Monthly State Let Construction Report For Brownwood District As Of May 15, 2013 Page 1 Of 1

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEASTLAND
Highway IH 20
From AT 0.5 MI. W OF FM 571 AND ALSO AT
To 2.5 MI. W OF SH 16
CSJ 0007-06-070
Proj ID STP 2005(276)TEG
Work Type CONSTRUCT TWO SAFETY REST AREAS
 
3.119 16358386.58 134145.99 1003429.06 6.1
Work Order 01-04-13
Work Began 02-01-13
Work Completed  
Time Computed 01-20-13
Contract Working Days 415
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 13
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-070
EROSION CONTROL MANAGEMENT SERVICES(0.83%)
ABILENE SHEET METAL(1.43%)
CURTIS MECHANICAL CONTRACTORS, INC.(2.10%)
GRIZZLY GLASS & MIRROR, INC. (1.01%)
LONE OAK LANDSCAPE LLC (0.38%)
LONE STAR BARRIER SERVICES, LLC(0.66%)
PEACHTREE CONSTRUCTION, LTD. (4.79%)
SCR CONSTRUCTION CO., INC. (0.18%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42%)
TIPPENN FABRICATION & ERECTION (5.06%)
ALVAREZ DRYWALL & ACCOUSTICS, INC. (0.57%)
BUFFALO GAP INSTRUMENTATION AND ELECTRICAL CO., INC. (9.53%)
CORPUS CHRISTI STAMP WORKS, INC. (0.05%)
FINLEY TERMITE AND PEST CONTROL, INC.(0.01%)
SOLID ROCK LAWN & LANDSCAPE(0.21%)
TEX OP CONSTRUCTION, LP(0.20%)
GOMEZ FLOOR COVERING, INC. (1.55%)
ENNIS ROOFING AND CONSTRUCTION, L.L.C. (2.07%)
B.A.D.J., INC. DBA THE TOPSPOT (0.21%)
WILKS MASONRY CORPORATION(4.34%)
LIBERTY PAINTING & DRYWALL (0.65%)
HUNTER KNEPSHIELD COMPANY(0.73%)
Contract # 10123203
Totals 16358386.58 134145.99 1003429.06 6.1

CountySHACKELFORD
Highway US 180
From 0.39 MI W OF STEPHENS CL
To STEPHENS CL
CSJ 0011-06-043
Proj ID BR 2012(555)
Work Type REPLACE BRIDGE APPROACH
 
0.379 435784.60 0.00 234928.20 53.9
CountySTEPHENS
Highway US 180
From SHAKELFORD CL
To 0.47 MI EAST
CSJ 0011-07-046
Proj ID BR 2012(555)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.473 2839183.85 149838.00 1848905.43 65.1
Work Order 06-14-12
Work Began 08-07-12
Work Completed  
Time Computed 09-12-12
Contract Working Days 251
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 72
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-07-046
CONTRACTORS SERVICE COMPANY(0.35%)
DUSTY ALLEN, INC.(2.26%)
HIGHWAY TECHNOLOGIES, INC. (1.38%)
HOUSTON SAWING & DRILLING(0.09%)
STREET FOUNDATION DRILLING (3.35%)
TEXAS ALTERNATIVE GRASSER, INC.(0.20%)
FARR FOUNDATION, INC.(0.63%)
Contract # 05123244
Totals 3274968.45 149838.00 2083833.63 63.6

CountyBROWN
Highway US 84
From NEAR TURTLE CREEK RD IN EARLY
To FM 2126
CSJ 0054-07-067
Proj ID NH 2012(597)
Work Type WDN SUBGRADE, BASE, SURF, STR, C & G
 
1.485 3857205.46 108282.39 940410.99 24.3
CountyBROWN
Highway CS
From US 84
To BUFFALO TRAIL
CSJ 0923-06-063
Proj ID CC 923-6-63
Work Type CONSTRUCT STORM DRAIN
 
0.200 62370.91 26240.00 45563.71 73.0
Work Order 08-16-12
Work Began 11-26-12
Work Completed  
Time Computed 11-14-12
Contract Working Days 293
Addl Days Granted 0
Working Days Charged 109
Percent Time Used 37
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-07-067
BEAR CREEK CONSTRUCTION, LLC ( 11.28%)
D. I. J. CONSTRUCTION, INC.(1.00%)
HJC FARMS, INC.(0.76%)
KARMY CONSTRUCTION INC (3.70%)
TEXAS ALTERNATIVE GRASSER, INC.(0.34%)
WILLIS ELECTRIC CO., LP(2.00%)
Contract # 06123027
Totals 3919576.37 134522.39 985974.70 25.1

CountyMILLS
Highway US 84
From BROWN C/L
To FM 573
CSJ 0054-08-026
Proj ID C 54-8-26
Work Type ADD PASSING LANES
 
17.087 2644309.18 260661.10 1812415.98 68.5
Work Order 07-12-12
Work Began 09-17-12
Work Completed  
Time Computed 07-28-12
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 135
Percent Time Used 80
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-08-026
RICE ENVIRONMENTAL SERVICES(3.25%)
SAN-ANN-CO., INC.(0.59%)
D. I. J. CONSTRUCTION, INC.(3.68%)
J & M CONTRACTING, COMPANY (8.65%)
Contract # 06123218
Totals 2644309.18 260661.10 1812415.98 68.5

CountyBROWN
Highway US 377 ETC
From 0.22 MI. S OF FM 45
To MCCULLOCH C/L
CSJ 0128-01-102
Proj ID STP 2013(200)
Work Type SEAL COAT
 
223.095 6328262.87 88760.70 122808.99 1.9
Work Order 12-03-12
Work Began 00-00-00
Work Completed  
Time Computed 05-27-13
Contract Working Days 83
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0128-01-102
FLASHER EQUIPMENT COMPANY(1.35%)
D. I. J. CONSTRUCTION, INC.(5.27%)
Contract # 11123006
Totals 6328262.87 88760.70 122808.99 1.9

CountyLAMPASAS
Highway SL 257
From US 281, EAST
To SULPHUR CREEK
CSJ 0231-17-009
Proj ID STP 2012(498)
Work Type GRADING, PVMT, C & G, STORM DRAIN, SU
 
0.493 2705592.72 152379.95 1575056.52 58.2
CountyLAMPASAS
Highway SL 257
From US 281, EAST
To SULPHUR CREEK
CSJ 0231-17-011
Proj ID STP 2010(017)
Work Type ROW UTL. ADJ.
 
0.001 539600.00 103025.00 396016.79 73.3
Work Order 06-21-12
Work Began 10-01-12
Work Completed  
Time Computed 08-21-12
Contract Working Days 299
Addl Days Granted 2
Working Days Charged 145
Percent Time Used 48
Contractor(s)
LEDCOR CMI INC.
SUBCONTRACTOR(S) FOR CCSJ: 0231-17-009
TACH SERVICES, INC.(1.08%)
FUQUAY, INC. (0.58%)
HIGHWAY TECHNOLOGIES, INC. (0.69%)
J.D. RAMMING PAVING CO., LTD.( 21.20%)
WOLFF CONSTRUCTION ( 10.09%)
G. CARTER CONSTRUCTION COMPANY, INC. (4.11%)
Contract # 05123232
Totals 3245192.72 255404.95 1971073.31 60.7

CountyLAMPASAS
Highway US 183
From US 190, S OF LOMETA
To US 281 N OF LAMPASAS
CSJ 0272-06-036
Proj ID C 272-6-36
Work Type ADD PASSING LANES
 
12.820 2650390.65 124511.67 1491818.72 56.2
Work Order 08-10-12
Work Began 08-29-12
Work Completed  
Time Computed 08-26-12
Contract Working Days 163
Addl Days Granted 0
Working Days Charged 143
Percent Time Used 87
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0272-06-036
D. I. J. CONSTRUCTION, INC.(5.07%)
BEAR CREEK CONSTRUCTION, LLC (7.72%)
RICE ENVIRONMENTAL SERVICES(1.14%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.08%)
ROADWAY SPECIALTIES, INC.(1.24%)
JOY LATTIMER, LLC. (1.13%)
TEX OP CONSTRUCTION, LP(0.45%)
Contract # 06123015
Totals 2650390.65 124511.67 1491818.72 56.2

CountySTEPHENS
Highway FM 717
From US 180
To EASTLAND C/L
CSJ 0714-03-022
Proj ID STP 2013(005)HES
Work Type PROVIDE ADD'L PAVED SURFACE WIDTH
 
15.126 2554818.37 137187.82 712475.72 27.8
Work Order 10-04-12
Work Began 10-11-12
Work Completed  
Time Computed 10-11-12
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 69
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0714-03-022
D. I. J. CONSTRUCTION, INC.(3.61%)
HIGHWAY TECHNOLOGIES, INC. (0.76%)
HJC FARMS, INC.(4.83%)
J.V. CONCRETE CONSTRUCTION ( 19.27%)
Contract # 09123242
Totals 2554818.37 137187.82 712475.72 27.8

CountyBROWN
Highway VA
From VARIOUS LOCATIONS
To .
CSJ 0923-00-057
Proj ID STP 2012(556)
Work Type ADA CURB RAMPS
 
1.000 967700.00 2916.39 933273.22 96.4
Work Order 06-14-12
Work Began 08-13-12
Work Completed  
Time Computed 09-17-12
Contract Working Days 162
Addl Days Granted 0
Working Days Charged 128
Percent Time Used 79
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-00-057
WILLIS ELECTRIC CO., LP(0.50%)
Contract # 05123009
Totals 967700.00 2916.39 933273.22 96.4

CountyBROWN
Highway CS
From US 67
To US 183
CSJ 0923-06-061
Proj ID C 923-6-61
Work Type CONSTRUCT NEW 2 LANE ROADWAY
 
0.320 726589.36 45233.28 588364.35 80.9
Work Order 07-12-12
Work Began 12-17-12
Work Completed  
Time Computed 07-28-12
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 76
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-06-061
BEAR CREEK CONSTRUCTION, LLC (7.71%)
D. I. J. CONSTRUCTION, INC.(1.13%)
KARMY CONSTRUCTION INC (6.29%)
TEXAS ALTERNATIVE GRASSER, INC.(0.49%)
Contract # 06123206
Totals 726589.36 45233.28 588364.35 80.9

CountySAN SABA
Highway CR
From ON CR 204 AT SAN SABA RIVER
To .
CSJ 0923-25-011
Proj ID BR 96(325)
Work Type REHAB STRUCTURE
 
0.100 849397.20 108459.71 577597.18 68.0
Work Order 06-15-12
Work Began 10-29-12
Work Completed  
Time Computed 09-13-12
Contract Working Days 120
Addl Days Granted 5
Working Days Charged 109
Percent Time Used 87
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0923-25-011
SAN-ANN-CO., INC.(0.32%)
BLACKTOPPER TECHNOLOGY, INC. (2.47%)
W. W. FOUNDATION DRILLING, LTD.(5.00%)
TEXAS BRIDGE, INC. ( 17.07%)
FORTSON CONTRACTING, INC.(1.51%)
SHINN & GREGORY, INC.(0.00%)
Contract # 05123044
Totals 849397.20 108459.71 577597.18 68.0

CountySAN SABA
Highway CS
From ON US 190 FROM .05 MI. W OF FM 1031
To 0.3 MI. E OF FM 1031
CSJ 0923-25-021
Proj ID NH 2013(661)
Work Type LANDSCAPE DEVELOPMENT
 
0.100 120270.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-25-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133032
Totals 120270.00 0.00 0.00 0.0

CountyLAMPASAS
Highway FM 580
From NEAR FM 2313
To CORYELL C/L
CSJ 1032-01-032
Proj ID STP 2013(006)HES
Work Type PROVIDE ADD'L PAVED SURFACE WIDTH
 
9.385 2683160.90 198634.98 626581.65 23.3
Work Order 11-30-12
Work Began 01-14-13
Work Completed  
Time Computed 02-28-13
Contract Working Days 193
Addl Days Granted 0
Working Days Charged 70
Percent Time Used 36
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1032-01-032
D. I. J. CONSTRUCTION, INC.(2.45%)
R K STEPHENS CONSTRUCTION, LLC ( 13.45%)
RPV CONSTRUCTION (3.37%)
ROADWAY SPECIALTIES, INC.(0.84%)
SAN-ANN-CO., INC.(2.29%)
TEXAS ALTERNATIVE GRASSER, INC.(0.60%)
Contract # 09123231
Totals 2683160.90 198634.98 626581.65 23.3

CountyCOMANCHE
Highway FM 1476
From AT MUSTANG CREEK
To .
CSJ 1039-01-033
Proj ID BR 2013(378)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.085 538202.00 0.00 0.00 0.0
CountyCOMANCHE
Highway FM 1476
From AT WALNUT CREEK
To .
CSJ 1039-01-034
Proj ID BR 2013(378)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.094 410117.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-26-13
Work Began 00-00-00
Work Completed  
Time Computed 06-03-13
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1039-01-033
HOUSTON SAWING & DRILLING(0.23%)
ODUM SERVICES, L.P.(3.70%)
PAVEMENT MARKINGS INC. (1.04%)
TEXAS ALTERNATIVE GRASSER, INC.(0.31%)
Contract # 02133008
Totals 948319.00 0.00 0.00 0.0

CountyBROWN
Highway FM 2524
From NORWOOD
To BROOKS STREET
CSJ 2377-01-039
Proj ID STP 2013(525)
Work Type REHABILITATE EXISTING ROAD
 
1.026 4394292.98 0.00 0.00 0.0
CountyBROWN
Highway FM 2524
From NORWOOD
To BROOKS STREET
CSJ 2377-01-044
Proj ID STP 2013(512)
Work Type ROW ACQ., RELO. ASSIST. & UTIL ADJ.
 
1.074 300464.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 291
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2377-01-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133205
Totals 4694756.98 0.00 0.00 0.0

CountyLAMPASAS
Highway FM 2657
From 0.412 MI. S OF US 190
To FM 2808
CSJ 2786-01-010
Proj ID C 2786-1-10
Work Type WIDEN, GRADING, STRS, BASE, AND SUR
 
2.639 6233124.09 166936.37 3258118.56 52.2
Work Order 08-20-12
Work Began 09-05-12
Work Completed  
Time Computed 09-17-12
Contract Working Days 327
Addl Days Granted 5
Working Days Charged 133
Percent Time Used 40
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2786-01-010
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.85%)
D. I. J. CONSTRUCTION, INC.(1.12%)
TACH SERVICES, INC.(0.33%)
TEXAS ALTERNATIVE GRASSER, INC.(0.16%)
WILLIS ELECTRIC CO., LP(2.40%)
Contract # 06123214
Totals 6233124.09 166936.37 3258118.56 52.2

page 1