Monthly State Let Construction Report For Corpus Christi District As Of Apr 11, 2014 Page 2 Of 2

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyKLEBERG
Highway FM 2045
From AT SAN FERNANDO CREEK ON FM 2045
To 2.4 MILES EAST OF US77
CSJ 0383-05-017
Proj ID BR 2013(709)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.201 798976.76 0.00 534590.28 66.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-13
Work Began 09-24-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 130
Addl Days Granted 0
Working Days Charged 106
Percent Time Used 81
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0383-05-017
GUERRA CONSTRUCTION COMPANY(5.76%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.49%)
DELTA SPECIALTIES SIGNS & SUPPLIES (0.39%)
JUST GROOVING, LTD.(0.18%)
FUQUAY, INC. (0.17%)
GARRETT CONSTRUCTION CO. (2.61%)
D & C CONCRETE CUTTING, INC. (0.27%)
SHINN & GREGORY, INC.(5.98%)
CERTIFIED PLACERS LLC(0.14%)
Contract # 05133024
Totals 798976.76 0.00 534590.28 66.9

CountyLIVE OAK
Highway SH 72
From MCMULLEN COUNTY LINE
To US 281
CSJ 0483-04-036
Proj ID STP 2013(256)
Work Type GRADE, BASE, SURF, STRS
 
9.561 7246817.28 145011.50 8875242.18 99.9
Work Order 02-22-13
Work Began 03-18-13
Work Completed  
Time Computed 03-10-13
Contract Working Days 180
Addl Days Granted 46
Working Days Charged 187
Percent Time Used 82
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0483-04-036
COWBELL TRAFFIC SERVICES, INC. (0.14%)
D&S TEXAS ICON CONSTRUCTION, LLC (0.27%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.88%)
FLASHER EQUIPMENT COMPANY(0.31%)
HIGHWAY TECHNOLOGIES, INC. (1.99%)
MURRAY CONSTRUCTION(0.89%)
MPB, INC.(0.76%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.99%)
Contract # 12123203
Totals 7246817.28 145011.50 8875242.18 99.9

CountyNUECES
Highway SH 358
From IH 37
To WEST POINT ROAD
CSJ 0617-01-180
Proj ID NH 2013(446)
Work Type MILL AND OVERLAY
 
4.095 2878356.55 0.00 764765.39 27.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-05-13
Work Began 07-31-13
Work Completed  
Time Computed 06-21-13
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 71
Percent Time Used 139
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0617-01-180
TEX OP CONSTRUCTION, LP(5.57%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.87%)
TAHOE TRUCKING, INC. (0.44%)
Contract # 03133023
Totals 2878356.55 0.00 764765.39 27.1

CountyNUECES
Highway PR 22
From SH 358 INTERS.
To SH 361 INTERS.
CSJ 0617-02-063
Proj ID NH 2013(447)
Work Type MILL AND OVERLAY
 
5.975 2212952.39 0.00 1034482.75 46.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-28-13
Work Began 02-18-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 51
Addl Days Granted 26
Working Days Charged 13
Percent Time Used 16
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0617-02-063
TAHOE TRUCKING, INC. (3.00%)
BAY LTD. (0.78%)
CHEROKEE SERVICES(0.75%)
INTERSTATE BARRICADES & MARKINGS, INC. (5.44%)
D S TEXAS ICON CONSTRUCTION, LLC (0.11%)
SYNERGY SIGNS & SERVICES, LLC(0.57%)
S.A. CONCEPTS CONSTRUCTION (1.12%)
R HESTER CONTRACTORS, INC. (8.29%)
Contract # 03133226
Totals 2212952.39 0.00 1034482.75 46.7

CountyNUECES
Highway VA
From AT VARIOUS LOCATIONS IN NUECES CO.
To .
CSJ 0916-00-069
Proj ID ITS 99(714)
Work Type ITS INTERGRATION
 
0.100 946694.00 37985.38 800238.61 84.5
Work Order 06-28-13
Work Began 07-29-13
Work Completed  
Time Computed 07-14-13
Contract Working Days 204
Addl Days Granted 0
Working Days Charged 170
Percent Time Used 83
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-069
HIGHWAY BARRICADES AND SERVICES, LLC (4.62%)
J.C. COMMUNICATION ( 27.95%)
VICKERS CONSTRUCTION (7.15%)
J. CARROLL WEAVER, INC.(1.83%)
Contract # 05133028
Totals 946694.00 37985.38 800238.61 84.5

CountyNUECES
Highway VA
From AT VARIOUS LOCATIONS IN KARNES CO.
To .
CSJ 0916-00-071
Proj ID STP 2013(976)
Work Type INTERSECTION IMPROVEMENTS
 
0.100 5181781.67 712944.06 2968120.56 57.2
CountyNUECES
Highway VA
From AT VARIOUS LOCATIONS IN GOLIAD CO.
To .
CSJ 0916-00-072
Proj ID STP 2013(976)
Work Type INTERSECTION IMPROVEMENTS
 
0.100 2611106.96 19054.85 1947925.19 74.6
Work Order 10-22-13
Work Began 11-12-13
Work Completed  
Time Computed 11-07-13
Contract Working Days 160
Addl Days Granted 12
Working Days Charged 73
Percent Time Used 42
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-071
D&S TEXAS ICON CONSTRUCTION, LLC (0.44%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.52%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.30%)
MURRAY CONSTRUCTION(0.51%)
STAR OPERATIONS, INC.(7.36%)
Contract # 08133248
Totals 7792888.63 731998.91 4916045.75 63.0

CountySAN PATRICIO
Highway CS
From ON MEMORIAL PARKWAY FROM OAK BROOK
To NORTH OF FM 3239 (BUDDY GANEM)
CSJ 0916-28-060
Proj ID STP 2012(778)MM
Work Type GRADE, BASE, SURF, STRS
 
0.180 673926.21 161630.65 612489.89 90.8
CountySAN PATRICIO
Highway FM 3239
From FM 2986
To US 181
CSJ 3340-01-005
Proj ID STP 2012(610)MM
Work Type GRADE, BASE, SURF & STRTS
 
1.007 4096865.07 603062.48 3857580.20 94.1
Work Order 10-18-12
Work Began 01-10-13
Work Completed  
Time Computed 11-03-12
Contract Working Days 220
Addl Days Granted 20
Working Days Charged 235
Percent Time Used 97
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3340-01-005
PENNTEX MILLING, LLC (0.67%)
TROUT TRUCKING_COMPANY INC.(3.39%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.20%)
HIGHWAY TECHNOLOGIES, INC. (1.06%)
STAR OPERATIONS, INC.(5.48%)
MURRAY CONSTRUCTION(0.54%)
SOIL-TECH, INC.(0.91%)
Contract # 08123236
Totals 4770791.28 764693.13 4470070.09 93.6

CountySAN PATRICIO
Highway SH 188
From FM 630
To US 77
CSJ 0994-01-030
Proj ID STP 2012(533)
Work Type REHAB
 
4.300 9223815.50 352802.10 5424910.15 58.8
Work Order 08-30-12
Work Began 02-22-13
Work Completed  
Time Computed 08-01-12
Contract Working Days 345
Addl Days Granted 0
Working Days Charged 133
Percent Time Used 38
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0994-01-030
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.49%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(0.94%)
MURRAY CONSTRUCTION(0.30%)
PRIMATE CONSTRUCTION, INC. (0.14%)
KL DURHAM CONSTRUCTION, LLC(0.07%)
SCOTT DERR PAINTING CO, LLC(0.04%)
TERRY L. ELLIS BACKHOE (0.41%)
HIGHWAY TECHNOLOGIES, INC. (0.84%)
JMHP, INC. (0.58%)
W.S. CONSTRUCTION COMPANY( 20.52%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.89%)
ADVANCED PUMPING, LLC(0.06%)
Contract # 06123226
Totals 9223815.50 352802.10 5424910.15 58.8

CountyNUECES
Highway FM 43
From SH 286
To YORKTOWN BLVD.
CSJ 1557-01-037
Proj ID STP 2013(556)MM
Work Type GRADE, BASE, SURF, STRS
 
1.884 9863126.39 607398.91 1580341.86 16.0
Work Order 08-02-13
Work Began 01-27-14
Work Completed  
Time Computed 06-03-13
Contract Working Days 317
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 11
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1557-01-037
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.20%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(2.42%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.22%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.22%)
SOIL-TECH, INC.(0.33%)
D & C CONCRETE CUTTING, INC. (0.11%)
BEDO CONSTRUCTION PRODUCTS, INC. (1.98%)
PRIMATE CONSTRUCTION, INC. (0.05%)
Contract # 04133202
Totals 9863126.39 607398.91 1580341.86 16.0

CountyNUECES
Highway SH 361
From AT FERRY BOAT LANDINGS
To .
CSJ 2263-02-091
Proj ID FBD 2012(227)
Work Type BULKHEAD REPAIRS
 
0.278 508752.00 182264.67 720570.96 99.9
Work Order 10-18-12
Work Began 12-17-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 54
Addl Days Granted 86
Working Days Charged 119
Percent Time Used 85
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2263-02-091
MUSTANG COLT SERVICES, INC.( 27.11%)
HIGHWAY TECHNOLOGIES, INC. (0.45%)
Contract # 09123246
Totals 508752.00 182264.67 720570.96 99.9

CountyNUECES
Highway SH 361
From AVE. G IN PORT ARANSAS
To BEACH ACCESS 1
CSJ 2263-03-029
Proj ID C 2263-3-29
Work Type GRD, BASE, STRS, STORM SEWER, C & G, SIDE
 
2.621 12988210.75 0.00 79300.00 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-23-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 408
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2263-03-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10133021
Totals 12988210.75 0.00 79300.00 0.6

CountyNUECES
Highway SH 361
From ACCESS RD1A
To MARINERS DR.
CSJ 2263-03-035
Proj ID STP 2014(610)
Work Type LANDSCAPE IMPROVEMENTS
 
4.570 143796.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2263-03-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143023
Totals 143796.00 0.00 0.00 0.0

CountyNUECES
Highway FM 2444
From SH 286
To OSO PARKWAY INTERSECTION
CSJ 2343-01-036
Proj ID STP 2013(936)MM
Work Type GRADE, BASE, SURF, STRTS
 
4.051 24447530.97 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-13-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 510
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2343-01-036
AARON CONCRETE CONTRACTORS, L.P. (0.33%)
MURRAY CONSTRUCTION(0.19%)
SOIL-TECH, INC.(0.10%)
PRIMATE CONSTRUCTION, INC. (0.08%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.57%)
STAR OPERATIONS, INC.(1.63%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.10%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.95%)
PENNTEX MILLING, LLC (0.30%)
Contract # 08133005
Totals 24447530.97 0.00 0.00 0.0

CountySAN PATRICIO
Highway FM 1068
From 250 FT. W. MATHIS CITY LIMITS
To PR 25A
CSJ 2521-01-015
Proj ID STP 2013(937)
Work Type WIDEN ROADWAY
 
2.797 1251857.41 0.00 404906.46 32.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-22-13
Work Began 02-20-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 30
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2521-01-015
CHASE TRANSIT, INC.(7.41%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.78%)
Contract # 08133060
Totals 1251857.41 0.00 404906.46 32.3

CountyKARNES
Highway FM 2724
From CIBOLO CREEK BRIDGE STR 1 ON FM 272
To 2.9 MI N OF FM 81
CSJ 2755-01-009
Proj ID BR 2013(038)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.197 1384041.18 107949.06 1219440.01 90.3
Work Order 10-12-12
Work Began 02-04-13
Work Completed  
Time Computed 10-28-12
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 198
Percent Time Used 129
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2755-01-009
FLASHER EQUIPMENT COMPANY(0.20%)
FUQUAY, INC. (0.80%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.44%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.56%)
ODUM SERVICES, L.P.(1.67%)
Contract # 09123029
Totals 1384041.18 107949.06 1219440.01 90.3

page 1 | page 2