Item No Description Units December 31, 2016 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
100 6002 PREPARING ROW STA 4.000 2,575.00000 28.850 3,942.80763 7
104 6009 REMOVING CONC (RIPRAP) SY 380.000 21.79737 535.000 28.79813 4
104 6010 REMOVING CONC (RIPRAP) CY 8.000 50.00000 8.000 50.00000 1
104 6028 REMOVING CONC (MISC) SY 112.000 150.00000 112.000 150.00000 1
104 6029 REMOVING CONC (CURB OR CURB & GUTTER) LF     700.000 20.00000 1
110 6001 EXCAVATION (ROADWAY) CY 137.000 10.00000 361.000 21.16898 2
110 6002 EXCAVATION (CHANNEL) CY 66.000 25.00000 667.000 45.23988 3
110 6003 EXCAVATION (SPECIAL) CY     10,043.000 14.00000 1
112 6001 SUBGRADE WIDENING (ORD COMP) STA 162.070 250.00000 463.030 217.50103 2
132 6005 EMBANKMENT (FINAL) (ORD COMP) (TY C) CY     2,332.000 33.07033 3
132 6006 EMBANKMENT (FINAL) (DENS CONT) (TY C) CY     4,167.000 35.00000 1
132 6007 EMBANKMENT (FINAL) (ORD COMP) (TY D) CY 46.000 20.00000 46.000 20.00000 1
132 6017 EMBANKMENT (VEHICLE) (ORD COMP) (TY A) CY     952.000 24.00000 1
132 6019 EMBANKMENT (VEHICLE) (ORD COMP) (TY B) CY 1,166.000 27.17324 1,627.000 28.95759 5
134 6002 BACKFILL (TY B) STA 163.070 75.00000 465.530 91.24278 2
150 6001 BLADING STA 162.070 75.00000 463.030 91.24949 2
150 6002 BLADING HR 8.000 100.00000 65.000 103.84615 3
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY     142.000 25.00000 1
164 6001 BROADCAST SEED (PERM) (RURAL) (SANDY) SY 20,831.000 0.10000 79,206.000 0.24082 5
164 6009 BROADCAST SEED (TEMP) (WARM) SY 10,416.000 0.10000 38,804.000 0.17699 4
164 6011 BROADCAST SEED (TEMP) (COOL) SY 10,416.000 0.10000 38,804.000 0.17699 4
164 6033 DRILL SEEDING (PERM) (RURAL) (SANDY) SY     5,699.000 0.55000 1
164 6035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY 330.000 3.00000 330.000 3.00000 1
164 6041 DRILL SEEDING (TEMP) (WARM) SY 165.000 3.00000 3,014.500 0.63684 2
164 6043 DRILL SEEDING (TEMP) (COOL) SY 165.000 3.00000 3,014.500 0.63684 2
168 6001 VEGETATIVE WATERING MG 208.300 25.00000 835.300 19.70250 5
169 6001 SOIL RETENTION BLANKETS (CL 1) (TY A) SY 330.000 7.00000 330.000 7.00000 1
169 6002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY     575.000 10.17391 3
169 6003 SOIL RETENTION BLANKETS (CL 1) (TY C) SY     5,699.000 1.30000 1