| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | MILAM |
| Highway |
US0077 |
| From |
VARIOUS HIGHWAYS IN MILAM COUNTY |
| To |
. |
| CSJ |
6020-74-001 |
| Proj ID |
RMC - 602074001 |
| Work Type |
RIGHT OF WAY MOWING |
| |
|
0.001 |
118675.01 |
0.00 |
116331.21 |
99.7 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-13-98 |
| Work Began |
06-03-98 |
| Work Completed |
|
| Time Computed |
05-26-98 |
| Contract Working Days |
100 |
| Addl Days Granted |
0 |
| Working Days Charged |
71 |
| Percent Time Used |
71 |
| Contractor(s) |
| HMC CONTRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6020-74-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02984050 |
|
Totals |
118675.01 |
0.00 |
116331.21 |
99.7 |
|
| County | GRIMES |
| Highway |
SH0006 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6020-89-001 |
| Proj ID |
RMC - 602089001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
112494.06 |
0.00 |
111384.46 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-30-98 |
| Work Began |
05-13-98 |
| Work Completed |
|
| Time Computed |
05-07-98 |
| Contract Working Days |
100 |
| Addl Days Granted |
0 |
| Working Days Charged |
61 |
| Percent Time Used |
61 |
| Contractor(s) |
| P-VILLE, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6020-89-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03984028 |
|
Totals |
112494.06 |
0.00 |
111384.46 |
99.9 |
|
| County | WALKER |
| Highway |
IH0045 |
| From |
MONTGOMERY/WALKER COUNTY LINE |
| To |
FREESTONE/NAVARRO COUNTY LINE |
| CSJ |
6165-62-001 |
| Proj ID |
RMC - 616562001 |
| Work Type |
FULL - DEPTH CONCRETE REPAIR |
| |
|
113.000 |
999858.00 |
0.00 |
301915.00 |
42.2 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
01-31-08 |
| Work Began |
02-20-08 |
| Work Completed |
|
| Time Computed |
02-20-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
255 |
| Percent Time Used |
69 |
| Contractor(s) |
| TOTAL HIGHWAY MAINTENANCE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6165-62-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12074019 |
|
Totals |
999858.00 |
0.00 |
301915.00 |
42.2 |
|
| County | FREESTONE |
| Highway |
FM0416 |
| From |
NAVARRO COUNTY LINE |
| To |
FM 488 |
| CSJ |
6173-82-001 |
| Proj ID |
RMC - 617382001 |
| Work Type |
ROADWAY REHABILITATION |
| |
|
5.980 |
1187247.56 |
0.00 |
604450.49 |
80.5 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
06-09-08 |
| Work Began |
06-09-08 |
| Work Completed |
|
| Time Computed |
06-09-08 |
| Contract Working Days |
65 |
| Addl Days Granted |
2 |
| Working Days Charged |
56 |
| Percent Time Used |
83 |
| Contractor(s) |
| BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6173-82-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04084024 |
|
Totals |
1187247.56 |
0.00 |
604450.49 |
80.5 |
|
| County | FREESTONE |
| Highway |
FM3059 |
| From |
SH 75 |
| To |
NAVARRO/FREESTONE COUNTY LINE |
| CSJ |
6173-92-001 |
| Proj ID |
RMC - 617392001 |
| Work Type |
ROADWAY REHABILITATION |
| |
|
4.878 |
953729.33 |
0.00 |
683542.30 |
85.2 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
06-09-08 |
| Work Began |
06-09-08 |
| Work Completed |
|
| Time Computed |
06-09-08 |
| Contract Working Days |
71 |
| Addl Days Granted |
0 |
| Working Days Charged |
65 |
| Percent Time Used |
91 |
| Contractor(s) |
| AJAX EQUIPMENT COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 6173-92-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02084025 |
|
Totals |
953729.33 |
0.00 |
683542.30 |
85.2 |
|
| County | WASHINGTON |
| Highway |
SH0036 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6180-33-001 |
| Proj ID |
RMC - 618033001 |
| Work Type |
CLEANING AND SEALING CRACKS |
| |
|
0.100 |
255725.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
57 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| INTERSTATE IMPROVEMENT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6180-33-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09084015 |
|
Totals |
255725.00 |
0.00 |
0.00 |
0.0 |
|
| County | MILAM |
| Highway |
US0079 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6180-35-001 |
| Proj ID |
RMC - 618035001 |
| Work Type |
CLEANING AND SEALING CRACKS |
| |
|
0.010 |
269242.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
59 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| KUNTZ CONTRACTING CORP. |
SUBCONTRACTOR(S) FOR CCSJ: 6180-35-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09084006 |
|
Totals |
269242.00 |
0.00 |
0.00 |
0.0 |
|