Monthly State Let Construction Report For Corpus Christi District As Of May 15, 2013 Page 1 Of 3

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLIVE OAK
Highway IH 37
From ATASCOSA COUNTY LINE
To .047 MI. SOUTH OF US 281 INTERS.
CSJ 0073-07-059
Proj ID IM 0371(136)
Work Type MILL AND OVERLAY
 
11.095 203587.79 0.00 0.00 0.0
CountyLIVE OAK
Highway IH 37
From .047 MI. SOUTH OF US 281 INTERS.
To 1.703 MI. SOUTH OF LITTLE GAMBLE CR
CSJ 0074-01-047
Proj ID IM 0371(136)
Work Type MILL AND OVERLAY
 
15.402 69688.84 0.00 0.00 0.0
CountyLIVE OAK
Highway IH 37
From SAN PATRICIO COUNTY LINE
To 1.703 MI. S. OF LITTLE GAMBLE CREEK
CSJ 0074-02-069
Proj ID IM 0371(136)
Work Type MILL AND OVERLAY
 
17.785 440159.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-07-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133222
Totals 713436.43 0.00 0.00 0.0

CountySAN PATRICIO
Highway IH 37
From NUECES CO. LINE
To 2.012 MI. N. OF FM 630
CSJ 0074-05-094
Proj ID IM 0371(135)
Work Type MILL, SEAL AND OVERLAY
 
13.802 3666947.94 0.00 0.00 0.0
Work Order 04-10-13
Work Began 00-00-00
Work Completed  
Time Computed 04-26-13
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0074-05-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133026
Totals 3666947.94 0.00 0.00 0.0

CountyNUECES
Highway IH 37
From .25 MI EAST OF CARBON PLANT RD.
To MCKINZIE RD.
CSJ 0074-06-202
Proj ID STP 2010(395)ES
Work Type GRADE, BASE, SURF & STRUCTURES
 
1.307 7845702.11 39072.49 7039724.54 100.0
Work Order 02-01-10
Work Began 04-06-10
Work Completed 04-16-13
Time Computed 02-17-10
Contract Working Days 232
Addl Days Granted 7
Working Days Charged 459
Percent Time Used 192
Contractor(s)
ZURICH AMERICAN INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0074-06-202
CARTEL PLACERS, LLC(0.08%)
HIGHWAY BARRICADES & SERVICES(1.20%)
PRIMATE CONSTRUCTION, INC. (0.05%)
STAR OPERATIONS, INC.(3.21%)
TRIPLE J CONSTRUCTION, LTD (1.77%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.52%)
WRANGLER CONTRACTING (0.05%)
Z & L CONCRETE CONTRACTORS, INC. (4.61%)
BEDO CONSTRUCTION PRODUCTS, INC. (3.19%)
TREVCON, INC.(7.02%)
TRICON PRECAST, LTD. (1.76%)
W. W. FOUNDATION DRILLING, LTD.(1.00%)
FARR FOUNDATION, INC.(0.17%)
M & M INDUSTRIAL PAINTING(0.20%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.33%)
Contract # 12093206
Totals 7845702.11 39072.49 7039724.54 100.0

CountyNUECES
Highway IH 37
From .25 MI EAST OF CARBON PLANT RD.
To MCKINZIE RD.
CSJ 0074-06-215
Proj ID IM 0371(131)
Work Type GRADE, BASE, SURF & STRUCTURES
 
0.920 23983255.37 0.00 24709984.38 99.9
Work Order 10-16-08
Work Began 01-05-09
Work Completed  
Time Computed 11-01-08
Contract Working Days 393
Addl Days Granted 371
Working Days Charged 834
Percent Time Used 109
Contractor(s)
BALLENGER CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0074-06-215
HIGHWAY TECHNOLOGIES, INC. (0.30%)
WRANGLER CONTRACTING (0.03%)
STAR CONCRETE PUMPING(0.12%)
STAR OPERATIONS, INC.(2.60%)
JAVELINA CONSTRUCTION SOUTH, INC.(0.04%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.10%)
CHOCTAW ERECTORS, INC. (1.28%)
Z & L CONCRETE CONTRACTORS, INC. (1.95%)
SUNBELT EXPRESS SERVICES, INC. (1.01%)
CARTEL PLACERS, LLC(0.85%)
M & M INDUSTRIAL PAINTING(0.50%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(2.10%)
HIGHWAY BARRICADES & SERVICES(0.16%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.14%)
W. W. FOUNDATION DRILLING, LTD.(0.14%)
D & C CONCRETE CUTTING, INC. (0.01%)
S & S BRIDGE PAINTING, INC.(0.30%)
Contract # 08083202
Totals 23983255.37 0.00 24709984.38 99.9

CountyNUECES
Highway IH 37 ETC
From CORN PRODUCTS ROAD
To NUECES RIVER BRIDGE
CSJ 0074-06-217
Proj ID IM 0371(134)
Work Type SEAL COAT ROADWAY
 
175.575 9514348.87 288968.24 1160703.33 12.1
Work Order 11-09-12
Work Began 00-00-00
Work Completed  
Time Computed 11-25-12
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0074-06-217
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10123226
Totals 9514348.87 288968.24 1160703.33 12.1

CountyJIM WELLS
Highway SH 44
From US 281
To .148 MI. S. OF FM 1554 CONTROL BRK.
CSJ 0086-11-043
Proj ID HP 2013(115)
Work Type TRAFFIC SIGNAL IMPROVEMENTS
 
1.208 256420.05 66490.02 242592.62 94.6
CountyJIM WELLS
Highway SH 44
From .148 MI S. OF FM1554 CONTROL BREAK
To DR. N. W. ATKINSON BLVD.
CSJ 0087-01-102
Proj ID HP 2013(115)
Work Type TRAFFIC SIGNAL IMPROVEMENTS
 
3.555 786264.40 0.00 0.00 0.0
Work Order 11-28-12
Work Began 05-02-13
Work Completed  
Time Computed 12-14-12
Contract Working Days 146
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 4
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-11-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10123009
Totals 1042684.45 66490.02 242592.62 23.2

CountyJIM WELLS
Highway SH 359
From SH 44
To 0.3 MI N OF CR 325
CSJ 0087-01-101
Proj ID STP 2012(162)
Work Type UNDERSEAL AND OVERLAY
 
6.142 3156489.33 0.00 3487854.13 99.9
CountyJIM WELLS
Highway SH 359
From ORANGE GROVE SOUTH CITY LIMITS
To CR 356
CSJ 0087-02-047
Proj ID STP 2012(162)
Work Type LEVEL UP AND OVERLAY
 
2.800 963832.98 0.00 833711.50 86.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-11-12
Work Began 09-04-12
Work Completed  
Time Computed 01-27-12
Contract Working Days 60
Addl Days Granted 17
Working Days Charged 75
Percent Time Used 97
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0087-01-101
PRIMATE CONSTRUCTION, INC. (0.12%)
SOIL-TECH, INC.(0.05%)
MURRAY CONSTRUCTION(0.41%)
J CARROLL WEAVER, INC. (9.40%)
FLASHER EQUIPMENT COMPANY(1.66%)
A BROTHERS (0.89%)
D & C CONCRETE CUTTING, INC. (0.11%)
EE CONSTRUCTION, LLC (4.68%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.88%)
Contract # 12113231
Totals 4120322.31 0.00 4321565.63 99.9

CountyJIM WELLS
Highway SH 44
From APPROX. 0.15 MI E. OF FM 1554
To SH 359
CSJ 0087-01-103
Proj ID NH 2013(555)
Work Type OVERLAY, SEAL & FULL - DEPTH REPAIR
 
2.269 3877169.75 0.00 0.00 0.0
CountyNUECES
Highway SH 44
From NUECES/JIM WELLS CO. LINE
To AGUA DULCE
CSJ 0373-03-052
Proj ID NH 2013(555)
Work Type GRADE, BASE, SURF
 
1.069 900128.37 0.00 0.00 0.0
CountyJIM WELLS
Highway SH 44
From SH 359, EAST
To JIM WELLS/NUECES COUNTY LINE
CSJ 0373-04-034
Proj ID NH 2013(555)
Work Type GRADE, BASE, SURF
 
5.192 3759636.15 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 124
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0087-01-103
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133022
Totals 8536934.27 0.00 0.00 0.0

CountyGOLIAD
Highway US 59
From AT US59/US183 INTERSECTION
To .
CSJ 0088-02-056
Proj ID NH 2012(532)
Work Type GRADE, BASE, SURF
 
0.100 2568318.92 78566.67 713505.03 27.7
Work Order 10-18-12
Work Began 01-18-13
Work Completed  
Time Computed 11-03-12
Contract Working Days 114
Addl Days Granted 10
Working Days Charged 66
Percent Time Used 53
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0088-02-056
D S TEXAS ICON CONSTRUCTION, LLC (0.27%)
FLASHER EQUIPMENT COMPANY(3.24%)
STAR OPERATIONS, INC.(8.25%)
TEX OP CONSTRUCTION, LP(2.59%)
Contract # 09123213
Totals 2568318.92 78566.67 713505.03 27.7

CountyKARNES
Highway US 181
From AT BOTH INTERS. OF FM 887/US 181
To .
CSJ 0100-05-073
Proj ID STP 2013(175)
Work Type INTERSECTION IMPROVEMENTS
 
0.149 879202.38 37126.13 179587.55 20.4
CountyKARNES
Highway US 181
From AT BOTH INTERS. OF FM 81/US 181
To .
CSJ 0100-05-074
Proj ID STP 2013(175)
Work Type INTERSECTION IMPROVEMENTS
 
0.113 904334.59 36287.20 195475.94 21.6
Work Order 12-07-12
Work Began 02-04-13
Work Completed  
Time Computed 12-23-12
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 70
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0100-05-073
FLASHER EQUIPMENT COMPANY(0.53%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.55%)
RICE ENVIRONMENTAL SERVICES(1.43%)
DOUBLE S PAVING, INC.(4.87%)
Contract # 11123013
Totals 1783536.97 73413.33 375063.49 21.0

CountyKARNES
Highway US 181
From 1.761 MI S. OF US 181-G
To KARNES/BEE COUNTY LINE
CSJ 0100-06-059
Proj ID NH 2013(253)
Work Type GRADE, BASE, SURF, STRS
 
6.682 3346386.76 195501.12 200488.09 5.9
CountyBEE
Highway US 181
From KARNES/BEE COUNTY LINE
To S. OF FM 1465
CSJ 0100-07-046
Proj ID NH 2013(253)
Work Type GRADE, BASE, SURF, STRS
 
8.500 3886662.76 265742.91 289516.42 7.4
CountyBEE
Highway US 181
From S. OF FM 1465
To 0.10 MI N. OF CR 104
CSJ 0100-08-089
Proj ID C 100-8-89
Work Type GRADE, BASE, SURF, STRS
 
1.877 1330284.02 497606.70 503733.67 37.8
Work Order 02-22-13
Work Began 03-10-13
Work Completed  
Time Computed 03-10-13
Contract Working Days 173
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 20
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0100-06-059
DUSTROL, INC.(0.16%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.11%)
MURRAY CONSTRUCTION(0.63%)
ROADWAY SPECIALTIES, INC.(5.93%)
VEGETATION MANAGEMENT SERVICES, LLC(0.33%)
Contract # 12123004
Totals 8563333.54 958850.73 993738.18 11.6

CountyNUECES
Highway US 77
From SH 44
To FM 892
CSJ 0102-02-095
Proj ID HP 2012(652)
Work Type GRADE, BASE, SURF, STRS
 
1.116 11246983.53 458308.47 2130076.41 18.9
Work Order 09-13-12
Work Began 01-16-13
Work Completed  
Time Computed 09-29-12
Contract Working Days 319
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 20
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0102-02-095
WEBBER BARRIER SERVICES, INC.(3.22%)
TROUT TRUCKING_COMPANY INC.(5.57%)
STAR OPERATIONS, INC.(2.23%)
FARR FOUNDATION, INC.(2.77%)
RICE ENVIRONMENTAL SERVICES(0.52%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.79%)
PENNTEX MILLING, LLC (0.64%)
SCOTT DERR PAINTING CO, LLC(0.03%)
Contract # 07123207
Totals 11246983.53 458308.47 2130076.41 18.9

CountyNUECES
Highway SH 44
From AT FM 1694/SH 44 INTERSECTION
To .
CSJ 0102-02-099
Proj ID NH 2013(656)
Work Type GRADE, BASE, SURF, STRS
 
0.756 12713097.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 302
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0102-02-099
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133203
Totals 12713097.88 0.00 0.00 0.0

CountyKLEBERG
Highway US 77
From S. OF SH 141
To N. OF FM 425
CSJ 0102-04-095
Proj ID NH 2012(313)
Work Type GRAD, BASE.SURF.STRS
 
0.798 14562421.93 232738.34 5800445.47 39.8
Work Order 06-18-12
Work Began 10-24-12
Work Completed  
Time Computed 07-02-12
Contract Working Days 352
Addl Days Granted 0
Working Days Charged 126
Percent Time Used 35
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0102-04-095
HIGHWAY TECHNOLOGIES, INC. (0.31%)
WEST TEXAS RUMBLE STRIP(0.03%)
WEBBER BARRIER SERVICES, INC.(1.36%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(0.63%)
SOIL-TECH, INC.(0.85%)
MURRAY CONSTRUCTION(0.36%)
FLASHER EQUIPMENT COMPANY(0.73%)
DUSTROL, INC.(0.45%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.03%)
KELLYSTONE, INC(0.48%)
SCOTT DERR PAINTING CO, LLC(0.48%)
W. W. FOUNDATION DRILLING, LTD.(0.50%)
TRIPLE J CONSTRUCTION, LTD (1.92%)
STAR OPERATIONS, INC.(1.59%)
TAHOE TRUCKING, INC. (5.69%)
D & C CONCRETE CUTTING, INC. (0.01%)
Contract # 04123001
Totals 14562421.93 232738.34 5800445.47 39.8

CountyARANSAS
Highway SH 35
From 549 FT. S OF PR13
To 1 MI. N. OF PR13
CSJ 0180-03-035
Proj ID STP 1102(113)
Work Type GR, BS, SURF
 
1.000 5196117.40 5000.00 4647075.00 89.4
CountyARANSAS
Highway SH 35
From N OF COPANO BAY CAUSEWAY
To S OF COPANO BAY CAUSEWAY
CSJ 0180-04-083
Proj ID BR 1102(114)
Work Type REPLACE EXISTING BRIDGE & REWK APRO
 
2.087 92966472.65 712732.31 44822342.01 48.2
Work Order 06-15-11
Work Began 08-03-11
Work Completed  
Time Computed 11-14-11
Contract Working Days 968
Addl Days Granted 0
Working Days Charged 450
Percent Time Used 46
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0180-03-035
HAAS - ANDERSON CONSTRUCTION, INC. (0.27%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.21%)
SCOTT DERR PAINTING CO (0.28%)
STAR OPERATIONS, INC.(0.45%)
A.Z. REBAR CONSTRUCTION, INC.(5.74%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09%)
ROADWAY SPECIALTIES, INC.(0.16%)
LAND SOLUTIONS CONSTRUCTION, LLC (0.15%)
ROADWAY CONSTRUCTION, INC. (0.77%)
Contract # 05113234
Totals 98162590.05 717732.31 49469417.01 50.3

CountySAN PATRICIO
Highway SH 35
From AT FM 136/ SH 35 INTERS.
To .
CSJ 0180-06-092
Proj ID STP 2011(909)
Work Type GRADE, BASE, SURF, STRS.
 
1.477 11936520.99 80666.30 12335996.33 100.0
Work Order 05-10-11
Work Began 05-26-11
Work Completed 04-16-13
Time Computed 05-26-11
Contract Working Days 305
Addl Days Granted 30
Working Days Charged 355
Percent Time Used 105
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0180-06-092
CHASE TRANSIT, INC.(2.94%)
AARON CONCRETE CONTRACTORS, L.P. (0.49%)
DUSTIN ALLEN, INC. (0.59%)
HIGHWAY TECHNOLOGIES, INC. (0.88%)
MURRAY CONSTRUCTION(0.46%)
PENNTEX MILLING INC. (0.30%)
RICE ENVIRONMENTAL SERVICES(0.97%)
STAR OPERATIONS, INC.(2.65%)
WEST TEXAS RUMBLE STRIP(0.03%)
TROUT TRUCKING_COMPANY INC.(4.25%)
SHINN & GREGORY, INC.(0.69%)
M & M INDUSTRIAL PAINTING(0.08%)
ADK ENVIRONMENTAL, INC.(0.58%)
RPV CONSTRUCTION (0.33%)
A.Z. REBAR CONSTRUCTION, INC.(0.16%)
Contract # 03113214
Totals 11936520.99 80666.30 12335996.33 100.0

CountyJIM WELLS
Highway US 281
From ON US 281 AT FM1554 INTERS.
To .
CSJ 0254-07-003
Proj ID STP 2012(234)SB
Work Type GRADE, BASE, SURF, STRS
 
1.000 16496831.87 652887.66 8778361.21 53.2
Work Order 09-13-12
Work Began 09-18-12
Work Completed  
Time Computed 09-29-12
Contract Working Days 353
Addl Days Granted 0
Working Days Charged 140
Percent Time Used 39
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0254-07-003
TAHOE TRUCKING, INC. (2.79%)
CUATRO T CONSTRUCTION, INC.(5.54%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.47%)
MURRAY CONSTRUCTION(0.03%)
CHEROKEE SERVICES(0.15%)
WEST TEXAS RUMBLE STRIP(0.02%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.18%)
STAR OPERATIONS, INC.(1.45%)
NORTH TEXAS REBAR, LLC (0.06%)
KL DURHAM CONSTRUCTION, LLC(0.19%)
HOUSTON SAWING & DRILLING(0.08%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.80%)
SCOTT DERR PAINTING CO, LLC(0.10%)
WEBBER BARRIER SERVICES, INC.(0.68%)
J CARROLL WEAVER, INC. (0.03%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.13%)
LHOIST NORTH AMERICA (2.05%)
ADVANCED PUMPING, LLC(0.04%)
Contract # 07123004
Totals 16496831.87 652887.66 8778361.21 53.2

CountyBEE
Highway SH 72
From KARNES COUNTY LINE
To LIVE OAK COUNTY LINE
CSJ 0270-08-022
Proj ID STP 2013(109)
Work Type GRADE, BASE, SURF, STRS
 
7.290 8336665.69 2623522.19 5478163.11 65.7
Work Order 11-14-12
Work Began 02-13-13
Work Completed  
Time Computed 11-30-12
Contract Working Days 143
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 30
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0270-08-022
COWBELL TRAFFIC SERVICES, INC. (0.13%)
D S TEXAS ICON CONSTRUCTION, LLC (0.32%)
DUSTIN ALLEN, INC. (0.56%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.61%)
MURRAY CONSTRUCTION(0.10%)
Contract # 10123208
Totals 8336665.69 2623522.19 5478163.11 65.7

CountyLIVE OAK
Highway SH 72
From US 281
To IH 37
CSJ 0270-09-026
Proj ID STP 2013(254)
Work Type GRADE, BASE, SURF, STRS
 
2.727 2946239.68 292929.52 926363.19 31.4
Work Order 01-29-13
Work Began 02-27-13
Work Completed  
Time Computed 02-14-13
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 50
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0270-09-026
MURRAY CONSTRUCTION(2.34%)
FLASHER EQUIPMENT COMPANY(0.33%)
HIGHWAY TECHNOLOGIES, INC. (1.49%)
M.V. HENKE ENTERPRISES, INC. (0.43%)
D&S TEXAS ICON CONSTRUCTION, LLC (0.54%)
Contract # 12123023
Totals 2946239.68 292929.52 926363.19 31.4

CountyNUECES
Highway BS 286A
From HOLLY ROAD
To SH 357
CSJ 0326-05-002
Proj ID STP 1102(250)SB
Work Type GRADE, BASE, SURF, STRS
 
0.989 5480200.76 0.00 3560941.94 64.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-06-11
Work Began 11-14-11
Work Completed  
Time Computed 12-05-11
Contract Working Days 250
Addl Days Granted 20
Working Days Charged 239
Percent Time Used 88
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0326-05-002
HIGHWAY BARRICADES AND SERVICES, LLC (2.03%)
PENNTEX MILLING INC. (0.61%)
SOIL-TECH, INC.(0.67%)
STOMPER DEMOLITION COMPANY, INC. (0.40%)
TROUT TRUCKING_COMPANY INC.(6.54%)
CHASE TRANSIT, INC.(1.58%)
TAMEZ-PEARSON CONSTRUCTION, INC. (3.71%)
LINDAMOOD DEMOLITION, INC. (0.18%)
Contract # 08113227
Totals 5480200.76 0.00 3560941.94 64.9