Monthly State Let Construction Report For Brownwood District As Of Feb 09, 2018 Page 1 Of 1

Last Update: Friday, February 09, 2018
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEASTLAND ETC
HighwaySH 206 ETC
FromFM 2943
To.1 MI N OF IH 20 S.F.R IN CISCO
CSJ0007-04-126
Proj IDSTP 1702(798)
Work TypeSEAL COAT
 
158.0726070587.660.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-22-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0007-04-126
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11173017
Totals6070587.660.000.000.0

CountyEASTLAND
HighwayIH 20
FromAT 0.5 MI. W OF FM 571 AND ALSO AT
To2.5 MI. W OF SH 16
CSJ0007-06-070
Proj IDSTP 2005(276)TEG
Work TypeCONSTRUCT TWO SAFETY REST AREAS
 
3.11916358386.5816466163.6299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-04-13
Work Began02-01-13
Work Completed
Time Computed01-20-13
Contract Working Days415
Addl Days Granted180
Working Days Charged628
Percent Time Used105
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-070
EROSION CONTROL MANAGEMENT SERVICES (0.83)
ABILENE SHEET METAL (1.43)
CURTIS MECHANICAL CONTRACTORS, INC. (2.10)
GRIZZLY GLASS & MIRROR, INC. (1.01)
LONE OAK LANDSCAPE LLC (0.38)
LONE STAR BARRIER SERVICES, LLC (0.66)
PEACHTREE CONSTRUCTION, LTD. (4.79)
SCR CONSTRUCTION CO., INC. (0.18)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42)
TIPPENN FABRICATION & ERECTION (5.06)
ALVAREZ DRYWALL & ACCOUSTICS, INC. (0.57)
BUFFALO GAP INSTRUMENTATION AND ELECTRICAL CO., INC. (9.53)
CORPUS CHRISTI STAMP WORKS, INC. (0.05)
FINLEY TERMITE AND PEST CONTROL, INC. (0.01)
SOLID ROCK LAWN & LANDSCAPE (0.21)
TEX OP CONSTRUCTION, LP (0.20)
GOMEZ FLOOR COVERING, INC. (1.55)
ENNIS ROOFING AND CONSTRUCTION, L.L.C. (2.07)
B.A.D.J., INC. DBA THE TOPSPOT (0.21)
WILKS MASONRY CORPORATION (4.34)
LIBERTY PAINTING & DRYWALL (0.65)
HUNTER KNEPSHIELD COMPANY (0.73)
CLLA GROUP, LLC (1.46)
AMERITEX FLAG & FLAGPOLE, LLC (0.03)
A & A CONSTRUCTION (0.26)
LIBERTY PAINTING & DRYWALL (0.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.11)
CONROE WOOD PRODUCTS INC. (0.00)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
SAR TRANSPORTATION, LLC (0.00)
CHAMPION FUEL SOLUTIONS (0.00)
Contract #10123203
Totals16358386.580.0016466163.6299.9

CountySTEPHENS
HighwayUS 180
From@ HUBBARD CREEK LAKE BRIDGE
To.
CSJ0011-07-051
Proj IDBR 1702(472)
Work TypeREHAB BRIDGE
 
0.7002875191.47169328.005.8
CountySTEPHENS
HighwayUS 180
FromAT SOUR BRANCH BRIDGE
To.
CSJ0011-09-070
Proj IDBR 1702(472)
Work TypeREHAB BRIDGE
 
0.020363962.60291514.1080.0
CountySTEPHENS
HighwayUS 183
FromAT SNAKE DEN CREEK
To.
CSJ0404-02-039
Proj IDBR 1702(472)
Work TypeREPLACE BRIDGE RAIL
 
0.100244990.50253920.1599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-17
Work Began10-24-17
Work Completed
Time Computed00-00-00
Contract Working Days199
Addl Days Granted0
Working Days Charged36
Percent Time Used18
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-07-051
BARRICADES UNLIMITED (1.58)
HJC FARMS, INC. (4.38)
ROCK SOLID, INC. (3.33)
S & S BRIDGE PAINTING, INC. (10.30)
SCR CIVIL CONSTRUCTION, LLC (3.13)
CF SOUTHWEST ENVIRONMENT SERVICES LLC (2.77)
TEXOP CONSTRUCTION (0.50)
Contract #07173038
Totals3484144.570.00714762.2520.5

CountySTEPHENS
HighwayUS 180
FromGONZALES CREEK
ToFM 287
CSJ0011-08-026
Proj IDSTP 1602(051)
Work TypeRECONSTRUCT URBAN ROADWAY
 
5.12913412991.587262713.4554.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-16
Work Began09-15-16
Work Completed
Time Computed00-00-00
Contract Working Days459
Addl Days Granted79
Working Days Charged272
Percent Time Used50
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-08-026
CHEROKEE SERVICES (0.17)
D. I. J. CONSTRUCTION, INC. (1.17)
GIBSON & ASSOCIATES, INC. (0.66)
HJC FARMS, INC. (0.63)
(USE 05113)J&M CONTRACTING COMPANY (14.52)
PENHALL COMPANY (0.08)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.49)
WILLIS ELECTRIC CO., LP (2.37)
FAMBRO CONSTRUCTION, INC. (12.03)
NELSON INDUSTRIAL SERVICES, INC. (0.05)
GM MASONRY (0.22)
Contract #05163002
Totals13412991.58225829.117262713.4554.1

CountyBROWN
HighwayUS 84
FromAT FT. WORTH & WESTERN RAILROAD
To.
CSJ0054-07-069
Proj IDSTP 1302(079)RGS
Work TypeRAILROAD BRIDGE REPLACEMENT
 
0.5208488149.705924304.8269.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-16
Work Began09-07-16
Work Completed
Time Computed00-00-00
Contract Working Days400
Addl Days Granted0
Working Days Charged282
Percent Time Used70
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-07-069
GRANBURY EXCAVATING, INC. (24.57)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.30)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.86)
TEXAS SHAFTS, INC. (4.37)
ODUM SERVICES, L.P. (0.58)
MCL CONTRACTING, LLC (0.25)
CHOCTAW ERECTORS, INC. (2.69)
TEXAS HIGHWAY MAINTENANCE, LLC (0.81)
Contract #02163207
Totals8488149.70130996.015924304.8269.8

CountyCOLEMAN
HighwayUS 67
FromSH 206
To.584 MI W OF CR 368
CSJ0078-03-055
Proj IDSTP 2017(457)HES
Work TypeIMPRV GR, SFT TREAT OBJECTS, ADD PA
 
8.2471678694.191180425.6570.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-10-17
Work Began04-17-17
Work Completed
Time Computed00-00-00
Contract Working Days187
Addl Days Granted0
Working Days Charged123
Percent Time Used65
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0078-03-055
CONTRACTORS SERVICE COMPANY (0.93)
DOUBLE A CONTRACTING, L.P. (2.72)
HJC FARMS, INC. (3.55)
TEXOP CONSTRUCTION (2.05)
Contract #01173215
Totals1678694.191600.001180425.6570.3

CountyEASTLAND
HighwayUS 183
FromIH 20
ToCR 181
CSJ0127-01-030
Proj IDSTP 1702(236)
Work TypeADD PASSING LANES
 
4.2433372833.811004925.0129.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-21-17
Work Began09-11-17
Work Completed
Time Computed00-00-00
Contract Working Days221
Addl Days Granted20
Working Days Charged69
Percent Time Used28
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0127-01-030
D.I.J. CONSTRUCTION, INC (1.86)
GIBSON & ASSOCIATES, INC. (2.02)
HJC FARMS, INC. (3.06)
LUZ LERMA CONSTRUCTION, INC. (2.01)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.24)
TEXAS ALTERNATIVE GRASSER, INC. (0.30)
PENHALL COMPANY (0.20)
Contract #05173045
Totals3372833.81361723.411004925.0129.7

CountyEASTLAND
HighwayUS 183
From5 MI. N OF RISING STAR NCL
ToRISING STAR NCL
CSJ0127-02-141
Proj IDSTP 2018(542)
Work TypeADD PASSING LANES
 
5.0003673746.040.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days260
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0127-02-141
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183234
Totals3673746.040.000.000.0

CountyMCCULLOCH
HighwayUS 190
FromUS 87
ToUS 377
CSJ0128-04-035
Proj IDSTP 2017(458)
Work TypeRECONSTRUCT URBAN ROAD
 
17.5745261640.440.000.0
CountyMCCULLOCH
HighwayUS 190
FromUS 87
ToUS 377
CSJ0128-04-036
Proj IDROW 128-4-36
Work TypeROW ACQUISITION
 
0.8803315712.430.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days446
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0128-04-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183224
Totals8577352.870.000.000.0

CountyCOMANCHE
HighwaySH 36
From1 MI. S. OF 1702
ToHAMILTON C/L
CSJ0183-01-043
Proj IDSTP 2018(227)
Work TypeACP OVERLAY
 
5.909918207.810.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-15-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0183-01-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173015
Totals918207.810.000.000.0

CountySTEPHENS
HighwayUS 183
FromUS 180
ToBRECKENRIDGE SCL
CSJ0257-01-041
Proj IDSTP 1602(303)
Work TypeREHABILITATE EXISTING ROADWAY
 
0.7343157515.04763072.0024.1
CountySTEPHENS
HighwayUS 183
FromUS 180
ToBRECKENRIDGE SCL
CSJ0257-01-044
Proj IDROW 257-1-44
Work TypeUTILITY ADJUSTMENTS
 
0.734580454.40496550.2085.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-22-17
Work Began10-16-17
Work Completed
Time Computed00-00-00
Contract Working Days238
Addl Days Granted0
Working Days Charged75
Percent Time Used31
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0257-01-041
D.I.J. CONSTRUCTION, INC (1.53)
FAMBRO CONSTRUCTION, INC. (13.08)
HJC FARMS, INC. (1.46)
J & M CONTRACTING COMPANY (17.96)
TEXAS ALTERNATIVE GRASSER, INC. (0.13)
WILLIS ELECTRIC CO., LP (0.53)
Contract #04173226
Totals3737969.44428317.031259622.2033.6

CountySTEPHENS
HighwayUS 183
From.5 MI N OF FM 2231
ToFM 2231
CSJ0257-01-047
Proj IDSTP 2018(244)
Work TypeDRAINAGE IMPROVEMENTS
 
0.500223073.50110903.0049.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-08-17
Work Began01-09-18
Work Completed
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged14
Percent Time Used41
Contractor(s)
REECE CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0257-01-047
CONTRACTORS SERVICE COMPANY (1.70)
JB FARM & RANCH (28.34)
WOLFE CONSTRUCTION GROUP, INC. (1.73)
Contract #11173006
Totals223073.50110903.00110903.0049.7

CountyMILLS
HighwaySH 16
From.021 MI SW OF BARROW ST
ToSAN SABA COUNTY LINE
CSJ0289-03-026
Proj IDSTP 2017(445)HES
Work TypeIMPRV GR, SFT TREAT FIXED, ADD PASS
 
9.2411203835.851174213.8297.5
CountyBURNET
HighwayFM 1478
FromLAMPASAS C/L
To7.096 MI. S OF LAMPASAS C/L
CSJ2206-02-006
Proj IDSTP 2017(471)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
7.096353795.02338398.5195.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-17
Work Began03-21-17
Work Completed
Time Computed00-00-00
Contract Working Days187
Addl Days Granted0
Working Days Charged170
Percent Time Used90
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0289-03-026
FLASHER EQUIPMENT COMPANY (1.87)
WOLFE CONSTRUCTION GROUP, INC. (0.57)
STRIPE-A-ZONE, INC. (1.55)
JE CASEY, LLC (9.79)
Contract #01173213
Totals1557630.870.001512612.3397.1

CountyMILLS
HighwayFM 45
FromBROWN C/L
ToSAN SABA C/L
CSJ0480-07-009
Proj IDSTP 1602(052)
Work TypeGRADING, STRUCTURES, BASE, AND SURF
 
4.3624563803.883881014.1485.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-16
Work Began09-06-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted99
Working Days Charged281
Percent Time Used79
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0480-07-009
D.I.J. CONSTRUCTION, INC (1.28)
TEXAS ALTERNATIVE GRASSER, INC. (0.60)
HJC FARMS, INC. (0.95)
J&M CONTRACTING COMPANY (14.23)
Contract #05163004
Totals4563803.8875289.523881014.1485.0

CountyCOMANCHE
HighwayCR
FromON CR 403 AT DRAW
To.
CSJ0923-17-076
Proj IDBR 2015(346)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100217652.00223423.0099.9
CountyCOMANCHE
HighwayCR
FromON CR 304 AT INDIAN CREEK
To.
CSJ0923-17-078
Proj IDBR 2016(003)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100568174.50287419.0050.5
CountyCOMANCHE
HighwayFM 1689
FromAT WALNUT CREEK
To.
CSJ1033-04-021
Proj IDBR 1602(572)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100994764.15904165.0590.8
CountyCOMANCHE
HighwayFM 1477
FromAT N COPPERAS CREEK
To.
CSJ1366-01-009
Proj IDBR 1602(573)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100684261.20641676.9093.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-16
Work Began12-07-16
Work Completed
Time Computed00-00-00
Contract Working Days264
Addl Days Granted0
Working Days Charged252
Percent Time Used95
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0923-17-076
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.69)
ODUM SERVICES, L.P. (2.90)
PEACHTREE CONSTRUCTION, LTD. (3.50)
STRIPE-A-ZONE, INC. (0.53)
TOTAL HIGHWAY MAINTENANCE, LLC (0.67)
DFW REBAR, INC. (0.28)
Contract #08163217
Totals2464851.8547115.002056683.9583.4

CountyCOMANCHE
HighwayCR
FromON CR 376 AT LEON RIVER
To.
CSJ0923-17-077
Proj IDBR 2018(414)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100636369.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-17-077
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183025
Totals636369.200.000.000.0

CountySTEPHENS
HighwayCR
FromON CR 157 AT W FORK GONZALES CREEK
To.
CSJ0923-22-021
Proj IDBR 2018(217)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100284043.7540032.7114.0
CountySTEPHENS
HighwayCR
FromON CR 154 AT W FORK GONZALES CREEK
To.
CSJ0923-22-022
Proj IDBR 2017(999)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100392222.75105940.0027.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-13-17
Work Began01-09-18
Work Completed
Time Computed00-00-00
Contract Working Days102
Addl Days Granted0
Working Days Charged16
Percent Time Used15
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-22-021
DUSTIN ALLEN, INC. (4.56)
WOLFE CONSTRUCTION GROUP, INC. (0.78)
Contract #10173009
Totals676266.50145972.71145972.7121.5

CountyMCCULLOCH
HighwaySH 71
FromNEAR FM 2309
To2.15 MI S OF FM 2309
CSJ1102-01-042
Proj IDSTP 1502(081)
Work TypeWDN SUBGRADE, STR, SURFACE
 
2.1612316169.672168086.3593.6
CountyMCCULLOCH
HighwaySH 71
From0.54 MI. W OF FM 2309
ToNEAR FM 2309
CSJ2561-01-013
Proj IDSTP 1502(081)
Work TypeWDN SUBGRADE, SURFACE
 
0.5661026756.54751509.0373.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-23-15
Work Began11-02-15
Work Completed
Time Computed00-00-00
Contract Working Days306
Addl Days Granted0
Working Days Charged239
Percent Time Used78
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1102-01-042
J & M CONTRACTING, COMPANY (14.87)
WILLIS ELECTRIC CO., LP (0.54)
HJC FARMS, INC. (1.67)
D.I.J. CONSTRUCTION, INC (2.29)
TEXAS ALTERNATIVE GRASSER, INC. (0.36)
Contract #05153232
Totals3342926.2131012.392919595.3887.3

CountyEASTLAND ETC
HighwaySH 206 ETC
FromIH 20
ToCALLAHAN C/L
CSJ2638-01-022
Proj IDSTP 1702(168)HES
Work TypePROFILE CENTER AND EDGELINE MARKING
 
61.329397732.27383321.8496.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-09-17
Work Began05-30-17
Work Completed
Time Computed00-00-00
Contract Working Days81
Addl Days Granted0
Working Days Charged38
Percent Time Used46
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2638-01-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173234
Totals397732.2751386.00383321.8496.3

page 1