Monthly State Let Construction Report For Corpus Christi District As Of Apr 12, 2024 Page 1 Of 5

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLIVE OAK
HighwayIH 37
FromON IH37 AT NB & SB RESTAREAS
To.
CSJ0073-07-068
Proj IDSTP 2022(831)TP
Work TypeSAFETY REST AREA
 
3.4681030452.141152975.8299.9
Work Order08-11-22
Work Began09-20-22
Work Completed
Time Computed09-01-22
Contract Working Days85
Addl Days Granted2
Working Days Charged225
Percent Time Used258
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-07-068
HIGHWAY BARRICADES AND SERVICES, LLC (1.66)
THOMAS EXCAVATIONS AND UTILITIES LLC (4.36)
TEX OP CONSTRUCTION, LP (2.01)
Contract #06223444
Totals1030452.140.001152975.8299.9

CountyLIVE OAK
HighwayIH 37
FromATASCOSA COUNTY LINE
To3.9 MILES NORTH OF SH 72
CSJ0073-07-071
Proj IDC 73-7-71
Work TypeOVERLAY
 
6063315.040.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days228
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0073-07-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04243205
Totals6063315.040.000.000.0

CountyLIVE OAK
HighwayUA 281
FromON UA281 .5 MI N OF FM99
To.5 MI S OF FM99
CSJ0073-14-008
Proj IDSTP 2023(932)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.96671944.0333924.4747.1
CountyJIM WELLS
HighwaySH 359
FromON SH359 FROM .5 MI N OF FM2044
To.5 MI S OF FM 2044
CSJ0087-01-110
Proj IDSTP 2023(932)HES
Work TypeTRAFFIC CONTROL DEVICES
 
1.06776212.6463180.3782.9
Work Order07-20-23
Work Began03-04-24
Work Completed
Time Computed08-01-23
Contract Working Days46
Addl Days Granted0
Working Days Charged13
Percent Time Used28
Contractor(s)
MALDONADO-BURKETT, LLP
SUBCONTRACTOR(S) FOR CCSJ: 0073-14-008
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06233050
Totals148156.6757191.9397104.8465.5

CountyLIVE OAK ETC
HighwayUA 281 ETC
FromIH 37
ToATASCOSA COUNTY LINE
CSJ0073-14-009
Proj IDC 73-14-9
Work TypeSEAL COAT
 
60.9876776929.866548801.4896.6
Work Order03-06-23
Work Began05-01-23
Work Completed
Time Computed12-01-22
Contract Working Days41
Addl Days Granted0
Working Days Charged44
Percent Time Used107
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-14-009
INTERSTATE BARRICADES & MARKINGS, INC. (0.85)
DOUBLE A CONTRACTING, L.P. (9.14)
Contract #10223207
Totals6776929.860.006548801.4896.6

CountyLIVE OAK ETC
HighwayIH 37 ETC
FromFM 799
ToSH 72
CSJ0074-01-059
Proj IDC 74-1-59
Work TypeSEAL COAT
 
74.3213899642.243854664.9799.2
Work Order02-14-23
Work Began05-01-23
Work Completed
Time Computed12-01-22
Contract Working Days37
Addl Days Granted0
Working Days Charged53
Percent Time Used143
Contractor(s)
CK NEWBERRY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0074-01-059
HIGHWAY BARRICADES AND SERVICES, LLC (12.18)
Contract #10223209
Totals3899642.2412177.053854664.9799.2

CountyLIVE OAK ETC
HighwayIH 37 ETC
FromSH 72
ToUS 281
CSJ0074-01-060
Proj IDF 2024(129)
Work TypeSEAL COAT
 
47.9905101524.261136880.2222.2
Work Order11-16-23
Work Began00-00-00
Work Completed
Time Computed12-01-24
Contract Working Days46
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0074-01-060
VIZCAINO, L.P. (16.13)
FLASHER EQUIPMENT COMPANY (1.29)
Contract #10233228
Totals5101524.26100037.891136880.2222.2

CountySAN PATRICIO
HighwayIH 37
FromSH 188
To0.47 MI SOUTH OF SH 188 (CONTROL BREAK)
CSJ0074-04-047
Proj IDF 2024(046)
Work TypeREHABILITATION OF EXISTING ROAD
 
493249.36361327.5073.2
CountySAN PATRICIO
HighwayIH 37
From0.47 MI SOUTH OF SH 188 (CONTROL BREAK)
ToCR 40
CSJ0074-05-102
Proj IDF 2024(046)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.9255538172.711978802.0235.7
Work Order10-12-23
Work Began10-31-23
Work Completed
Time Computed11-01-23
Contract Working Days153
Addl Days Granted0
Working Days Charged84
Percent Time Used54
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0074-04-047
HIGHWAY BARRICADES AND SERVICES, LLC (3.66)
SOIL TECH ADVANCE INC. (0.30)
STAFF CONCRETE CONSTRUCTION (11.47)
Contract #09233213
Totals6031422.071073047.102340129.5238.7

CountySAN PATRICIO
HighwayIH 37
FromNUECES RIVER (CB)
ToIH37/US 77 INTERCHANGE
CSJ0074-05-098
Proj IDNH 2B20(014)
Work TypeWIDEN FREEWAY
 
0.52021739732.6822740192.5399.9
CountyNUECES
HighwayIH 37
FromREDBIRD LN. (OVERPASS)
ToNUECES RIVER_(CB)
CSJ0074-06-241
Proj IDNH 2B20(015)
Work TypeWIDEN FREEWAY
 
1.76959711872.4034146551.5757.1
CountyNUECES
HighwayIH 37
FromRED BIRD LANE
ToNUECES RIVER
CSJ0074-06-249
Proj IDNH 2B20(015)
Work TypeOVERLAY
 
1.7722539142.09148500.005.8
Work Order07-14-21
Work Began09-20-21
Work Completed
Time Computed07-01-21
Contract Working Days1,959
Addl Days Granted0
Working Days Charged865
Percent Time Used44
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0074-05-098
A BROTHERS MILLING, LLC (0.25)
ADCOCK 4 INVESTMENTS, LLC (1.78)
CREACOM, INC. (5.48)
DEPENDABLE FENCE (0.40)
GP7 CONSTRUCTION INC. (3.04)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.07)
SCOTT DERR PAINTING CO, LLC (0.13)
HIGHWAY BARRICADES AND SERVICES, LLC (0.85)
LONE STAR EROSION CONTROL (0.67)
A. H. BECK FOUNDATION CO., INC. (6.29)
FRANK JR REINFORCEMENT LLC (0.55)
BAY LTD. (10.44)
MARTIN MARIETTA MATERIALS, INC. (1.27)
BRAZOS RIVER CONTRACTORS LLC (2.81)
TEXAS STEEL INDUSTRIAL PLACING, LLC (2.58)
4E INFRA CONSTRUCTION LLC (0.47)
Contract #05213001
Totals83990747.171127592.2257035244.1067.9

CountyNUECES
HighwayUS 181
FromTANCHAHUA ST.
ToBREWSTER ST.
CSJ0074-06-253
Proj IDF 2021(550)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.717269165.00305653.3599.9
Work Order05-20-21
Work Began04-05-22
Work Completed
Time Computed06-01-21
Contract Working Days23
Addl Days Granted0
Working Days Charged20
Percent Time Used86
Contractor(s)
HIGHWAY BARRICADES AND SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0074-06-253
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04213203
Totals269165.000.00305653.3599.9

CountyNUECES
HighwayIH 37
FromSH 358
ToFM 2292
CSJ0074-06-254
Proj IDSTP 2023(504)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.407420461.88125684.8429.8
CountyNUECES
HighwaySH 286
FromSH 358
To.5 MI S OF FM 43
CSJ0326-01-066
Proj IDSTP 2023(504)HES
Work TypeTRAFFIC CONTROL DEVICES
 
4.205214945.000.000.0
CountyNUECES
HighwaySH 286
FromON SH286 FROM SS544
ToSH 358
CSJ0326-03-106
Proj IDSTP 2023(504)HES
Work TypeTRAFFIC CONTROL DEVICES
 
3.764321998.630.000.0
CountyNUECES
HighwaySH 358
FromWEBER RD
To310 FT W OF CLARIDE ST
CSJ0617-01-209
Proj IDSTP 2023(504)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.091481245.880.000.0
Work Order06-01-23
Work Began00-00-00
Work Completed
Time Computed05-01-23
Contract Working Days113
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0074-06-254
HIGHWAY BARRICADES AND SERVICES, LLC (1.15)
Contract #03233024
Totals1438651.390.00125684.848.7

CountyJIM WELLS ETC
HighwaySH 359 ETC
From800 FT S OF FM 534
To800 FT N OF FM 534
CSJ0087-02-055
Proj IDSTP 2B23(114)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.1821046002.45378942.0036.2
Work Order07-26-23
Work Began01-09-24
Work Completed
Time Computed08-01-23
Contract Working Days122
Addl Days Granted0
Working Days Charged46
Percent Time Used37
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0087-02-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06233446
Totals1046002.4586357.00378942.0036.2

CountySAN PATRICIO
HighwayBS 359B
FromON E. SAN PATRICIO AVE @ N. BEE ST
ToSH 359
CSJ0087-06-031
Proj IDC 87-6-31
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1078556.751006327.8299.1
CountySAN PATRICIO
HighwayFM 666
FromSH 359
ToON FM 666 @ MATHIS MS
CSJ1052-03-031
Proj IDC 1052-3-31
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
860298.70764754.4088.8
Work Order03-16-23
Work Began04-27-23
Work Completed
Time Computed03-01-23
Contract Working Days125
Addl Days Granted0
Working Days Charged201
Percent Time Used160
Contractor(s)
MAKO CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0087-06-031
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (9.99)
HIGHWAY BARRICADES AND SERVICES, LLC (1.55)
GULF COAST CONTRACTORS, INC. (4.18)
TEX-MIX PAVING, LLC (1.12)
FR GREENTHUMB LANDSCAPING, LLC (0.00)
Contract #01233228
Totals1938855.45199760.451771082.2294.6

CountyGOLIAD
HighwayUS 59
FromVICTORIA COUNTY LINE
ToWRIGHT ST.
CSJ0088-03-048
Proj IDF 2023(931)
Work TypeOVERLAY
 
12.75510014542.279108644.9690.9
Work Order08-09-23
Work Began11-14-23
Work Completed
Time Computed08-01-23
Contract Working Days76
Addl Days Granted0
Working Days Charged57
Percent Time Used75
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-03-048
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.46)
HIGHWAY BARRICADES AND SERVICES, LLC (2.88)
FLASHER EQUIPMENT COMPANY (0.10)
MURRAY CONSTRUCTION (0.10)
TEXAS GUARDRAIL CONTRACTORS LLC (6.27)
Contract #06233215
Totals10014542.271238280.119108644.9690.9

CountyKARNES
HighwayUS 181
FromAT SAN ANTONIO RIVER BRIDGE
To.
CSJ0100-05-001
Proj IDBR 2019(669)
Work TypeBRIDGE MAINTENANCE
 
0.178786452.20942819.3799.9
Work Order07-14-22
Work Began01-23-23
Work Completed
Time Computed08-01-22
Contract Working Days33
Addl Days Granted20
Working Days Charged93
Percent Time Used175
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-05-001
S&S BRIDGE PAINTING (8.90)
LONE STAR PAVING COMPANY (11.31)
HIGHWAY BARRICADES AND SERVICES, LLC (1.16)
Contract #06223048
Totals786452.200.00942819.3799.9

CountyKARNES
HighwayUS 181
FromON US181 FROM .5 MI N OF FM81
To.5 MI S OF FM81
CSJ0100-05-187
Proj IDSTP 2022(543)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.830257823.86311990.6299.9
CountyKARNES
HighwayUS 181
FromON US181 FROM .5 MI N OF FM1144
To.5 MI S OF FM 1144
CSJ0100-05-188
Proj IDSTP 2022(543)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.994226984.28246498.6899.9
CountyJIM WELLS
HighwayBU 281R
FromON BU281R FROM .5 MI N OF FM1930
To.5 MI S OF FM1930
CSJ0255-01-094
Proj IDSTP 2022(543)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.918157760.67135990.1086.2
Work Order06-15-22
Work Began11-16-22
Work Completed
Time Computed07-01-22
Contract Working Days88
Addl Days Granted0
Working Days Charged63
Percent Time Used71
Contractor(s)
MALDONADO-BURKETT, LLP
SUBCONTRACTOR(S) FOR CCSJ: 0100-05-187
SAFETY FIRST TRAFFIC SOLUTIONS, LLC (6.86)
HIGHWAY BARRICADES AND SERVICES, LLC (0.96)
Contract #05223021
Totals642568.810.00694479.4099.9

CountyBEE
HighwayUS 181
From.3 MI N. OF BU 1810J
ToBU 181-J INTERSECTION_(SOUTH Y)
CSJ0100-08-095
Proj IDC 100-8-95
Work TypeOVERLAY
 
9.6167771037.188327283.7599.9
CountyBEE
HighwayUS 181
FromBU 181J
To.1 MI S OF RIDGEWAY LN. (CB)
CSJ0100-08-097
Proj IDC 100-8-97
Work TypeOVERLAY
 
0.5081001106.861010802.4699.9
CountyBEE
HighwayUS 181
From0.1 MI S OF RIDGEWAY LN. (CB)
ToSH 359
CSJ0101-01-067
Proj IDC 101-1-67
Work TypeOVERLAY
 
7.8665967594.005793782.8097.0
Work Order08-20-20
Work Began02-22-21
Work Completed
Time Computed09-01-20
Contract Working Days184
Addl Days Granted181
Working Days Charged365
Percent Time Used100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0100-08-095
CHEROKEE SERVICES (0.15)
DEPENDABLE FENCE & WELDING CO. INC. (2.53)
FLASHER EQUIPMENT COMPANY (1.63)
HIGHWAY BARRICADES AND SERVICES, LLC (0.50)
LONE STAR EROSION CONTROL (0.22)
RELMCO, INC. (4.14)
PRIMATE CONSTRUCTION, LP (0.05)
DEPENDABLE FENCE (2.53)
Contract #07203013
Totals14739738.040.0015131869.0199.9

CountyBEE
HighwayUS 181
FromNB AND SB FRONTAGE ROADS
ToAT POESTA CREEK
CSJ0100-08-105
Proj IDBR 2B23(115)
Work TypeBRIDGE MAINTENANCE
 
142685.00221501.0099.9
Work Order08-03-23
Work Began10-17-23
Work Completed
Time Computed08-01-23
Contract Working Days51
Addl Days Granted16
Working Days Charged59
Percent Time Used88
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0100-08-105
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06233454
Totals142685.008944.00221501.0099.9

CountyBEE
HighwayBU 181J
From.1 MI N OF HUNTINGTON ST.
To.48 MI N OF US 59
CSJ0100-13-027
Proj IDF 2021(568)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
563119.90521434.5892.5
CountyBEE
HighwayBU 181J
From.48 MI N OF US 59
To.1 MI S OF SH 202
CSJ0101-07-024
Proj IDF 2021(568)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
192517.45168649.4587.6
CountyJIM WELLS
HighwayUS 281
From.2 MI N OF FM 716
To.2 MI S OF FM 716
CSJ0255-02-060
Proj IDF 2021(568)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
86124.2568959.9580.0
Work Order06-10-21
Work Began03-01-22
Work Completed
Time Computed07-01-21
Contract Working Days195
Addl Days Granted0
Working Days Charged163
Percent Time Used83
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-13-027
G & E ESCOBEDO CONSTRUCTION, INC. (0.52)
Contract #05213214
Totals841761.600.00759043.9890.1

CountyBEE
HighwayUS 181
FromSAN PATRICIO COUNTY LINE
ToCR 519
CSJ0101-02-039
Proj IDC 101-2-39
Work TypeOVERLAY
 
9.4959794885.9511536672.9299.9
Work Order09-21-22
Work Began01-03-23
Work Completed
Time Computed10-01-22
Contract Working Days139
Addl Days Granted25
Working Days Charged160
Percent Time Used97
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0101-02-039
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.97)
WEST TEXAS ROCK RESOURCES, LLC (0.16)
EGGEMEYER LAND CLEARING, LLC (0.68)
HIGHWAY BARRICADES AND SERVICES, LLC (1.94)
K. L. DURHAM CONSTRUCTION, L.L.C. (1.36)
MPB, INC. (0.20)
SOIL TECH ADVANCE INC. (0.09)
J. CARROLL WEAVER, INC. (9.12)
EPIC ENERGY SERVICES LLC (0.33)
ADK ENVIRONMENTAL, INC. (0.15)
Contract #08223014
Totals9794885.950.0011536672.9299.9

CountySAN PATRICIO ETC
HighwayUS 181 ETC
FromSH 188
To.06 MI SE OF CR 65
CSJ0101-03-123
Proj IDSTP 2B23(209)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
13.8692721211.000.000.0
Work Order09-07-23
Work Began00-00-00
Work Completed
Time Computed10-01-23
Contract Working Days102
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0101-03-123
TEXAS ICON CONSTRUCTION, LLC (0.25)
Contract #08233024
Totals2721211.000.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5