used 100
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-069
HIGHWAY BARRICADES AND SERVICES, LLC (4.62%)
J.C. COMMUNICATION ( 27.95%)
VICKERS CONSTRUCTION (7.15%)
J. CARROLL WEAVER, INC.(1.83%)
SPLICERS, INC. (5.13%)
Contract # 05133028
Totals 946694.00 0.00 1048424.90 100.0

CountyNUECES
Highway VA
From AT VARIOUS LOCATIONS IN KARNES CO.
To .
CSJ 0916-00-071
Proj ID STP 2013(976)
Work Type INTERSECTION IMPROVEMENTS
 
0.100 5181781.67 0.00 5245734.82 100.0
CountyNUECES
Highway VA
From AT VARIOUS LOCATIONS IN GOLIAD CO.
To .
CSJ 0916-00-072
Proj ID STP 2013(976)
Work Type INTERSECTION IMPROVEMENTS
 
0.100 2611106.96 0.00 2418536.59 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-22-13
Work Began 11-12-13
Work Completed 04-07-15
Time Computed 11-07-13
Contract Working Days 160
Addl Days Granted 12
Working Days Charged 171
Percent Time Used 99
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-071
D&S TEXAS ICON CONSTRUCTION, LLC (0.44%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.52%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.30%)
MURRAY CONSTRUCTION(0.51%)
STAR OPERATIONS, INC.(7.36%)
Contract # 08133248
Totals 7792888.63 0.00 7664271.41 100.0

CountyBEE
Highway CR
From STR1 (AA0137001)CR536 @ BULLSHEAD C
To APPROX. 0.85 MI. SW OF US 181
CSJ 0916-25-018
Proj ID BR 1302(063)
Work Type BRIDGE REPLACEMENT
 
0.090 694394.73 40433.00 537866.20 77.4
Work Order 07-22-14
Work Began 09-22-14
Work Completed  
Time Computed 08-07-14
Contract Working Days 112
Addl Days Granted 0
Working Days Charged 85
Percent Time Used 75
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0916-25-018
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.99%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.39%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.83%)
Contract # 06143007
Totals 694394.73 40433.00 537866.20 77.4

CountyGOLIAD
Highway PW
From AT GOLIAD SHS
To .
CSJ 0916-26-018
Proj ID C 916-26-18
Work Type SEAL COAT ROADS & LEVEL UP CAMPSITE
 
0.100 212182.44 0.00 208674.29 99.1
Work Order 06-11-14
Work Began 07-21-14
Work Completed  
Time Computed 06-27-14
Contract Working Days 17
Addl Days Granted 2
Working Days Charged 22
Percent Time Used 115
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0916-26-018
FLASHER EQUIPMENT COMPANY(1.45%)
HIGHWAY BARRICADES AND SERVICES, LLC (5.60%)
ROAD REPAIR, LLC ( 42.70%)
Contract # 05143040
Totals 212182.44 0.00 208674.29 99.1

CountyLIVE OAK
Highway CR
From STR 1(AA0210001)GOOD HOPE @ ATASCOS
To APPROX 1.0 MI W OF US 281
CSJ 0916-29-012
Proj ID BR 2012(440)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.068 1340912.53 149112.15 1060888.52 79.1
Work Order 08-15-14
Work Began 10-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 181
Addl Days Granted 9
Working Days Charged 116
Percent Time Used 61
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0916-29-012
ALTUS TRAFFIC MANAGEMENT LLC (0.62%)
BEAIRD DRILLING(6.83%)
CERTIFIED PLACERS LLC(0.83%)
DELTA SPECIALTIES SIGNS & SUPPLIES (0.15%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.50%)
DOUBLE S PAVING, INC.(1.37%)
FUQUAY, INC. (1.28%)
PAVEMENT MARKINGS INC. (0.46%)
PENHALL COMPANY(0.39%)
Contract # 06143236
Totals 1340912.53 149112.15 1060888.52 79.1

CountySAN PATRICIO
Highway SH 188
From FM 630
To US 77
CSJ 0994-01-030
Proj ID STP 2012(533)
Work Type REHAB
 
4.300 9223815.50 58401.72 9732617.05 99.9
Work Order 08-30-12
Work Began 02-22-13
Work Completed  
Time Computed 08-01-12
Contract Working Days 345
Addl Days Granted 0
Working Days Charged 331
Percent Time Used 95
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0994-01-030
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.49%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(0.94%)
MURRAY CONSTRUCTION(0.30%)
PRIMATE CONSTRUCTION, INC. (0.14%)
KL DURHAM CONSTRUCTION, LLC(0.07%)
SCOTT DERR PAINTING CO, LLC(0.04%)
TERRY L. ELLIS BACKHOE (0.41%)
HIGHWAY TECHNOLOGIES, INC. (0.84%)
JMHP, INC. (0.58%)
W.S. CONSTRUCTION COMPANY( 20.52%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.89%)
ADVANCED PUMPING, LLC(0.06%)
STAR OPERATIONS, INC.(0.61%)
TAHOE TRUCKING, INC. (3.39%)
Contract # 06123226
Totals 9223815.50 58401.72 9732617.05 99.9

CountyBEE
Highway FM 888
From AT OLMOS CREEK ON FM 888
To 9.2 MILES SW OF FM 351
CSJ 1063-02-015
Proj ID BR 2015(890)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.080 927181.97 0.00 0.00 0.0
CountyBEE
Highway FM 796
From AT PAPLOTE CREEK ON FM 796
To APPOX. 1.2 MI NW OF SH 359
CSJ 1118-01-021
Proj ID BR 2015(890)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 721986.94 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-01-15
Work Began 00-00-00
Work Completed  
Time Computed 07-02-15
Contract Working Days 235
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1063-02-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153205
Totals 1649168.91 0.00 0.00 0.0

CountyBEE
Highway FM 888
From FM 797
To 2.3 MI S. OF FM 797
CSJ 1063-02-017
Proj ID STP 1502(245)HES
Work Type GRADE, BASE, SURF
 
2.292 1168693.15 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1063-02-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153209
Totals 1168693.15 0.00 0.00 0.0

CountyKARNES
Highway FM 743
From .070 MI E. OF CR 139
To .085 MI E. OF FM 2443
CSJ 1095-03-016
Proj ID STP 2014(628)HES
Work Type PROVIDE ADDIT. PAVED SURFACE WIDTH
 
6.014 2619906.61 0.00 2630897.49 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-16-14
Work Began 07-22-14
Work Completed 01-16-15
Time Computed 07-02-14
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 102
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1095-03-016
ALTUS TRAFFIC MANAGEMENT LLC (0.35%)
MURRAY CONSTRUCTION(0.95%)
PAVEMENT MARKINGS INC. (1.32%)
ROADWAY SPECIALTIES, INC.(5.07%)
STAFF CONCRETE (6.48%)
Contract # 05143021
Totals 2619906.61 0.00 2630897.49 100.0

CountyGOLIAD
Highway FM 884
From FM 1726
To FM 81
CSJ 1196-03-016
Proj ID STP 2015(379)HES
Work Type PROVIDE ADDIT. PAVED SURFACE WIDTH
 
6.669 2800473.65 47149.51 245996.15 8.7
Work Order 02-27-15
Work Began 04-09-15
Work Completed  
Time Computed 03-15-15
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 19
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1196-03-016
ENVIRONMENTAL SAFETY SERVICES, INC.(1.80%)
MURRAY CONSTRUCTION(1.11%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.70%)
Contract # 12143012
Totals 2800473.65 47149.51 245996.15 8.7

CountyKLEBERG
Highway FM 1356
From BU 77
To .4 MI EAST OF BU 77
CSJ 1446-02-019
Proj ID STP 2014(727)
Work Type REHAB AND WIDEN
 
0.400 639655.98 0.00 592607.60 92.6
CountyKLEBERG
Highway FM 1717
From FM 1356 (GENERAL CAVAZOS BLVD.)
To .5 MILE SE
CSJ 1845-01-019
Proj ID STP 2014(727)
Work Type GRADE, BASE, SURF
 
0.500 1135345.42 1600.00 1052428.29 92.6
Work Order 08-08-14
Work Began 09-15-14
Work Completed  
Time Computed 08-24-14
Contract Working Days 136
Addl Days Granted 0
Working Days Charged 116
Percent Time Used 85
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1446-02-019
HIGHWAY BARRICADES AND SERVICES, LLC (3.00%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.79%)
DUSTROL, INC.(0.55%)
SOIL-TECH, INC.(1.89%)
Contract # 06143221
Totals 1775001.40 1600.00 1645035.89 92.6

CountySAN PATRICIO
Highway FM 1069
From SH 361 IN INGLESIDE
To BS 35
CSJ 1549-03-017
Proj ID STP 1402(067)
Work Type GR, STRS, BASE, SURF & C & G
 
3.584 4902667.27 97423.30 332205.00 6.7
CountySAN PATRICIO
Highway FM 1069
From SH 361
To 8TH STREET
CSJ 1549-04-029
Proj ID STP 1402(067)
Work Type MILL, OVERLAY AND BASE REPAIR
 
2.274 1011236.42 158205.41 251229.41 24.8
Work Order 01-05-15
Work Began 04-21-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 12
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1549-03-017
WOODSTOCK TREE SURGEONS(0.16%)
K.L. DURHAM CONSTRUCTION, LLC(1.46%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.23%)
SOIL-TECH, INC.(0.54%)
CLARK PIPELINE SERVICES( 15.57%)
JM MAINTENANCE SERVICE INC.(0.39%)
Contract # 08143045
Totals 5913903.69 255628.71 583434.41 9.8

CountyNUECES
Highway FM 43
From SH 286
To YORKTOWN BLVD.
CSJ 1557-01-037
Proj ID STP 2013(556)MM
Work Type GRADE, BASE, SURF, STRS
 
1.884 9863126.39 207894.10 7423077.61 75.2
Work Order 08-02-13
Work Began 01-27-14
Work Completed  
Time Computed 06-03-13
Contract Working Days 317
Addl Days Granted 25
Working Days Charged 306
Percent Time Used 89
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1557-01-037
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.20%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(2.42%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.22%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.22%)
SOIL-TECH, INC.(0.33%)
D & C CONCRETE CUTTING, INC. (0.11%)
BEDO CONSTRUCTION PRODUCTS, INC. (1.98%)
PRIMATE CONSTRUCTION, INC. (0.05%)
DELTA PRIME SPECIALTY SERVICES, INC. (0.06%)
ADVANCED PUMPING, LLC(0.10%)
CABCOS CONTRACTORS LLC (3.09%)
SCR CONSTRUCTION CO., INC. (0.41%)
Contract # 04133202
Totals 9863126.39 207894.10 7423077.61 75.2

CountyLIVE OAK
Highway FM 534
From 5.51 MILES W OF FM 3024
To FM 3162
CSJ 1808-01-028
Proj ID STP 1502(152)HES
Work Type GRADE, BASE, SURF
 
6.550 2602993.61 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1808-01-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153036
Totals 2602993.61 0.00 0.00 0.0

CountyNUECES
Highway SH 361
From AVE. G IN PORT ARANSAS
To BEACH ACCESS 1
CSJ 2263-03-029
Proj ID C 2263-3-29
Work Type GRD, BASE, STRS, STORM SEWER, C & G, SIDE
 
2.621 12988210.75 204495.62 3545988.51 27.3
Work Order 12-23-13
Work Began 12-01-14
Work Completed  
Time Computed 12-01-14
Contract Working Days 408
Addl Days Granted 0
Working Days Charged 86
Percent Time Used 21
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2263-03-029
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.56%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.42%)
CABCOS CONTRACTORS LLC (8.59%)
TROUT TRUCKING_COMPANY INC.(3.49%)
JHABORES CONSTRUCTION CO, INC. ( 22.15%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.95%)
STAR OPERATIONS, INC.(2.14%)
K.L. DURHAM CONSTRUCTION, LLC(1.29%)
Contract # 10133021
Totals 12988210.75 204495.62 3545988.51 27.3

CountyNUECES
Highway SH 361
From ACCESS RD1A
To MARINERS DR.
CSJ 2263-03-035
Proj ID STP 2014(610)
Work Type LANDSCAPE IMPROVEMENTS
 
4.570 143796.00 1000.00 150403.90 99.9
Work Order 05-09-14
Work Began 06-11-14
Work Completed  
Time Computed 05-25-14
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 58
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2263-03-035
HIGHWAY BARRICADES AND SERVICES, LLC (1.73%)
Contract # 04143023
Totals 143796.00 1000.00 150403.90 99.9

CountyGOLIAD
Highway FM 2442
From SH 239
To MAIL RD
CSJ 2342-01-011
Proj ID STP 2015(895)HES
Work Type GRADE, BASE, SURF
 
1.970 747427.41 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-04-15
Work Began 00-00-00
Work Completed  
Time Computed 07-05-15
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2342-01-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153218
Totals 747427.41 0.00 0.00 0.0

CountyNUECES
Highway FM 2444
From SH 286
To OSO PARKWAY INTERSECTION
CSJ 2343-01-036
Proj ID STP 2013(936)MM
Work Type GRADE, BASE, SURF, STRTS
 
4.051 24447530.97 0.00 2236452.73 9.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-13-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 510
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2343-01-036
AARON CONCRETE CONTRACTORS, L.P. (0.33%)
MURRAY CONSTRUCTION(0.19%)
SOIL-TECH, INC.(0.10%)
PRIMATE CONSTRUCTION, INC. (0.08%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.57%)
STAR OPERATIONS, INC.(1.63%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.10%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.95%)
PENNTEX MILLING, LLC (0.30%)
Contract # 08133005
Totals 24447530.97 0.00 2236452.73 9.1

page 1 | page 2 | page 3 | page 4