AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - CHILDRESS DISTRICT
ITEMS 100 6002 TO 169 6004 |
Items | Items | Bid Code Range |
---|---|---|
0100 - 0169 0216 - 0275 0310 - 0360 0400 - 0496 0500 - 0552 0610 - 0690 0780 - 0786 | 3045 - 3045 4002 - 4132 6001 - 6227 | 100 6002 - 169 6004 |
Item No | Description | Units | March 31, 2019 | Twelve-Month-Moving | Usage | ||
---|---|---|---|---|---|---|---|
Quantity | Avg Bid | Quantity | Avg Bid | ||||
100 6002 | PREPARING ROW | STA | 148.000 | 213.00000 | 1 | ||
100 6004 | PREPARING ROW(TREE)(12" TO 24" DIA) | EA | 6.000 | 556.66667 | 2 | ||
100 6007 | PREP ROW (TREE)(GREATER THAN 24" DIA) | EA | 23.000 | 2,600.00000 | 1 | ||
100 6016 | PREPARING ROW (TREE) (36" TO 48" DIA) | EA | 3.000 | 2,793.33333 | 2 | ||
104 6001 | REMOVING CONC (PAV) | SY | 4,088.000 | 22.80785 | 2 | ||
104 6009 | REMOVING CONC (RIPRAP) | SY | 1,140.000 | 25.00000 | 1,147.200 | 25.77197 | 2 |
104 6015 | REMOVING CONC (SIDEWALKS) | SY | 89.000 | 13.50000 | 1 | ||
104 6017 | REMOVING CONC (DRIVEWAYS) | SY | 76.000 | 31.00000 | 1 | ||
104 6021 | REMOVING CONC (CURB) | LF | 4,036.000 | 3.00000 | 1 | ||
104 6022 | REMOVING CONC (CURB AND GUTTER) | LF | 175.000 | 4.00000 | 1 | ||
104 6025 | REMOVE CONC (WINGWALL) | CY | 1.600 | 1,200.00000 | 1.600 | 1,200.00000 | 1 |
104 6032 | REMOVING CONC (WHEELCHAIR RAMP) | SY | 17.000 | 33.50000 | 1 | ||
104 6039 | REMOVE CONC (ABUTMENT BACKWALL) | CY | 3.000 | 1,200.00000 | 3.000 | 1,200.00000 | 1 |
105 6002 | REMOVING STAB BASE AND ASPH PAV (2") | SY | 531.000 | 13.00000 | 1 | ||
105 6013 | REMOVING STAB BASE & ASPH PAV (9") | SY | 7,094.000 | 6.00000 | 1 | ||
105 6023 | REMOVING STAB BASE AND ASPH PAV (5") | SY | 31,127.000 | 2.85000 | 1 | ||
105 6092 | REMOVING STAB BASE AND ASPH PAV (5"-8" | SY | 734.000 | 5.50000 | 1 | ||
105 6132 | REMOVE TRT BASE & ASPH PAV (1"-8") | SY | 905.000 | 4.50000 | 1 | ||
106 6001 | OBLITERATING ABANDONED ROAD | STA | 39.000 | 600.00000 | 1 | ||
106 6002 | OBLITERATING ABANDONED ROAD | SY | 35,223.000 | 3.00000 | 1 | ||
110 6001 | EXCAVATION (ROADWAY) | CY | 67,945.000 | 8.44305 | 4 | ||
110 6002 | EXCAVATION (CHANNEL) | CY | 2,963.100 | 9.55707 | 3 | ||
110 6003 | EXCAVATION (SPECIAL) | CY | 682.000 | 18.00000 | 1 | ||
132 6003 | EMBANKMENT (FINAL)(ORD COMP)(TY B) | CY | 2,766.600 | 16.93407 | 3 | ||
132 6004 | EMBANKMENT (FINAL)(DENS CONT)(TY B) | CY | 83,966.000 | 10.57666 | 4 | ||
134 6004 | BACKFILL (TY A OR B) | STA | 344.000 | 82.39000 | 1,722.550 | 181.74010 | 4 |
150 6002 | BLADING | HR | 108.000 | 161.86111 | 7 | ||
164 6022 | CELL FBR MLCH SEED(PERM)(RURAL)(SANDY) | AC | 33.000 | 1,450.80000 | 1 | ||
164 6034 | DRILL SEEDING (PERM) (RURAL) (SANDY) | AC | 16.240 | 345.00000 | 116.440 | 390.98205 | 10 |
164 6042 | DRILL SEEDING (TEMP) (WARM) | AC | 8.120 | 330.00000 | 55.760 | 330.97166 | 8 |
164 6044 | DRILL SEEDING (TEMP) (COOL) | AC | 8.120 | 330.00000 | 55.760 | 370.10994 | 8 |
166 6001 | FERTILIZER | AC | .340 | 166.00000 | 1 | ||
168 6001 | VEGETATIVE WATERING | MG | 633.000 | 16.75000 | 6,352.790 | 23.79407 | 10 |
169 6002 | SOIL RETENTION BLANKETS (CL 1) (TY B) | SY | 44,575.000 | 1.06000 | 1 | ||
169 6004 | SOIL RETENTION BLANKETS (CL 1) (TY D) | SY | 585.000 | 2.73590 | 2 |