Monthly State Let Construction Report For Brownwood District As Of Sep 21, 2017 Page 1 Of 2

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEASTLAND
HighwayIH 20
From0.17 MI W OF SH 206
ToSH 206
CSJ0007-03-093
Proj IDNH 1702(176)
Work TypeRECONSTRUCT FRONTAGE ROAD
 
0.171192955.50296366.4099.9
CountyEASTLAND
HighwaySH 206
FromIH 20, S
To0.246 MI SOUTH OF IH 20
CSJ2638-01-023
Proj IDSTP 1702(177)
Work TypeRECONSTRUCT ROADWAY
 
0.246519768.00413647.3279.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-22-17
Work Began07-19-17
Work Completed
Time Computed00-00-00
Contract Working Days43
Addl Days Granted0
Working Days Charged41
Percent Time Used95
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0007-03-093
HJC FARMS, INC. (0.80)
TOTAL HIGHWAY MAINTENANCE, LLC (2.49)
Contract #04173236
Totals712723.50230032.16710013.7299.6

CountyEASTLAND
HighwayIH 20
FromAT 0.5 MI. W OF FM 571 AND ALSO AT
To2.5 MI. W OF SH 16
CSJ0007-06-070
Proj IDSTP 2005(276)TEG
Work TypeCONSTRUCT TWO SAFETY REST AREAS
 
3.11916358386.5816466163.6299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-04-13
Work Began02-01-13
Work Completed
Time Computed01-20-13
Contract Working Days415
Addl Days Granted180
Working Days Charged628
Percent Time Used105
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-070
EROSION CONTROL MANAGEMENT SERVICES (0.83)
ABILENE SHEET METAL (1.43)
CURTIS MECHANICAL CONTRACTORS, INC. (2.10)
GRIZZLY GLASS & MIRROR, INC. (1.01)
LONE OAK LANDSCAPE LLC (0.38)
LONE STAR BARRIER SERVICES, LLC (0.66)
PEACHTREE CONSTRUCTION, LTD. (4.79)
SCR CONSTRUCTION CO., INC. (0.18)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42)
TIPPENN FABRICATION & ERECTION (5.06)
ALVAREZ DRYWALL & ACCOUSTICS, INC. (0.57)
BUFFALO GAP INSTRUMENTATION AND ELECTRICAL CO., INC. (9.53)
CORPUS CHRISTI STAMP WORKS, INC. (0.05)
FINLEY TERMITE AND PEST CONTROL, INC. (0.01)
SOLID ROCK LAWN & LANDSCAPE (0.21)
TEX OP CONSTRUCTION, LP (0.20)
GOMEZ FLOOR COVERING, INC. (1.55)
ENNIS ROOFING AND CONSTRUCTION, L.L.C. (2.07)
B.A.D.J., INC. DBA THE TOPSPOT (0.21)
WILKS MASONRY CORPORATION (4.34)
LIBERTY PAINTING & DRYWALL (0.65)
HUNTER KNEPSHIELD COMPANY (0.73)
CLLA GROUP, LLC (1.46)
AMERITEX FLAG & FLAGPOLE, LLC (0.03)
A & A CONSTRUCTION (0.26)
LIBERTY PAINTING & DRYWALL (0.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.11)
CONROE WOOD PRODUCTS INC. (0.00)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
SAR TRANSPORTATION, LLC (0.00)
CHAMPION FUEL SOLUTIONS (0.00)
Contract #10123203
Totals16358386.580.0016466163.6299.9

CountySTEPHENS
HighwayUS 180
From@ HUBBARD CREEK LAKE BRIDGE
To.
CSJ0011-07-051
Proj IDBR 1702(472)
Work TypeREHAB BRIDGE
 
0.7002875191.470.000.0
CountySTEPHENS
HighwayUS 180
FromAT SOUR BRANCH BRIDGE
To.
CSJ0011-09-070
Proj IDBR 1702(472)
Work TypeREHAB BRIDGE
 
0.020363962.600.000.0
CountySTEPHENS
HighwayUS 183
FromAT SNAKE DEN CREEK
To.
CSJ0404-02-039
Proj IDBR 1702(472)
Work TypeREPLACE BRIDGE RAIL
 
0.100244990.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days199
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-07-051
BARRICADES UNLIMITED (1.58)
HJC FARMS, INC. (4.38)
ROCK SOLID, INC. (3.33)
S & S BRIDGE PAINTING, INC. (10.30)
SCR CIVIL CONSTRUCTION, LLC (3.13)
CF SOUTHWEST ENVIRONMENT SERVICES LLC (2.77)
TEXOP CONSTRUCTION (0.50)
Contract #07173038
Totals3484144.570.000.000.0

CountySTEPHENS
HighwayUS 180
FromGONZALES CREEK
ToFM 287
CSJ0011-08-026
Proj IDSTP 1602(051)
Work TypeRECONSTRUCT URBAN ROADWAY
 
5.12913412991.585668361.0142.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-16
Work Began09-15-16
Work Completed
Time Computed00-00-00
Contract Working Days459
Addl Days Granted6
Working Days Charged191
Percent Time Used41
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-08-026
CHEROKEE SERVICES (0.17)
D. I. J. CONSTRUCTION, INC. (1.17)
GIBSON & ASSOCIATES, INC. (0.66)
HJC FARMS, INC. (0.63)
(USE 05113)J&M CONTRACTING COMPANY (14.52)
PENHALL COMPANY (0.08)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.49)
WILLIS ELECTRIC CO., LP (2.37)
FAMBRO CONSTRUCTION, INC. (12.03)
NELSON INDUSTRIAL SERVICES, INC. (0.05)
Contract #05163002
Totals13412991.58180000.505668361.0142.2

CountyCOLEMAN ETC
HighwayUS 67 ETC
FromBROWN C/L
To0.1 MI. N OF US 67
CSJ0054-04-107
Proj IDNH 2017(262)
Work TypeSEAL COAT
 
203.0676367226.545863022.8592.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-07-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged74
Percent Time Used102
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-04-107
COX PAVING OF TEXAS, INC. (7.18)
BARRICADES PLUS, LLC (1.80)
FLAT LINE, INC. (7.34)
RED 16 CONSTRUCTION (1.10)
Contract #11163026
Totals6367226.54751381.135863022.8592.1

CountyBROWN
HighwayUS 67
From0.5 MI. W OF FM 3254
ToCR 152
CSJ0054-06-097
Proj IDNH 2017(369)
Work TypeREHABILITATE EXISTING ROADWAY
 
3.0553342055.983241060.5597.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-22-17
Work Began04-17-17
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged80
Percent Time Used117
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0054-06-097
ALTUS TRAFFIC MANAGEMENT LLC (0.21)
TEXOP CONSTRUCTION (2.92)
FLASHER EQUIPMENT COMPANY (0.90)
TEXAS ALTERNATIVE GRASSER, INC. (0.19)
PENHALL COMPANY (0.20)
Contract #01173010
Totals3342055.98788959.013241060.5597.3

CountyBROWN
HighwayUS 84
FromAT FT. WORTH & WESTERN RAILROAD
To.
CSJ0054-07-069
Proj IDSTP 1302(079)RGS
Work TypeRAILROAD BRIDGE REPLACEMENT
 
0.5208488149.704850246.2157.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-16
Work Began09-07-16
Work Completed
Time Computed00-00-00
Contract Working Days400
Addl Days Granted0
Working Days Charged208
Percent Time Used52
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-07-069
GRANBURY EXCAVATING, INC. (24.57)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.30)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.86)
TEXAS SHAFTS, INC. (4.37)
ODUM SERVICES, L.P. (0.58)
MCL CONTRACTING, LLC (0.25)
CHOCTAW ERECTORS, INC. (2.69)
TEXAS HIGHWAY MAINTENANCE, LLC (0.81)
Contract #02163207
Totals8488149.70809808.154850246.2157.1

CountyMCCULLOCH ETC
HighwayUS 87 ETC
From1.2 MI N OF FM 1955
ToMASON CO LINE
CSJ0071-02-032
Proj IDSTP 2017(864)HES
Work TypePROFILE EDGELINE&CENTERLINE MARKING
 
73.350285999.9914224.264.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-19-17
Work Began06-08-17
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged20
Percent Time Used29
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0071-02-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173024
Totals285999.990.0014224.264.9

CountyCOLEMAN
HighwayUS 67
FromSH 206
To.584 MI W OF CR 368
CSJ0078-03-055
Proj IDSTP 2017(457)HES
Work TypeIMPRV GR, SFT TREAT OBJECTS, ADD PA
 
8.2471678694.19634146.0037.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-10-17
Work Began04-17-17
Work Completed
Time Computed00-00-00
Contract Working Days187
Addl Days Granted0
Working Days Charged85
Percent Time Used45
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0078-03-055
CONTRACTORS SERVICE COMPANY (0.93)
DOUBLE A CONTRACTING, L.P. (2.72)
HJC FARMS, INC. (3.55)
TEXOP CONSTRUCTION (2.05)
Contract #01173215
Totals1678694.19313063.00634146.0037.7

CountyEASTLAND
HighwayUS 183
FromIH 20
ToCR 181
CSJ0127-01-030
Proj IDSTP 1702(236)
Work TypeADD PASSING LANES
 
4.2433372833.810.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-21-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days221
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0127-01-030
D.I.J. CONSTRUCTION, INC (1.86)
GIBSON & ASSOCIATES, INC. (2.02)
HJC FARMS, INC. (3.06)
LUZ LERMA CONSTRUCTION, INC. (2.01)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.24)
TEXAS ALTERNATIVE GRASSER, INC. (0.30)
Contract #05173045
Totals3372833.810.000.000.0

CountySAN SABA
HighwayFM 580
FromUS 190
ToLAMPASAS C/L
CSJ0231-14-017
Proj IDSTP 2015(389)HES
Work TypeADD'L PAVED SURF WIDTH, WDN STRS
 
14.1445387952.965735977.8799.9
Work Order03-13-15
Work Began06-23-15
Work Completed
Time Computed06-11-15
Contract Working Days474
Addl Days Granted0
Working Days Charged465
Percent Time Used98
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0231-14-017
D. I. J. CONSTRUCTION, INC. (2.05)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.37)
PRIMATE CONSTRUCTION, INC. (0.14)
ROADWAY SPECIALTIES, INC. (4.88)
SAN-ANN-CO., INC. (0.99)
TEXAS ALTERNATIVE GRASSER, INC. (0.47)
BROCK CONSTRUCTION, LLC (0.30)
WOLFE CONSTRUCTION GROUP, INC. (0.09)
Contract #01153225
Totals5387952.965482.945735977.8799.9

CountySTEPHENS
HighwayUS 183
FromUS 180
ToBRECKENRIDGE SCL
CSJ0257-01-041
Proj IDSTP 1602(303)
Work TypeREHABILITATE EXISTING ROADWAY
 
0.7343157515.040.000.0
CountySTEPHENS
HighwayUS 183
FromUS 180
ToBRECKENRIDGE SCL
CSJ0257-01-044
Proj IDROW 257-1-44
Work TypeUTILITY ADJUSTMENTS
 
0.734580454.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-22-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days238
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0257-01-041
D.I.J. CONSTRUCTION, INC (1.53)
FAMBRO CONSTRUCTION, INC. (13.08)
HJC FARMS, INC. (1.46)
J & M CONTRACTING COMPANY (17.96)
TEXAS ALTERNATIVE GRASSER, INC. (0.13)
WILLIS ELECTRIC CO., LP (0.53)
Contract #04173226
Totals3737969.440.000.000.0

CountyMCCULLOCH
HighwayUS 190
FromUS 377
ToSAN SABA C/L
CSJ0272-01-031
Proj IDSTP 2016(924)HES
Work TypeUPGRADE GUARDRAIL & SFTY TREAT STRS
 
17.1741084525.501063151.72100.0
CountySAN SABA
HighwayFM 45
FromMILLS C/L
ToRICHLAND SPRINGS NORTH CITY LIMIT
CSJ0480-08-023
Proj IDSTP 2016(925)HRR
Work TypeUPGRADE GUARDRAIL & SFTY TREAT STRS
 
12.071714070.00688793.05100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-03-16
Work Began08-08-16
Work Completed08-28-17
Time Computed00-00-00
Contract Working Days230
Addl Days Granted0
Working Days Charged226
Percent Time Used98
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0272-01-031
ODUM SERVICES, L.P. (19.21)
Contract #04163025
Totals1798595.5014000.001751944.77100.0

CountyMILLS
HighwaySH 16
From.021 MI SW OF BARROW ST
ToSAN SABA COUNTY LINE
CSJ0289-03-026
Proj IDSTP 2017(445)HES
Work TypeIMPRV GR, SFT TREAT FIXED, ADD PASS
 
9.2411203835.851146703.8295.2
CountyBURNET
HighwayFM 1478
FromLAMPASAS C/L
To7.096 MI. S OF LAMPASAS C/L
CSJ2206-02-006
Proj IDSTP 2017(471)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
7.096353795.02217700.0161.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-17
Work Began03-21-17
Work Completed
Time Computed00-00-00
Contract Working Days187
Addl Days Granted0
Working Days Charged103
Percent Time Used55
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0289-03-026
FLASHER EQUIPMENT COMPANY (1.87)
WOLFE CONSTRUCTION GROUP, INC. (0.57)
STRIPE-A-ZONE, INC. (1.55)
JE CASEY, LLC (9.79)
Contract #01173213
Totals1557630.87158257.791364403.8387.5

CountyMILLS
HighwayFM 45
FromBROWN C/L
ToSAN SABA C/L
CSJ0480-07-009
Proj IDSTP 1602(052)
Work TypeGRADING, STRUCTURES, BASE, AND SURF
 
4.3624563803.882954937.0064.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-16
Work Began09-06-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted6
Working Days Charged209
Percent Time Used80
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0480-07-009
D.I.J. CONSTRUCTION, INC (1.28)
TEXAS ALTERNATIVE GRASSER, INC. (0.60)
HJC FARMS, INC. (0.95)
J&M CONTRACTING COMPANY (14.23)
Contract #05163004
Totals4563803.88156610.562954937.0064.7

CountyEASTLAND
HighwayFM 8
From0.273 MI. E OF FM 2214
To0.06 MI. W OF HOG CREEK
CSJ0550-01-023
Proj IDSTP 2014(544)
Work TypeGRADING, STRS, FLEX BASE, AND SURF
 
0.322458987.68398632.3486.8
CountyEASTLAND
HighwayFM 2214
From0.5 MI E OF FM 571
ToFM 8
CSJ1697-02-019
Proj IDSTP 2014(544)
Work TypeGRADING, STRS, FLEX BASE AND SURFAC
 
4.7014840589.805800113.3299.9
Work Order08-07-14
Work Began01-06-15
Work Completed
Time Computed12-10-14
Contract Working Days272
Addl Days Granted31
Working Days Charged459
Percent Time Used151
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0550-01-023
MARCOM"S MOWING SERVICE, LLC (0.49)
NORTH EASTERN PAVERS (11.45)
S & S BRIDGE PAINTING, INC. (0.55)
TEXAS ALTERNATIVE GRASSER, INC. (0.62)
TOTAL HIGHWAY MAINTENANCE, LLC (1.37)
WILLIS ELECTRIC CO., LP (2.05)
SHINN & GREGORY, INC. (0.48)
EROSION CONTROL MANAGEMENT SERVICES (0.61)
ELLIS-MCGINNIS CONSTRUCTION CO. (3.96)
D.I.J. CONSTRUCTION, INC (0.30)
Contract #05143002
Totals5299577.4810176.556198745.6699.9

CountyBROWN
HighwayCS
FromON SUDDERTH DR, SUNRISE, MCCULLOGH
ToDR, AND EAST RIVER OAKS AND INEZ ST
CSJ0923-06-075
Proj IDSTP 2017(214)TAPS
Work TypeCNSTR BIKE/ PED PATH
 
0.100427889.98421592.98100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-28-17
Work Began06-01-17
Work Completed09-01-17
Time Computed00-00-00
Contract Working Days63
Addl Days Granted0
Working Days Charged70
Percent Time Used111
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-06-075
CONTRACTORS SERVICE COMPANY (2.10)
TOTAL HIGHWAY MAINTENANCE, LLC (6.27)
Contract #03173227
Totals427889.980.00421592.98100.0

CountyCOMANCHE
HighwayCR
FromON CR 403 AT DRAW
To.
CSJ0923-17-076
Proj IDBR 2015(346)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100217652.00223423.0099.9
CountyCOMANCHE
HighwayCR
FromON CR 304 AT INDIAN CREEK
To.
CSJ0923-17-078
Proj IDBR 2016(003)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100568174.5064190.0011.2
CountyCOMANCHE
HighwayFM 1689
FromAT WALNUT CREEK
To.
CSJ1033-04-021
Proj IDBR 1602(572)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100994764.15777518.8078.1
CountyCOMANCHE
HighwayFM 1477
FromAT N COPPERAS CREEK
To.
CSJ1366-01-009
Proj IDBR 1602(573)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100684261.20469620.7068.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-16
Work Began12-07-16
Work Completed
Time Computed00-00-00
Contract Working Days264
Addl Days Granted0
Working Days Charged167
Percent Time Used63
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0923-17-076
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.69)
ODUM SERVICES, L.P. (2.90)
PEACHTREE CONSTRUCTION, LTD. (3.50)
STRIPE-A-ZONE, INC. (0.53)
TOTAL HIGHWAY MAINTENANCE, LLC (0.67)
DFW REBAR, INC. (0.28)
Contract #08163217
Totals2464851.8556570.001534752.5062.2

CountyMCCULLOCH
HighwayCR
FromON CR 214 AT SAN SABA RIVER
To.
CSJ0923-24-014
Proj IDBR 2013(824)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100659680.59705277.2199.9
CountyMCCULLOCH
HighwaySH 71
FromAT SAN SABA RIVER
To.
CSJ1102-01-039
Proj IDBR 2013(825)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.2263536720.833856986.1599.9
CountyMCCULLOCH
HighwaySH 71
FromAT TIGER CREEK
To.
CSJ1102-01-040
Proj IDBR 2013(825)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.094845670.30976971.0899.9
CountyMCCULLOCH
HighwaySH 71
FromNEAR FM 2309
To.2 MI. S OF CR 220
CSJ1102-01-041
Proj IDSTP 2013(265)
Work TypeWDN SUBGRADE, STR, SURFACE
 
10.6997626706.077455045.6697.7
Work Order10-24-13
Work Began01-21-14
Work Completed
Time Computed02-14-14
Contract Working Days575
Addl Days Granted115
Working Days Charged670
Percent Time Used97
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-24-014
COPPELL CONSTRUCTION CO., INC. (30.07)
D. I. J. CONSTRUCTION, INC. (1.59)
HJC FARMS, INC. (2.11)
J & M CONTRACTING, COMPANY (5.46)
RICE ENVIRONMENTAL SERVICES (0.40)
TEXAS ALTERNATIVE GRASSER, INC. (0.32)
WILLIS ELECTRIC CO., LP (0.91)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.60)
S & S BRIDGE PAINTING, INC. (0.66)
GIBSON & ASSOCIATES, INC. (0.81)
MESA ROD BUSTERS, INC. (0.06)
Contract #07133245
Totals12668777.79333822.2412994280.1099.9

CountyMCCULLOCH
HighwaySH 71
FromNEAR FM 2309
To2.15 MI S OF FM 2309
CSJ1102-01-042
Proj IDSTP 1502(081)
Work TypeWDN SUBGRADE, STR, SURFACE
 
2.1612316169.671946497.3584.0
CountyMCCULLOCH
HighwaySH 71
From0.54 MI. W OF FM 2309
ToNEAR FM 2309
CSJ2561-01-013
Proj IDSTP 1502(081)
Work TypeWDN SUBGRADE, SURFACE
 
0.5661026756.54712979.1269.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-23-15
Work Began11-02-15
Work Completed
Time Computed00-00-00
Contract Working Days306
Addl Days Granted0
Working Days Charged200
Percent Time Used65
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1102-01-042
J & M CONTRACTING, COMPANY (14.87)
WILLIS ELECTRIC CO., LP (0.54)
HJC FARMS, INC. (1.67)
D.I.J. CONSTRUCTION, INC (2.29)
TEXAS ALTERNATIVE GRASSER, INC. (0.36)
Contract #05153232
Totals3342926.2163711.902659476.4779.5

page 1 | page 2