Monthly State Let Construction Report For Austin District As Of Apr 7, 2016 Page 12 Of 14

Last Update: Thursday, April 7, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWILLIAMSON
Highway RM 1431
From FM 734
To CR 175
CSJ 1378-02-036
Proj ID PTF 2014(560)
Work Type WIDEN TO 6 - LANE URBAN ROADWAY
 
1.491 17353255.75 963876.44 12602771.63 72.6
Work Order 06-05-14
Work Began 08-17-14
Work Completed  
Time Computed 01-04-16
Contract Working Days 269
Addl Days Granted 150
Working Days Charged 283
Percent Time Used 67
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-036
AARON CONCRETE CONTRACTORS, L.P. (4.48%)
ABC EROSION CONTROL, INC.(0.65%)
AUSTIN WOOD RECYCLING(0.11%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.30%)
FLASHER EQUIPMENT COMPANY(1.47%)
G. CARTER CONSTRUCTION COMPANY, INC. (7.06%)
GK CONSTRUCTION, LLC (0.07%)
KELLYSTONE, INC(0.94%)
ROADWAY SPECIALTIES, INC.(2.95%)
ROYAL VISTA INC. ( 16.40%)
VOGES DRILLING CO. (0.14%)
TEXAS CUTTING & CORING, INC. (0.03%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.25%)
SCOTT DERR PAINTING CO, LLC(0.02%)
SPEEDY PAVING(0.99%)
Contract # 04143201
Totals 17353255.75 963876.44 12602771.63 72.6

CountyWILLIAMSON
Highway RM 1431
From US 183
To 183-A
CSJ 1378-02-037
Proj ID STP 1102(351)
Work Type LANDSCAPING, IRRIGATION & PAVERS
 
0.904 357255.50 0.00 351458.62 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-13-11
Work Began 03-05-12
Work Completed 11-11-15
Time Computed 12-12-11
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 95
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-037
N-LINE TRAFFIC MAINTENANCE, L.P. (1.04%)
Contract # 08113010
Totals 357255.50 0.00 351458.62 100.0

CountyWILLIAMSON
Highway RM 1431
From ANDERSON MILL RD
To 600 FT WEST OF 183A
CSJ 1378-02-039
Proj ID C 1378-2-39
Work Type INNOVATIVE INTERSECTION IMPROVEMNTS
 
1.417 3965954.63 84372.41 3900503.66 98.3
Work Order 11-13-13
Work Began 03-05-14
Work Completed  
Time Computed 01-12-14
Contract Working Days 108
Addl Days Granted 72
Working Days Charged 175
Percent Time Used 97
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-039
PERFORMANCE EQUIPMENT(0.15%)
RAMMING PAVING COMPANY ( 40.83%)
ROADWAY SPECIALTIES, INC.(0.58%)
FLASHER EQUIPMENT COMPANY(4.37%)
G. CARTER CONSTRUCTION COMPANY, INC. (7.73%)
Contract # 08133073
Totals 3965954.63 84372.41 3900503.66 98.3

CountyWILLIAMSON
Highway RM 1431
From 1000 WEST OF CHANDLER CREEK
To 200 EAST OF UNIVERSITY OAKS BLVD.
CSJ 1378-02-040
Proj ID STP 2013(297)
Work Type CONST DIVERGING DIAMOND INTRSCTN
 
0.392 6684011.97 26962.70 6058689.68 90.6
Work Order 08-13-14
Work Began 10-20-14
Work Completed  
Time Computed 08-29-14
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 177
Percent Time Used 100
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-040
N-LINE TRAFFIC MAINTENANCE, L.P. (0.37%)
ROADWAY SPECIALTIES, INC.(5.23%)
CHEROKEE SERVICES(0.32%)
SPEEDY PAVING(1.10%)
TEXAS TRUCKING COMPANY, INC. (0.95%)
EARTH REINFORCEMENT SPECIALISTS(4.83%)
Contract # 06143242
Totals 6684011.97 26962.70 6058689.68 90.6

CountyWILLIAMSON
Highway RM 1431
From 183A (TOLL) NBFR
To 0.20 MI. EAST OF CR 185
CSJ 1378-02-045
Proj ID STP 2014(938)
Work Type MILL, SEAL, OVRLAY & RESTRP TO 6 - LN
 
0.821 430708.20 0.00 518982.53 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-15-14
Work Began 09-23-14
Work Completed  
Time Computed 09-22-14
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 88
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-045
D. I. J. CONSTRUCTION, INC.(8.39%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.81%)
Contract # 07143241
Totals 430708.20 0.00 518982.53 99.9

CountyWILLIAMSON
Highway FM 3406
From 0.13 MI. EAST OF WYOMING SPRINGS DR
To 0.05 MI. WEST OF GTRR
CSJ 1378-06-011
Proj ID STP 2015(882)
Work Type WIDEN TO 5 - LANE WITH CENTER LTL
 
1.290 4776174.80 172046.32 2731313.13 57.1
Work Order 06-04-15
Work Began 07-30-15
Work Completed  
Time Computed 07-05-15
Contract Working Days 260
Addl Days Granted 0
Working Days Charged 164
Percent Time Used 63
Contractor(s)
CHASCO CONSTRUCTORS
SUBCONTRACTOR(S) FOR CCSJ: 1378-06-011
ENVIRONMENTAL SAFETY SERVICES, INC.(7.01%)
BEAIRD DRILLING(0.56%)
FARR FOUNDATION, INC.(3.11%)
VIKING FENCE CO, LTD.(0.00%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.64%)
FLASHER EQUIPMENT COMPANY(1.66%)
APAC-TEXAS, INC. ( 14.93%)
Contract # 04153233
Totals 4776174.80 172046.32 2731313.13 57.1

CountyCALDWELL
Highway FM 1977
From SAN MARCOS RIVER
To (STR 1434-03-002)
CSJ 1434-03-010
Proj ID BR 2013(250)
Work Type REPLACE BRIDGE & APPROACHES
 
0.104 1254724.88 0.00 1118151.13 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-15-13
Work Began 06-10-13
Work Completed 02-04-15
Time Computed 01-31-13
Contract Working Days 80
Addl Days Granted 34
Working Days Charged 314
Percent Time Used 275
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1434-03-010
O & S TRAFFIC SUPPLIES (0.51%)
RICE ENVIRONMENTAL SERVICES(3.26%)
FLASHER EQUIPMENT COMPANY(0.26%)
WEBBER-BALKE FOUNDATION COMPANY, INC.( 16.88%)
Contract # 12123209
Totals 1254724.88 0.00 1118151.13 100.0

CountyHAYS
Highway RM 1826
From AT DARDEN HILL RD
To .
CSJ 1754-02-019
Proj ID CC 1754-2-19
Work Type ADD TURN LANES & SHOULDERS
 
0.365 746842.80 0.00 778356.57 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-05-15
Work Began 02-02-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 116
Percent Time Used 89
Contractor(s)
M. A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1754-02-019
ENVIRONMENTAL SAFETY SERVICES, INC.(4.64%)
LONE STAR PAVING COMPANY ( 39.74%)
TRP CONSTRUCTION GROUP, LLC(4.37%)
ROADWAY SPECIALTIES, INC.( 24.40%)
Contract # 10143210
Totals 746842.80 0.00 778356.57 99.9

CountyHAYS
Highway RM 1826
From TRAVIS C/L
To RM 150
CSJ 1754-02-024
Proj ID STP 2015(193)HESG
Work Type C.L & SHOULDERS RAISED PROF MARKS
 
26.276 605145.34 4246.72 679000.74 99.9
Work Order 11-14-14
Work Began 07-21-15
Work Completed  
Time Computed 11-30-14
Contract Working Days 40
Addl Days Granted 12
Working Days Charged 75
Percent Time Used 144
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1754-02-024
ROADWAY SPECIALTIES, INC.( 30.11%)
NIXON ENGINEERING(3.74%)
Contract # 10143009
Totals 605145.34 4246.72 679000.74 99.9

CountyHAYS
Highway RM 1826
From TRAVIS COUNTY LINE
To NUTTY BROWN ROAD
CSJ 1754-02-025
Proj ID STP 1502(597)
Work Type GRADING, BASE, ACP & PVMNT MARKINGS
 
2.186 4013235.58 249473.82 249473.82 6.2
Work Order 01-22-16
Work Began 03-01-16
Work Completed  
Time Computed 03-01-16
Contract Working Days 252
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 7
Contractor(s)
BPI - BAUERLE PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1754-02-025
A BROTHERS MILLING, LLC(0.85%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.57%)
FLASHER EQUIPMENT COMPANY(0.35%)
RAMMING PAVING COMPANY ( 52.04%)
ROADWAY SPECIALTIES, INC.(6.33%)
Contract # 08153029
Totals 4013235.58 249473.82 249473.82 6.2

CountyHAYS
Highway RM 967
From COLE SPRING ROAD
To FM 1626
CSJ 1776-01-032
Proj ID STP 2013(655)
Work Type ADD TWLTL AND SHOULDERS
 
2.618 4408237.86 678612.03 3899619.38 89.4
Work Order 07-11-14
Work Began 09-08-14
Work Completed  
Time Computed 09-08-14
Contract Working Days 227
Addl Days Granted 46
Working Days Charged 320
Percent Time Used 117
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1776-01-032
ALTUS TRAFFIC MANAGEMENT LLC (0.41%)
AUSTIN WOOD RECYCLING(1.86%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.21%)
FLASHER EQUIPMENT COMPANY(0.45%)
FUQUAY, INC. (1.42%)
RAMMING PAVING COMPANY ( 32.68%)
ROADWAY SPECIALTIES, INC.(1.40%)
Contract # 05143014
Totals 4408237.86 678612.03 3899619.38 89.4

CountyTRAVIS
Highway FM 1825
From 10TH STREET IN PFLUGERVILLE
To FM 685
CSJ 1902-01-027
Proj ID STP 2015(738)
Work Type FULL DEPTH REPAIR, SEAL & OVERLAY
 
0.904 406530.37 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-15
Work Began 00-00-00
Work Completed  
Time Computed 05-11-15
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1902-01-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153028
Totals 406530.37 0.00 0.00 0.0

CountyTRAVIS
Highway RM 2222
From LP 1
To LAMAR BLVD
CSJ 2100-01-056
Proj ID NH 2015(739)
Work Type MILL, SEAL & OVERLAY
 
2.089 1390365.50 42477.65 1596126.50 99.9
Work Order 04-10-15
Work Began 09-21-15
Work Completed  
Time Computed 05-11-15
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 112
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2100-01-056
THE LEVY COMPANY, L.P. (5.86%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.69%)
LONE STAR PAVING ( 30.11%)
TRP CONSTRUCTION GROUP, LLC(3.14%)
Contract # 03153227
Totals 1390365.50 42477.65 1596126.50 99.9

CountyTRAVIS
Highway RM 2222
From 0.151 MILES WEST OF MCNEIL DRIVE
To 0.260 MILES EAST OF MCNEIL DRIVE
CSJ 2100-01-057
Proj ID STP 1502(043)
Work Type CONSTRUCT DUAL LEFT TURN LANE
 
0.411 1104648.20 270.00 1180665.62 100.0
Work Order 04-20-15
Work Began 06-22-15
Work Completed 02-25-16
Time Computed 05-21-15
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 65
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2100-01-057
LONE STAR PAVING CO. ( 23.12%)
G. CARTER CONSTRUCTION COMPANY, INC. ( 14.88%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.96%)
TRP CONSTRUCTION GROUP, LLC(2.68%)
Contract # 03153231
Totals 1104648.20 270.00 1180665.62 100.0

CountyTRAVIS
Highway RM 2222
From 500 W OF WESTSLOPE CIRCLE
To LP 1 SBFR
CSJ 2100-01-058
Proj ID STP 2014(535)
Work Type UNDERSEAL AND OVERLAY
 
3.154 747616.73 0.00 819480.04 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 10-07-14
Work Completed  
Time Computed 05-01-14
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 105
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2100-01-058
N-LINE TRAFFIC MAINTENANCE, L.P. (0.46%)
TEX OP CONSTRUCTION, LP(1.41%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.96%)
FLASHER EQUIPMENT COMPANY(5.71%)
Contract # 03143215
Totals 747616.73 0.00 819480.04 99.9

CountyTRAVIS
Highway RM 2244
From 1000 FT. WEST OF BUCKEYE TRAIL
To WALSH TARLTON
CSJ 2102-01-064
Proj ID ROW 2102-1-64
Work Type UTILITY ADJUSTMENTS
 
1.230 7057669.40 0.00 0.00 0.0
CountyTRAVIS
Highway RM 2244
From 0.1 MILE EAST OF REDBUD TRAIL
To 1000 FT. WEST OF BUCKEYE TRAIL
CSJ 2102-01-066
Proj ID STP 1502(598)
Work Type CONST 4 - LN URBAN RDWY W / CONT LTL
 
1.799 21695145.83 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-11-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 524
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2102-01-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153004
Totals 28752815.23 0.00 0.00 0.0

CountyBURNET
Highway RM 2341
From 0.85 MI N OF CR 114
To SH 29
CSJ 2206-01-015
Proj ID STP 1502(390)HES
Work Type SAFETY TREATMENTS, ADD PAVE WIDTH
 
5.400 3547716.58 172483.00 1534500.10 43.2
Work Order 09-11-15
Work Began 10-12-15
Work Completed  
Time Computed 10-12-15
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 42
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2206-01-015
N-LINE TRAFFIC MAINTENANCE, L.P. (0.54%)
ROADWAY SPECIALTIES, INC.(8.86%)
DELGADO"S CONSTRUCTION (1.37%)
AUSTIN WOOD RECYCLING(1.73%)
LONE STAR PAVING COMPANY (6.71%)
Contract # 07153212
Totals 3547716.58 172483.00 1534500.10 43.2

CountyWILLIAMSON
Highway FM 1460
From 0.1 MI. N. OF QUAIL VALLEY DRIVE
To 0.6 MI. N. OF CR 111 (WESTINGHOUSE)
CSJ 2211-02-017
Proj ID STP 1402(060)
Work Type CONST 4 - LN DIV & LTL
 
2.022 11875032.06 803097.50 894223.41 7.5
CountyWILLIAMSON
Highway FM 1460
From 0.1 MI. N. OF QUAIL VALLEY DRIVE
To 0.6 MI. N. OF CR 111 (WESTINGHOUSE)
CSJ 2211-02-019
Proj ID HP 2012(774)
Work Type ROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
2.232 490003.34 0.00 0.00 0.0
CountyWILLIAMSON
Highway FM 1460
From 0.6 MI. N OF CR 111 (WESTINGHOUSE)
To 0.05 MI. N. OF UNIVERSITY BLVD
CSJ 2211-02-026
Proj ID STP 1402(059)MM
Work Type CONSTRUCT 4 - LANE DIVIDED SECTION
 
1.600 9154356.30 384622.44 452886.47 4.9
Work Order 05-14-15
Work Began 02-08-16
Work Completed  
Time Computed 11-10-15
Contract Working Days 390
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 8
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2211-02-017
R K STEPHENS CONSTRUCTION, LLC (3.23%)
TRP CONSTRUCTION GROUP, LLC(0.25%)
FLASHER EQUIPMENT COMPANY(0.08%)
AUSTIN WOOD RECYCLING(0.18%)
AARON CONCRETE CONTRACTORS, L.P. (4.21%)
JUST GROOVING, LTD.(0.01%)
Contract # 08143204
Totals 21519391.70 1187719.94 1347109.88 6.2

CountyHAYS
Highway FM 2439
From CENTERPOINT ROAD
To POSEY ROAD
CSJ 2293-01-023
Proj ID C 2293-1-23
Work Type ADD CTL & 2 - LANE DIVIDED WITH SHLDR
 
0.100 2375537.19 0.00 2253672.30 96.9
CountyHAYS
Highway FM 2439
From CENTERPOINT ROAD
To POSEY ROAD
CSJ 2293-01-026
Proj ID RW 2293-1-23
Work Type ROW UTL. ADJ.
 
0.100 586353.33 0.00 624199.20 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-06-14
Work Began 03-08-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 95
Addl Days Granted 30
Working Days Charged 188
Percent Time Used 150
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2293-01-023
AUSTIN WOOD RECYCLING(1.17%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.14%)
THE LEVY COMPANY, L.P. (1.03%)
M & M INDUSTRIAL PAINTING(0.18%)
FLASHER EQUIPMENT COMPANY(2.14%)
M. C. ETHRIDGE COMPANY ( 17.68%)
ROADWAY SPECIALTIES, INC.(2.35%)
ROSCH COMPANY(1.97%)
Contract # 08133055
Totals 2961890.52 0.00 2877871.50 98.8

CountyHAYS
Highway FM 2439
From WONDER WORLD DR
To BISHOP STREET
CSJ 2293-01-024
Proj ID C 2293-1-24
Work Type ADD CENTER TURN LANE
 
0.840 5945396.48 56185.36 5444921.22 92.3
CountyHAYS
Highway FM 2439
From WONDER WORLD DR
To BISHOP STREET
CSJ 2293-01-025
Proj ID RW 2293-1-25
Work Type ADJUSTMENT OF UTILITIES
 
0.840 1005448.75 0.00 1059596.34 99.9
Work Order 01-09-14
Work Began 03-17-14
Work Completed  
Time Computed 03-03-14
Contract Working Days 263
Addl Days Granted 68
Working Days Charged 356
Percent Time Used 107
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2293-01-024
ANGEL BROTHERS ENTERPRISES, LTD. ( 16.23%)
ENCINO LANDSCAPE, INC. (1.01%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.89%)
GK CONSTRUCTION, LLC (0.45%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.52%)
THE LEVY COMPANY, L.P. (4.50%)
JUST GROOVING, LTD.(0.05%)
SCOTT DERR PAINTING CO (0.01%)
VOGES DRILLING (0.44%)
THOMAS TURF GRASS(0.32%)
UNDERGROUND WATER SOLUTIONS, CO. (2.11%)
Contract # 10133012
Totals 6950845.23 56185.36 6504517.56 94.2

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14