Monthly State Let Construction Report For Corpus Christi District As Of Jul 12, 2016 Page 2 Of 4

Last Update: Tuesday, July 12, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyREFUGIO
Highway US 183
From 4 MILES N OF SH 202
To US 77
CSJ 0155-05-039
Proj ID STP 1502(433)
Work Type GRADE, BASE SURF
 
1.700 6324506.65 0.00 0.00 0.0
Work Order 12-21-15
Work Began 00-00-00
Work Completed  
Time Computed 01-01-16
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 12
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0155-05-039
FUQUAY, INC. (0.07%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.90%)
Contract # 11153030
Totals 6324506.65 0.00 0.00 0.0

CountyARANSAS
Highway SH 35
From 549 FT. S OF PR13
To 1 MI. N. OF PR13
CSJ 0180-03-035
Proj ID STP 1102(113)
Work Type GR, BS, SURF
 
1.000 5196117.40 7644.80 8756825.65 99.9
CountyARANSAS
Highway SH 35
From N OF COPANO BAY CAUSEWAY
To S OF COPANO BAY CAUSEWAY
CSJ 0180-04-083
Proj ID BR 1102(114)
Work Type REPLACE EXISTING BRIDGE & REWK APRO
 
2.087 92966472.65 1712305.43 85019213.76 91.4
Work Order 06-15-11
Work Began 08-03-11
Work Completed  
Time Computed 11-14-11
Contract Working Days 968
Addl Days Granted 455
Working Days Charged 1,328
Percent Time Used 93
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0180-03-035
HAAS - ANDERSON CONSTRUCTION, INC. (0.27%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.21%)
SCOTT DERR PAINTING CO (0.28%)
STAR OPERATIONS, INC.(0.45%)
A.Z. REBAR CONSTRUCTION, INC.(5.74%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09%)
ROADWAY SPECIALTIES, INC.(0.16%)
LAND SOLUTIONS CONSTRUCTION, LLC (0.15%)
ROADWAY CONSTRUCTION, INC. (0.77%)
ARROW DIRECTIONAL DRILLING, INC. (0.00%)
Contract # 05113234
Totals 98162590.05 1719950.23 93776039.41 95.5

CountyLIVE OAK
Highway US 281
From US 59 IN GEORGE WEST
To APPROX. 5.3 MI SOUTH (CB)
CSJ 0254-01-134
Proj ID NH 1602(068)
Work Type SPOT BASE REPAIR AND OVERALY
 
5.284 5606795.34 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-11-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0254-01-134
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163203
Totals 5606795.34 0.00 0.00 0.0

CountyLIVE OAK
Highway US 281
From O.447 MI N. SH 72
To W TULLOS ST.
CSJ 0254-01-141
Proj ID NH 2015(888)
Work Type BASE, SURF
 
1.360 1411480.04 0.00 1486074.58 99.9
Work Order 10-21-15
Work Began 02-15-16
Work Completed  
Time Computed 11-02-15
Contract Working Days 55
Addl Days Granted 2
Working Days Charged 44
Percent Time Used 77
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0254-01-141
FLASHER EQUIPMENT COMPANY(2.64%)
SCR CONSTRUCTION CO., INC. (1.34%)
SOIL-TECH, INC.(1.95%)
Contract # 09153230
Totals 1411480.04 0.00 1486074.58 99.9

CountyJIM WELLS
Highway US 281
From FM 2508
To SH 141
CSJ 0255-01-081
Proj ID NH 2016(698)
Work Type REHAB ROADWAY
 
6.770 1764248.12 1136799.36 1136799.36 65.0
Work Order 03-14-16
Work Began 04-13-16
Work Completed  
Time Computed 04-01-16
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 138
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-01-081
FOREMOST PAVING, INC.(3.96%)
Contract # 02163017
Totals 1764248.12 1136799.36 1136799.36 65.0

CountyNUECES
Highway SH 286
From SH 357
To 1 MI S OF FM 43
CSJ 0326-01-052
Proj ID NH 2013(795)
Work Type GRADE, BASE, SURF, STRS
 
2.755 45818725.52 1466675.76 29990755.28 65.4
Work Order 09-05-13
Work Began 03-05-14
Work Completed  
Time Computed 08-01-13
Contract Working Days 687
Addl Days Granted 19
Working Days Charged 480
Percent Time Used 67
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0326-01-052
LARGE & SONS_FOUNDATION DRILLING,INC.(0.20%)
MURRAY CONSTRUCTION(0.20%)
SOIL-TECH, INC.(0.35%)
MASTERPIECE GRINDING & GROOVING, LLC (0.07%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(1.72%)
TEXAS BOMANITE (0.21%)
TERRY L. ELLIS BACKHOE (0.05%)
TROUT TRUCKING_COMPANY INC.(2.72%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.70%)
JHABORES CONSTRUCTION CO, INC. (2.92%)
CROSSROADS MILLING, LLC(0.24%)
CABCOS CONTRACTORS LLC (5.62%)
AARON CONCRETE CONTRACTORS, L.P. (1.86%)
STAR OPERATIONS, INC.(2.06%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.65%)
MCL CONTRACTING, LLC (0.49%)
HAYWARD BAKER, INC.(0.15%)
PERFORMANCE EQUIPMENT SERVICE(0.30%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09%)
Contract # 06133001
Totals 45818725.52 1466675.76 29990755.28 65.4

CountyNUECES
Highway SH 286
From LAREDO ST..
To GOLLIHAR OVERPASS
CSJ 0326-03-091
Proj ID NH 2015(889)
Work Type NOVACHIP ROADWAY
 
2.310 4244327.43 0.00 5107761.23 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-24-15
Work Began 02-17-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 51
Addl Days Granted 20
Working Days Charged 73
Percent Time Used 102
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0326-03-091
HIGHWAY BARRICADES AND SERVICES, LLC ( 11.15%)
CHEROKEE SERVICES(1.26%)
FUQUAY, INC. (0.20%)
Contract # 10153219
Totals 4244327.43 0.00 5107761.23 99.9

CountyKARNES
Highway SH 80
From FM 1354
To .865 MI S OF FM1354
CSJ 0348-03-025
Proj ID STP 1502(574)
Work Type OVERLAY ROADWAY & SPOT BASE REPAIR
 
0.870 755079.04 -66182.13 385177.04 51.0
CountyKARNES
Highway SH 80
From WILSON COUNTY LINE
To .854 MI S OF FM 1354 (CONTROL BR)
CSJ 0348-03-029
Proj ID STP 1502(575)HES
Work Type GRADE, BASE, SURF
 
15.599 4931107.44 539382.03 2750345.70 55.7
CountyKARNES
Highway SH 80
From .865 MI S OF FM 1354 INTERS.
To SH 123
CSJ 0348-04-045
Proj ID STP 1502(576)
Work Type OVERLAY ROADWAY & SPOT BASE REPAIR
 
9.010 7065596.01 203824.80 750591.91 10.6
CountyKARNES
Highway SH 80
From .854 MI S OF FM1354 (CONTROL BREAK)
To SH 123
CSJ 0348-04-050
Proj ID STP 1502(577)HES
Work Type GRADE, BASE, SURF
 
9.553 2276766.39 0.00 246107.86 10.8
Work Order 11-12-15
Work Began 01-18-16
Work Completed  
Time Computed 10-01-15
Contract Working Days 340
Addl Days Granted 0
Working Days Charged 96
Percent Time Used 28
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0348-03-025
D&S TEXAS ICON CONSTRUCTION(1.82%)
FLASHER EQUIPMENT COMPANY(0.22%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.13%)
THE LEVY COMPANY, L.P. (0.05%)
MURRAY CONSTRUCTION(0.38%)
ROADWAY SPECIALTIES, INC.(0.80%)
TEXAS CUTTING & CORING, INC. (0.13%)
Contract # 08153205
Totals 15028548.88 677024.70 4132222.51 27.4

CountyKARNES
Highway FM 99
From US 181
To ATASCOSA COUNTY LINE
CSJ 0348-06-023
Proj ID STP 1502(061)
Work Type PAVEMENT REPAIR AND RESURFACE
 
13.676 8219037.30 473049.16 4765370.09 57.9
Work Order 05-21-15
Work Began 09-15-15
Work Completed  
Time Computed 06-21-15
Contract Working Days 167
Addl Days Granted 2
Working Days Charged 169
Percent Time Used 100
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0348-06-023
FLASHER EQUIPMENT COMPANY(1.46%)
MURRAY CONSTRUCTION(0.83%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.89%)
DANCO TRANSPORT INC. ( 10.13%)
Contract # 04153052
Totals 8219037.30 473049.16 4765370.09 57.9

CountyREFUGIO
Highway SH 239
From SH 35
To 4.3 MI E OF SH 35
CSJ 0350-01-016
Proj ID STP 1602(251)HESG
Work Type TEXTURIZE SHLDRS, CENTERLINE TEXTUR
 
19.472 179857.84 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0350-01-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163224
Totals 179857.84 0.00 0.00 0.0

CountyREFUGIO
Highway SH 239
From SH 35
To FM 774
CSJ 0350-01-017
Proj ID STP 1502(241)HES
Work Type GARDE, BASE, SURF
 
4.318 1996043.76 11028.84 1407407.53 70.5
CountyREFUGIO
Highway FM 2040
From FM 774
To ARANSAS COUNTY LINE
CSJ 0350-03-015
Proj ID STP 1502(242)HES
Work Type GRADE, BASE, SURF
 
5.535 2626977.96 392567.48 1642534.84 62.5
CountyARANSAS
Highway FM 2040
From REFUGIO COUNTY LINE
To 0.842 MI S OF ARANSAS C/L
CSJ 0350-04-011
Proj ID STP 1502(243)HES
Work Type GRADE, BASE, SURF
 
0.847 424378.21 45714.20 275641.54 64.9
CountyREFUGIO
Highway FM 774
From 7 MI W. OF SH 35
To 5 MI W. OF SH 35
CSJ 0447-05-068
Proj ID STP 1502(244)HES
Work Type GRADE, BASE, SURF
 
2.000 1064191.27 194.20 146989.66 13.8
Work Order 07-16-15
Work Began 10-19-15
Work Completed  
Time Computed 08-16-15
Contract Working Days 176
Addl Days Granted 12
Working Days Charged 136
Percent Time Used 72
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0350-01-017
FUQUAY, INC. (0.10%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.11%)
Contract # 06153056
Totals 6111591.20 449504.72 3472573.57 56.8

CountyREFUGIO
Highway US 77
From VICTORIA COUNTY LINE
To 7 MI N. OF REFUGIO CITY LIMITS
CSJ 0371-02-069
Proj ID NH 1602(069)
Work Type MILL, SEAL AND OVERLAY
 
12.946 5008823.01 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0371-02-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163036
Totals 5008823.01 0.00 0.00 0.0

CountyREFUGIO
Highway US 77
From 4.5 MI N OF FM 774
To .1 MI N OF UPPR INTERS.(CONTROL BR)
CSJ 0371-02-071
Proj ID STP 1502(434)HES
Work Type TRADE, BASE, SURF
 
1.676 1612106.37 233664.13 239343.40 14.8
CountyREFUGIO
Highway US 77
From .1 MI N OF UPRR INTERS.(CONTROL BR)
To 2.7 MI N OF FM 774
CSJ 0371-03-117
Proj ID STP 1502(435)HES
Work Type GRADE, BASE, SURF
 
0.204 704322.77 175190.91 182432.90 25.9
Work Order 02-03-16
Work Began 05-12-16
Work Completed  
Time Computed 11-02-15
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 29
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0371-02-071
COWBELL TRAFFIC SERVICES, INC. (0.66%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.47%)
JMHP, INC. (6.30%)
LONE STAR EROSION CONTROL(0.13%)
MURRAY CONSTRUCTION(0.61%)
PAVEMENT MARKINGS INC. (1.20%)
PRIMATE CONSTRUCTION, INC. (1.28%)
Contract # 09153035
Totals 2316429.14 408855.04 421776.30 18.2

CountyREFUGIO
Highway US 77
From VICTORIA COUNTY LINE
To 7 MI N OF REFUGIO CITY LIMITS
CSJ 0371-02-072
Proj ID NH 1602(070)
Work Type MILL, SEAL AND OVERLAY
 
13.454 4610259.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0371-02-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163023
Totals 4610259.16 0.00 0.00 0.0

CountySAN PATRICIO
Highway US 77
From ARANSAS RIVER BRIDGE
To BU 77T
CSJ 0371-04-061
Proj ID NH 1502(578)
Work Type OVERLAY ROADWAY
 
5.379 3883042.09 1533653.94 1533653.94 39.4
Work Order 09-22-15
Work Began 05-31-16
Work Completed  
Time Computed 10-01-15
Contract Working Days 66
Addl Days Granted 10
Working Days Charged 17
Percent Time Used 22
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0371-04-061
HIGHWAY BARRICADES AND SERVICES, LLC (1.51%)
COX PAVING OF TEXAS, INC.(8.95%)
WEST TEXAS RUMBLE STRIP(1.59%)
K.L. DURHAM CONSTRUCTION, LLC(1.60%)
Contract # 08153049
Totals 3883042.09 1533653.94 1533653.94 39.4

CountySAN PATRICIO
Highway US 77
From COOPER RD.
To IH 37
CSJ 0372-01-096
Proj ID NH 2016(803)
Work Type MILL, SEAL AND OVERLAY
 
3.831 2636291.70 0.00 0.00 0.0
Work Order 05-19-16
Work Began 00-00-00
Work Completed  
Time Computed 05-01-16
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0372-01-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163216
Totals 2636291.70 0.00 0.00 0.0

CountyNUECES
Highway SH 44
From FM 666 (IN BANQUETE, TX)
To CONCHO ST. (IN ROBSTOWN)
CSJ 0373-02-090
Proj ID NH 2016(457)
Work Type LEVEL UP, UNDERSEAL AND OVERLAY
 
7.226 4937118.64 111533.63 4993157.45 99.9
Work Order 01-29-16
Work Began 03-02-16
Work Completed  
Time Computed 01-01-16
Contract Working Days 204
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 28
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0373-02-090
SCR CONSTRUCTION CO., INC. (0.39%)
MURRAY CONSTRUCTION(1.93%)
DUSTROL, INC.(3.46%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.15%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.29%)
WEST TEXAS RUMBLE STRIP(0.24%)
D & C CONCRETE CUTTING, INC. (0.32%)
Contract # 11153026
Totals 4937118.64 111533.63 4993157.45 99.9

CountyNUECES
Highway SH 44
From CONCHO ST.
To SS 22 (BAUER ST.)
CSJ 0373-02-092
Proj ID NH 2016(267)
Work Type NOVACHIP ROADWAY
 
1.600 771547.13 0.00 11209.13 1.4
CountyNUECES
Highway FM 624
From I 69E
To FM 1889 (END OF C&G SECTION)
CSJ 0989-02-050
Proj ID NH 2016(267)
Work Type NOVACHIP ROADWAY
 
1.700 959270.88 0.00 0.00 0.0
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 01-01-16
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0373-02-092
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153039
Totals 1730818.01 0.00 11209.13 0.6

CountyKLEBERG
Highway SH 141
From .2 MI W OF ARMSTRONG
To .2 MI E OF 10TH STREET
CSJ 0383-04-055
Proj ID STP 2016(115)HES
Work Type IMPROVE TRAFFIC SIGNALS
 
1.400 783875.25 88945.03 170724.50 21.7
Work Order 11-24-15
Work Began 05-23-16
Work Completed  
Time Computed 12-01-15
Contract Working Days 261
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 26
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0383-04-055
GREEN LIGHT IN THE GROUND(4.02%)
Contract # 10153019
Totals 783875.25 88945.03 170724.50 21.7

CountyBEE
Highway SH 202
From CR 425
To REFUGIO COUNTY LINE
CSJ 0447-03-039
Proj ID STP 1502(436)
Work Type SPOT BASE REPAIR AND OVERLAY
 
0.100 8641470.29 266709.74 2453845.82 28.3
Work Order 08-24-15
Work Began 03-08-16
Work Completed  
Time Computed 09-01-15
Contract Working Days 204
Addl Days Granted 0
Working Days Charged 83
Percent Time Used 40
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0447-03-039
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.34%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.09%)
D&S TEXAS ICON CONSTRUCTION(0.96%)
Contract # 07153013
Totals 8641470.29 266709.74 2453845.82 28.3

page 1 | page 2 | page 3 | page 4