Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
County | BASTROP |
Highway |
FM 696 |
From |
1.165 MI N OF US 290 |
To |
1.296 MI N OF US 290 |
CSJ |
1073-01-020 |
Proj ID |
BR 1502(072) |
Work Type |
REPLACE BRIDGE AND APPROACHES |
|
|
0.131 |
2191679.00 |
110706.25 |
878163.96 |
40.0 |
Work Order |
08-26-15 |
Work Began |
01-05-16 |
Work Completed |
|
Time Computed |
10-25-15 |
Contract Working Days |
202 |
Addl Days Granted |
0 |
Working Days Charged |
60 |
Percent Time Used |
29 |
Contractor(s) |
ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1073-01-020 ROADWAY SPECIALTIES, INC.(1.90%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.35%) MESA ROD BUSTERS, INC. (0.82%) ROADSAFE TRAFFIC SYSTEMS, INC. (0.95%) AUSTIN WOOD RECYCLING(0.71%) MURRAY CONSTRUCTION(0.14%) TEXAS CUTTING & CORING, INC. (0.20%)
|
Contract # |
06153008 |
|
Totals |
2191679.00 |
110706.25 |
878163.96 |
40.0 |
|
County | GILLESPIE |
Highway |
RM 783 |
From |
US 290 |
To |
8.977 MI S OF US 290 |
CSJ |
1135-01-026 |
Proj ID |
STP 2013(028)HES |
Work Type |
PROVIDE ADDITIONAL PAVED SURFACE WI |
|
|
8.977 |
5106864.29 |
0.00 |
5192717.80 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
04-03-13 |
Work Began |
04-15-13 |
Work Completed |
01-09-15 |
Time Computed |
04-15-13 |
Contract Working Days |
229 |
Addl Days Granted |
102 |
Working Days Charged |
331 |
Percent Time Used |
100 |
Contractor(s) |
ALLEN KELLER COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1135-01-026 ROADWAY SPECIALTIES, INC.(3.51%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.40%) RELMCO, INC. ( 31.14%) D. I. J. CONSTRUCTION, INC.(1.16%) VOGES DRILLING CO. (1.08%) LONE STAR PAVING COMPANY (2.40%)
|
Contract # |
02133212 |
|
Totals |
5106864.29 |
0.00 |
5192717.80 |
100.0 |
|
County | TRAVIS |
Highway |
FM 969 |
From |
DECKER CREEK DRIVE |
To |
BASTROP COUNTY LINE |
CSJ |
1186-01-087 |
Proj ID |
STP 2015(277)HES |
Work Type |
PROVIDE ADD'L PAVED SURFACE WIDTH |
|
|
7.101 |
5894316.37 |
88699.35 |
2901907.30 |
49.2 |
Work Order |
01-05-15 |
Work Began |
03-17-15 |
Work Completed |
|
Time Computed |
03-17-15 |
Contract Working Days |
398 |
Addl Days Granted |
0 |
Working Days Charged |
204 |
Percent Time Used |
51 |
Contractor(s) |
M. A. SMITH CONTRACTING COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-087 ENVIRONMENTAL SAFETY SERVICES, INC.(7.14%) TRP CONSTRUCTION GROUP, LLC(2.30%) LONE STAR PAVING, INC. ( 47.54%)
|
Contract # |
11143219 |
|
Totals |
5894316.37 |
88699.35 |
2901907.30 |
49.2 |
|
County | TRAVIS |
Highway |
FM 969 |
From |
TANNEHILL LANE |
To |
FM 3177 |
CSJ |
1186-01-089 |
Proj ID |
STP 2016(636) |
Work Type |
MILL, SEAL & TY D OVERLAY |
|
|
2.051 |
1000145.83 |
0.00 |
0.00 |
0.0 |
County | TRAVIS |
Highway |
FM 969 |
From |
AIRPORT BLVD |
To |
TANNEHILL LN |
CSJ |
1186-01-093 |
Proj ID |
STP 2016(853) |
Work Type |
MILL, SEAL & OVERLAY |
|
|
2.083 |
1067405.85 |
0.00 |
0.00 |
0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
00-00-00 |
Work Began |
00-00-00 |
Work Completed |
|
Time Computed |
00-00-00 |
Contract Working Days |
38 |
Addl Days Granted |
0 |
Working Days Charged |
0 |
Percent Time Used |
0 |
Contractor(s) |
ANGEL BROTHERS HOLDINGS CORP. |
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-089 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # |
03163028 |
|
Totals |
2067551.68 |
0.00 |
0.00 |
0.0 |
|
County | TRAVIS |
Highway |
FM 973 |
From |
1.2 MILES N OF THE COLORADO RIVER |
To |
SH 71 |
CSJ |
1200-03-028 |
Proj ID |
BR 2013(930) |
Work Type |
REPLACE BRIDGE & APPROACHES |
|
|
1.530 |
11659867.54 |
226970.45 |
9327528.61 |
79.9 |
County | TRAVIS |
Highway |
FM 973 |
From |
1.2 MILES N OF THE COLORADO RIVER |
To |
SH 71 |
CSJ |
1200-03-048 |
Proj ID |
STP 2012(591) |
Work Type |
ROW ACQ., UTL. ADJ.; RELOC. ASSIST. |
|
|
1.530 |
2188836.25 |
5080.00 |
2216775.04 |
99.9 |
Work Order |
02-13-14 |
Work Began |
05-19-14 |
Work Completed |
|
Time Computed |
05-19-14 |
Contract Working Days |
296 |
Addl Days Granted |
8 |
Working Days Charged |
301 |
Percent Time Used |
99 |
Contractor(s) |
THE LANE CONSTRUCTION CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-028 N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%) C4 CONSTRUCTION SERVICES, LLC(0.88%) ENVIRONMENTAL SAFETY SERVICES, INC.(0.67%) LINDAMOOD DEMOLITION, INC. (0.95%) MURRAY CONSTRUCTION(0.13%) ROADWAY SPECIALTIES, INC.(1.54%) M & M STRIPING & POWER WASHING, LLC(0.43%) AARON CONCRETE CONTRACTORS, L.P. (0.81%) AUSTIN WOOD RECYCLING(0.28%) BRYANT & FREY CONSTRUCTION (1.50%) TEX OP CONSTRUCTION, LP(0.14%) APAC-TEXAS, INC. ( 11.02%) CP REBAR AND PT INSTALLATION (0.46%) PRIMATE CONSTRUCTION, INC. (0.12%) MCKINNEY DRILLING COMPANY(2.77%) TEXAS HIGHWAY WALLS(3.63%) PANTHER CREEK TRANSPORTATION, INC. (0.89%)
|
Contract # |
12133203 |
|
Totals |
13848703.79 |
232050.45 |
11544303.65 |
83.3 |
|
County | TRAVIS |
Highway |
FM 973 |
From |
0.159 MI. SOUTH OF BLAKE MANOR RD. |
To |
600 FT. SOUTH OF MURCHISON ST. |
CSJ |
1200-03-045 |
Proj ID |
CC 1200-3-45 |
Work Type |
ADD CONTINUOUS LEFT TURN LANE |
|
|
0.312 |
85872.74 |
0.00 |
83077.17 |
96.7 |
County | TRAVIS |
Highway |
FM 973 |
From |
0.159 MI. SOUTH OF BLAKE MANOR RD. |
To |
DECKER CREEK |
CSJ |
1200-03-052 |
Proj ID |
STP 1402(058) |
Work Type |
REHAB RDWY, ADD 6' SHOULDERS |
|
|
4.911 |
3246677.62 |
110421.14 |
1686687.79 |
51.9 |
Work Order |
11-12-14 |
Work Began |
01-26-15 |
Work Completed |
|
Time Computed |
11-28-14 |
Contract Working Days |
247 |
Addl Days Granted |
0 |
Working Days Charged |
244 |
Percent Time Used |
98 |
Contractor(s) |
ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-052 M.V. HENKE ENTERPRISES, INC. (1.13%) ROADWAY SPECIALTIES, INC.(7.55%) ROADSAFE TRAFFIC SYSTEMS, INC. (1.83%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.69%)
|
Contract # |
09143236 |
|
Totals |
3332550.36 |
110421.14 |
1769764.96 |
53.1 |
|
County | TRAVIS |
Highway |
FM 973 |
From |
3880 FT SOUTH OF SH 71 |
To |
FM 812 |
CSJ |
1200-03-046 |
Proj ID |
STP 2014(621) |
Work Type |
ADD SHOULDERS, REPAIR & OVERLAY |
|
|
3.418 |
4060301.69 |
38133.66 |
3770835.28 |
92.9 |
Work Order |
05-29-14 |
Work Began |
08-07-14 |
Work Completed |
|
Time Computed |
07-28-14 |
Contract Working Days |
288 |
Addl Days Granted |
0 |
Working Days Charged |
292 |
Percent Time Used |
101 |
Contractor(s) |
HUNTER INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-046 AUSTIN WOOD RECYCLING(1.13%) CHEROKEE SERVICES(0.13%) FLASHER EQUIPMENT COMPANY(2.42%) ROADWAY SPECIALTIES, INC.(7.52%) TRP CONSTRUCTION GROUP, LLC(0.43%) RELMCO, INC. ( 13.01%) HAYWOOD BAKER(4.07%) THE LEVY COMPANY, L.P. (0.10%) MURRAY CONSTRUCTION(0.53%) VOGES DRILLING CO. (1.38%)
|
Contract # |
04143030 |
|
Totals |
4060301.69 |
38133.66 |
3770835.28 |
92.9 |
|
County | WILLIAMSON |
Highway |
FM 1466 |
From |
AT DRAW |
To |
(STR 1200-4-6) |
CSJ |
1200-04-011 |
Proj ID |
BR 1502(353) |
Work Type |
REPLACE BRIDGE AND APPROACHES |
|
|
0.063 |
597945.34 |
95127.21 |
581786.43 |
97.2 |
Work Order |
08-10-15 |
Work Began |
11-11-15 |
Work Completed |
|
Time Computed |
11-08-15 |
Contract Working Days |
48 |
Addl Days Granted |
0 |
Working Days Charged |
48 |
Percent Time Used |
100 |
Contractor(s) |
SB CONTRACTORS LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1200-04-011 ENVIRONMENTAL SAFETY SERVICES, INC.(6.53%) FLASHER EQUIPMENT COMPANY(1.65%) JJ KOONS, LLC. (8.28%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.82%) RAMMING PAVING COMPANY (7.46%)
|
Contract # |
06153052 |
|
Totals |
597945.34 |
95127.21 |
581786.43 |
97.2 |
|
County | TRAVIS |
Highway |
FM 973 |
From |
FM 812 |
To |
US 183 |
CSJ |
1200-05-016 |
Proj ID |
STP 2014(559) |
Work Type |
ADD SHOULDERS, REPAIR & OVERLAY |
|
|
2.466 |
3060816.52 |
20401.89 |
3102963.24 |
99.9 |
Work Order |
06-16-14 |
Work Began |
07-14-14 |
Work Completed |
|
Time Computed |
07-14-14 |
Contract Working Days |
180 |
Addl Days Granted |
0 |
Working Days Charged |
177 |
Percent Time Used |
98 |
Contractor(s) |
HUNTER INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1200-05-016 AUSTIN WOOD RECYCLING(1.13%) D. I. J. CONSTRUCTION, INC.(1.12%) THE LEVY COMPANY, L.P. (0.14%) MURRAY CONSTRUCTION(0.88%) RELMCO, INC. ( 30.62%) ROADWAY SPECIALTIES, INC.(4.85%) TRP CONSTRUCTION GROUP, LLC(0.28%)
|
Contract # |
04143018 |
|
Totals |
3060816.52 |
20401.89 |
3102963.24 |
99.9 |
|
County | TRAVIS |
Highway |
SH 45 |
From |
LOOP 1 |
To |
RM 1826 |
CSJ |
1200-06-010 |
Proj ID |
STP 2014(724) |
Work Type |
MILL, SEAL & THIN OVERLAY |
|
|
2.599 |
1283793.90 |
0.00 |
1158500.75 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
08-04-14 |
Work Began |
09-03-14 |
Work Completed |
03-03-15 |
Time Computed |
08-20-14 |
Contract Working Days |
41 |
Addl Days Granted |
0 |
Working Days Charged |
55 |
Percent Time Used |
134 |
Contractor(s) |
RAMMING PAVING COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1200-06-010 N-LINE TRAFFIC MAINTENANCE, L.P. (0.36%) D. I. J. CONSTRUCTION, INC.(3.74%) ROADWAY SPECIALTIES, INC.(4.80%)
|
Contract # |
06143028 |
|
Totals |
1283793.90 |
0.00 |
1158500.75 |
100.0 |
|
County | WILLIAMSON |
Highway |
FM 487 |
From |
IH35 |
To |
BELL COUNTY LINE |
CSJ |
1201-02-018 |
Proj ID |
STP 2015(737) |
Work Type |
REHAB RDWY |
|
|
4.212 |
6851307.42 |
471301.26 |
1056749.68 |
15.4 |
County | WILLIAMSON |
Highway |
FM 487 |
From |
IH35 |
To |
BELL COUNTY LINE |
CSJ |
1201-02-020 |
Proj ID |
ROW 1201-2-20 |
Work Type |
ROW ACQ & UTIL ADJ |
|
|
4.212 |
286200.00 |
29000.00 |
162900.06 |
56.9 |
Work Order |
10-20-15 |
Work Began |
01-11-16 |
Work Completed |
|
Time Computed |
11-19-15 |
Contract Working Days |
263 |
Addl Days Granted |
0 |
Working Days Charged |
50 |
Percent Time Used |
19 |
Contractor(s) |
M. A. SMITH CONTRACTING COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-018 TRP CONSTRUCTION GROUP, LLC(0.95%) RAMMING PAVING COMPANY ( 11.19%) ENVIRONMENTAL SAFETY SERVICES, INC.(4.34%) ACTION SERVICES(0.12%) R K STEPHENS CONSTRUCTION, LLC (6.55%)
|
Contract # |
03153230 |
|
Totals |
7137507.42 |
500301.26 |
1219649.74 |
17.0 |
|
County | WILLIAMSON |
Highway |
FM 487 |
From |
SH 195 |
To |
1500 FEET WEST OF CR 233 |
CSJ |
1201-02-019 |
Proj ID |
STP 2014(420) |
Work Type |
REHAB RDWY |
|
|
5.303 |
6128687.87 |
22004.00 |
5985014.87 |
97.6 |
Work Order |
04-16-14 |
Work Began |
06-25-14 |
Work Completed |
|
Time Computed |
05-02-14 |
Contract Working Days |
287 |
Addl Days Granted |
0 |
Working Days Charged |
284 |
Percent Time Used |
98 |
Contractor(s) |
APAC-TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-019 AARON CONCRETE CONTRACTORS, L.P. (1.40%) AUSTIN WOOD RECYCLING(1.19%) TEXAS HIGHWAY WALLS(5.57%) R K STEPHENS CONSTRUCTION, LLC (3.21%) D. I. J. CONSTRUCTION, INC.(0.77%) J & M CONTRACTING, COMPANY (7.41%) ROADWAY SPECIALTIES, INC.(2.24%) SAN-ANN-CO., INC.(0.55%) LONE STAR PAVING CO. ( 10.66%) INDUS CONSTRUCTION, L.P. (0.07%)
|
Contract # |
02143227 |
|
Totals |
6128687.87 |
22004.00 |
5985014.87 |
97.6 |
|
County | WILLIAMSON |
Highway |
FM 487 |
From |
1500 FEET WEST OF CR 233 |
To |
IH 35 |
CSJ |
1201-02-021 |
Proj ID |
STP 2015(190) |
Work Type |
REHAB RDWY |
|
|
7.186 |
9058441.29 |
474241.26 |
5404150.66 |
59.6 |
Work Order |
01-05-15 |
Work Began |
02-09-15 |
Work Completed |
|
Time Computed |
01-21-15 |
Contract Working Days |
306 |
Addl Days Granted |
0 |
Working Days Charged |
238 |
Percent Time Used |
77 |
Contractor(s) |
HUNTER INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-021 AARON CONCRETE CONTRACTORS, L.P. (5.81%) D&S TEXAS ICON CONSTRUCTION, LLC (3.67%) ENVIRONMENTAL SAFETY SERVICES, INC.(1.67%) FLASHER EQUIPMENT COMPANY(0.26%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.45%) R K STEPHENS CONSTRUCTION, LLC (4.64%) TRP CONSTRUCTION GROUP, LLC(1.39%) CHANDLER CONCRETE, INC.(2.57%) AUSTIN FORMULA UTILITIES (0.31%) EGGEMEYER LAND CLEARING, LLC (0.68%)
|
Contract # |
10143016 |
|
Totals |
9058441.29 |
474241.26 |
5404150.66 |
59.6 |
|
County | WILLIAMSON |
Highway |
FM 487 |
From |
BELL C/L |
To |
BELL C/L IN BARTLETT |
CSJ |
1201-03-021 |
Proj ID |
STP 2012(417) |
Work Type |
PAVMNT RESTORATION AND ADD SHLDRS |
|
|
7.520 |
6421595.35 |
0.00 |
7459105.17 |
100.0 |
County | BELL |
Highway |
FM 487 |
From |
WILLIAMSON CO LINE W OF FM 2115 |
To |
WILLIAMSON CO LINE E OF FM 2115 |
CSJ |
1201-05-010 |
Proj ID |
STP 2012(423) |
Work Type |
PAV RESTORATION AND ADD SHOULDERS |
|
|
0.395 |
285832.17 |
0.00 |
309719.23 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
05-04-12 |
Work Began |
05-20-13 |
Work Completed |
02-09-16 |
Time Computed |
05-20-12 |
Contract Working Days |
391 |
Addl Days Granted |
0 |
Working Days Charged |
359 |
Percent Time Used |
91 |
Contractor(s) |
JAMES CONSTRUCTION GROUP, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 1201-03-021 SOUTHWEST ENVIRONMENT SERVICES LLC (2.36%) SILVA CONTRACTING COMPANY, INC.( 11.18%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.62%) MURRAY CONSTRUCTION(0.48%) D. I. J. CONSTRUCTION, INC.(1.28%) ENVIRONMENTAL SAFETY SERVICES, INC.(4.04%) JAG TRUCKING INC (0.00%) PANTHER CREEK TRANSPORTATION, INC. (0.00%) THE LEVY COMPANY, L.P. (0.25%) R K STEPHENS CONSTRUCTION, LLC (6.66%) RAMMING PAVING COMPANY (3.88%) NEWMAN & KENG PAVING COMPANY, INC. (2.17%)
|
Contract # |
03123002 |
|
Totals |
6707427.52 |
0.00 |
7768824.40 |
100.0 |
|
County | WILLIAMSON |
Highway |
FM 972 |
From |
IH 35 |
To |
0.128 MILES WEST OF CR 150 |
CSJ |
1202-01-017 |
Proj ID |
STP 1502(073) |
Work Type |
REHAB PVMT, ADD SHLDR & SAFTY TREAT |
|
|
3.198 |
4156413.83 |
59321.45 |
640349.97 |
15.4 |
Work Order |
11-24-15 |
Work Began |
01-04-16 |
Work Completed |
|
Time Computed |
01-04-16 |
Contract Working Days |
234 |
Addl Days Granted |
0 |
Working Days Charged |
27 |
Percent Time Used |
11 |
Contractor(s) |
JORDAN FOSTER CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1202-01-017 APAC-TEXAS, INC. (8.51%) ROADWAY SPECIALTIES, INC.(3.02%) TRP CONSTRUCTION GROUP, LLC(0.98%)
|
Contract # |
09153204 |
|
Totals |
4156413.83 |
59321.45 |
640349.97 |
15.4 |
|
County | WILLIAMSON |
Highway |
FM 1063 |
From |
AT TURKEY CREEK |
To |
(STR 1202-3-12) |
CSJ |
1202-03-010 |
Proj ID |
BR 2014(534) |
Work Type |
REPLACE BRIDGE AND APPROACHES |
|
|
0.115 |
643228.90 |
0.00 |
661924.41 |
100.0 |
County | WILLIAMSON |
Highway |
FM 1063 |
From |
AT TURKEY CREEK RELIEF |
To |
(STR 1202-3-11) |
CSJ |
1202-03-011 |
Proj ID |
BR 2014(534) |
Work Type |
REPLACE BRIDGE AND APPROACHES |
|
|
0.064 |
286828.45 |
0.00 |
290786.28 |
100.0 |
County | WILLIAMSON |
Highway |
FM 1063 |
From |
AT DRAW |
To |
(STR 1202-3-10) |
CSJ |
1202-03-012 |
Proj ID |
BR 2014(673) |
Work Type |
REPLACE BRIDGE AND APPROACHES |
|
|
0.131 |
609386.85 |
0.00 |
607115.78 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
04-25-14 |
Work Began |
05-19-14 |
Work Completed |
06-24-15 |
Time Computed |
05-11-14 |
Contract Working Days |
150 |
Addl Days Granted |
0 |
Working Days Charged |
148 |
Percent Time Used |
98 |
Contractor(s) |
ELLIS-MCGINNIS CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 1202-03-010 FLASHER EQUIPMENT COMPANY(1.52%) GK CONSTRUCTION, LLC (0.78%) HOUSTON SAWING & DRILLING(0.23%) ROADWAY SPECIALTIES, INC.(0.62%) APAC-TEXAS, INC. (9.18%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.81%) SAN-ANN-CO., INC.(0.42%)
|
Contract # |
03143222 |
|
Totals |
1539444.20 |
0.00 |
1559826.47 |
100.0 |
|
County | WILLIAMSON |
Highway |
FM 1063 |
From |
0.046 MI N OF SPRING BRANCH |
To |
0.019 MI S OF SPRING BRANCH |
CSJ |
1202-03-015 |
Proj ID |
BR 2015(881) |
Work Type |
REPLACE BRIDGE |
|
|
0.065 |
758521.10 |
840.00 |
760998.87 |
99.2 |
Work Order |
06-01-15 |
Work Began |
11-09-15 |
Work Completed |
|
Time Computed |
09-30-15 |
Contract Working Days |
90 |
Addl Days Granted |
0 |
Working Days Charged |
80 |
Percent Time Used |
88 |
Contractor(s) |
ELLIS-MCGINNIS CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 1202-03-015 APAC-TEXAS, INC. (4.39%) ALTUS TRAFFIC MANAGEMENT LLC (0.46%) VOGES DRILLING CO. (4.95%) FLASHER EQUIPMENT COMPANY(0.64%) ROADWAY SPECIALTIES, INC.(5.70%) JUST GROOVING, LTD.(0.25%) GK CONSTRUCTION, LLC (0.71%)
|
Contract # |
04153245 |
|
Totals |
758521.10 |
840.00 |
760998.87 |
99.2 |
|
County | CALDWELL |
Highway |
FM 1322 ETC |
From |
4.914 MI. NORTH OF FM 86 |
To |
FM 86 |
CSJ |
1375-01-010 |
Proj ID |
STP 2016(174) |
Work Type |
ACP, LVL - UP, FULL DEPTH REPAIR & SC |
|
|
31.597 |
2572762.09 |
965505.36 |
1741402.49 |
67.6 |
Work Order |
11-24-15 |
Work Began |
02-15-16 |
Work Completed |
|
Time Computed |
11-24-15 |
Contract Working Days |
56 |
Addl Days Granted |
0 |
Working Days Charged |
21 |
Percent Time Used |
37 |
Contractor(s) |
LONE STAR PAVING COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1375-01-010 GREEN MILLING GROUP(1.78%) TRP CONSTRUCTION GROUP, LLC(7.88%) F. N. PLOCH CONSTRUCTION COMPANY, INC. ( 27.45%)
|
Contract # |
10153006 |
|
Totals |
2572762.09 |
965505.36 |
1741402.49 |
67.6 |
|
County | TRAVIS |
Highway |
FM 1325 |
From |
LP 1 |
To |
US 183 |
CSJ |
1376-02-039 |
Proj ID |
STP 2013(478) |
Work Type |
MILL, SEAL & THIN OVERLAY |
|
|
2.500 |
2027036.96 |
0.00 |
1734155.12 |
86.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
06-03-13 |
Work Began |
09-30-13 |
Work Completed |
|
Time Computed |
08-02-13 |
Contract Working Days |
50 |
Addl Days Granted |
26 |
Working Days Charged |
92 |
Percent Time Used |
121 |
Contractor(s) |
RAMMING PAVING COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1376-02-039 AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.98%) D. I. J. CONSTRUCTION, INC.(3.65%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.20%) A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C. (2.98%) ROADWAY SPECIALTIES, INC.(0.42%) NEWMAN & KENG PAVING COMPANY, INC. ( 19.25%) TEX OP CONSTRUCTION, LP(0.43%) TEXAS TRUCKING COMPANY, INC. (3.37%)
|
Contract # |
03133230 |
|
Totals |
2027036.96 |
0.00 |
1734155.12 |
86.1 |
|
County | WILLIAMSON |
Highway |
RM 1431 |
From |
0.2 MI E OF CR 185 |
To |
IH 35 |
CSJ |
1378-02-033 |
Proj ID |
STP 2012(251) |
Work Type |
FULL DEPTH REPAIR, SEAL & THIN OV |
|
|
6.888 |
2895175.70 |
0.00 |
2401514.51 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
02-22-12 |
Work Began |
06-03-13 |
Work Completed |
01-21-15 |
Time Computed |
03-09-12 |
Contract Working Days |
66 |
Addl Days Granted |
15 |
Working Days Charged |
107 |
Percent Time Used |
132 |
Contractor(s) |
ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-033 D. I. J. CONSTRUCTION, INC.(4.01%) CPAVE, INC.(2.17%) RPV CONSTRUCTION ( 15.51%)
|
Contract # |
01123226 |
|
Totals |
2895175.70 |
0.00 |
2401514.51 |
100.0 |
|