|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | EASTLAND |
| Highway |
IH 20 |
| From |
AT 0.5 MI. W OF FM 571 AND ALSO AT |
| To |
2.5 MI. W OF SH 16 |
| CSJ |
0007-06-070 |
| Proj ID |
STP 2005(276)TEG |
| Work Type |
CONSTRUCT TWO SAFETY REST AREAS |
| |
|
3.119 |
16358386.58 |
134145.99 |
1003429.06 |
6.1 |
| Work Order |
01-04-13 |
| Work Began |
02-01-13 |
| Work Completed |
|
| Time Computed |
01-20-13 |
| Contract Working Days |
415 |
| Addl Days Granted |
0 |
| Working Days Charged |
55 |
| Percent Time Used |
13 |
| Contractor(s) |
| JAY MILLS CONTRACTING, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-070 EROSION CONTROL MANAGEMENT SERVICES(0.83%) ABILENE SHEET METAL(1.43%) CURTIS MECHANICAL CONTRACTORS, INC.(2.10%) GRIZZLY GLASS & MIRROR, INC. (1.01%) LONE OAK LANDSCAPE LLC (0.38%) LONE STAR BARRIER SERVICES, LLC(0.66%) PEACHTREE CONSTRUCTION, LTD. (4.79%) SCR CONSTRUCTION CO., INC. (0.18%) TOTAL HIGHWAY MAINTENANCE, LLC (0.42%) TIPPENN FABRICATION & ERECTION (5.06%) ALVAREZ DRYWALL & ACCOUSTICS, INC. (0.57%) BUFFALO GAP INSTRUMENTATION AND ELECTRICAL CO., INC. (9.53%) CORPUS CHRISTI STAMP WORKS, INC. (0.05%) FINLEY TERMITE AND PEST CONTROL, INC.(0.01%) SOLID ROCK LAWN & LANDSCAPE(0.21%) TEX OP CONSTRUCTION, LP(0.20%) GOMEZ FLOOR COVERING, INC. (1.55%) ENNIS ROOFING AND CONSTRUCTION, L.L.C. (2.07%) B.A.D.J., INC. DBA THE TOPSPOT (0.21%) WILKS MASONRY CORPORATION(4.34%) LIBERTY PAINTING & DRYWALL (0.65%) HUNTER KNEPSHIELD COMPANY(0.73%)
|
| Contract # |
10123203 |
|
Totals |
16358386.58 |
134145.99 |
1003429.06 |
6.1 |
|
| County | SHACKELFORD |
| Highway |
US 180 |
| From |
0.39 MI W OF STEPHENS CL |
| To |
STEPHENS CL |
| CSJ |
0011-06-043 |
| Proj ID |
BR 2012(555) |
| Work Type |
REPLACE BRIDGE APPROACH |
| |
|
0.379 |
435784.60 |
0.00 |
234928.20 |
53.9 |
| County | STEPHENS |
| Highway |
US 180 |
| From |
SHAKELFORD CL |
| To |
0.47 MI EAST |
| CSJ |
0011-07-046 |
| Proj ID |
BR 2012(555) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.473 |
2839183.85 |
149838.00 |
1848905.43 |
65.1 |
| Work Order |
06-14-12 |
| Work Began |
08-07-12 |
| Work Completed |
|
| Time Computed |
09-12-12 |
| Contract Working Days |
251 |
| Addl Days Granted |
0 |
| Working Days Charged |
181 |
| Percent Time Used |
72 |
| Contractor(s) |
| HODGES AND SON CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0011-07-046 CONTRACTORS SERVICE COMPANY(0.35%) DUSTY ALLEN, INC.(2.26%) HIGHWAY TECHNOLOGIES, INC. (1.38%) HOUSTON SAWING & DRILLING(0.09%) STREET FOUNDATION DRILLING (3.35%) TEXAS ALTERNATIVE GRASSER, INC.(0.20%) FARR FOUNDATION, INC.(0.63%)
|
| Contract # |
05123244 |
|
Totals |
3274968.45 |
149838.00 |
2083833.63 |
63.6 |
|
| County | BROWN |
| Highway |
US 84 |
| From |
NEAR TURTLE CREEK RD IN EARLY |
| To |
FM 2126 |
| CSJ |
0054-07-067 |
| Proj ID |
NH 2012(597) |
| Work Type |
WDN SUBGRADE, BASE, SURF, STR, C & G |
| |
|
1.485 |
3857205.46 |
108282.39 |
940410.99 |
24.3 |
| County | BROWN |
| Highway |
CS |
| From |
US 84 |
| To |
BUFFALO TRAIL |
| CSJ |
0923-06-063 |
| Proj ID |
CC 923-6-63 |
| Work Type |
CONSTRUCT STORM DRAIN |
| |
|
0.200 |
62370.91 |
26240.00 |
45563.71 |
73.0 |
| Work Order |
08-16-12 |
| Work Began |
11-26-12 |
| Work Completed |
|
| Time Computed |
11-14-12 |
| Contract Working Days |
293 |
| Addl Days Granted |
0 |
| Working Days Charged |
109 |
| Percent Time Used |
37 |
| Contractor(s) |
| PRATER EQUIPMENT CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0054-07-067 BEAR CREEK CONSTRUCTION, LLC ( 11.28%) D. I. J. CONSTRUCTION, INC.(1.00%) HJC FARMS, INC.(0.76%) KARMY CONSTRUCTION INC (3.70%) TEXAS ALTERNATIVE GRASSER, INC.(0.34%) WILLIS ELECTRIC CO., LP(2.00%)
|
| Contract # |
06123027 |
|
Totals |
3919576.37 |
134522.39 |
985974.70 |
25.1 |
|
| County | MILLS |
| Highway |
US 84 |
| From |
BROWN C/L |
| To |
FM 573 |
| CSJ |
0054-08-026 |
| Proj ID |
C 54-8-26 |
| Work Type |
ADD PASSING LANES |
| |
|
17.087 |
2644309.18 |
260661.10 |
1812415.98 |
68.5 |
| Work Order |
07-12-12 |
| Work Began |
09-17-12 |
| Work Completed |
|
| Time Computed |
07-28-12 |
| Contract Working Days |
168 |
| Addl Days Granted |
0 |
| Working Days Charged |
135 |
| Percent Time Used |
80 |
| Contractor(s) |
| PRATER EQUIPMENT CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0054-08-026 RICE ENVIRONMENTAL SERVICES(3.25%) SAN-ANN-CO., INC.(0.59%) D. I. J. CONSTRUCTION, INC.(3.68%) J & M CONTRACTING, COMPANY (8.65%)
|
| Contract # |
06123218 |
|
Totals |
2644309.18 |
260661.10 |
1812415.98 |
68.5 |
|
| County | BROWN |
| Highway |
US 377 ETC |
| From |
0.22 MI. S OF FM 45 |
| To |
MCCULLOCH C/L |
| CSJ |
0128-01-102 |
| Proj ID |
STP 2013(200) |
| Work Type |
SEAL COAT |
| |
|
223.095 |
6328262.87 |
88760.70 |
122808.99 |
1.9 |
| Work Order |
12-03-12 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
05-27-13 |
| Contract Working Days |
83 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| RONALD R. WAGNER & CO., LP |
SUBCONTRACTOR(S) FOR CCSJ: 0128-01-102 FLASHER EQUIPMENT COMPANY(1.35%) D. I. J. CONSTRUCTION, INC.(5.27%)
|
| Contract # |
11123006 |
|
Totals |
6328262.87 |
88760.70 |
122808.99 |
1.9 |
|
| County | LAMPASAS |
| Highway |
SL 257 |
| From |
US 281, EAST |
| To |
SULPHUR CREEK |
| CSJ |
0231-17-009 |
| Proj ID |
STP 2012(498) |
| Work Type |
GRADING, PVMT, C & G, STORM DRAIN, SU |
| |
|
0.493 |
2705592.72 |
152379.95 |
1575056.52 |
58.2 |
| County | LAMPASAS |
| Highway |
SL 257 |
| From |
US 281, EAST |
| To |
SULPHUR CREEK |
| CSJ |
0231-17-011 |
| Proj ID |
STP 2010(017) |
| Work Type |
ROW UTL. ADJ. |
| |
|
0.001 |
539600.00 |
103025.00 |
396016.79 |
73.3 |
| Work Order |
06-21-12 |
| Work Began |
10-01-12 |
| Work Completed |
|
| Time Computed |
08-21-12 |
| Contract Working Days |
299 |
| Addl Days Granted |
2 |
| Working Days Charged |
145 |
| Percent Time Used |
48 |
| Contractor(s) |
| LEDCOR CMI INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0231-17-009 TACH SERVICES, INC.(1.08%) FUQUAY, INC. (0.58%) HIGHWAY TECHNOLOGIES, INC. (0.69%) J.D. RAMMING PAVING CO., LTD.( 21.20%) WOLFF CONSTRUCTION ( 10.09%) G. CARTER CONSTRUCTION COMPANY, INC. (4.11%)
|
| Contract # |
05123232 |
|
Totals |
3245192.72 |
255404.95 |
1971073.31 |
60.7 |
|
| County | LAMPASAS |
| Highway |
US 183 |
| From |
US 190, S OF LOMETA |
| To |
US 281 N OF LAMPASAS |
| CSJ |
0272-06-036 |
| Proj ID |
C 272-6-36 |
| Work Type |
ADD PASSING LANES |
| |
|
12.820 |
2650390.65 |
124511.67 |
1491818.72 |
56.2 |
| Work Order |
08-10-12 |
| Work Began |
08-29-12 |
| Work Completed |
|
| Time Computed |
08-26-12 |
| Contract Working Days |
163 |
| Addl Days Granted |
0 |
| Working Days Charged |
143 |
| Percent Time Used |
87 |
| Contractor(s) |
| KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 0272-06-036 D. I. J. CONSTRUCTION, INC.(5.07%) BEAR CREEK CONSTRUCTION, LLC (7.72%) RICE ENVIRONMENTAL SERVICES(1.14%) N-LINE TRAFFIC MAINTENANCE, L.P. (1.08%) ROADWAY SPECIALTIES, INC.(1.24%) JOY LATTIMER, LLC. (1.13%) TEX OP CONSTRUCTION, LP(0.45%)
|
| Contract # |
06123015 |
|
Totals |
2650390.65 |
124511.67 |
1491818.72 |
56.2 |
|
| County | STEPHENS |
| Highway |
FM 717 |
| From |
US 180 |
| To |
EASTLAND C/L |
| CSJ |
0714-03-022 |
| Proj ID |
STP 2013(005)HES |
| Work Type |
PROVIDE ADD'L PAVED SURFACE WIDTH |
| |
|
15.126 |
2554818.37 |
137187.82 |
712475.72 |
27.8 |
| Work Order |
10-04-12 |
| Work Began |
10-11-12 |
| Work Completed |
|
| Time Computed |
10-11-12 |
| Contract Working Days |
170 |
| Addl Days Granted |
0 |
| Working Days Charged |
118 |
| Percent Time Used |
69 |
| Contractor(s) |
| NOBLES ROAD CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0714-03-022 D. I. J. CONSTRUCTION, INC.(3.61%) HIGHWAY TECHNOLOGIES, INC. (0.76%) HJC FARMS, INC.(4.83%) J.V. CONCRETE CONSTRUCTION ( 19.27%)
|
| Contract # |
09123242 |
|
Totals |
2554818.37 |
137187.82 |
712475.72 |
27.8 |
|
| County | BROWN |
| Highway |
VA |
| From |
VARIOUS LOCATIONS |
| To |
. |
| CSJ |
0923-00-057 |
| Proj ID |
STP 2012(556) |
| Work Type |
ADA CURB RAMPS |
| |
|
1.000 |
967700.00 |
2916.39 |
933273.22 |
96.4 |
| Work Order |
06-14-12 |
| Work Began |
08-13-12 |
| Work Completed |
|
| Time Computed |
09-17-12 |
| Contract Working Days |
162 |
| Addl Days Granted |
0 |
| Working Days Charged |
128 |
| Percent Time Used |
79 |
| Contractor(s) |
| ENCINO LANDSCAPE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0923-00-057 WILLIS ELECTRIC CO., LP(0.50%)
|
| Contract # |
05123009 |
|
Totals |
967700.00 |
2916.39 |
933273.22 |
96.4 |
|
| County | BROWN |
| Highway |
CS |
| From |
US 67 |
| To |
US 183 |
| CSJ |
0923-06-061 |
| Proj ID |
C 923-6-61 |
| Work Type |
CONSTRUCT NEW 2 LANE ROADWAY |
| |
|
0.320 |
726589.36 |
45233.28 |
588364.35 |
80.9 |
| Work Order |
07-12-12 |
| Work Began |
12-17-12 |
| Work Completed |
|
| Time Computed |
07-28-12 |
| Contract Working Days |
101 |
| Addl Days Granted |
0 |
| Working Days Charged |
77 |
| Percent Time Used |
76 |
| Contractor(s) |
| PRATER EQUIPMENT CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0923-06-061 BEAR CREEK CONSTRUCTION, LLC (7.71%) D. I. J. CONSTRUCTION, INC.(1.13%) KARMY CONSTRUCTION INC (6.29%) TEXAS ALTERNATIVE GRASSER, INC.(0.49%)
|
| Contract # |
06123206 |
|
Totals |
726589.36 |
45233.28 |
588364.35 |
80.9 |
|
| County | SAN SABA |
| Highway |
CR |
| From |
ON CR 204 AT SAN SABA RIVER |
| To |
. |
| CSJ |
0923-25-011 |
| Proj ID |
BR 96(325) |
| Work Type |
REHAB STRUCTURE |
| |
|
0.100 |
849397.20 |
108459.71 |
577597.18 |
68.0 |
| Work Order |
06-15-12 |
| Work Began |
10-29-12 |
| Work Completed |
|
| Time Computed |
09-13-12 |
| Contract Working Days |
120 |
| Addl Days Granted |
5 |
| Working Days Charged |
109 |
| Percent Time Used |
87 |
| Contractor(s) |
| ELLIS-MCGINNIS CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0923-25-011 SAN-ANN-CO., INC.(0.32%) BLACKTOPPER TECHNOLOGY, INC. (2.47%) W. W. FOUNDATION DRILLING, LTD.(5.00%) TEXAS BRIDGE, INC. ( 17.07%) FORTSON CONTRACTING, INC.(1.51%) SHINN & GREGORY, INC.(0.00%)
|
| Contract # |
05123044 |
|
Totals |
849397.20 |
108459.71 |
577597.18 |
68.0 |
|
| County | SAN SABA |
| Highway |
CS |
| From |
ON US 190 FROM .05 MI. W OF FM 1031 |
| To |
0.3 MI. E OF FM 1031 |
| CSJ |
0923-25-021 |
| Proj ID |
NH 2013(661) |
| Work Type |
LANDSCAPE DEVELOPMENT |
| |
|
0.100 |
120270.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
34 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ENCINO LANDSCAPE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0923-25-021 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05133032 |
|
Totals |
120270.00 |
0.00 |
0.00 |
0.0 |
|
| County | LAMPASAS |
| Highway |
FM 580 |
| From |
NEAR FM 2313 |
| To |
CORYELL C/L |
| CSJ |
1032-01-032 |
| Proj ID |
STP 2013(006)HES |
| Work Type |
PROVIDE ADD'L PAVED SURFACE WIDTH |
| |
|
9.385 |
2683160.90 |
198634.98 |
626581.65 |
23.3 |
| Work Order |
11-30-12 |
| Work Began |
01-14-13 |
| Work Completed |
|
| Time Computed |
02-28-13 |
| Contract Working Days |
193 |
| Addl Days Granted |
0 |
| Working Days Charged |
70 |
| Percent Time Used |
36 |
| Contractor(s) |
| APAC-TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1032-01-032 D. I. J. CONSTRUCTION, INC.(2.45%) R K STEPHENS CONSTRUCTION, LLC ( 13.45%) RPV CONSTRUCTION (3.37%) ROADWAY SPECIALTIES, INC.(0.84%) SAN-ANN-CO., INC.(2.29%) TEXAS ALTERNATIVE GRASSER, INC.(0.60%)
|
| Contract # |
09123231 |
|
Totals |
2683160.90 |
198634.98 |
626581.65 |
23.3 |
|
| County | COMANCHE |
| Highway |
FM 1476 |
| From |
AT MUSTANG CREEK |
| To |
. |
| CSJ |
1039-01-033 |
| Proj ID |
BR 2013(378) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.085 |
538202.00 |
0.00 |
0.00 |
0.0 |
| County | COMANCHE |
| Highway |
FM 1476 |
| From |
AT WALNUT CREEK |
| To |
. |
| CSJ |
1039-01-034 |
| Proj ID |
BR 2013(378) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.094 |
410117.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-26-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
06-03-13 |
| Contract Working Days |
120 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| HODGES AND SON CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1039-01-033 HOUSTON SAWING & DRILLING(0.23%) ODUM SERVICES, L.P.(3.70%) PAVEMENT MARKINGS INC. (1.04%) TEXAS ALTERNATIVE GRASSER, INC.(0.31%)
|
| Contract # |
02133008 |
|
Totals |
948319.00 |
0.00 |
0.00 |
0.0 |
|
| County | BROWN |
| Highway |
FM 2524 |
| From |
NORWOOD |
| To |
BROOKS STREET |
| CSJ |
2377-01-039 |
| Proj ID |
STP 2013(525) |
| Work Type |
REHABILITATE EXISTING ROAD |
| |
|
1.026 |
4394292.98 |
0.00 |
0.00 |
0.0 |
| County | BROWN |
| Highway |
FM 2524 |
| From |
NORWOOD |
| To |
BROOKS STREET |
| CSJ |
2377-01-044 |
| Proj ID |
STP 2013(512) |
| Work Type |
ROW ACQ., RELO. ASSIST. & UTIL ADJ. |
| |
|
1.074 |
300464.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
291 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| JAY MILLS CONTRACTING, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 2377-01-039 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04133205 |
|
Totals |
4694756.98 |
0.00 |
0.00 |
0.0 |
|
| County | LAMPASAS |
| Highway |
FM 2657 |
| From |
0.412 MI. S OF US 190 |
| To |
FM 2808 |
| CSJ |
2786-01-010 |
| Proj ID |
C 2786-1-10 |
| Work Type |
WIDEN, GRADING, STRS, BASE, AND SUR |
| |
|
2.639 |
6233124.09 |
166936.37 |
3258118.56 |
52.2 |
| Work Order |
08-20-12 |
| Work Began |
09-05-12 |
| Work Completed |
|
| Time Computed |
09-17-12 |
| Contract Working Days |
327 |
| Addl Days Granted |
5 |
| Working Days Charged |
133 |
| Percent Time Used |
40 |
| Contractor(s) |
| BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 2786-01-010 N-LINE TRAFFIC MAINTENANCE, L.P. (0.41%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.85%) D. I. J. CONSTRUCTION, INC.(1.12%) TACH SERVICES, INC.(0.33%) TEXAS ALTERNATIVE GRASSER, INC.(0.16%) WILLIS ELECTRIC CO., LP(2.40%)
|
| Contract # |
06123214 |
|
Totals |
6233124.09 |
166936.37 |
3258118.56 |
52.2 |
|