|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | EASTLAND |
| Highway |
FM 2945 ETC |
| From |
CALLAHAN C/L |
| To |
SH 206 |
| CSJ |
0007-14-005 |
| Proj ID |
CPM 7-14-5 |
| Work Type |
SEAL COAT |
| |
|
227.513 |
5555666.38 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
76 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| BRANNAN PAVING CO., LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0007-14-005 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11083004 |
|
Totals |
5555666.38 |
0.00 |
0.00 |
0.0 |
|
| County | STEPHENS |
| Highway |
US 180 ETC |
| From |
AT LITTLE CADDO CREEK |
| To |
. |
| CSJ |
0011-09-062 |
| Proj ID |
BR 2008(869) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.919 |
2491112.22 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
239 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| HODGES AND SON CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0011-09-062 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10083209 |
|
Totals |
2491112.22 |
0.00 |
0.00 |
0.0 |
|
| County | COLEMAN |
| Highway |
US 84 ETC |
| From |
TAYLOR C/L |
| To |
NEAR ROUGH CREEK |
| CSJ |
0054-02-030 |
| Proj ID |
CPM 54-2-30 |
| Work Type |
SEAL COAT |
| |
|
189.942 |
5166363.80 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
76 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| BRANNAN PAVING CO., LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0054-02-030 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11083204 |
|
Totals |
5166363.80 |
0.00 |
0.00 |
0.0 |
|
| County | BROWN |
| Highway |
US 67 |
| From |
LUCAS STREET |
| To |
NEAR FM 2525 |
| CSJ |
0054-07-064 |
| Proj ID |
NH 2008(434) |
| Work Type |
RECONSTRUCT OUTSIDE LANES, ACP OVER |
| |
|
0.817 |
4234779.93 |
535421.72 |
1116933.36 |
26.3 |
| Work Order |
05-05-08 |
| Work Began |
09-25-08 |
| Work Completed |
|
| Time Computed |
09-02-08 |
| Contract Working Days |
239 |
| Addl Days Granted |
0 |
| Working Days Charged |
47 |
| Percent Time Used |
19 |
| Contractor(s) |
| LINDSEY CONTRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0054-07-064 J & M CONTRACTING, COMPANY ( 19.14%) D. I. J. CONSTRUCTION, INC.(3.31%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.73%) NORTH TEXAS BOMANITE, INC. (1.24%) TOTAL HIGHWAY MAINTENANCE, LLC (0.50%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.54%) WILEY CONSTRUCTION COMPANY, INC. ( 13.48%)
|
| Contract # |
03083006 |
|
Totals |
4234779.93 |
535421.72 |
1116933.36 |
26.3 |
|
| County | COMANCHE |
| Highway |
US 67 |
| From |
ELM STREET NEAR WCL OF COMANCHE, WE |
| To |
0.5 MILES WEST OF INDIAN CREEK |
| CSJ |
0079-02-035 |
| Proj ID |
NH 2001(492) |
| Work Type |
CONSTRUCT RR OVERPASS AND APPROACHE |
| |
|
1.177 |
14808428.80 |
1068587.32 |
7571644.27 |
51.1 |
| Work Order |
08-30-07 |
| Work Began |
01-10-08 |
| Work Completed |
|
| Time Computed |
08-30-07 |
| Contract Working Days |
423 |
| Addl Days Granted |
0 |
| Working Days Charged |
186 |
| Percent Time Used |
43 |
| Contractor(s) |
| PRATER EQUIPMENT CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0079-02-035 CEN-TEX SEEDING, INC.(0.81%) D. I. J. CONSTRUCTION, INC.(0.47%) ELLIS-MCGINNIS CONSTRUCTION CO.( 33.35%) KARMY CONSTRUCTION INC (5.37%) WILLIS ELECTRIC CO., LP(2.23%) W.W. WEBBER INC. (1.32%) PRIMATE CONSTRUCTION, INC. (0.04%) SCOTT DERR PAINTING CO (0.32%) ATS DRILLING, L.P. (1.18%) GUAJARDO STEEL (0.29%) MIKE BARKER CONSTRUCTION, INC. (0.58%)
|
| Contract # |
07073004 |
|
Totals |
14808428.80 |
1068587.32 |
7571644.27 |
51.1 |
|
| County | LAMPASAS |
| Highway |
US 281 |
| From |
US 183 |
| To |
BURNET C/L |
| CSJ |
0251-06-033 |
| Proj ID |
STP 2009(013) |
| Work Type |
GR, BASE, SURF, SIGNAL, ILLUM, C & G |
| |
|
1.946 |
1131594.03 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-10-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
01-05-09 |
| Contract Working Days |
114 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| RAY FARIS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0251-06-033 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09083210 |
|
Totals |
1131594.03 |
0.00 |
0.00 |
0.0 |
|
| County | COLEMAN |
| Highway |
US 283 |
| From |
CALLAHAN C/L |
| To |
NEAR SH 206 |
| CSJ |
0437-05-014 |
| Proj ID |
STP 2008(596) |
| Work Type |
ADD SHOULDERS, BASE OVERLAY, & SURF |
| |
|
16.800 |
5889808.27 |
306355.03 |
844478.88 |
14.3 |
| Work Order |
07-02-08 |
| Work Began |
07-07-08 |
| Work Completed |
|
| Time Computed |
07-07-08 |
| Contract Working Days |
360 |
| Addl Days Granted |
0 |
| Working Days Charged |
82 |
| Percent Time Used |
22 |
| Contractor(s) |
| STEPHENS MARTIN PAVING, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0437-05-014 TEXAS ALTERNATIVE GRASSER, INC.(0.44%) J.V. CONCRETE CONSTRUCTION ( 16.26%) CONTRACTORS SERVICE COMPANY(1.22%) BAKER BRIDGE, L.P. (6.20%) GIBSON & ASSOCIATES, INC.(2.18%) DUSTROL, INC.(0.10%) HJC FARMS, INC.(1.84%) NITE LITE, INC.(2.04%) TEXAS MULCHERS ENVIRONMENTAL SERVICES(0.38%)
|
| Contract # |
05083202 |
|
Totals |
5889808.27 |
306355.03 |
844478.88 |
14.3 |
|
| County | STEPHENS |
| Highway |
FM 207 |
| From |
US 180 |
| To |
2 MI. SOUTH OF US 180 |
| CSJ |
0570-02-021 |
| Proj ID |
STP 2008(355) |
| Work Type |
WIDEN, BASE OVERLAY, OCST |
| |
|
2.229 |
760576.82 |
60265.52 |
614514.51 |
81.5 |
| Work Order |
03-18-08 |
| Work Began |
04-18-08 |
| Work Completed |
|
| Time Computed |
04-03-08 |
| Contract Working Days |
108 |
| Addl Days Granted |
0 |
| Working Days Charged |
119 |
| Percent Time Used |
110 |
| Contractor(s) |
| STEPHENS MARTIN PAVING, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0570-02-021 CONTRACTORS SERVICE COMPANY(0.95%) SHANNON YOUNG CO., INC.( 19.99%) TEXAS ALTERNATIVE GRASSER, INC.(0.33%) TEXAS HIGHWAY MARKINGS, LLC(1.91%) TEXAS MULCHERS ENVIRONMENTAL SERVICES(0.06%) WILLIS ELECTRIC CO., LP(1.18%)
|
| Contract # |
02083214 |
|
Totals |
760576.82 |
60265.52 |
614514.51 |
81.5 |
|
| County | BROWN |
| Highway |
VA |
| From |
VARIOUS_LOCATIONS DISTRICTWIDE |
| To |
. |
| CSJ |
0923-00-051 |
| Proj ID |
STP 2008(820) |
| Work Type |
CONSTRUCT CURB RAMPS |
| |
|
0.100 |
1224576.00 |
0.00 |
0.00 |
0.0 |
| Work Order |
09-09-08 |
| Work Began |
10-28-08 |
| Work Completed |
|
| Time Computed |
09-25-08 |
| Contract Working Days |
216 |
| Addl Days Granted |
0 |
| Working Days Charged |
23 |
| Percent Time Used |
10 |
| Contractor(s) |
| INTERSTATE IMPROVEMENT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0923-00-051 HIGHWAY TECHNOLOGIES (1.02%) WILLIS ELECTRIC CO., LP(0.53%)
|
| Contract # |
08083019 |
|
Totals |
1224576.00 |
0.00 |
0.00 |
0.0 |
|
| County | BROWN |
| Highway |
VA |
| From |
DISTRICTWIDE |
| To |
. |
| CSJ |
0923-00-053 |
| Proj ID |
CPM 923-00-53 |
| Work Type |
THERMOPLASTIC STRIPING |
| |
|
191.842 |
460230.43 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-31-08 |
| Work Began |
11-03-08 |
| Work Completed |
|
| Time Computed |
11-16-08 |
| Contract Working Days |
45 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| FLAT LINE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0923-00-053 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10083011 |
|
Totals |
460230.43 |
0.00 |
0.00 |
0.0 |
|
| County | COLEMAN |
| Highway |
CR |
| From |
ON CR 140 AT JIM NED CREEK |
| To |
. |
| CSJ |
0923-08-016 |
| Proj ID |
BR 96(312) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.200 |
843363.85 |
110678.62 |
351514.09 |
41.6 |
| Work Order |
07-11-08 |
| Work Began |
08-12-08 |
| Work Completed |
|
| Time Computed |
07-27-08 |
| Contract Working Days |
142 |
| Addl Days Granted |
0 |
| Working Days Charged |
57 |
| Percent Time Used |
40 |
| Contractor(s) |
| VILLA & SONS CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0923-08-016 W. W. FOUNDATION DRILLING, LTD.(8.68%) TEXAS ALTERNATIVE GRASSER, INC.(0.47%) S & S BRIDGE PAINTING(0.30%)
|
| Contract # |
06083219 |
|
Totals |
843363.85 |
110678.62 |
351514.09 |
41.6 |
|
| County | EASTLAND |
| Highway |
CR |
| From |
ON CR 141 AT BR S FK LEON RIVER |
| To |
. |
| CSJ |
0923-09-045 |
| Proj ID |
BR 2008(400) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.501 |
1048439.45 |
74474.58 |
335679.39 |
32.0 |
| Work Order |
07-30-08 |
| Work Began |
08-21-08 |
| Work Completed |
|
| Time Computed |
08-15-08 |
| Contract Working Days |
165 |
| Addl Days Granted |
0 |
| Working Days Charged |
44 |
| Percent Time Used |
26 |
| Contractor(s) |
| AJAX EQUIPMENT COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0923-09-045 FOUNDATION DRILLERS, INC.(7.30%) DIAMONDBACK STEEL CO., INC.(7.27%)
|
| Contract # |
06083020 |
|
Totals |
1048439.45 |
74474.58 |
335679.39 |
32.0 |
|
| County | EASTLAND |
| Highway |
VA |
| From |
ON IH 20 AT SH 16, SH 206, US 183, |
| To |
AND AT SH 6 |
| CSJ |
0923-09-046 |
| Proj ID |
STP 2007(791) |
| Work Type |
SAFETY LIGHTING |
| |
|
0.200 |
1334366.55 |
0.00 |
1268284.25 |
95.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
09-11-07 |
| Work Began |
03-24-08 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
133 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| WILLIS ELECTRIC CO., LP |
SUBCONTRACTOR(S) FOR CCSJ: 0923-09-046 CONTRACTORS SERVICE COMPANY(1.47%) ODUM SERVICES, L.P.(0.24%) BAKER BRIDGE, L.P. (3.55%) MICA CORPORATION ( 22.27%) RAYDON, INC. (3.39%)
|
| Contract # |
08073213 |
|
Totals |
1334366.55 |
0.00 |
1268284.25 |
95.9 |
|
| County | EASTLAND |
| Highway |
CS |
| From |
ON SADOSA ST FROM SEAMAN ST (SH 6) |
| To |
COLLEGE ST (SIEBERT ELEM SCHOOL) |
| CSJ |
0923-09-055 |
| Proj ID |
STP 2008(712)SRS |
| Work Type |
PEDESTRIAN FACILITIES |
| |
|
0.806 |
268987.80 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
51 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| M & S CONCRETE CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0923-09-055 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10083018 |
|
Totals |
268987.80 |
0.00 |
0.00 |
0.0 |
|
| County | LAMPASAS |
| Highway |
VA |
| From |
VARIOUS LOCATIONS IN SAN SABA, |
| To |
BROWN AND MCCULLOCH COUNTIES |
| CSJ |
0923-10-015 |
| Proj ID |
STP 2007(514) |
| Work Type |
SET AND GUARDRAIL REPLACEMENT |
| |
|
0.100 |
1907604.92 |
92140.05 |
1437249.48 |
75.3 |
| Work Order |
07-09-07 |
| Work Began |
08-14-07 |
| Work Completed |
|
| Time Computed |
07-25-07 |
| Contract Working Days |
167 |
| Addl Days Granted |
120 |
| Working Days Charged |
266 |
| Percent Time Used |
92 |
| Contractor(s) |
| RYAN MATERIALS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0923-10-015 WS CONSTRUCTION CO.( 10.50%) UNITED RENTALS HIGHWAY TECHNOLOGIES, L.P. (HOUSTON)(0.78%) HJC FARMS, INC.(1.43%) MIKE BARKER CONSTRUCTION, INC. (9.11%)
|
| Contract # |
05073017 |
|
Totals |
1907604.92 |
92140.05 |
1437249.48 |
75.3 |
|
| County | STEPHENS |
| Highway |
VA |
| From |
SHACKELFORD C/L ON US 180 |
| To |
PALO PINTO C/L |
| CSJ |
0923-22-018 |
| Proj ID |
STP 2008(356) |
| Work Type |
GUARDRAIL & BRIDGE RAIL REPLACEMENT |
| |
|
0.100 |
394754.45 |
74132.67 |
400740.85 |
99.9 |
| Work Order |
03-18-08 |
| Work Began |
08-11-08 |
| Work Completed |
|
| Time Computed |
04-03-08 |
| Contract Working Days |
45 |
| Addl Days Granted |
0 |
| Working Days Charged |
49 |
| Percent Time Used |
108 |
| Contractor(s) |
| STEPHENS MARTIN PAVING, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0923-22-018 HJC FARMS, INC.( 40.56%)
|
| Contract # |
02083016 |
|
Totals |
394754.45 |
74132.67 |
400740.85 |
99.9 |
|
| County | COMANCHE |
| Highway |
FM 1689 |
| From |
0.65 MI S OF FM 589, S |
| To |
SH 36 |
| CSJ |
1033-04-017 |
| Proj ID |
STP 2007(747) |
| Work Type |
BASE OVERLAY, SFTY TRT STRS, SURF TRT |
| |
|
7.848 |
2819766.70 |
171154.26 |
2011307.77 |
71.3 |
| Work Order |
10-05-07 |
| Work Began |
10-31-07 |
| Work Completed |
|
| Time Computed |
10-21-07 |
| Contract Working Days |
220 |
| Addl Days Granted |
0 |
| Working Days Charged |
201 |
| Percent Time Used |
91 |
| Contractor(s) |
| PRATER EQUIPMENT CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1033-04-017 CEN-TEX SEEDING, INC.(3.04%) JONA CONTRACTING, INC. (1.53%) MIKE BARKER CONSTRUCTION, INC. (4.68%) D. I. J. CONSTRUCTION, INC.(1.75%) WILLIS ELECTRIC CO., LP(0.65%)
|
| Contract # |
08073221 |
|
Totals |
2819766.70 |
171154.26 |
2011307.77 |
71.3 |
|
| County | EASTLAND |
| Highway |
FM 2214 |
| From |
FM 2461 |
| To |
0.5 MI E OF FM 571 |
| CSJ |
1697-02-018 |
| Proj ID |
STP 2006(762) |
| Work Type |
GRADING, STRS, FLEX BASE AND SURFAC |
| |
|
5.116 |
5409346.36 |
319911.83 |
4524925.96 |
83.6 |
| Work Order |
10-31-06 |
| Work Began |
01-08-07 |
| Work Completed |
|
| Time Computed |
12-31-06 |
| Contract Working Days |
357 |
| Addl Days Granted |
0 |
| Working Days Charged |
338 |
| Percent Time Used |
94 |
| Contractor(s) |
| JAY MILLS CONTRACTING, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 1697-02-018 CEN-TEX SEEDING, INC.(2.38%) D. I. J. CONSTRUCTION, INC.(2.47%) NORTHEASTERN PAVERS, INC.( 11.38%) REBAR SERVICE & SUPPLY CO. (1.22%) SAN_ANN BARRICADES,INC.(1.01%) RICOCHET FUEL DISTRIBUTORS, INC. (0.85%) ELLIS-MCGINNIS CONSTRUCTION CO.( 19.10%) ATS DRILLING, L.P. (1.08%) FORTSON CONTRACTING, INC.(1.68%)
|
| Contract # |
08063010 |
|
Totals |
5409346.36 |
319911.83 |
4524925.96 |
83.6 |
|
| County | BROWN |
| Highway |
FM 2524 |
| From |
AT AVE. A |
| To |
. |
| CSJ |
2377-01-038 |
| Proj ID |
STP 2008(305) |
| Work Type |
LANDSCAPE DEVELOPMENT |
| |
|
0.054 |
84793.10 |
38651.50 |
61600.30 |
82.5 |
| Work Order |
05-27-08 |
| Work Began |
06-20-08 |
| Work Completed |
|
| Time Computed |
06-12-08 |
| Contract Working Days |
47 |
| Addl Days Granted |
10 |
| Working Days Charged |
78 |
| Percent Time Used |
136 |
| Contractor(s) |
| FAST-TRAK CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2377-01-038 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04083014 |
|
Totals |
84793.10 |
38651.50 |
61600.30 |
82.5 |
|
| County | LAMPASAS |
| Highway |
FM 1715 |
| From |
FM 580 E & S |
| To |
US 190 |
| CSJ |
3605-01-001 |
| Proj ID |
C 3605-1-1 |
| Work Type |
GR., BA., STR., SURF. |
| |
|
6.351 |
6245968.01 |
96528.86 |
5749782.67 |
95.8 |
| Work Order |
06-13-07 |
| Work Began |
07-17-07 |
| Work Completed |
|
| Time Computed |
09-04-07 |
| Contract Working Days |
270 |
| Addl Days Granted |
27 |
| Working Days Charged |
251 |
| Percent Time Used |
84 |
| Contractor(s) |
| JAMES CONSTRUCTION GROUP, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 3605-01-001 LONE STAR TRAFFIC SERVICE, INC.(0.33%) TACH SERVICES, INC.(0.60%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.21%) GUAJARDO STEEL (0.39%) ALTEX LANDSCAPE CONSTRUCTION, INC. (0.59%) WOODARD CONSTRUCTION COMPANY (7.57%) PRIMATE CONSTRUCTION, INC. (0.05%) ODUM SERVICES, L.P.(0.28%) D. I. J. CONSTRUCTION, INC.(0.85%) UNITED RENTALS HIGHWAY TECHNOLOGIES (TEMPE)(0.82%) MICA CORPORATION (0.53%) SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.01%) WHEELER COATINGS ASPHALT, INC. (7.29%) TRIPLE J-SA CONSTRUCTION (1.62%)
|
| Contract # |
05073003 |
|
Totals |
6245968.01 |
96528.86 |
5749782.67 |
95.8 |
|