Monthly State Let Construction Report For Brownwood District As Of Apr 10, 2017 Page 2 Of 2

Last Update: Monday, April 10, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBROWN
HighwayCS
FromON SUDDERTH DR, SUNRISE, MCCULLOGH
ToDR, AND EAST RIVER OAKS AND INEZ ST
CSJ0923-06-075
Proj IDSTP 2017(214)TAPS
Work TypeCNSTR BIKE/ PED PATH
 
0.100427889.980.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days63
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-06-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173227
Totals427889.980.000.000.0

CountyCOMANCHE
HighwayCR
FromON CR 403 AT DRAW
To.
CSJ0923-17-076
Proj IDBR 2015(346)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100217652.00217913.0099.9
CountyCOMANCHE
HighwayCR
FromON CR 304 AT INDIAN CREEK
To.
CSJ0923-17-078
Proj IDBR 2016(003)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100568174.5064190.0011.2
CountyCOMANCHE
HighwayFM 1689
FromAT WALNUT CREEK
To.
CSJ1033-04-021
Proj IDBR 1602(572)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100994764.15382362.4038.4
CountyCOMANCHE
HighwayFM 1477
FromAT N COPPERAS CREEK
To.
CSJ1366-01-009
Proj IDBR 1602(573)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100684261.2048020.007.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-16
Work Began12-07-16
Work Completed
Time Computed00-00-00
Contract Working Days264
Addl Days Granted0
Working Days Charged72
Percent Time Used27
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0923-17-076
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.69)
ODUM SERVICES, L.P. (2.90)
PEACHTREE CONSTRUCTION, LTD. (3.50)
STRIPE-A-ZONE, INC. (0.53)
TOTAL HIGHWAY MAINTENANCE, LLC (0.67)
DFW REBAR, INC. (0.28)
Contract #08163217
Totals2464851.850.00712485.4028.9

CountyMILLS
HighwayCR
FromON CR 333 AT BENNETT CREEK.
To.
CSJ0923-23-014
Proj IDBR 96(274)OX
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100363760.40170094.3046.7
CountySAN SABA
HighwayCR
FromON CR 236 AT RICHLAND CREEK
To.
CSJ0923-25-020
Proj IDBR 2007(630)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100604350.40451512.4075.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-30-16
Work Began09-19-16
Work Completed
Time Computed00-00-00
Contract Working Days102
Addl Days Granted10
Working Days Charged115
Percent Time Used102
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-23-014
DALLAS LITE AND BARRICADE INC. (0.52)
MORRIS COUNTY CONTRACTORS, L.L.C. (3.79)
PRIMATE CONSTRUCTION, INC. (0.75)
Contract #05163225
Totals968110.800.00621606.7064.3

CountyMCCULLOCH
HighwayCR
FromON CR 214 AT SAN SABA RIVER
To.
CSJ0923-24-014
Proj IDBR 2013(824)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100659680.59705277.2199.9
CountyMCCULLOCH
HighwaySH 71
FromAT SAN SABA RIVER
To.
CSJ1102-01-039
Proj IDBR 2013(825)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.2263536720.833848264.4099.9
CountyMCCULLOCH
HighwaySH 71
FromAT TIGER CREEK
To.
CSJ1102-01-040
Proj IDBR 2013(825)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.094845670.30976971.0899.9
CountyMCCULLOCH
HighwaySH 71
FromNEAR FM 2309
To.2 MI. S OF CR 220
CSJ1102-01-041
Proj IDSTP 2013(265)
Work TypeWDN SUBGRADE, STR, SURFACE
 
10.6997626706.076716582.1788.0
Work Order10-24-13
Work Began01-21-14
Work Completed
Time Computed02-14-14
Contract Working Days575
Addl Days Granted7
Working Days Charged582
Percent Time Used100
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-24-014
COPPELL CONSTRUCTION CO., INC. (30.07)
D. I. J. CONSTRUCTION, INC. (1.59)
HJC FARMS, INC. (2.11)
J & M CONTRACTING, COMPANY (5.46)
RICE ENVIRONMENTAL SERVICES (0.40)
TEXAS ALTERNATIVE GRASSER, INC. (0.32)
WILLIS ELECTRIC CO., LP (0.91)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.60)
S & S BRIDGE PAINTING, INC. (0.66)
GIBSON & ASSOCIATES, INC. (0.81)
MESA ROD BUSTERS, INC. (0.06)
Contract #07133245
Totals12668777.79249866.3712247094.8696.6

CountyMCCULLOCH
HighwaySH 71
FromNEAR FM 2309
To2.15 MI S OF FM 2309
CSJ1102-01-042
Proj IDSTP 1502(081)
Work TypeWDN SUBGRADE, STR, SURFACE
 
2.1612316169.671907772.9582.3
CountyMCCULLOCH
HighwaySH 71
From0.54 MI. W OF FM 2309
ToNEAR FM 2309
CSJ2561-01-013
Proj IDSTP 1502(081)
Work TypeWDN SUBGRADE, SURFACE
 
0.5661026756.54671991.6265.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-23-15
Work Began11-02-15
Work Completed
Time Computed00-00-00
Contract Working Days306
Addl Days Granted0
Working Days Charged200
Percent Time Used65
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1102-01-042
J & M CONTRACTING, COMPANY (14.87)
WILLIS ELECTRIC CO., LP (0.54)
HJC FARMS, INC. (1.67)
D.I.J. CONSTRUCTION, INC (2.29)
TEXAS ALTERNATIVE GRASSER, INC. (0.36)
Contract #05153232
Totals3342926.210.002579764.5777.1

CountyEASTLAND ETC
HighwaySH 206 ETC
FromIH 20
ToCALLAHAN C/L
CSJ2638-01-022
Proj IDSTP 1702(168)HES
Work TypePROFILE CENTER AND EDGELINE MARKING
 
61.329397732.270.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days81
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2638-01-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173234
Totals397732.270.000.000.0

page 1 | page 2