Item No Description Units March 31, 2015 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
467 2484 SET (TY II) (18 IN) (CMP) (3: 1) (P) EA     1.000 1,535.45000 1
467 2553 SET (TY II) (30 IN) (CMP) (3: 1) (P) EA     1.000 1,535.45000 1
467 6009 SET (TY I) (30 IN) (4: 1) (C) EA 1.000 2,500.00000 1.000 2,500.00000 1
472 2003 REMOV & RE - LAY PIPE (18 IN) LF     506.000 36.72332 2
474 2005 SLOT DRAIN (GAL STL) (18 IN) LF     770.000 140.00000 1
474 2006 SLOT DRAIN OUTFALL (GAL STL) (18 IN) LF     6.000 140.00000 1
479 2001 ADJ MANHS EA     2.000 800.00000 1
479 2002 ADJ INLETS EA     2.000 15,000.00000 1
479 2006 ADJUST INLET (CAP) EA     3.000 2,253.33333 2
479 2007 ADJ MANH (CAP) EA     1.000 2,795.00000 1
480 2001 CLEAN EXIST CULVS EA     19.000 1,775.77895 3
496 2002 REMOV STR (INLET) EA     5.000 1,120.00000 2
496 2004 REMOV STR (SET) EA     151.000 372.18543 7
496 2005 REMOV STR (WINGWALL) EA     8.000 775.00000 1
496 2006 REMOV STR (HEADWALL) EA     25.000 719.00000 5
496 2007 REMOV STR (PIPE) LF     7,628.000 13.51788 8
496 2008 REMOV STR (BOX CULVERT) LF     13.000 175.00000 1
496 2010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) EA     2.000 44,214.17500 2
496 2014 REMOV STR (RAILROAD CROSSING) EA     1.000 4,000.00000 1
496 6006 REMOV STR (HEADWALL) EA 1.000 1,500.00000 1.000 1,500.00000 1