Monthly State Let Construction Report For Corpus Christi District As Of Jul 14, 2017 Page 3 Of 3

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNUECES
HighwayPW
FromAT THE CCA-CPL MARINE DEVEL. CENTER
To.
CSJ0916-35-164
Proj IDC 916-35-164
Work TypeRESURFACING OF ROADWAY & PARKING
 
0.0012331963.360.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0916-35-164
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173226
Totals2331963.360.000.000.0

CountyJIM WELLS
HighwayCR
FromSTR 1 (AA0175-001) CR 320/AGUA DULC
To2.9 MI E OF SH 359
CSJ0916-37-030
Proj IDBR 1602(582)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.066348040.690.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-12-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0916-37-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173025
Totals348040.690.000.000.0

CountyARANSAS
HighwayPW
FromAT GOOSE ISLAND STATE PARK
To.
CSJ0916-38-009
Proj IDC 916-38-9
Work TypeRAISE RD PROFILE & INSTALL SEAWALL
 
0.1451003164.461049345.3899.9
Work Order02-15-17
Work Began03-08-17
Work Completed
Time Computed03-01-17
Contract Working Days51
Addl Days Granted5
Working Days Charged52
Percent Time Used92
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0916-38-009
HIGHWAY BARRICADES AND SERVICES, LLC (1.00)
Contract #01173229
Totals1003164.46125915.281049345.3899.9

CountyJIM WELLS
HighwayFM 624
FromSH 359
ToUS 281
CSJ0989-01-037
Proj IDSTP 1602(264)HES
Work TypePROVIDE ADDIT. PAVED SURFACE WIDTH
 
10.8914558633.803007376.1165.9
Work Order12-28-16
Work Began01-27-17
Work Completed
Time Computed01-02-17
Contract Working Days187
Addl Days Granted0
Working Days Charged97
Percent Time Used51
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0989-01-037
INTERSTATE BARRICADES & MARKINGS, INC. (0.53)
MV HENKE COMPANY, LLC (3.60)
PAVEMENT MARKINGS INC. (1.53)
HIGHWAY BARRICADES AND SERVICES, LLC (1.13)
STAFF CONCRETE (13.05)
D&S TEXAS ICON CONSTRUCTION (0.47)
LONE STAR PAVING (0.15)
Contract #11163016
Totals4558633.80881419.563007376.1165.9

CountyBEE
HighwayFM 882
FromAT ELM CREEK BRIDGE ON FM 882
To2.8 MI W. OF SH 72
CSJ0991-04-011
Proj IDBR 1702(117)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.206737683.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days139
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ACME BRIDGE COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0991-04-011
DUSTROL, INC. (0.89)
ENVIRONMENTAL SAFETY SERVICES, INC. (2.90)
FLASHER EQUIPMENT COMPANY (0.64)
HIGHWAY BARRICADES AND SERVICES, LLC (0.57)
HOUSTON SAWING & DRILLING (0.36)
LONE STAR EROSION CONTROL (4.25)
LONE STAR PAVING (4.77)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.77)
Contract #05173223
Totals737683.480.000.000.0

CountyNUECES
HighwayFM 666
FromSH 44
ToFM 624
CSJ1052-01-076
Proj IDSTP 2017(819)
Work TypeGRADE,BASE,SURF
 
6.3218117215.711275267.7715.7
Work Order04-24-17
Work Began05-03-17
Work Completed
Time Computed05-01-17
Contract Working Days204
Addl Days Granted0
Working Days Charged32
Percent Time Used15
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1052-01-076
D&S TEXAS ICON CONSTRUCTION (2.20)
AWP, INC. (0.33)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.38)
BEAVER CONTRACTORS, LLC (12.31)
M.V. HENKE ENTERPRISES, INC. (0.15)
THE LEVY COMPANY, L.P. (0.36)
FLASHER EQUIPMENT COMPANY (1.17)
Contract #03173231
Totals8117215.71325323.381275267.7715.7

CountyNUECES
HighwaySH 357
FromSH 286
ToRODD FIELD
CSJ1069-01-037
Proj IDNH 2017(964)
Work TypeNOVACHIP ROADWAY
 
6.2004532438.530.000.0
CountyNUECES
HighwaySH 357
FromSH 357
ToSH 358
CSJ1069-01-038
Proj IDNH 2017(964)
Work TypeNOVACHIP ROADWAY
 
1.800627553.2633369.005.3
CountyNUECES
HighwayFM 43
FromYORKTOWN
ToSH 358
CSJ1557-01-044
Proj IDNH 2017(964)
Work TypeNOVACHIP ROADWAY
 
2.460922993.400.000.0
Work Order05-11-17
Work Began00-00-00
Work Completed
Time Computed06-01-17
Contract Working Days89
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1069-01-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173219
Totals6082985.1933369.0033369.000.5

CountyBEE
HighwayFM 798
FromUS 181
ToFM 2985
CSJ1117-01-015
Proj IDSTP 2016(811)
Work TypeWIDEN ROADWAY
 
6.4984270569.944242403.2899.3
Work Order05-10-16
Work Began06-13-16
Work Completed
Time Computed05-01-16
Contract Working Days220
Addl Days Granted0
Working Days Charged198
Percent Time Used90
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1117-01-015
BEAVER CONTRACTORS, LLC (8.64)
EGGEMEYER LAND CLEARING, LLC (3.66)
MPB, INC. (0.19)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.18)
ROADWAY SPECIALTIES, INC. (6.22)
Contract #03163006
Totals4270569.940.004242403.2899.3

CountyBEE
HighwayFM 796
FromAT OLMOS CREEK ON FM 796
To1 MILE S OF FM 797
CSJ1118-01-019
Proj IDBR 1702(491)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.132444575.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 1118-01-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173027
Totals444575.500.000.000.0

CountyNUECES
HighwayFM 43
FromW. OF CR 49
ToSH 286
CSJ1557-01-041
Proj IDSTP 1602(484)
Work TypeGRADE,BASE,SURF
 
2.0303286683.802284826.1369.5
Work Order09-20-16
Work Began12-12-16
Work Completed
Time Computed10-20-16
Contract Working Days131
Addl Days Granted0
Working Days Charged115
Percent Time Used87
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1557-01-041
TROUT TRUCKING_COMPANY INC. (6.82)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.71)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.84)
PERFORMANCE EQUIPMENT SERVICE (0.59)
HIGHWAY BARRICADES AND SERVICES, LLC (3.32)
Contract #08163212
Totals3286683.8061886.252284826.1369.5

CountyNUECES
HighwayFM 70
From1.464 MI E. OF FM 892
To3.496 MI W. OF FM 892
CSJ1558-03-035
Proj IDSTP 1502(442)HES
Work TypeGRADE,BASE,SURF
 
4.9602830324.402517798.8088.9
Work Order00-00-00
Work Began02-01-16
Work Completed
Time Computed09-24-15
Contract Working Days139
Addl Days Granted25
Working Days Charged143
Percent Time Used87
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1558-03-035
HIGHWAY BARRICADES AND SERVICES, LLC (2.76)
MURRAY CONSTRUCTION (0.69)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (5.30)
WEST TEXAS RUMBLE STRIP (0.17)
EPIC ENERGY SERVICES LLC (1.56)
Contract #07153230
Totals2830324.401900.002517798.8088.9

CountyNUECES
HighwaySH 361
FromAT THE PORT ARANSAS FERRY LANDING
To.
CSJ2263-02-096
Proj IDSTP 2017(157)
Work TypeCONSTRUCT NEW 28 CAR FERRY BOAT
 
0.1008195000.002663375.0032.5
CountyNUECES
HighwaySH 361
FromAT THE PORT ARANSAS FERRY LANDING
To.
CSJ2263-02-097
Proj IDFT 2263-2-97
Work TypeCONSTRUCT NEW 28 CAR FERRY BOAT
 
0.1008195000.002327380.0028.4
Work Order11-21-16
Work Began12-29-16
Work Completed
Time Computed12-01-16
Contract Working Days396
Addl Days Granted0
Working Days Charged141
Percent Time Used35
Contractor(s)
SOUTHWEST SHIPYARD, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2263-02-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163203
Totals16390000.00803110.004990755.0030.4

CountyNUECES
HighwaySH 361
From0.21 MILES S. OF ACCESS ROAD 1
To1.06 MILES S. OF ACCESS ROAD 2
CSJ2263-03-039
Proj IDSTP 2016(413)
Work TypeGRADE,BASE,SURF,STRS
 
8.3206542666.536297477.3897.0
Work Order03-07-16
Work Began05-10-16
Work Completed
Time Computed02-01-16
Contract Working Days181
Addl Days Granted0
Working Days Charged225
Percent Time Used124
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2263-03-039
HIGHWAY BARRICADES AND SERVICES, LLC (2.45)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.18)
MURRAY CONSTRUCTION (0.52)
HUDSON, INC. (1.08)
WEST TEXAS RUMBLE STRIP (0.40)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.34)
EPIC ENERGY SERVICES LLC (1.10)
Contract #12153210
Totals6542666.53931813.186297477.3897.0

CountyNUECES
HighwaySH 361
FromAT THE PORT ARANSAS FERRY LANDING
To.
CSJ2263-03-040
Proj IDFBD 2263-3-40
Work TypeCONSTRUCT NEW 28 CAR FERRY BOAT
 
0.1008989000.008920408.0099.7
Work Order10-20-15
Work Began10-27-15
Work Completed
Time Computed11-20-15
Contract Working Days385
Addl Days Granted60
Working Days Charged482
Percent Time Used108
Contractor(s)
SOUTHWEST SHIPYARD, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2263-03-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08153211
Totals8989000.00388755.008920408.0099.7

CountyNUECES
HighwaySH 361
FromBEACH ACCESS RD 1A
ToBEACH ACCESS 1
CSJ2263-03-041
Proj IDC 2263-3-41
Work TypeGRADE,BASE,SURF,STRS,STORM SEWER
 
0.8105552811.601179088.5321.2
Work Order04-25-16
Work Began12-19-16
Work Completed
Time Computed05-02-16
Contract Working Days183
Addl Days Granted0
Working Days Charged92
Percent Time Used50
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2263-03-041
EPIC ENERGY SERVICES LLC (11.44)
CABCOS CONTRACTORS LLC (5.06)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.27)
HIGHWAY BARRICADES AND SERVICES, LLC (1.95)
FUQUAY, INC. (0.32)
KL DURHAM CONSTRUCTION, LLC (0.58)
Contract #03163212
Totals5552811.60414916.101179088.5321.2

CountyNUECES
HighwayFM 2444
FromSH 286
ToOSO PARKWAY INTERSECTION
CSJ2343-01-036
Proj IDSTP 2013(936)MM
Work TypeGRADE, BASE, SURF,STRTS
 
4.05124447530.9714830779.5160.6
Work Order11-13-13
Work Began05-31-16
Work Completed
Time Computed05-12-14
Contract Working Days510
Addl Days Granted21
Working Days Charged254
Percent Time Used51
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2343-01-036
AARON CONCRETE CONTRACTORS, L.P. (0.33)
MURRAY CONSTRUCTION (0.19)
SOIL-TECH, INC. (0.10)
PRIMATE CONSTRUCTION, INC. (0.08)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.57)
STAR OPERATIONS, INC. (1.63)
HIGHWAY BARRICADES AND SERVICES, LLC (1.10)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.95)
PENNTEX MILLING, LLC (0.30)
WOODSTOCK TREE SURGEONS (0.06)
SHINN & GREGORY, INC. (1.91)
GALBRAITH CONTRACTING, INC. (0.01)
ROADWAY SPECIALTIES, INC. (0.56)
K.L. DURHAM CONSTRUCTION, LLC (0.33)
ADVANCED PUMPING, LLC (0.25)
D & C CONCRETE CUTTING, INC. (0.01)
ACME READY MIX LTD., LLP (0.38)
DELTA PRIME SPECIALTY SERVICES, INC. (0.02)
Contract #08133005
Totals24447530.97584791.6014830779.5160.6

CountyARANSAS
HighwaySH 188
FromFM 1069
ToBS 35-L
CSJ2607-01-011
Proj IDSTP 2016(962)
Work TypeSEAL AND OVERLAY
 
2.4841142011.551199362.3899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-11-16
Work Began03-01-17
Work Completed
Time Computed06-01-16
Contract Working Days51
Addl Days Granted5
Working Days Charged65
Percent Time Used116
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2607-01-011
HIGHWAY BARRICADES AND SERVICES, LLC (3.89)
K.L. DURHAM CONSTRUCTION, LLC (1.09)
SOIL-TECH, INC. (0.22)
TERRY L. ELLIS BACKHOE (1.05)
Contract #04163205
Totals1142011.550.001199362.3899.9

page 1 | page 2 | page 3