MIS.CIS.19 MONTHLY STATE LET CONSTRUCTION REPORT DISTRICT 16 AS OF DEC 11, 2008 PAGE 45 ************************************************************************************************************************************ * | | CONTRACT | AMOUNT THIS | TOTAL ESTIMATE | % * * CONTRACT IDENTIFICATION AND INFORMATION | LENGTH | AMOUNT | ESTIMATE | TO DATE | COMP* ************************************************************************************************************************************ BEE ETC BEE COUNTY LINE | 15.618 | 35,570,742.71| 784,901.95| 24,483,682.55| 68.8| US 181 ETC 1.8 MI WEST OF US 77 RELIEF ROUTE | | | | | | 0101-01-057 | | | | | | C 101-1-57 CONSTRUCT ADDITIONAL 2 LANES | | | | | | | | | | | | WORK ORDER- 08-14-06 WORK BEGAN- 04-20-07 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 08-30-06 | | | | | | CONTRACT WORKING DAYS- 635 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 407 PERCENT TIME USED- 64 | | | | | | | | | | | | HAAS-ANDERSON CONSTRUCTION, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0101-01-057 | | | | | | F & W ELECTRICAL CONTRACTORS, INC. | |SUB %: 1.19 | | | | JAVELINA CONSTRUCTION SOUTH, INC. | |SUB %: 0.09 | | | | LARGE & SONS_FOUNDATION DRILLING,INC. | |SUB %: 0.24 | | | | LISKA CONSTRUCTION COMPANY, INC. | |SUB %: 0.66 | | | | MURRAY CONSTRUCTION | |SUB %: 0.57 | | | | STOMPER DEMOLITION | |SUB %: 0.32 | | | | TROUT TRUCKING_COMPANY INC. | |SUB %: 5.96 | | | | UNITED RENTAL (CORPUS CHRISTI) | |SUB %: 1.46 | | | | VAN - TECH LANDSCAPING & EROSION CONTROL, INC. | |SUB %: 1.70 | | | | WEST TEXAS RUMBLE STRIP | |SUB %: 0.07 | | | | ALL TERRAIN EQUIPMENT COMPANY | |SUB %: 0.55 | | | | | | | | | | CONTRACT 07063203 | TOTALS | 35,570,742.71| 784,901.95| 24,483,682.55| 68.8| ************************************************************************************************************************************ BEE HILLSIDE DRIVE | 1.103 | 4,345,400.20| 0.00| 0.00| 0.0| US 59 BU181-J | | | | | | 0088-01-063 | | | | | | NH 2008(729) REHAB. ROADWAY | | | | | | | | | | | | BEE CLEVELAND ST. | 0.233 | 565,084.70| 0.00| 0.00| 0.0| BU 181J CORPUS CHRISTI ST. | | | | | | 0100-13-022 | | | | | | STP 2008(776) MISCELLANEOUS WORK | | | | | | | | | | | | BEE CORPUS CHRISTI ST. | 0.057 | 137,230.98| 0.00| 0.00| 0.0| BU 181J US 59 | | | | | | 0101-07-020 | | | | | | STP 2008(776) MISCELLANEOUS WORK | | | | | | | | | | | | BEE ON ST. MARY'S ST. FROM CLEVELAND ST | 0.445 | 702,833.20| 0.00| 0.00| 0.0| CS US 59 | | | | | | 0916-25-016 | | | | | | STP 2008(543) MISCELLANEOUS WORK | | | | | | | | | | | | WORK ORDER- 09-05-08 WORK BEGAN- 00-00-00 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-01-08 | | | | | | CONTRACT WORKING DAYS- 209 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | | | | | | | | | | | | HUNTER INDUSTRIES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0088-01-063 | | | | | | F & W ELECTRICAL CONTRACTORS, INC. | |SUB %: 2.20 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 1.06 | | | | HIGHWAY TECHNOLOGIES | |SUB %: 1.03 | | | | J & M CONTRACTING, COMPANY | |SUB %: 35.81 | | | | JAVELINA CONSTRUCTION SOUTH, INC. | |SUB %: 0.80 | | | | MURRAY CONSTRUCTION | |SUB %: 0.51 | | | | VAN - TECH LANDSCAPING & EROSION CONTROL, INC. | |SUB %: 0.49 | | | | | | | | | | CONTRACT 07083004 | TOTALS | 5,750,549.08| 0.00| 0.00| 0.0| ************************************************************************************************************************************ BEE STR 1 (AA0391001)CR 422 @ NEDDY CRE | 0.068 | 498,942.60| 48,567.44| 174,979.26| 35.0| CR APPROX 1.2 MI S OF SH 202 | | | | | | 0916-25-015 | | | | | | BR 2005(142) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 08-12-08 WORK BEGAN- 09-17-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 08-28-08 | | | | | | CONTRACT WORKING DAYS- 144 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 51 PERCENT TIME USED- 35 | | | | | | | | | | | | RELMCO, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0916-25-015 | | | | | | M & D FOUNDATION DRILLING INDUSTRIES, INC. | |SUB %: 9.14 | | | | HIGHWAY TECHNOLOGIES | |SUB %: 1.65 | | | | | | | | | | CONTRACT 07083223 | TOTALS | 498,942.60| 48,567.44| 174,979.26| 35.0| ************************************************************************************************************************************ BEE AT MEDIO CREEK | 0.489 | 2,478,000.00| 0.00| 0.00| 0.0| US 59 6.7 MI NE OF US 181 | | | | | | 0088-01-053 | | | | | | BR 2009(081) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 184 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | BALLENGER CONSTRUCTION COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0088-01-053 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 11083008 | TOTALS | 2,478,000.00| 0.00| 0.00| 0.0| ************************************************************************************************************************************ GOLIAD COLETO PARK ROAD | 13.234 | 49,412,253.70| 1,113,603.63| 42,336,301.61| 89.2| US 59 FORT STREET | | | | | | 0088-03-030 | | | | | | NH 2006(049) GR, BASE, SURF & STRS | | | | | | | | | | | | WORK ORDER- 01-06-06 WORK BEGAN- 01-10-06 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 01-22-06 | | | | | | CONTRACT WORKING DAYS- 544 ADDL DAYS GRANTED- 114 | | | | | | WORKING DAYS CHARGED- 589 PERCENT TIME USED- 89 | | | | | | | | | | | | HUNTER INDUSTRIES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0088-03-030 | | | | | | VIKING CONSTRUCTION, INC. | |SUB %: 0.68 | | | | AARON CONCRETE CONTRACTORS, L.P. | |SUB %: 1.70 | | | | W. W. FOUNDATION DRILLING, LTD. | |SUB %: 1.17 | | | | HIGHWAY PAVEMENT SPECIALTIES, INC. | |SUB %: 0.06 | | | | MURRAY CONSTRUCTION | |SUB %: 0.48 | | | | MICA CORPORATION | |SUB %: 0.79 | | | | L.A. UTILITIES, INC. | |SUB %: 6.00 | | | | JAVELINA CONSTRUCTION SOUTH, INC. | |SUB %: 0.02 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.81 | | | | SCOTT DERR PAINTING CO | |SUB %: 0.01 | | | | UNITED EQUIPMENT RENTALS GULF, L.P. (CORPUS CHRISTI) | |SUB %: 1.33 | | | | SILVA CONTRACTING COMPANY, INC. | |SUB %: 2.01 | | | | VAN - TECH LANDSCAPING & EROSION CONTROL, INC. | |SUB %: 0.92 | | | | SOUTH BEND CONSTRUCTION, L.C. | |SUB %: 0.05 | | | | ALL TERRAIN EQUIPMENT COMPANY | |SUB %: 0.34 | | | | J.L. STEEL, L.P. | |SUB %: 0.15 | | | | PORTADAM | |SUB %: 0.39 | | | | FRIEDEL DRILLING COMPANY | |SUB %: 0.05 | | | | COASTAL MAINTENANCE | |SUB %: 0.02 | | | | DUSTROL, INC. (ROANOKE) | |SUB %: 0.05 | | | | | | | | | | CONTRACT 10053201 | TOTALS | 49,412,253.70| 1,113,603.63| 42,336,301.61| 89.2| ************************************************************************************************************************************ GOLIAD KARNES CO. LINE | 17.831 | 4,486,037.93| 0.00| 0.00| 0.0| SH 239 US 59 | | | | | | 0516-02-024 | | | | | | STP 2008(486)HES GRADE,BASE,SURF | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 155 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | BAY LTD | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0516-02-024 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 10083205 | TOTALS | 4,486,037.93| 0.00| 0.00| 0.0| ************************************************************************************************************************************ JIM WELLS ETC CR 145 | 240.708 | 5,416,982.00| 480.00| 2,659,964.40| 51.1| SH 44 ETC .148 MILES EAST OF FM 1554 | | | | | | 0086-11-039 | | | | | | CPM 86-11-39 SEAL COAT ROADWAY | | | | | | | | | | | | WORK ORDER- 11-07-07 WORK BEGAN- 06-04-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-23-07 | | | | | | CONTRACT WORKING DAYS- 93 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 46 PERCENT TIME USED- 49 | | | | | | | | | | | | NEWMAN & KENG PAVING COMPANY, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0086-11-039 | | | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 17.92 | | | | | | | | | | CONTRACT 10073207 | TOTALS | 5,416,982.00| 480.00| 2,659,964.40| 51.1| ************************************************************************************************************************************ JIM WELLS ETC FM 624 | 160.144 | 6,173,783.16| 0.00| 0.00| 0.0| SH 359 ETC S. END OF NUECES RIVER BRIDGE | | | | | | 0087-02-046 | | | | | | STP 2009(155) SEAL COAT ROADWAY | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 78 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | BRANNAN PAVING CO., LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0087-02-046 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 12083202 | TOTALS | 6,173,783.16| 0.00| 0.00| 0.0| ************************************************************************************************************************************ KARNES BU 181-F | 0.830 | 1,780,537.22| 148,105.85| 151,317.68| 8.4| SH 72 FM 792 | | | | | | 0270-03-069 | | | | | | STP 2008(485) ASPH CONC. PAV. CURB & GUTTER & SID | | | | | | | | | | | | WORK ORDER- 10-16-08 WORK BEGAN- 10-31-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-01-08 | | | | | | CONTRACT WORKING DAYS- 119 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 18 PERCENT TIME USED- 15 | | | | | | | | | | | | HUNTER INDUSTRIES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0270-03-069 | | | | | | DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) | |SUB %: 0.29 | | | | F & W ELECTRICAL CONTRACTORS, INC. | |SUB %: 12.89 | | | | HIGHWAY TECHNOLOGIES | |SUB %: 3.94 | | | | JAVELINA CONSTRUCTION SOUTH, INC. | |SUB %: 2.08 | | | | RELMCO, INC. | |SUB %: 24.87 | | | | WIMS ENVIRONMENTAL CONSTRUCTION, LTD. | |SUB %: 2.07 | | | | | | | | | | CONTRACT 08083015 | TOTALS | 1,780,537.22| 148,105.85| 151,317.68| 8.4| ************************************************************************************************************************************ KLEBERG US 77 IN RIVIERA | 12.065 | 3,781,798.70| 512,451.07| 4,015,317.71| 99.9| SH 285 TO BROOKS COUNTY LINE | | | | | | 0102-06-027 | | | | | | STP 2008(279) GRADE,BASE,SURF,STRS. | | | | | | | | | | | | WORK ORDER- 02-25-08 WORK BEGAN- 03-28-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 03-12-08 | | | | | | CONTRACT WORKING DAYS- 318 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 150 PERCENT TIME USED- 47 | | | | | | | | | | | | BALLENGER CONSTRUCTION COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0102-06-027 | | | | | | TONY A. ENTERPRISES, INC. | |SUB %: 2.74 | | | | SUNBELT EXPRESS SERVICES, INC. | |SUB %: 15.05 | | | | HIGHWAY TECHNOLOGIES | |SUB %: 5.64 | | | | COX PAVING COMPANY, L.P. | |SUB %: 7.96 | | | | CRAWFORD YANT | |SUB %: 0.44 | | | | WRANGLER CONTRACTING | |SUB %: 1.21 | | | | | | | | | | CONTRACT 01083204 | TOTALS | 3,781,798.70| 512,451.07| 4,015,317.71| 99.9| ************************************************************************************************************************************ LIVE OAK AT THE INTERS. OF US281/SH72 | 0.020 | 44,270.00| 0.00| 0.00| 0.0| US 281 . | | | | | | 0254-01-129 | | | | | | CL 254-1-129 LANDSCAPE | | | | | | | | | | | | WORK ORDER- 03-21-07 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 04-06-07 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 32 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 17 PERCENT TIME USED- 53 | |**************************************************| | | | | | | | STRUCTURE MANAGEMENT, LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0254-01-129 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 02073216 | TOTALS | 44,270.00| 0.00| 0.00| 0.0| ************************************************************************************************************************************ LIVE OAK AT REST AREAS NORTH OF FM 2049 | 0.001 | 683,606.81| 0.00| 467,750.00| 68.4| IH 37 AT REST AREAS NORTH OF FM 2049 | | | | | | 0073-07-056 | | | | | | MC 73-7-56 WASTEWATER TREATMENT IMPROVEMENTS | | | | | | | | | | | | WORK ORDER- 04-28-08 WORK BEGAN- 05-14-08 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 05-14-08 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 120 ADDL DAYS GRANTED- 13 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 48 PERCENT TIME USED- 36 | |**************************************************| | | | | | | | ALL CONSTRUCTION WERKS | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0073-07-056 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 03083224 | TOTALS | 683,606.81| 0.00| 467,750.00| 68.4| ************************************************************************************************************************************ LIVE OAK IH 37 | 4.238 | 22,458,380.02| 382,537.62| 23,423,646.65| 99.9| US 59 BU 59 INTERSECTION | | | | | | 0447-01-050 | | | | | | HP 2006(811) GRADE,SUBGR,BASE,SURFACE,STRS,ETC. | | | | | | | | | | | | LIVE OAK IH 37 | 0.800 | 1,062,057.48| 255,711.03| 959,844.26| 90.3| US 59 APPROX. 0.8 MILE EAST OF IH 37 | | | | | | 0447-01-052 | | | | | | CPM 447-1-52 BASE REPAIR,UNDSEAL,OVLAY&RAIL UPGR | | | | | | | | | | | | LIVE OAK AT US59/FM799 INTERSECTION | 0.200 | 169,101.09| 31,688.00| 171,283.59| 99.9| US 59 . | | | | | | 0447-01-056 | | | | | | SFT 447-1-56 INSTALL ILLUMINATION | | | | | | | | | | | | LIVE OAK AT GAMBLE GULLEY BRIDGE | 0.032 | 709,189.64| -140,407.60| 741,367.17| 99.9| US 59 . | | | | | | 0447-01-058 | | | | | | BR 2006(775) BRIDGE REPLACEMENT | | | | | | | | | | | | WORK ORDER- 10-19-06 WORK BEGAN- 01-25-07 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-04-06 | | | | | | CONTRACT WORKING DAYS- 542 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 471 PERCENT TIME USED- 86 | | | | | | | | | | | | HUNTER INDUSTRIES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0447-01-050 | | | | | | MCALLEN CONSTRUCTION, INC. | |SUB %: 37.14 | | | | ATS DESIGN & CONSTRUCTION | |SUB %: 2.48 | | | | SCOTT DERR PAINTING CO | |SUB %: 0.02 | | | | HOUSTON SAWING & DRILLING | |SUB %: 0.18 | | | | HIGHWAY PAVEMENT SPECIALTIES, INC. | |SUB %: 0.16 | | | | GUAJARDO STEEL | |SUB %: 0.72 | | | | LISKA CONSTRUCTION COMPANY, INC. | |SUB %: 3.05 | | | | VAN - TECH LANDSCAPING & EROSION CONTROL, INC. | |SUB %: 0.54 | | | | UNITED RENTAL (CORPUS CHRISTI) | |SUB %: 0.55 | | | | MURRAY CONSTRUCTION | |SUB %: 0.78 | | | | THE LEVY COMPANY, L.P. | |SUB %: 0.87 | | | | JAVELINA CONSTRUCTION SOUTH, INC. | |SUB %: 0.11 | | | | WEST TEXAS RUMBLE STRIP | |SUB %: 0.03 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 0.95 | | | | ALL TERRAIN EQUIPMENT COMPANY | |SUB %: 0.34 | | | | CAPROCK SPECIALITY CONTRACTORS | |SUB %: 0.03 | | | | RIO GRANDE REBAR PLACING, LTD. | |SUB %: 0.06 | | | | EGGEMEYER LAND CLEARING, LLC | |SUB %: 0.06 | | | | COASTAL MAINTENANCE | |SUB %: 0.10 | | | | | | | | | | CONTRACT 08063004 | TOTALS | 24,398,728.23| 529,529.05| 25,296,141.67| 99.9| ************************************************************************************************************************************ LIVE OAK SALT BRANCH BRIDGE STR 20 ON FM 99 | 0.744 | 2,785,458.03| 0.00| 0.00| 0.0| FM 99 ETC 1.5 MI NE OF IH 37 | | | | | | 0348-11-011 | | | | | | BR 2009(065) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 350 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | LISKA CONSTRUCTION COMPANY, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0348-11-011 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 10083003 | TOTALS | 2,785,458.03| 0.00| 0.00| 0.0| ************************************************************************************************************************************ NUECES AT VARIOUS LOCATIONS IN CC DISTRICT | 0.100 | 231,008.25| 0.00| 187,256.50| 81.0| VA . | | | | | | 0916-00-059 | | | | | | STP 2008(280) TRAFFIC MANAGMENT | | | | | | | | | | | | NUECES VARIOUS LOCATIONS IN C.C. DISTRICT | 0.100 | 330,554.85| 0.00| 323,068.80| 97.7| VA . | | | | | | 0916-00-060 | | | | | | STP 2008(280) SIGNALS AND RD SIDE FLASHERS | | | | | | | | | | | | WORK ORDER- 02-20-08 WORK BEGAN- 05-23-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 03-07-08 | | | | | | CONTRACT WORKING DAYS- 60 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 58 PERCENT TIME USED- 96 | | | | | | | | | | | | STAR OPERATIONS, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0916-00-059 | | | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 4.33 | | | | | | | | | | CONTRACT 01083213 | TOTALS | 561,563.10| 0.00| 510,325.30| 90.8| ************************************************************************************************************************************ NUECES 4.072 MILES EAST OF THE COUNTY LINE | 0.701 | 10,883,926.75| 266,782.27| 1,777,813.01| 16.3| SH 361 4.773 MILES EAST OF THE COUNTY LINE | | | | | | 2263-02-079 | | | | | | BR 2008(374) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 04-14-08 WORK BEGAN- 10-01-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-30-08 | | | | | | CONTRACT WORKING DAYS- 724 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 40 PERCENT TIME USED- 5 | | | | | | | | | | | | AUSTIN BRIDGE & ROAD, LP | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 2263-02-079 | | | | | | HIGHWAY PAVEMENT SPECIALTIES, INC. | |SUB %: 0.15 | | | | GUAJARDO STEEL | |SUB %: 2.27 | | | | HIGHWAY TECHNOLOGIES, L.P. | |SUB %: 0.75 | | | | S & S BRIDGE PAINTING, INC. | |SUB %: 0.05 | | | | STAR OPERATIONS, INC. | |SUB %: 0.11 | | | | TRIPLE J CONSTRUCTION, LTD | |SUB %: 0.38 | | | | SOIL-TECH, INC. | |SUB %: 1.64 | | | | J CARROLL WEAVER, INC. | |SUB %: 11.08 | | | | | | | | | | CONTRACT 02083205 | TOTALS | 10,883,926.75| 266,782.27| 1,777,813.01| 16.3| ************************************************************************************************************************************ NUECES AT INTERSECTION OF FM43/SH286 | 3.952 | 3,093,589.71| 190,422.20| 1,430,797.61| 46.2| SH 286 . | | | | | | 0326-01-053 | | | | | | STP 2008(410) INTERSECTION IMPROVEMENTS | | | | | | | | | | | | WORK ORDER- 05-27-08 WORK BEGAN- 06-24-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 06-24-08 | | | | | | CONTRACT WORKING DAYS- 170 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 109 PERCENT TIME USED- 64 | | | | | | | | | | | | BAY LTD | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0326-01-053 | | | | | | HIGHWAY TECHNOLOGIES | |SUB %: 2.97 | | | | STAR OPERATIONS, INC. | |SUB %: 4.12 | | | | JAVELINA CONSTRUCTION SOUTH, INC. | |SUB %: 0.49 | | | | D & C CONCRETE CUTTING, INC. | |SUB %: 1.05 | | | | COX PAVING COMPANY, L.P. | |SUB %: 6.73 | | | | HIGHWAY PAVEMENT SPECIALTIES, INC. | |SUB %: 0.35 | | | | WRANGLER CONTRACTING | |SUB %: 0.08 | | | | LISKA CONSTRUCTION COMPANY, INC. | |SUB %: 1.15 | | | | VAN - TECH LANDSCAPING & EROSION CONTROL, INC. | |SUB %: 0.76 | | | | BAY AREA CONTRACTING & CONSTRUCTION | |SUB %: 1.13 | | | | | | | | | | CONTRACT 03083206 | TOTALS | 3,093,589.71| 190,422.20| 1,430,797.61| 46.2| ************************************************************************************************************************************ NUECES SOUTH OF CORPUS CHRISTI SHIP CHANNE | 1.102 | 7,911,000.00| 0.00| 5,980,899.13| 75.6| US 181 NORTH OF CORPUS CHRISTI SHIP CHANNE | | | | | | 0101-06-096 | | | | | | MC 101-6-96 CLEAN AND PAINT HARBOR BRIDGE | | | | | | | | | | | | WORK ORDER- 06-15-04 WORK BEGAN- 01-17-05 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 12-01-04 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 850 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 816 PERCENT TIME USED- 96 | |**************************************************| | | | | | | | ROYAL BRIDGE, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0101-06-096 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 05043204 | TOTALS | 7,911,000.00| 0.00| 5,980,899.13| 75.6| ************************************************************************************************************************************ NUECES STAPLES STREET | 2.000 | 19,456,831.03| 1,240,607.57| 17,571,912.71| 90.3| SH 358 CARROLL LANE | | | | | | 0617-01-169 | | | | | | STP 2006(572)MM GRADE, BASE, SURF, STRS | | | | | | | | | | | | NUECES EAST OF STAPLES | 3.568 | 2,774,327.10| 1,184.21| 2,861,786.61| 99.9| SH 358 SH 286 | | | | | | 0617-01-171 | | | | | | STP 2006(572)MM ILLUMINATION WORK | | | | | | | | | | | | WORK ORDER- 08-24-06 WORK BEGAN- 12-22-06 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 12-22-06 | | | | | | CONTRACT WORKING DAYS- 575 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 495 PERCENT TIME USED- 86 | | | | | | | | | | | | BAY LTD | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0617-01-169 | | | | | | W. W. FOUNDATION DRILLING, LTD. | |SUB %: 6.61 | | | | UNITED RENTAL (CORPUS CHRISTI) | |SUB %: 1.13 | | | | SCOTT DERR PAINTING CO | |SUB %: 0.09 | | | | BEAVER UNDERGROUND CONTRACTORS, INC. | |SUB %: 1.84 | | | | LISKA CONSTRUCTION COMPANY, INC. | |SUB %: 1.49 | | | | HIGHWAY PAVEMENT SPECIALTIES, INC. | |SUB %: 0.26 | | | | W.W. WEBBER, LLC | |SUB %: 0.84 | | | | JAVELINA CONSTRUCTION SOUTH, INC. | |SUB %: 0.20 | | | | BENTEX SWEEPING, INC. | |SUB %: 0.23 | | | | SOIL-TECH, INC. | |SUB %: 0.92 | | | | SIDCO ENTERPRISES, INC. | |SUB %: 2.48 | | | | M & D FOUNDATION DRILLING INDUSTRIES, INC. | |SUB %: 0.92 | | | | MICA CORPORATION | |SUB %: 19.34 | | | | DELTA PRIME SPECIALTY SERVICES | |SUB %: 0.95 | | | | D & C CONCRETE CUTTING, INC. | |SUB %: 0.06 | | | | BAY AREA CONTRACTING & CONSTRUCTION | |SUB %: 0.76 | | | | G & E ESCOBEDO CONSTRUCTION, INC. | |SUB %: 0.05 | | | | MUNGLE BROS. CONSTRUCTION, LLC | |SUB %: 1.97 | | | | | | | | | | CONTRACT 06063004 | TOTALS | 22,231,158.13| 1,241,791.78| 20,433,699.32| 91.9| ************************************************************************************************************************************ NUECES SH 44 | 6.536 | 3,990,350.31| 532,876.44| 1,243,503.70| 31.1| FM 1694 FM 665 | | | | | | 1742-01-023 | | | | | | C 1742-1-23 GRADE,BASE,SURF | | | | | | | | | | | | NUECES FM 892 | 2.985 | 2,105,718.29| 128,543.10| 318,063.20| 15.1| FM 2826 FM 1694 | | | | | | 2886-02-016 | | | | | | C 2886-2-16 GRADE,BASE,SURF | | | | | | | | | | | | WORK ORDER- 07-10-08 WORK BEGAN- 00-00-00 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 07-26-08 | | | | | | CONTRACT WORKING DAYS- 170 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 65 PERCENT TIME USED- 38 | | | | | | | | | | | | HAAS-ANDERSON CONSTRUCTION, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1742-01-023 | | | | | | HIGHWAY TECHNOLOGIES | |SUB %: 1.87 | | | | G. P. TRANSPORT, INC. | |SUB %: 2.48 | | | | PENNTEX MILLING, LLC | |SUB %: 0.07 | | | | SOIL-TECH, INC. | |SUB %: 2.56 | | | | MURRAY CONSTRUCTION | |SUB %: 1.12 | | | | SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC | |SUB %: 1.93 | | | | | | | | | | CONTRACT 06083004 | TOTALS | 6,096,068.60| 661,419.54| 1,561,566.90| 25.6| ************************************************************************************************************************************ NUECES SEAWALL CHANNEL STR 1 ON SH 361 | 0.262 | 3,469,709.05| 7,942.60| 3,450,570.34| 99.4| SH 361 0.45 MI SE OF COMMERCIAL | | | | | | 2263-02-082 | | | | | | BR 2007(015) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 10-19-07 WORK BEGAN- 01-28-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-04-07 | | | | | | CONTRACT WORKING DAYS- 259 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 188 PERCENT TIME USED- 72 | | | | | | | | | | | | BAY LTD | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 2263-02-082 | | | | | | SOIL-TECH, INC. | |SUB %: 1.11 | | | | LISKA CONSTRUCTION COMPANY, INC. | |SUB %: 1.06 | | | | WEBBER-BALKE FOUNDATION COMPANY, INC. | |SUB %: 5.41 | | | | HIGHWAY TECHNOLOGIES | |SUB %: 1.03 | | | | PRIMATE CONSTRUCTION, INC. | |SUB %: 0.27 | | | | MUNGLE BROS. CONSTRUCTION, LLC | |SUB %: 0.52 | | | | WRANGLER CONTRACTING | |SUB %: 0.27 | | | | | | | | | | CONTRACT 08073224 | TOTALS | 3,469,709.05| 7,942.60| 3,450,570.34| 99.4| ************************************************************************************************************************************ NUECES .25 MI EAST OF CARBON PLANT RD. | 0.920 | 23,983,255.37| 153,253.00| 153,253.00| 0.6| IH 37 MCKINZIE RD. | | | | | | 0074-06-215 | | | | | | IM 0371(131) GRADE,BASE,SURF & STRUCTURES | | | | | | | | | | | | WORK ORDER- 10-16-08 WORK BEGAN- 00-00-00 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-01-08 | | | | | | CONTRACT WORKING DAYS- 393 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | | | | | | | | | | | | BALLENGER CONSTRUCTION COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0074-06-215 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 08083202 | TOTALS | 23,983,255.37| 153,253.00| 153,253.00| 0.6| ************************************************************************************************************************************ SAN PATRICIO BU 77-T IN SINTON | 1.154 | 3,415,890.46| 162,808.97| 2,464,899.05| 72.8| US 181 N. PIRATE BLVD. | | | | | | 0101-03-080 | | | | | | STP 2007(320) MILL & OVERLAY, BASE,STRTS | | | | | | | | | | | | WORK ORDER- 04-20-07 WORK BEGAN- 08-13-07 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 05-06-07 | | | | | | CONTRACT WORKING DAYS- 202 ADDL DAYS GRANTED- 49 | | | | | | WORKING DAYS CHARGED- 281 PERCENT TIME USED- 111 | | | | | | | | | | | | IHS CONSTRUCTION, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0101-03-080 | | | | | | JAVELINA CONSTRUCTION SOUTH, INC. | |SUB %: 0.54 | | | | STAR OPERATIONS, INC. | |SUB %: 10.08 | | | | LONE STAR TRAFFIC SERVICE, INC. | |SUB %: 0.39 | | | | UNITED RENTAL (CORPUS CHRISTI) | |SUB %: 1.25 | | | | D & C CONCRETE CUTTING, INC. | |SUB %: 1.24 | | | | MUNGLE BROS. | |SUB %: 3.63 | | | | TONY A. ENTERPRISES, INC. | |SUB %: 1.36 | | | | A-PLUS PAVING & CONSTRUCTION, INC. | |SUB %: 0.19 | | | | SOIL-TECH, INC. | |SUB %: 0.17 | | | | F. N. PLOCH CONSTRUCTION COMPANY, INC. | |SUB %: 2.79 | | | | | | | | | | CONTRACT 03073210 | TOTALS | 3,415,890.46| 162,808.97| 2,464,899.05| 72.8| ************************************************************************************************************************************ SAN PATRICIO INTERSECTION OF SS 459 NORTH | 1.594 | 2,636,524.72| 274,654.40| 274,654.40| 10.4| IH 37 INTERSECTION OF SH 359 | | | | | | 0074-03-036 | | | | | | HP 2008(728) GRADE, BASE, SURF, STRS | | | | | | | | | | | | WORK ORDER- 09-12-08 WORK BEGAN- 11-03-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 09-28-08 | | | | | | CONTRACT WORKING DAYS- 225 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 18 PERCENT TIME USED- 8 | | | | | | | | | | | | BAY LTD | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0074-03-036 | | | | | | WIMS ENVIRONMENTAL CONSTRUCTION, LTD. | |SUB %: 2.24 | | | | JAVALINA CONSTRUCTION SOUTH, INC. | |SUB %: 0.48 | | | | HIGHWAY TECHNOLOGIES | |SUB %: 1.78 | | | | TRIPLE J CONSTRUCTION, LTD | |SUB %: 2.08 | | | | MURRAY CONSTRUCTION | |SUB %: 1.05 | | | | STAR OPERATIONS, INC. | |SUB %: 4.42 | | | | | | | | | | CONTRACT 07083008 | TOTALS | 2,636,524.72| 274,654.40| 274,654.40| 10.4| ************************************************************************************************************************************ SAN PATRICIO PORTLAND CITY LIMIT | 3.663 | 1,912,287.78| 86,438.60| 1,940,646.79| 99.9| FM 893 FM 1074 | | | | | | 1209-01-021 | | | | | | STP 2007(570) GRADE,BASE,SURF,STRS | | | | | | | | | | | | SAN PATRICIO AT GUM HOLLOW CREEK STR 2 ON FM 893 | 0.244 | 1,053,332.35| 118,155.25| 1,064,206.63| 99.9| FM 893 APPROX 2.80 MI E OF FM 1074 | | | | | | 1209-01-024 | | | | | | BR 2007(578) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | SAN PATRICIO US 181 | 1.828 | 857,494.10| 0.00| 170,697.18| 19.9| FM 893 PORTLAND CITY LIMIT | | | | | | 1209-01-026 | | | | | | STP 2007(570) BASE REPAIR, MILL, SEAL AND OVERLAY | | | | | | | | | | | | WORK ORDER- 10-12-07 WORK BEGAN- 01-14-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 10-28-07 | | | | | | CONTRACT WORKING DAYS- 195 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 117 PERCENT TIME USED- 60 | | | | | | | | | | | | BAY LTD | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1209-01-021 | | | | | | CRAWFORD YANT | |SUB %: 0.88 | | | | LISKA CONSTRUCTION COMPANY, INC. | |SUB %: 2.03 | | | | HIGHWAY TECHNOLOGIES | |SUB %: 1.80 | | | | MURRAY CONSTRUCTION | |SUB %: 0.05 | | | | PRIMATE CONSTRUCTION, INC. | |SUB %: 0.13 | | | | M & D FOUNDATION DRILLING INDUSTRIES, INC. | |SUB %: 1.18 | | | | JAVELINA CONSTRUCTION, INC. | |SUB %: 0.56 | | | | STAR OPERATIONS, INC. | |SUB %: 2.50 | | | | D & C CONCRETE CUTTING, INC. | |SUB %: 0.12 | | | | BAY AREA CONTRACTING & CONSTRUCTION | |SUB %: 0.72 | | | | WRANGLER CONTRACTING | |SUB %: 0.05 | | | | | | | | | | CONTRACT 08073227 | TOTALS | 3,823,114.23| 204,593.85| 3,175,550.60| 83.0| ************************************************************************************************************************************ SAN PATRICIO US 181, 3.2 MI NW OF SINTON | 6.818 | 5,258,317.32| 471,490.88| 4,974,489.30| 94.6| SH 89 US 181, 3.2 MI E OF SINTON | | | | | | 0101-08-002 | | | | | | STP 2008(078) OVERLAY ROADWAY | | | | | | | | | | | | WORK ORDER- 11-13-07 WORK BEGAN- 07-17-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 12-03-07 | | | | | | CONTRACT WORKING DAYS- 68 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 61 PERCENT TIME USED- 89 | | | | | | | | | | | | BAY LTD | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0101-08-002 | | | | | | JAVALINA CONSTRUCTION SOUTH, INC. | |SUB %: 0.32 | | | | LISKA CONSTRUCTION COMPANY, INC. | |SUB %: 0.07 | | | | HIGHWAY TECHNOLOGIES | |SUB %: 2.65 | | | | WEST TEXAS RUMBLE STRIP | |SUB %: 0.17 | | | | SOIL-TECH, INC. | |SUB %: 0.31 | | | | | | | | | | CONTRACT 10073208 | TOTALS | 5,258,317.32| 471,490.88| 4,974,489.30| 94.6| ************************************************************************************************************************************ DISTRICT CONTRACT AMOUNT 236,625,807.61 DISTRICT ESTIMATES THIS MONTH 6,772,798.48 DISTRICT TOTAL ESTIMATES PAID TO DATE 145,773,972.84