Item No Description Units April 30, 2016 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
712 2005 JT / CRCK SEAL (RUBBER - ASPHALT) LMI     552.323 432.42916 2
712 6005 JT / CRCK SEAL (RUBBER - ASPHALT) LF     2,830.000 4.50000 1
712 6008 JT / CRCK SEAL (RUBBER - ASPHALT) LMI     935.835 638.46537 3
712 6009 JT / CRCK SEAL (HOT - POURED RUBBER) LF     24,634.000 2.18980 2
713 6001 JT SEALING AND CLEANING (TRANS CNTR JTS LF     2,626.000 8.25000 1
713 6002 JT SEALING AND CLEANING (LONGT CNTR JTS LF     2,838.000 8.25000 1
713 6003 JT SEALING AND CLEANING (LNGT CNSTR JTS LF     5,166.000 8.00000 1
713 6005 CRACK CLEANING AND SEALING (JCP) LF     4,481.000 5.00000 1
730 6001 STRIP MOWING AC     6,967.000 30.66852 7
730 6002 FULL - WIDTH MOWING AC     90,345.600 34.98402 9
730 6003 SPOT MOWING AC     720.000 48.21250 6
738 6002 CLEANING / SWEEPING (CENTER MEDIAN) MI     1,638.000 400.00000 1
738 6004 CLEANING / SWEEPING (OUTSIDE MAIN LANE MI     1,626.180 400.00000 1
738 6006 CLEANING / SWEEPING (FRONTAGE ROAD) MI     734.800 350.00000 1
738 6008 CLEANING / SWEEPING (ENTRANCE / EXIT RAMP MI     323.600 350.00000 1
738 6009 CLEANING / SWEEPING (AGGREGATE REMOVAL MI     200.000 500.00000 1
738 6010 CLEANING / SWEEPING (SPOT) MI     110.000 300.00000 1
738 6011 CLEANING / SWEEPING (HANDWORK) SY     1,225,598.000 0.40000 1
738 6034 CLEAN / SWEEP - OUTSIDE MAIN LANE - AREA (1 MI     6.680 100.00000 1
751 6008 MOWING, TRIMMING, AND EDGING CYC     16.000 145.00000 1
751 6009 MULCH & RESHAPING OF PLANT BEDS CYC     1.000 440.00000 1
751 6010 PLANT BED MAINTENANCE CYC     16.000 58.00000 1
751 6064 MOWING, TRIMMING AND EDGING (SITE A) CYC     1.000 145.00000 1
751 6079 PLANT BED MAINTENANCE (SITE A) CYC     1.000 58.00000 1
752 6003 TREE TRIMMING / BRUSH REMOVAL MI     9.000 3,000.00000 2
752 6005 TREE REMOVAL (4" - 12" DIA) EA     1,092.000 80.00000 2
752 6006 TREE REMOVAL (12" - 18" DIA) EA     544.000 100.00000 2
752 6007 TREE REMOVAL (18" - 24" DIA) EA     471.000 127.91932 3
752 6008 TREE REMOVAL (24" - 30" DIA) EA     164.000 225.00000 2
752 6009 TREE REMOVAL (30" - 36" DIA) EA     68.000 300.00000 2
752 6010 TREE REMOVAL (36" - 42" DIA) EA     16.000 900.00000 2
752 6011 TREE REMOVAL (42" - 48" DIA) EA     40.000 900.00000 2
752 6012 TREE REMOVAL (48" - 60" DIA) EA     34.000 900.00000 2
752 6013 TREE REMOVAL (60" - 72" DIA) EA     36.000 900.00000 2
752 6019 TREE REMOVAL (72" - 84" DIA) EA     12.000 900.00000 2
760 6001 DITCH CLEANING AND RESHAPING (FOOT) LF 381,355.000 1.65000 459,909.000 1.64146 2
770 2001 REPAIR RAIL ELEMENT (W - BEAM) LF     9,500.000 14.54789 2
770 2002 REPAIR RAIL ELEMENT (THRIE - BEAM) LF     31.000 14.59968 2
770 2003 REP RAIL ELMNT (THRIE - BM TRANS TO W - BM) LF     31.000 14.68484 2
770 2004 REM / REPL TIMBER / STL POST W / O CONC FND EA     200.000 36.75500 2
770 2005 REM / REPL TIMBER / STL POST W / CONC FND EA     330.000 32.74000 2
770 2006 REALIGN POSTS EA     218.000 13.16606 2
770 2007 REPAIR OF TERMINAL ANCHORS POSTS EA     2.000 15.60500 2
770 2008 REPLACE TERMINAL ANCHOR POSTS EA     13.000 77.20231 2
770 2009 REMOVE GDRAIL END TRT / REPL WITH SGT EA     17.000 2,118.22765 2
770 2010 REPL SINGLE GDRAIL TERM IMPACT HEAD EA     34.000 972.74588 2
770 2011 REPLACE SINGLE GDRAIL TERMINAL RAIL LF     2,400.000 19.76500 2
770 2012 REPLACE SINGLE GDRAIL TERMINAL POST EA     350.000 35.71429 2
770 2014 REPAIR STEEL POST WITH BASE PLATE EA     2.000 100.00000 2
770 2022 REM & RESET SGT IMPACT HEAD EA     115.000 104.34783 2
770 2025 REPLACE SGT CABLE ASSEMBLY EA     50.000 54.40000 2
770 2026 REPLACE SGT STRUT EA     6.000 114.00000 2
770 2027 REMOVE & REPLACE BLOCKOUT EA     800.000 5.75000 2
770 2035 REPAIR RAIL ELEMENT (CURVED RAIL) LF     375.000 19.40000 2
770 6001 REPAIR RAIL ELEMENT (W - BEAM) LF     1,500.000 25.00000 1
770 6002 REPAIR RAIL ELEMENT (THRIE - BEAM) LF     1.000 50.00000 1
770 6003 REP RAIL ELMNT (THRIE - BM TRANS TO W - BM LF     1.000 50.00000 1
770 6004 REPAIR RAIL ELEMENT (CURVED RAIL) LF     50.000 15.00000 1
770 6010 REM / REPL TIMBER / STL POST W / O CONC FN EA     50.000 80.00000 1
770 6011 REM / REPL TIMBER / STL POST W / CONC FN EA     30.000 80.00000 1
770 6017 REALIGN POSTS EA     68.000 40.00000 1
770 6019 REMOVE & REPLACE BLOCKOUT EA     200.000 1.00000 1
770 6021 REPLACE SINGLE GDRAIL TERMINAL RAIL LF     400.000 23.00000 1
770 6022 REPLACE SINGLE GDRAIL TERMINAL POST EA     100.000 50.00000 1
770 6023 REPAIR OF TERMINAL ANCHORS POSTS EA     1.000 1.00000 1
770 6024 REPLACE TERMINAL ANCHOR POSTS EA     3.000 1.00000 1
770 6027 REMOVE GDRAIL END TRT / REPL WITH SGT EA     5.000 2,900.00000 1
770 6028 REPL SINGLE GDRAIL TERM IMPACT HEAD EA     10.000 800.00000 1
770 6029 REM & RESET SGT IMPACT HEAD EA     10.000 150.00000 1
770 6030 REPLACE SGT CABLE ASSEMBLY EA     10.000 1.00000 1
770 6032 REPLACE SGT STRUT EA     2.000 500.00000 1
770 6052 REPAIR STEEL POST WITH BASE PLATE EA     1.000 200.00000 1
771 6001 REPLACE POSTS (TL - 3) EA     350.000 135.00000 1
771 6002 REPLACE POSTS (TL - 4) EA     700.000 200.00000 1
771 6003 CABLE SPLICE / TURNBUCKLE (TL - 3) EA     5.000 100.00000 1
771 6004 CABLE SPLICE / TURNBUCKLE (TL - 4) EA     10.000 100.00000 1
771 6005 REPAIR CONCRETE FOUNDATION (TL - 3) EA     1.000 380.00000 1
771 6006 REPAIR CONCRETE FOUNDATION (TL - 4) EA     1.000 480.00000 1
771 6007 REPR OR REPLC CABLE BARR TERM SEC (TL - 3 EA     5.000 400.00000 1
771 6008 REPR OR REPLC CABLE BARR TERM SEC (TL - 4 EA     50.000 100.00000 1
771 6009 REPLACE CABLE (TL - 3) LF     50.000 5.00000 1
771 6010 REPLACE CABLE (TL - 4) LF     50.000 5.00000 1
771 6011 CHECK / RE - TENSION CABLE EA     50.000 100.00000 1
774 2001 REMOVE AND REPLACE (TRACC) EA     2.000 12,000.00000 2
774 2014 REMOVE AND REPLACE (NARROW QUAD) EA     2.000 15,000.00000 2
774 2018 REPAIR (CATGR - FRONT SECTION) EA     1.000 3,850.00000 1
774 2019 REPAIR (CATGR - END SECTION) EA     1.000 1,400.00000 1
774 2022 REMOVE AND REPLACE (CATGR) EA     2.000 3,800.00000 2
774 2028 REPAIR (QUAD) (N) (BAY) EA     15.000 1,000.00000 1
774 2029 REPAIR (QUAD) (W) (BAY) EA     2.000 2,100.00000 2
774 2035 REPAIR REACT (CYLINDERS) EA     25.000 1,480.00000 2
774 2037 REPAIR REACT (W) (CYLINDERS) EA     2.000 1,350.00000 2
774 2059 REPAIR (TRACC) (BAY) EA     25.000 520.00000 2
774 2060 REPAIR (WIDE TRACC) (BAY) EA     2.000 1,600.00000 2
774 6001 REMOVE AND REPLACE (TRACC) EA     1.000 18,000.00000 1
774 6014 REMOVE AND REPLACE (NARROW QUAD) EA     1.000 18,000.00000 1
774 6018 REPAIR (CATGR - FRONT SECTION) EA     1.000 3,500.00000 1
774 6019 REPAIR (CATGR - END SECTION) EA     1.000 500.00000 1
774 6022 REMOVE AND REPLACE (CATGR) EA     1.000 4,500.00000 1
774 6028 REPAIR (QUAD) (N) (BAY) EA     15.000 1,300.00000 1
774 6029 REPAIR (QUAD) (W) (BAY) EA     1.000 1,900.00000 1
774 6035 REPAIR REACT (CYLINDERS) EA     10.000 1,000.00000 1
774 6037 REPAIR REACT (W) (CYLINDERS) EA     1.000 500.00000 1
774 6059 REPAIR (TRACC) (BAY) EA     10.000 1,400.00000 1
774 6060 REPAIR (WIDE TRACC) (BAY) EA     1.000 2,000.00000 1
774 6079 REMOVE & REPLACE TRACC (TXDOT FURNISHD EA     2.000 4,500.00000 1
774 6080 REMOVE & REPLACE REACT 350 (TXDOT FRNSH EA     2.000 3,500.00000 1
785 6008 BRIDGE JOINT REPAIR (FULL DEPTH) LF     816.000 325.00000 2