Monthly State Let Construction Report For Corpus Christi District As Of Jul 13, 2015 Page 2 Of 4

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyNUECES
Highway SH 44
From AT FM 1694/SH 44 INTERSECTION
To .
CSJ 0102-02-099
Proj ID NH 2013(656)
Work Type GRADE, BASE, SURF, STRS
 
0.756 12713097.88 11194.78 13137404.93 99.9
Work Order 07-31-13
Work Began 09-25-13
Work Completed  
Time Computed 08-16-13
Contract Working Days 302
Addl Days Granted 0
Working Days Charged 295
Percent Time Used 97
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0102-02-099
PRIMATE CONSTRUCTION, INC. (0.05%)
WEBBER BARRIER SERVICES, LLC.(1.04%)
D&S TEXAS ICON CONSTRUCTION, LLC (0.51%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.72%)
D & C CONCRETE CUTTING, INC. (0.32%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.93%)
BEAVER CONTRACTORS, LLC(5.68%)
SCOTT DERR PAINTING CO, LLC(0.34%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.50%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(1.72%)
BEDO CONSTRUCTION PRODUCTS, INC. (4.21%)
CP REBAR AND PT INSTALLATION (0.14%)
CABCOS CONTRACTORS LLC (2.46%)
CERTIFIED PLACERS LLC(0.15%)
TEX OP CONSTRUCTION, LP(0.63%)
ADVANCED PUMPING, LLC(0.03%)
Contract # 05133203
Totals 12713097.88 11194.78 13137404.93 99.9

CountyKLEBERG
Highway US 77
From S. OF SH 141
To N. OF FM 425
CSJ 0102-04-095
Proj ID NH 2012(313)
Work Type GRAD, BASE.SURF.STRS
 
0.798 14562421.93 0.00 14859709.78 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-12
Work Began 10-24-12
Work Completed 01-05-15
Time Computed 07-02-12
Contract Working Days 352
Addl Days Granted 47
Working Days Charged 399
Percent Time Used 100
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0102-04-095
HIGHWAY TECHNOLOGIES, INC. (0.31%)
WEST TEXAS RUMBLE STRIP(0.03%)
WEBBER BARRIER SERVICES, INC.(1.36%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(0.63%)
SOIL-TECH, INC.(0.85%)
MURRAY CONSTRUCTION(0.36%)
FLASHER EQUIPMENT COMPANY(0.73%)
DUSTROL, INC.(0.45%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.03%)
KELLYSTONE, INC(0.48%)
SCOTT DERR PAINTING CO, LLC(0.48%)
W. W. FOUNDATION DRILLING, LTD.(0.50%)
TRIPLE J CONSTRUCTION, LTD (1.92%)
STAR OPERATIONS, INC.(1.59%)
TAHOE TRUCKING, INC. (5.69%)
D & C CONCRETE CUTTING, INC. (0.01%)
LHOIST NORTH AMERICA (1.39%)
CABCOS CONTRACTORS LLC (0.72%)
Contract # 04123001
Totals 14562421.93 0.00 14859709.78 100.0

CountyKLEBERG
Highway SH 285
From US 77
To BROOKS COUNTY LINE
CSJ 0102-06-030
Proj ID STP 2015(495)
Work Type MILL, FILL MAINLANES, SC FULL WIDTH
 
12.100 11207164.46 596970.54 1220095.22 10.8
CountyKLEBERG
Highway SH 285
From 4.9 MI E OF FM 2191
To 0.3 MI W OF US 77
CSJ 0102-06-031
Proj ID STP 2015(638)HES
Work Type TEXTURIZE SHLDRS, CENTERLINE TEXTUR
 
11.800 79213.98 0.00 0.00 0.0
Work Order 03-18-15
Work Began 04-28-15
Work Completed  
Time Computed 04-03-15
Contract Working Days 162
Addl Days Granted 2
Working Days Charged 43
Percent Time Used 26
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0102-06-030
HIGHWAY BARRICADES AND SERVICES, LLC (2.31%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.89%)
DUSTROL, INC.(3.53%)
ALTUS TRAFFIC MANAGEMENT LLC (0.21%)
Contract # 01153216
Totals 11286378.44 596970.54 1220095.22 10.8

CountyARANSAS
Highway SH 35
From 549 FT. S OF PR13
To 1 MI. N. OF PR13
CSJ 0180-03-035
Proj ID STP 1102(113)
Work Type GR, BS, SURF
 
1.000 5196117.40 14483.84 8664559.09 99.9
CountyARANSAS
Highway SH 35
From N OF COPANO BAY CAUSEWAY
To S OF COPANO BAY CAUSEWAY
CSJ 0180-04-083
Proj ID BR 1102(114)
Work Type REPLACE EXISTING BRIDGE & REWK APRO
 
2.087 92966472.65 200996.53 79633897.29 85.6
Work Order 06-15-11
Work Began 08-03-11
Work Completed  
Time Computed 11-14-11
Contract Working Days 968
Addl Days Granted 455
Working Days Charged 1,044
Percent Time Used 73
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0180-03-035
HAAS - ANDERSON CONSTRUCTION, INC. (0.27%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.21%)
SCOTT DERR PAINTING CO (0.28%)
STAR OPERATIONS, INC.(0.45%)
A.Z. REBAR CONSTRUCTION, INC.(5.74%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09%)
ROADWAY SPECIALTIES, INC.(0.16%)
LAND SOLUTIONS CONSTRUCTION, LLC (0.15%)
ROADWAY CONSTRUCTION, INC. (0.77%)
ARROW DIRECTIONAL DRILLING, INC. (0.00%)
Contract # 05113234
Totals 98162590.05 215480.37 88298456.38 89.9

CountySAN PATRICIO
Highway SH 35
From US 181
To SH 361
CSJ 0180-06-094
Proj ID NH 2013(752)
Work Type RAMP REVERSAL
 
1.368 2981488.08 22512.81 1547581.64 52.4
Work Order 05-29-14
Work Began 07-07-14
Work Completed  
Time Computed 06-14-14
Contract Working Days 182
Addl Days Granted 0
Working Days Charged 203
Percent Time Used 111
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0180-06-094
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.28%)
FARR FOUNDATION, INC.(1.48%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.43%)
STAR OPERATIONS, INC.(6.81%)
ADVANCED PIPELINE SERVICES, INC. (0.04%)
Contract # 04143233
Totals 2981488.08 22512.81 1547581.64 52.4

CountyLIVE OAK
Highway US 281
From TULLOS ST. (IN THREE RIVERS)
To MILLIAM ST. (IN GEORGE WEST)
CSJ 0254-01-132
Proj ID NH 2014(223)
Work Type OVERLAY ROADWAY
 
9.476 4926163.23 98772.74 7752563.78 99.9
Work Order 01-06-14
Work Began 08-11-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 102
Addl Days Granted 54
Working Days Charged 156
Percent Time Used 100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0254-01-132
COWBELL TRAFFIC SERVICES, INC. (0.38%)
D&S TEXAS ICON CONSTRUCTION, LLC (0.31%)
D. I. J. CONSTRUCTION, INC.(2.81%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.18%)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.29%)
PRIMATE CONSTRUCTION, INC. (1.87%)
BRANNAN PAVING CO., LTD. (6.00%)
Contract # 11133012
Totals 4926163.23 98772.74 7752563.78 99.9

CountyLIVE OAK
Highway US 281
From IH 37, SOUTH
To SH 72 IN THREE RIVERS
CSJ 0254-01-137
Proj ID NH 2015(527)
Work Type SPOT BASE REPAIR AND OVERLAY
 
3.180 4390803.88 281873.55 1294919.75 29.4
Work Order 02-18-15
Work Began 04-06-15
Work Completed  
Time Computed 03-06-15
Contract Working Days 61
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 96
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0254-01-137
FLASHER EQUIPMENT COMPANY(1.25%)
FUQUAY, INC. (0.21%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.58%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.24%)
CHEROKEE SERVICES(0.21%)
Contract # 01153016
Totals 4390803.88 281873.55 1294919.75 29.4

CountyJIM WELLS
Highway US 281
From ON US 281 AT FM1554 INTERS.
To .
CSJ 0254-07-003
Proj ID STP 2012(234)SB
Work Type GRADE, BASE, SURF, STRS
 
1.000 16496831.87 0.00 16290181.79 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-13-12
Work Began 09-18-12
Work Completed 02-25-15
Time Computed 09-29-12
Contract Working Days 353
Addl Days Granted 32
Working Days Charged 385
Percent Time Used 100
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0254-07-003
TAHOE TRUCKING, INC. (2.79%)
CUATRO T CONSTRUCTION, INC.(5.54%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.47%)
MURRAY CONSTRUCTION(0.03%)
CHEROKEE SERVICES(0.15%)
WEST TEXAS RUMBLE STRIP(0.02%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.18%)
STAR OPERATIONS, INC.(1.45%)
NORTH TEXAS REBAR, LLC (0.06%)
KL DURHAM CONSTRUCTION, LLC(0.19%)
HOUSTON SAWING & DRILLING(0.08%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.80%)
SCOTT DERR PAINTING CO, LLC(0.10%)
WEBBER BARRIER SERVICES, INC.(0.68%)
J CARROLL WEAVER, INC. (0.03%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.13%)
LHOIST NORTH AMERICA (2.05%)
ADVANCED PUMPING, LLC(0.04%)
VIDEO PLUMBING INC.(0.04%)
Contract # 07123004
Totals 16496831.87 0.00 16290181.79 100.0

CountyKARNES
Highway SH 72
From FM 792
To 1 MILE NE OF SH 239
CSJ 0270-03-072
Proj ID STP 2014(992)
Work Type GRADE, BASE, SURF
 
2.820 4624732.66 66728.39 3755000.80 81.1
Work Order 09-22-14
Work Began 10-31-14
Work Completed  
Time Computed 10-08-14
Contract Working Days 136
Addl Days Granted 30
Working Days Charged 127
Percent Time Used 76
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0270-03-072
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.60%)
FLASHER EQUIPMENT COMPANY(2.20%)
FUQUAY, INC. (0.86%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.42%)
THE LEVY COMPANY, L.P. (0.60%)
MPB, INC.(0.17%)
Contract # 07143243
Totals 4624732.66 66728.39 3755000.80 81.1

CountyKARNES
Highway SH 72
From BEE COUNTY LINE
To US 181
CSJ 0270-07-029
Proj ID STP 2013(753)
Work Type GRADE, BASE, SURF, STRS
 
11.450 16740118.91 137474.66 16750167.76 99.9
Work Order 10-22-13
Work Began 11-07-13
Work Completed  
Time Computed 11-07-13
Contract Working Days 228
Addl Days Granted 0
Working Days Charged 240
Percent Time Used 105
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0270-07-029
COWBELL TRAFFIC SERVICES, INC. (0.21%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.34%)
INTERSTATE CONCRETE & STEEL SERVICES INCORPORATED(6.29%)
MURRAY CONSTRUCTION(0.55%)
ROADWAY SPECIALTIES, INC.(2.68%)
VEGETATION MANAGEMENT SERVICES (0.37%)
THE LEVY COMPANY, L.P. (1.19%)
Contract # 08133207
Totals 16740118.91 137474.66 16750167.76 99.9

CountyLIVE OAK
Highway SH 72
From IH 37
To BEE COUNTY LINE
CSJ 0270-09-027
Proj ID STP 2013(750)
Work Type GRADE, BASE, SURF, SRTS
 
9.139 16894487.98 160002.42 17606831.36 100.0
Work Order 01-06-14
Work Began 01-22-14
Work Completed 05-13-15
Time Computed 01-22-14
Contract Working Days 221
Addl Days Granted 0
Working Days Charged 364
Percent Time Used 164
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0270-09-027
RELMCO, INC. (3.05%)
ROADWAY SPECIALTIES, INC.(1.49%)
FLASHER EQUIPMENT COMPANY(0.17%)
D. I. J. CONSTRUCTION, INC.(1.39%)
MURRAY CONSTRUCTION(0.24%)
CLAUDIA SERNA DBA SERNA"S TRUCKING (1.25%)
M.V. HENKE ENTERPRISES, INC. (0.85%)
WEST TEXAS RUMBLE STRIP(0.07%)
Contract # 09133005
Totals 16894487.98 160002.42 17606831.36 100.0

CountyNUECES
Highway SH 286
From SH 357
To 1 MI S OF FM 43
CSJ 0326-01-052
Proj ID NH 2013(795)
Work Type GRADE, BASE, SURF, STRS
 
2.755 45818725.52 515595.69 18452465.01 40.2
Work Order 09-05-13
Work Began 03-05-14
Work Completed  
Time Computed 08-01-13
Contract Working Days 687
Addl Days Granted 16
Working Days Charged 236
Percent Time Used 33
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0326-01-052
LARGE & SONS_FOUNDATION DRILLING,INC.(0.20%)
MURRAY CONSTRUCTION(0.20%)
SOIL-TECH, INC.(0.35%)
MASTERPIECE GRINDING & GROOVING, LLC (0.07%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(1.72%)
TEXAS BOMANITE (0.21%)
TERRY L. ELLIS BACKHOE (0.05%)
TROUT TRUCKING_COMPANY INC.(2.72%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.70%)
JHABORES CONSTRUCTION CO, INC. (2.92%)
CROSSROADS MILLING, LLC(0.24%)
CABCOS CONTRACTORS LLC (5.62%)
AARON CONCRETE CONTRACTORS, L.P. (1.86%)
STAR OPERATIONS, INC.(2.06%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.65%)
MCL CONTRACTING, LLC (0.49%)
HAYWARD BAKER, INC.(0.15%)
PERFORMANCE EQUIPMENT SERVICE(0.30%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09%)
Contract # 06133001
Totals 45818725.52 515595.69 18452465.01 40.2

CountyNUECES
Highway SH 286
From SH 358 INTERCHANGE SOUTH
To HOLLY RD (N ABUTMENT)
CSJ 0326-01-058
Proj ID NH 2014(566)
Work Type ULTRA THIN BONDED WEARING COURSE
 
0.703 790155.68 0.00 1057508.22 100.0
CountyNUECES
Highway SH 286
From GOLIHAR RD
To SH 358 INTERCHANGE
CSJ 0326-03-094
Proj ID NH 2014(566)
Work Type ULTRA THIN BONDED WEARING COURSE
 
0.707 780952.40 0.00 769356.38 100.0
CountyNUECES
Highway SH 358
From 700 FT W. OF KOSTORYZ
To W OF GREENWOOD
CSJ 0617-01-188
Proj ID NH 2014(566)
Work Type ULTRA THIN BONDED WEARING COURSE
 
1.868 2897209.00 0.00 2973692.68 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-14
Work Began 05-29-14
Work Completed 11-21-14
Time Computed 05-29-14
Contract Working Days 68
Addl Days Granted 10
Working Days Charged 96
Percent Time Used 123
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0326-01-058
FUQUAY, INC. (0.40%)
MPB, INC.(1.34%)
WEST TEXAS RUMBLE STRIP(0.08%)
HIGHWAY BARRICADES AND SERVICES, LLC (5.12%)
GORDILLO TRUCKING, INC,(0.78%)
Contract # 04143216
Totals 4468317.08 0.00 4800557.28 100.0

CountyKARNES
Highway FM 99
From US 181
To ATASCOSA COUNTY LINE
CSJ 0348-06-023
Proj ID STP 1502(061)
Work Type PAVEMENT REPAIR AND RESURFACE
 
13.676 8219037.30 0.00 0.00 0.0
Work Order 05-21-15
Work Began 00-00-00
Work Completed  
Time Computed 06-21-15
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0348-06-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153052
Totals 8219037.30 0.00 0.00 0.0

CountyREFUGIO
Highway SH 239
From SH 35
To FM 774
CSJ 0350-01-017
Proj ID STP 1502(241)HES
Work Type GARDE, BASE, SURF
 
4.318 1996043.76 0.00 0.00 0.0
CountyREFUGIO
Highway FM 2040
From FM 774
To ARANSAS COUNTY LINE
CSJ 0350-03-015
Proj ID STP 1502(242)HES
Work Type GRADE, BASE, SURF
 
5.535 2626977.96 0.00 0.00 0.0
CountyARANSAS
Highway FM 2040
From REFUGIO COUNTY LINE
To 0.842 MI S OF ARANSAS C/L
CSJ 0350-04-011
Proj ID STP 1502(243)HES
Work Type GRADE, BASE, SURF
 
0.847 424378.21 0.00 0.00 0.0
CountyREFUGIO
Highway FM 774
From 7 MI W. OF SH 35
To 5 MI W. OF SH 35
CSJ 0447-05-068
Proj ID STP 1502(244)HES
Work Type GRADE, BASE, SURF
 
2.000 1064191.27 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 176
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0350-01-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153056
Totals 6111591.20 0.00 0.00 0.0

CountyKARNES
Highway SH 123
From WILSON COUNTY LINE
To SH 80
CSJ 0366-06-039
Proj ID STP 2015(033)
Work Type GRADING, BASE, SURFACE, STRUCTURES
 
12.595 4771137.53 0.00 0.00 0.0
Work Order 11-14-14
Work Began 00-00-00
Work Completed  
Time Computed 11-30-14
Contract Working Days 271
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0366-06-039
D. I. J. CONSTRUCTION, INC.(5.05%)
FLASHER EQUIPMENT COMPANY(0.54%)
LONE STAR EROSION CONTROL(1.61%)
MURRAY CONSTRUCTION(1.70%)
ROADWAY SPECIALTIES, INC.(0.39%)
Contract # 09143213
Totals 4771137.53 0.00 0.00 0.0

CountyREFUGIO
Highway US 77
From 3.036 MI N OF SH 239
To 7.183 MI S OF SH 239
CSJ 0371-02-068
Proj ID STP 2015(034)HES
Work Type INSTALL MEDIAN BARRIER
 
4.147 800470.60 0.00 640587.24 80.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-07-14
Work Began 10-23-14
Work Completed  
Time Computed 10-23-14
Contract Working Days 44
Addl Days Granted 0
Working Days Charged 48
Percent Time Used 109
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0371-02-068
HIGHWAY BARRICADES AND SERVICES, LLC (0.38%)
LOCKHART CONTRACTING SERVICES, INC.( 22.81%)
Contract # 09143034
Totals 800470.60 0.00 640587.24 80.3

CountySAN PATRICIO
Highway US 77
From ON US77 AT NORTH BU 77-T INTERS.
To .
CSJ 0371-04-059
Proj ID STP 1102(157)SB
Work Type GRADE, BASE, SURF, STRS
 
1.000 9914522.85 14876.10 9759705.68 100.0
Work Order 09-27-11
Work Began 12-01-11
Work Completed 01-27-15
Time Computed 09-01-11
Contract Working Days 269
Addl Days Granted 84
Working Days Charged 550
Percent Time Used 155
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0371-04-059
HIGHWAY BARRICADES AND SERVICES, LLC (0.26%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.02%)
S & S BRIDGE PAINTING, INC.(0.06%)
STAR OPERATIONS, INC.(1.89%)
F & W ELECTRICAL CONTRACTORS, INC. (0.32%)
WRANGLER CONTRACTING (0.84%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.36%)
HIGHWAY TECHNOLOGIES, INC. (0.63%)
PENNTEX MILLING, LLC (0.05%)
TROUT TRUCKING_COMPANY INC.(8.69%)
SOIL-TECH, INC.(1.16%)
W.S. CONSTRUCTION COMPANY(3.19%)
AARON CONCRETE CONTRACTORS, L.P. (0.86%)
NORTH TEXAS REBAR, LLC (0.18%)
PRIMATE CONSTRUCTION, INC. (0.06%)
Contract # 07113206
Totals 9914522.85 14876.10 9759705.68 100.0

CountyKLEBERG
Highway FM 2045
From AT SAN FERNANDO CREEK ON FM 2045
To 2.4 MILES EAST OF US77
CSJ 0383-05-017
Proj ID BR 2013(709)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.201 798976.76 0.00 774884.96 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-13
Work Began 09-24-13
Work Completed 09-16-14
Time Computed 08-22-13
Contract Working Days 130
Addl Days Granted 0
Working Days Charged 169
Percent Time Used 130
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0383-05-017
GUERRA CONSTRUCTION COMPANY(5.76%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.49%)
DELTA SPECIALTIES SIGNS & SUPPLIES (0.39%)
JUST GROOVING, LTD.(0.18%)
FUQUAY, INC. (0.17%)
GARRETT CONSTRUCTION CO. (2.61%)
D & C CONCRETE CUTTING, INC. (0.27%)
SHINN & GREGORY, INC.(5.98%)
CERTIFIED PLACERS LLC(0.14%)
Contract # 05133024
Totals 798976.76 0.00 774884.96 100.0

CountyBEE
Highway SH 202
From CR 425
To REFUGIO COUNTY LINE
CSJ 0447-03-039
Proj ID STP 1502(436)
Work Type SPOT BASE REPAIR AND OVERLAY
 
0.100 8641470.29 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 204
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0447-03-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153013
Totals 8641470.29 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4