Monthly State Let Construction Report For Brownwood District As Of Jun 12, 2017 Page 2 Of 2

Last Update: Monday, June 12, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMILLS
HighwayCR
FromON CR 333 AT BENNETT CREEK.
To.
CSJ0923-23-014
Proj IDBR 96(274)OX
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100363760.40455900.0099.9
CountySAN SABA
HighwayCR
FromON CR 236 AT RICHLAND CREEK
To.
CSJ0923-25-020
Proj IDBR 2007(630)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100604350.40573713.4098.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-30-16
Work Began09-19-16
Work Completed
Time Computed00-00-00
Contract Working Days102
Addl Days Granted10
Working Days Charged152
Percent Time Used135
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-23-014
DALLAS LITE AND BARRICADE INC. (0.52)
MORRIS COUNTY CONTRACTORS, L.L.C. (4.59)
PRIMATE CONSTRUCTION, INC. (0.75)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.79)
Contract #05163225
Totals968110.80266036.901029613.4099.9

CountyMCCULLOCH
HighwayCR
FromON CR 214 AT SAN SABA RIVER
To.
CSJ0923-24-014
Proj IDBR 2013(824)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100659680.59705277.2199.9
CountyMCCULLOCH
HighwaySH 71
FromAT SAN SABA RIVER
To.
CSJ1102-01-039
Proj IDBR 2013(825)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.2263536720.833848264.4099.9
CountyMCCULLOCH
HighwaySH 71
FromAT TIGER CREEK
To.
CSJ1102-01-040
Proj IDBR 2013(825)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.094845670.30976971.0899.9
CountyMCCULLOCH
HighwaySH 71
FromNEAR FM 2309
To.2 MI. S OF CR 220
CSJ1102-01-041
Proj IDSTP 2013(265)
Work TypeWDN SUBGRADE, STR, SURFACE
 
10.6997626706.076922976.7690.7
Work Order10-24-13
Work Began01-21-14
Work Completed
Time Computed02-14-14
Contract Working Days575
Addl Days Granted115
Working Days Charged616
Percent Time Used89
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-24-014
COPPELL CONSTRUCTION CO., INC. (30.07)
D. I. J. CONSTRUCTION, INC. (1.59)
HJC FARMS, INC. (2.11)
J & M CONTRACTING, COMPANY (5.46)
RICE ENVIRONMENTAL SERVICES (0.40)
TEXAS ALTERNATIVE GRASSER, INC. (0.32)
WILLIS ELECTRIC CO., LP (0.91)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.60)
S & S BRIDGE PAINTING, INC. (0.66)
GIBSON & ASSOCIATES, INC. (0.81)
MESA ROD BUSTERS, INC. (0.06)
Contract #07133245
Totals12668777.79144635.1712453489.4598.3

CountyMCCULLOCH
HighwaySH 71
FromNEAR FM 2309
To2.15 MI S OF FM 2309
CSJ1102-01-042
Proj IDSTP 1502(081)
Work TypeWDN SUBGRADE, STR, SURFACE
 
2.1612316169.671915772.9582.7
CountyMCCULLOCH
HighwaySH 71
From0.54 MI. W OF FM 2309
ToNEAR FM 2309
CSJ2561-01-013
Proj IDSTP 1502(081)
Work TypeWDN SUBGRADE, SURFACE
 
0.5661026756.54671991.6265.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-23-15
Work Began11-02-15
Work Completed
Time Computed00-00-00
Contract Working Days306
Addl Days Granted0
Working Days Charged200
Percent Time Used65
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1102-01-042
J & M CONTRACTING, COMPANY (14.87)
WILLIS ELECTRIC CO., LP (0.54)
HJC FARMS, INC. (1.67)
D.I.J. CONSTRUCTION, INC (2.29)
TEXAS ALTERNATIVE GRASSER, INC. (0.36)
Contract #05153232
Totals3342926.214000.002587764.5777.4

CountyEASTLAND ETC
HighwaySH 206 ETC
FromIH 20
ToCALLAHAN C/L
CSJ2638-01-022
Proj IDSTP 1702(168)HES
Work TypePROFILE CENTER AND EDGELINE MARKING
 
61.329397732.2755318.7513.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-09-17
Work Began05-30-17
Work Completed
Time Computed00-00-00
Contract Working Days81
Addl Days Granted0
Working Days Charged2
Percent Time Used2
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2638-01-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173234
Totals397732.2755318.7555318.7513.9

page 1 | page 2