Monthly State Let Construction Report For Brownwood District As Of Jul 14, 2017 Page 1 Of 2

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEASTLAND
HighwayIH 20
From0.17 MI W OF SH 206
ToSH 206
CSJ0007-03-093
Proj IDNH 1702(176)
Work TypeRECONSTRUCT FRONTAGE ROAD
 
0.171192955.500.000.0
CountyEASTLAND
HighwaySH 206
FromIH 20, S
To0.246 MI SOUTH OF IH 20
CSJ2638-01-023
Proj IDSTP 1702(177)
Work TypeRECONSTRUCT ROADWAY
 
0.246519768.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-22-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days43
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0007-03-093
HJC FARMS, INC. (0.80)
TOTAL HIGHWAY MAINTENANCE, LLC (2.49)
Contract #04173236
Totals712723.500.000.000.0

CountyEASTLAND
HighwayIH 20
FromAT 0.5 MI. W OF FM 571 AND ALSO AT
To2.5 MI. W OF SH 16
CSJ0007-06-070
Proj IDSTP 2005(276)TEG
Work TypeCONSTRUCT TWO SAFETY REST AREAS
 
3.11916358386.5816466163.6299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-04-13
Work Began02-01-13
Work Completed
Time Computed01-20-13
Contract Working Days415
Addl Days Granted180
Working Days Charged628
Percent Time Used105
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-070
EROSION CONTROL MANAGEMENT SERVICES (0.83)
ABILENE SHEET METAL (1.43)
CURTIS MECHANICAL CONTRACTORS, INC. (2.10)
GRIZZLY GLASS & MIRROR, INC. (1.01)
LONE OAK LANDSCAPE LLC (0.38)
LONE STAR BARRIER SERVICES, LLC (0.66)
PEACHTREE CONSTRUCTION, LTD. (4.79)
SCR CONSTRUCTION CO., INC. (0.18)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42)
TIPPENN FABRICATION & ERECTION (5.06)
ALVAREZ DRYWALL & ACCOUSTICS, INC. (0.57)
BUFFALO GAP INSTRUMENTATION AND ELECTRICAL CO., INC. (9.53)
CORPUS CHRISTI STAMP WORKS, INC. (0.05)
FINLEY TERMITE AND PEST CONTROL, INC. (0.01)
SOLID ROCK LAWN & LANDSCAPE (0.21)
TEX OP CONSTRUCTION, LP (0.20)
GOMEZ FLOOR COVERING, INC. (1.55)
ENNIS ROOFING AND CONSTRUCTION, L.L.C. (2.07)
B.A.D.J., INC. DBA THE TOPSPOT (0.21)
WILKS MASONRY CORPORATION (4.34)
LIBERTY PAINTING & DRYWALL (0.65)
HUNTER KNEPSHIELD COMPANY (0.73)
CLLA GROUP, LLC (1.46)
AMERITEX FLAG & FLAGPOLE, LLC (0.03)
A & A CONSTRUCTION (0.26)
LIBERTY PAINTING & DRYWALL (0.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.11)
CONROE WOOD PRODUCTS INC. (0.00)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
SAR TRANSPORTATION, LLC (0.00)
CHAMPION FUEL SOLUTIONS (0.00)
Contract #10123203
Totals16358386.580.0016466163.6299.9

CountySTEPHENS
HighwayUS 180
From0.47 MI. E OF SHACKELFORD C/L
To0.77 MI. E OF FM 3201
CSJ0011-07-047
Proj IDSTP 1302(081)
Work TypeBASE OVERLAY,2CST,ADD PASSING LANES
 
4.4524046707.374322572.0599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-03-16
Work Began04-04-16
Work Completed
Time Computed00-00-00
Contract Working Days175
Addl Days Granted40
Working Days Charged216
Percent Time Used100
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-07-047
CONTRACTORS SERVICE COMPANY (0.45)
MARCOM"S MOWING SERVICE, LLC (1.03)
STRIPING TECHNOLOGY, L.P. (2.46)
W.S. CONSTRUCTION COMPANY (5.18)
STRIPING SYSTEMS, INC. (0.03)
Contract #11153222
Totals4046707.3742982.794322572.0599.9

CountySTEPHENS
HighwayUS 180
From@ HUBBARD CREEK LAKE BRIDGE
To.
CSJ0011-07-051
Proj IDBR 1702(472)
Work TypeREHAB BRIDGE
 
0.7002875191.470.000.0
CountySTEPHENS
HighwayUS 180
FromAT SOUR BRANCH BRIDGE
To.
CSJ0011-09-070
Proj IDBR 1702(472)
Work TypeREHAB BRIDGE
 
0.020363962.600.000.0
CountySTEPHENS
HighwayUS 183
FromAT SNAKE DEN CREEK
To.
CSJ0404-02-039
Proj IDBR 1702(472)
Work TypeREPLACE BRIDGE RAIL
 
0.100244990.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days199
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-07-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173038
Totals3484144.570.000.000.0

CountySTEPHENS
HighwayUS 180
FromGONZALES CREEK
ToFM 287
CSJ0011-08-026
Proj IDSTP 1602(051)
Work TypeRECONSTRUCT URBAN ROADWAY
 
5.12913412991.585231998.1539.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-16
Work Began09-15-16
Work Completed
Time Computed00-00-00
Contract Working Days459
Addl Days Granted6
Working Days Charged160
Percent Time Used34
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-08-026
CHEROKEE SERVICES (0.17)
D. I. J. CONSTRUCTION, INC. (1.17)
GIBSON & ASSOCIATES, INC. (0.66)
HJC FARMS, INC. (0.63)
J&M CONTRACTING COMPANY (14.52)
PENHALL COMPANY (0.08)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.49)
WILLIS ELECTRIC CO., LP (2.37)
FAMBRO CONSTRUCTION, INC. (12.03)
NELSON INDUSTRIAL SERVICES, INC. (0.05)
Contract #05163002
Totals13412991.58154526.275231998.1539.0

CountyCOLEMAN ETC
HighwayUS 67 ETC
FromBROWN C/L
To0.1 MI. N OF US 67
CSJ0054-04-107
Proj IDNH 2017(262)
Work TypeSEAL COAT
 
203.0676367226.544674617.4673.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-07-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged22
Percent Time Used30
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-04-107
COX PAVING OF TEXAS, INC. (7.18)
BARRICADES PLUS, LLC (1.80)
FLAT LINE, INC. (7.34)
Contract #11163026
Totals6367226.544674617.464674617.4673.4

CountyBROWN
HighwayUS 67
From0.5 MI. W OF FM 3254
ToCR 152
CSJ0054-06-097
Proj IDNH 2017(369)
Work TypeREHABILITATE EXISTING ROADWAY
 
3.0553342055.981605246.8148.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-22-17
Work Began04-17-17
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged45
Percent Time Used66
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0054-06-097
ALTUS TRAFFIC MANAGEMENT LLC (0.21)
TEXOP CONSTRUCTION (2.92)
FLASHER EQUIPMENT COMPANY (0.90)
TEXAS ALTERNATIVE GRASSER, INC. (0.19)
PENHALL COMPANY (0.20)
Contract #01173010
Totals3342055.98531809.811605246.8148.0

CountyBROWN
HighwayUS 84
FromAT FT. WORTH & WESTERN RAILROAD
To.
CSJ0054-07-069
Proj IDSTP 1302(079)RGS
Work TypeRAILROAD BRIDGE REPLACEMENT
 
0.5208488149.703786068.4444.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-16
Work Began09-07-16
Work Completed
Time Computed00-00-00
Contract Working Days400
Addl Days Granted0
Working Days Charged170
Percent Time Used42
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-07-069
GRANBURY EXCAVATING, INC. (24.57)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.30)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.86)
TEXAS SHAFTS, INC. (4.37)
ODUM SERVICES, L.P. (0.58)
MCL CONTRACTING, LLC (0.25)
CHOCTAW ERECTORS, INC. (2.69)
TEXAS HIGHWAY MAINTENANCE, LLC (0.81)
Contract #02163207
Totals8488149.7047042.933786068.4444.6

CountyMCCULLOCH ETC
HighwayUS 87 ETC
From1.2 MI N OF FM 1955
ToMASON CO LINE
CSJ0071-02-032
Proj IDSTP 2017(864)HES
Work TypePROFILE EDGELINE&CENTERLINE MARKING
 
73.350285999.9914224.264.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-19-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged20
Percent Time Used29
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0071-02-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173024
Totals285999.9914224.2614224.264.9

CountyCOLEMAN
HighwayUS 67
FromSH 206
To.584 MI W OF CR 368
CSJ0078-03-055
Proj IDSTP 2017(457)HES
Work TypeIMPRV GR, SFT TREAT OBJECTS, ADD PA
 
8.2471678694.19138335.008.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-10-17
Work Began04-17-17
Work Completed
Time Computed00-00-00
Contract Working Days187
Addl Days Granted0
Working Days Charged49
Percent Time Used26
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0078-03-055
CONTRACTORS SERVICE COMPANY (0.93)
DOUBLE A CONTRACTING, L.P. (2.72)
HJC FARMS, INC. (3.55)
TEXOP CONSTRUCTION (2.05)
Contract #01173215
Totals1678694.191600.00138335.008.2

CountyEASTLAND
HighwayUS 183
FromIH 20
ToCR 181
CSJ0127-01-030
Proj IDSTP 1702(236)
Work TypeADD PASSING LANES
 
4.2433372833.810.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-21-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days221
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0127-01-030
D.I.J. CONSTRUCTION, INC (1.86)
GIBSON & ASSOCIATES, INC. (2.02)
HJC FARMS, INC. (3.06)
LUZ LERMA CONSTRUCTION, INC. (2.01)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.24)
TEXAS ALTERNATIVE GRASSER, INC. (0.30)
Contract #05173045
Totals3372833.810.000.000.0

CountyEASTLAND
HighwayUS 183
From0.599 MI. N
ToBROWN C/L
CSJ0127-02-140
Proj IDSTP 2015(785)
Work TypeADD PASSING LANES
 
0.246113364.13108564.5995.7
CountyBROWN
HighwayUS 183
FromEASTLAND C/L
ToFM 1467
CSJ0127-03-031
Proj IDSTP 2015(785)
Work TypeADD PASSING LANES
 
7.8862377048.462128825.2092.8
CountyBROWN
HighwayUS 183
FromFM 1467
To3.6 MI N OF US 67(NEAR BWD AIRPORT)
CSJ0127-04-032
Proj IDSTP 1502(143)HES
Work TypeADD PASSING LANES
 
2.9851788921.691722210.0996.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-11-15
Work Began12-15-15
Work Completed
Time Computed00-00-00
Contract Working Days168
Addl Days Granted0
Working Days Charged248
Percent Time Used147
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0127-02-140
D. I. J. CONSTRUCTION, INC. (3.35)
TEXAS ALTERNATIVE GRASSER, INC. (0.29)
HJC FARMS, INC. (1.37)
NORTH EASTERN PAVERS (23.51)
RAMBO CONTRACTING, INC. (3.20)
TEXOP CONSTRUCTION (0.84)
Contract #04153259
Totals4279334.28129767.963959599.8894.3

CountyMCCULLOCH
HighwayUS 190
FromUS 87
ToUS 377
CSJ0128-04-035
Proj IDSTP 2017(458)
Work TypeRECONSTRUCT URBAN ROAD
 
17.62613787872.970.000.0
CountyMCCULLOCH
HighwayUS 190
FromUS 87
ToUS 377
CSJ0128-04-036
Proj IDROW 128-4-36
Work TypeROW ACQUISITION
 
0.8803687328.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days636
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0128-04-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173207
Totals17475201.620.000.000.0

CountySAN SABA
HighwayFM 580
FromUS 190
ToLAMPASAS C/L
CSJ0231-14-017
Proj IDSTP 2015(389)HES
Work TypeADD'L PAVED SURF WIDTH, WDN STRS
 
14.1445387952.965687254.9399.9
Work Order03-13-15
Work Began06-23-15
Work Completed
Time Computed06-11-15
Contract Working Days474
Addl Days Granted0
Working Days Charged432
Percent Time Used91
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0231-14-017
D. I. J. CONSTRUCTION, INC. (2.05)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.37)
PRIMATE CONSTRUCTION, INC. (0.14)
ROADWAY SPECIALTIES, INC. (4.88)
SAN-ANN-CO., INC. (0.99)
TEXAS ALTERNATIVE GRASSER, INC. (0.47)
BROCK CONSTRUCTION, LLC (0.30)
WOLFE CONSTRUCTION GROUP, INC. (0.09)
Contract #01153225
Totals5387952.96112743.415687254.9399.9

CountySTEPHENS
HighwayUS 183
FromUS 180
ToBRECKENRIDGE SCL
CSJ0257-01-041
Proj IDSTP 1602(303)
Work TypeREHABILITATE EXISTING ROADWAY
 
0.7343157515.040.000.0
CountySTEPHENS
HighwayUS 183
FromUS 180
ToBRECKENRIDGE SCL
CSJ0257-01-044
Proj IDROW 257-1-44
Work TypeUTILITY ADJUSTMENTS
 
0.734580454.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-22-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days238
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0257-01-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173226
Totals3737969.440.000.000.0

CountyMCCULLOCH
HighwayUS 190
FromUS 377
ToSAN SABA C/L
CSJ0272-01-031
Proj IDSTP 2016(924)HES
Work TypeUPGRADE GUARDRAIL & SFTY TREAT STRS
 
17.1741084525.501024927.6394.5
CountySAN SABA
HighwayFM 45
FromMILLS C/L
ToRICHLAND SPRINGS NORTH CITY LIMIT
CSJ0480-08-023
Proj IDSTP 2016(925)HRR
Work TypeUPGRADE GUARDRAIL & SFTY TREAT STRS
 
12.071714070.00685727.3496.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-03-16
Work Began08-08-16
Work Completed
Time Computed00-00-00
Contract Working Days230
Addl Days Granted0
Working Days Charged202
Percent Time Used87
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0272-01-031
ODUM SERVICES, L.P. (19.21)
Contract #04163025
Totals1798595.5053120.331710654.9795.1

CountyMILLS
HighwaySH 16
From.021 MI SW OF BARROW ST
ToSAN SABA COUNTY LINE
CSJ0289-03-026
Proj IDSTP 2017(445)HES
Work TypeIMPRV GR, SFT TREAT FIXED, ADD PASS
 
9.2411203835.85832857.8169.1
CountyBURNET
HighwayFM 1478
FromLAMPASAS C/L
To7.096 MI. S OF LAMPASAS C/L
CSJ2206-02-006
Proj IDSTP 2017(471)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
7.096353795.0252170.0114.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-17
Work Began03-21-17
Work Completed
Time Computed00-00-00
Contract Working Days187
Addl Days Granted0
Working Days Charged65
Percent Time Used34
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0289-03-026
FLASHER EQUIPMENT COMPANY (1.87)
WOLFE CONSTRUCTION GROUP, INC. (0.57)
STRIPE-A-ZONE, INC. (1.55)
JE CASEY, LLC (9.79)
Contract #01173213
Totals1557630.87204594.00885027.8256.8

CountyMILLS
HighwayFM 45
FromBROWN C/L
ToSAN SABA C/L
CSJ0480-07-009
Proj IDSTP 1602(052)
Work TypeGRADING, STRUCTURES, BASE, AND SURF
 
4.3624563803.882660918.1358.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-16
Work Began09-06-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted6
Working Days Charged172
Percent Time Used65
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0480-07-009
D.I.J. CONSTRUCTION, INC (1.28)
TEXAS ALTERNATIVE GRASSER, INC. (0.60)
HJC FARMS, INC. (0.95)
J&M CONTRACTING COMPANY (14.23)
Contract #05163004
Totals4563803.88210707.732660918.1358.3

CountyEASTLAND
HighwayFM 8
From0.273 MI. E OF FM 2214
To0.06 MI. W OF HOG CREEK
CSJ0550-01-023
Proj IDSTP 2014(544)
Work TypeGRADING, STRS, FLEX BASE, AND SURF
 
0.322458987.68396528.0486.3
CountyEASTLAND
HighwayFM 2214
From0.5 MI E OF FM 571
ToFM 8
CSJ1697-02-019
Proj IDSTP 2014(544)
Work TypeGRADING, STRS, FLEX BASE AND SURFAC
 
4.7014840589.805752675.0299.9
Work Order08-07-14
Work Began01-06-15
Work Completed
Time Computed12-10-14
Contract Working Days272
Addl Days Granted31
Working Days Charged446
Percent Time Used147
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0550-01-023
MARCOM"S MOWING SERVICE, LLC (0.49)
NORTH EASTERN PAVERS (11.45)
S & S BRIDGE PAINTING, INC. (0.55)
TEXAS ALTERNATIVE GRASSER, INC. (0.62)
TOTAL HIGHWAY MAINTENANCE, LLC (1.37)
WILLIS ELECTRIC CO., LP (2.05)
SHINN & GREGORY, INC. (0.48)
EROSION CONTROL MANAGEMENT SERVICES (0.61)
ELLIS-MCGINNIS CONSTRUCTION CO. (3.96)
D.I.J. CONSTRUCTION, INC (0.30)
Contract #05143002
Totals5299577.4846344.376149203.0699.9

CountyBROWN
HighwayCS
FromON SUDDERTH DR, SUNRISE, MCCULLOGH
ToDR, AND EAST RIVER OAKS AND INEZ ST
CSJ0923-06-075
Proj IDSTP 2017(214)TAPS
Work TypeCNSTR BIKE/ PED PATH
 
0.100427889.9860618.0014.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-28-17
Work Began06-01-17
Work Completed
Time Computed00-00-00
Contract Working Days63
Addl Days Granted0
Working Days Charged28
Percent Time Used44
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-06-075
CONTRACTORS SERVICE COMPANY (2.10)
Contract #03173227
Totals427889.9860618.0060618.0014.1

page 1 | page 2