Monthly State Let Construction Report For Corpus Christi District As Of Nov 9, 2016 Page 3 Of 4

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyREFUGIO
Highway FM 774
From AT MELON CREEK STR 33 ON FM 774
To APPROX 3.45 MI E OF US 77
CSJ 0447-05-061
Proj ID BR 1502(037)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.135 2333640.42 58547.95 968192.04 41.4
CountyREFUGIO
Highway FM 774
From AT ALAMEDA CREEK ON FM 774
To APPOX. 8.8 MI E. OF US 77
CSJ 0447-05-067
Proj ID BR 1502(037)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.021 1890284.15 94824.28 817852.98 43.2
Work Order 08-26-15
Work Began 02-17-16
Work Completed  
Time Computed 09-26-15
Contract Working Days 195
Addl Days Granted 15
Working Days Charged 71
Percent Time Used 33
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0447-05-061
STAR OPERATIONS, INC (SAN ANTONIO) (3.40%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.46%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.04%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.35%)
JMHP, INC. (3.01%)
MESA ROD BUSTERS, INC. (0.39%)
D & C CONCRETE CUTTING, INC. (0.17%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.21%)
CABCOS CONTRACTORS LLC (0.12%)
MCL CONTRACTING, LLC (0.48%)
Contract # 06153248
Totals 4223924.57 153372.23 1786045.02 42.2

CountySAN PATRICIO
Highway FM 631
From US 77
To FM 2512
CSJ 0507-02-053
Proj ID STP 1502(150)HES
Work Type GRADE, BASE, SURF
 
8.950 1714386.35 0.00 1917431.40 99.9
CountySAN PATRICIO
Highway FM 1944
From FM 1074
To FM 631
CSJ 1208-03-021
Proj ID STP 1502(151)HES
Work Type GRADE, BASE, SURF
 
3.822 1418998.35 0.00 1407197.84 99.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-07-15
Work Began 09-01-15
Work Completed  
Time Computed 08-07-15
Contract Working Days 119
Addl Days Granted 11
Working Days Charged 129
Percent Time Used 99
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0507-02-053
HIGHWAY BARRICADES AND SERVICES, LLC (3.46%)
SOIL-TECH, INC.(0.28%)
TERRY L. ELLIS BACKHOE (0.00%)
Contract # 05153242
Totals 3133384.70 0.00 3324629.24 99.9

CountyARANSAS
Highway FM 1069 ETC
From FM 1781
To 0.2 MI N OF SH 188
CSJ 0507-04-041
Proj ID STP 1602(253)HESG
Work Type TEXTURIZE SHLDRS, CENTERLINE TEXTUR
 
60.305 340987.21 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-11-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0507-04-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163006
Totals 340987.21 0.00 0.00 0.0

CountyKARNES
Highway SH 239
From SH 72
To 1000 FT S. OF CR 129
CSJ 0516-01-015
Proj ID STP 1402(066)
Work Type GRADE, BASE, SURF, STRS
 
6.067 8525937.55 111694.91 10232354.72 99.9
Work Order 09-12-14
Work Began 10-13-14
Work Completed  
Time Computed 09-28-14
Contract Working Days 185
Addl Days Granted 82
Working Days Charged 290
Percent Time Used 108
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0516-01-015
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.32%)
FLASHER EQUIPMENT COMPANY(1.60%)
LONE STAR EROSION CONTROL(1.12%)
MURRAY CONSTRUCTION(0.56%)
RELMCO, INC. (4.71%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.34%)
F. N. PLOCH CONSTRUCTION COMPANY, INC. ( 18.07%)
TRINITY EAGLEFORD SERVICES LLC (1.17%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.36%)
Contract # 08143226
Totals 8525937.55 111694.91 10232354.72 99.9

CountyKARNES
Highway SH 239
From CR 129 S OF CHOATE
To GOLIAD COUNTY LINE
CSJ 0516-01-016
Proj ID STP 2016(412)
Work Type GRADE, BASE, SURF
 
3.440 6288757.06 240529.02 1198796.71 19.0
CountyGOLIAD
Highway SH 239
From KARNES COUNTY LINE
To W OF FM 2442
CSJ 0516-02-027
Proj ID STP 2016(412)
Work Type GRADE, BASE, SURF
 
4.760 3313834.41 665973.79 1152322.39 34.7
Work Order 01-29-16
Work Began 04-12-16
Work Completed  
Time Computed 02-01-16
Contract Working Days 200
Addl Days Granted 19
Working Days Charged 141
Percent Time Used 64
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0516-01-016
FLASHER EQUIPMENT COMPANY(1.02%)
MV HENKE COMPANY, LLC(0.53%)
MPB, INC.(0.08%)
MURRAY CONSTRUCTION(0.23%)
RELMCO, INC. ( 14.77%)
ROADWAY SPECIALTIES, INC.(1.43%)
TRP CONSTRUCTION GROUP, LLC(0.14%)
Contract # 12153232
Totals 9602591.47 906502.81 2351119.10 24.4

CountyGOLIAD
Highway SH 239
From BAKER RD.
To US 59
CSJ 0516-02-025
Proj ID STP 1502(579)
Work Type GRADE, BASE, SURF
 
3.414 5936471.37 0.00 5722697.85 96.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-13-15
Work Began 01-29-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 144
Percent Time Used 106
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0516-02-025
ALL MATERIALS CONSTRUCTION, LLC(0.87%)
FLASHER EQUIPMENT COMPANY(0.36%)
THE LEVY COMPANY, L.P. (0.30%)
LONE STAR EROSION CONTROL(0.70%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.89%)
EGGEMEYER LAND CLEARING, LLC (0.84%)
PECOS FENCE, INC.(0.20%)
Contract # 08153222
Totals 5936471.37 0.00 5722697.85 96.5

CountyNUECES
Highway SH 358
From .2 MI W OF FM 43
To .2 MI E OF FM 43
CSJ 0617-01-185
Proj ID STP 2014(982)HES
Work Type IMPORVE TRAFFIC SIGNAL
 
0.400 281111.29 -348.38 179135.76 93.0
CountyNUECES
Highway SH 358
From .2 MI W OF EVERHART
To .2 MI E OF EVERHART
CSJ 0617-01-186
Proj ID STP 2014(990)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.400 280827.44 0.00 391492.93 99.9
CountyNUECES
Highway SH 358
From .4 MI W OF SS3
To .4 MI E OF SS3
CSJ 0617-01-187
Proj ID STP 2014(991)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.600 373871.92 7214.59 370860.29 99.1
Work Order 07-24-14
Work Began 07-29-15
Work Completed  
Time Computed 07-01-15
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 254
Percent Time Used 213
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0617-01-185
HIGHWAY BARRICADES AND SERVICES, LLC (2.37%)
SHERON STONE DBA DOUBLE-S CONSTRUCTION ( 14.73%)
COLLIER SERVICES, INC. (5.66%)
Contract # 06143057
Totals 935810.65 6866.21 941488.98 99.9

CountyNUECES
Highway SH 358
From AIRLINE RD
To SH358/PR22 INTERSECTION
CSJ 0617-01-190
Proj ID NH 2016(807)
Work Type NOVACHIP
 
5.110 3222777.09 0.00 2030.00 0.0
CountyNUECES
Highway PR 22
From SH 358/PR22 INTERSECTION
To .2 MI E OF LAGUNA SHORES RD
CSJ 0617-02-065
Proj ID NH 2016(807)
Work Type NOVACHIP
 
1.114 863272.78 0.00 21750.00 2.5
Work Order 05-10-16
Work Began 00-00-00
Work Completed  
Time Computed 06-09-16
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 35
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0617-01-190
SAN ANTONIO CONCEPTS CONSTRUCTION, LLLC(0.39%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.75%)
INTERSTATE BARRICADES & MARKINGS, INC. (4.98%)
SOIL-TECH, INC.(0.31%)
TAHOE TRUCKING, INC. (0.29%)
Contract # 03163026
Totals 4086049.87 0.00 23780.00 0.5

CountyBEE
Highway FM 2441
From SH 202
To REFUGIO COUNTY LINE
CSJ 0738-05-013
Proj ID STP 1502(500)HES
Work Type GRADE, BASE, SURF
 
3.523 1450103.70 64983.00 301768.53 20.8
CountyREFUGIO
Highway FM 2441
From BEE COUNTY LINE
To US 77
CSJ 0738-06-013
Proj ID STP 1502(437)HES
Work Type GRADE, BASE, SURF
 
9.753 2853723.95 472471.39 2003890.61 70.2
Work Order 03-02-16
Work Began 06-15-16
Work Completed  
Time Computed 03-01-16
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 49
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0738-05-013
ROADSAFE TRAFFIC SYSTEMS, INC. (1.88%)
TROUT TRUCKING_COMPANY INC.( 13.06%)
MURRAY CONSTRUCTION(1.09%)
TERRY L. ELLIS BACKHOE (1.17%)
A BROTHERS MILLING, LLC(1.32%)
Contract # 01163241
Totals 4303827.65 537454.39 2305659.14 53.5

CountyNUECES
Highway VA
From AT VARIOUS LOCATIONS IN CC DISTRICT
To .
CSJ 0916-00-079
Proj ID STP 1502(438)
Work Type CONSTRUCT CURB RAMPS
 
0.100 1792916.93 0.00 1770983.23 98.7
Work Order 11-16-15
Work Began 02-01-16
Work Completed  
Time Computed 11-02-15
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 115
Percent Time Used 95
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-079
GARRETT CONSTRUCTION CO. (1.55%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.19%)
W.A. ROBBINS CONSTRUCTION CO., INC.(7.41%)
Contract # 09153034
Totals 1792916.93 0.00 1770983.23 98.7

CountyNUECES
Highway VA
From AT VARIOUS LOCATION IN CC DISTRICT
To .
CSJ 0916-00-081
Proj ID STP 1602(194)
Work Type PAVEMENT MARKINGS AND MARKERS
 
0.100 879465.40 363045.54 639729.47 72.7
Work Order 07-28-16
Work Began 09-12-16
Work Completed  
Time Computed 08-27-16
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 55
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163222
Totals 879465.40 363045.54 639729.47 72.7

CountyNUECES
Highway VA
From AT VARIOUS LOCATION IN CC DISTRICT
To .
CSJ 0916-00-082
Proj ID STP 2016(809)
Work Type SMALL SIGN REPLACEMENT
 
0.100 839680.00 0.00 445554.34 53.0
Work Order 04-21-16
Work Began 00-00-00
Work Completed  
Time Computed 05-02-16
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY BARRICADES AND SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-082
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163020
Totals 839680.00 0.00 445554.34 53.0

CountyNUECES
Highway CR
From STR2 (AA0133002) CR42@DRAIN DITCH
To 1.2 MI W OF FM 1889
CSJ 0916-35-177
Proj ID BR 1502(038)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.036 299375.00 121275.39 310943.39 99.9
Work Order 03-15-16
Work Began 04-25-16
Work Completed  
Time Computed 04-01-16
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 114
Contractor(s)
BXB GROUP INCORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0916-35-177
HIGHWAY BARRICADES AND SERVICES, LLC (3.34%)
LONE STAR EROSION CONTROL(2.74%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.29%)
GARRETT CONSTRUCTION CO. (2.63%)
Contract # 02163027
Totals 299375.00 121275.39 310943.39 99.9

CountyJIM WELLS
Highway FM 624
From SH 359
To US 281
CSJ 0989-01-037
Proj ID STP 1602(264)HES
Work Type PROVIDE ADDIT. PAVED SURFACE WIDTH
 
10.891 4558633.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0989-01-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11163016
Totals 4558633.80 0.00 0.00 0.0

CountyJIM WELLS
Highway FM 70
From SH 359
To FM 624
CSJ 1088-01-022
Proj ID STP 2014(627)HES
Work Type PROVIDE ADDIT. PAVED SURFACE WIDTH
 
9.017 2191916.68 78986.34 2111731.04 96.6
CountyJIM WELLS
Highway FM 70
From FM 624
To FM 1833
CSJ 1088-01-023
Proj ID STP 2014(626)
Work Type CEMENT TRT BASE, SPOT BASE REP & SEAL
 
1.870 1253056.05 37373.81 1264602.57 99.9
CountyJIM WELLS
Highway FM 70
From AT SANDY HOLLOW CR. STR.3
To APPROX. 2.4 MI. NE OF FM 624
CSJ 1088-01-024
Proj ID STP 2014(626)
Work Type REPLACE BRIDGE
 
0.067 632869.57 0.00 587109.44 92.7
CountyNUECES
Highway FM 70
From 2.93 MI N. OF SH 44
To 4.13 MI N. OF SH 44
CSJ 1558-01-021
Proj ID STP 1502(074)HES
Work Type GRADE, BASE, SURF
 
1.230 686680.52 0.00 640346.05 93.2
Work Order 10-30-15
Work Began 11-30-15
Work Completed  
Time Computed 11-30-15
Contract Working Days 170
Addl Days Granted 22
Working Days Charged 198
Percent Time Used 103
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1088-01-022
ENVIRONMENTAL SAFETY SERVICES, INC.(0.88%)
HIGHWAY BARRICADES AND SERVICES, LLC (4.07%)
WEBER-BALKE FOUNDATION COMPANY, INC(1.08%)
D & S TEXAS ICON CONSTRUCTION, LLC.(0.93%)
MV HENKE COMPANY, LLC(3.46%)
Contract # 07153044
Totals 4764522.82 116360.15 4603789.10 96.7

CountyBEE
Highway FM 798
From US 181
To FM 2985
CSJ 1117-01-015
Proj ID STP 2016(811)
Work Type WIDEN ROADWAY
 
6.498 4270569.94 851712.70 1863269.97 43.6
Work Order 05-10-16
Work Began 06-13-16
Work Completed  
Time Computed 05-01-16
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 86
Percent Time Used 39
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1117-01-015
BEAVER CONTRACTORS, LLC(8.64%)
EGGEMEYER LAND CLEARING, LLC (3.66%)
MPB, INC.(0.19%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.18%)
ROADWAY SPECIALTIES, INC.(6.22%)
Contract # 03163006
Totals 4270569.94 851712.70 1863269.97 43.6

CountyNUECES
Highway FM 43
From W. OF CR 49
To SH 286
CSJ 1557-01-041
Proj ID STP 1602(484)
Work Type GRADE, BASE, SURF
 
2.030 3286683.80 0.00 0.00 0.0
Work Order 09-20-16
Work Began 00-00-00
Work Completed  
Time Computed 10-20-16
Contract Working Days 131
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1557-01-041
TROUT TRUCKING_COMPANY INC.(6.82%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.71%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.84%)
PERFORMANCE EQUIPMENT SERVICE(0.59%)
HIGHWAY BARRICADES AND SERVICES, LLC (3.32%)
Contract # 08163212
Totals 3286683.80 0.00 0.00 0.0

CountyNUECES
Highway FM 70
From 1.464 MI E. OF FM 892
To 3.496 MI W. OF FM 892
CSJ 1558-03-035
Proj ID STP 1502(442)HES
Work Type GRADE, BASE, SURF
 
4.960 2830324.40 38263.89 2499898.35 88.3
Work Order 00-00-00
Work Began 02-01-16
Work Completed  
Time Computed 09-24-15
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 139
Percent Time Used 100
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1558-03-035
HIGHWAY BARRICADES AND SERVICES, LLC (2.76%)
MURRAY CONSTRUCTION(0.69%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(5.30%)
WEST TEXAS RUMBLE STRIP(0.17%)
Contract # 07153230
Totals 2830324.40 38263.89 2499898.35 88.3

CountyJIM WELLS
Highway FM 1931
From SH 44
To FM 665
CSJ 1693-01-020
Proj ID STP 1602(141)
Work Type GRADE, BASE, SURF, STRS
 
2.150 3432309.48 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-14-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 99
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1693-01-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163232
Totals 3432309.48 0.00 0.00 0.0

CountyLIVE OAK
Highway FM 534
From 5.51 MILES W OF FM 3024
To FM 3162
CSJ 1808-01-028
Proj ID STP 1502(152)HES
Work Type GRADE, BASE, SURF
 
6.550 2602993.61 0.00 2511568.25 96.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-16-15
Work Began 08-17-15
Work Completed  
Time Computed 08-16-15
Contract Working Days 129
Addl Days Granted 2
Working Days Charged 126
Percent Time Used 96
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1808-01-028
EGGEMEYER LAND CLEARING, LLC ( 10.00%)
HIGHWAY BARRICADES AND SERVICES, LLC (6.21%)
SOIL-TECH, INC.(0.33%)
MURRAY CONSTRUCTION(0.81%)
ALTUS TRAFFIC MANAGEMENT LLC (0.41%)
Contract # 05153036
Totals 2602993.61 0.00 2511568.25 96.4

page 1 | page 2 | page 3 | page 4