MIS.CIS.19 MONTHLY STATE LET CONSTRUCTION REPORT DISTRICT 14 AS OF MAY 15, 2013 PAGE 40 ************************************************************************************************************************************ * | | CONTRACT | AMOUNT THIS | TOTAL ESTIMATE | % * * CONTRACT IDENTIFICATION AND INFORMATION | LENGTH | AMOUNT | ESTIMATE | TO DATE | COMP* ************************************************************************************************************************************ BASTROP 0.879 MI. NW OF SH 304 | 0.297 | 1,167,862.65| 161,097.50| 161,097.50| 13.7| FM 535 0.582 MI. NW OF SH 304 | | | | | | 0807-01-024 | | | | | | BR 2013(340) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 03-04-13 WORK BEGAN- 03-26-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 03-26-13 | | | | | | CONTRACT WORKING DAYS- 127 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 17 PERCENT TIME USED- 13 | | | | | | | | | | | | CAPITAL EXCAVATION COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0807-01-024 | | | | | | EGGEMEYER LAND CLEARING, LLC | |SUB %: 4.17 | | | | APAC-TEXAS, INC. | |SUB %: 18.69 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 1.23 | | | | W. W. FOUNDATION DRILLING, LTD. | |SUB %: 2.55 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 4.61 | | | | WIMS ENVIRONMENTAL CONSTRUCTION, LTD. | |SUB %: 2.14 | | | | | | | | | | CONTRACT 01133005 | TOTALS | 1,167,862.65| 161,097.50| 161,097.50| 13.7| ************************************************************************************************************************************ BASTROP TRAVIS COUNTY LINE | 8.168 | 3,366,603.51| 0.00| 0.00| 0.0| SH 71 2.944 MI WEST OF SH 21 | | | | | | 0265-03-038 | | | | | | STP 2013(339) MILL,SEAL & INLAY MAINLANES | | | | | | | | | | | | WORK ORDER- 05-14-13 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 48 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | APAC-TEXAS, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0265-03-038 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 01133208 | TOTALS | 3,366,603.51| 0.00| 0.00| 0.0| ************************************************************************************************************************************ BASTROP US 290 | 5.811 | 6,402,843.38| 589,959.63| 4,887,041.09| 76.3| SH 21 .80 MILES EAST OF FM 1441 | | | | | | 0472-01-037 | | | | | | STP 2012(415) ADD SHOULDERS,PAVEMENT REPAIR& SEAL | | | | | | | | | | | | WORK ORDER- 05-22-12 WORK BEGAN- 07-11-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 06-07-12 | | | | | | CONTRACT WORKING DAYS- 161 ADDL DAYS GRANTED- 43 | | | | | | WORKING DAYS CHARGED- 197 PERCENT TIME USED- 96 | | | | | | | | | | | | HUNTER INDUSTRIES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0472-01-037 | | | | | | EGGEMEYER LAND CLEARING, LLC | |SUB %: 0.92 | | | | RELMCO, INC. | |SUB %: 4.08 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.71 | | | | MURRAY CONSTRUCTION | |SUB %: 0.40 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 4.56 | | | | WIMS ENVIRONMENTAL CONSTRUCTION, LTD. | |SUB %: 1.58 | | | | | | | | | | CONTRACT 03123202 | TOTALS | 6,402,843.38| 589,959.63| 4,887,041.09| 76.3| ************************************************************************************************************************************ BASTROP 0.261 MI S OF FM 535 | 0.850 | 1,527,586.43| 1,448.12| 1,453,004.54| 95.1| FM 20 0.175 MI N OF FM 535 | | | | | | 0115-04-042 | | | | | | STP 2012(548) WDN, RE-ALIGN VERT, TWLTL, CULV, OV | | | | | | | | | | | | WORK ORDER- 07-09-12 WORK BEGAN- 10-22-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 09-07-12 | | | | | | CONTRACT WORKING DAYS- 63 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 60 PERCENT TIME USED- 95 | | | | | | | | | | | | HUNTER INDUSTRIES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0115-04-042 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.41 | | | | AUSTIN WOOD RECYCLING | |SUB %: 0.66 | | | | MPB, INC. | |SUB %: 3.36 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.92 | | | | MURRAY CONSTRUCTION | |SUB %: 1.13 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 0.85 | | | | | | | | | | CONTRACT 05123210 | TOTALS | 1,527,586.43| 1,448.12| 1,453,004.54| 95.1| ************************************************************************************************************************************ BASTROP 0.043 MI. SOUTH OF SH 71 | 2.634 | 6,181,473.52| 0.00| 0.00| 0.0| SH 304 2.677 MI. SOUTH OF SH 71 | | | | | | 0573-01-029 | | | | | | STP 2013(703) UPGRD TO 3 LN SEC WITH SHOULDERS | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 144 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | DAN WILLIAMS COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0573-01-029 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 05133207 | TOTALS | 6,181,473.52| 0.00| 0.00| 0.0| ************************************************************************************************************************************ BASTROP FM 20 | 29.901 | 1,180,575.40| 0.00| 1,018,055.40| 86.6| FM 535 SH 95 | | | | | | 0807-01-026 | | | | | | STP 1102(080)HES GUARDRAIL&SAFETY TREAT FIXED OBJCTS | | | | | | | | | | | | WORK ORDER- 08-16-11 WORK BEGAN- 01-13-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 10-15-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 123 ADDL DAYS GRANTED- 8 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 138 PERCENT TIME USED- 105 | |**************************************************| | | | | | | | BYRD BROTHERS EMERGENCY SERVICES, LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0807-01-026 | | | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | |SUB %: 33.08 | | | | ABC EROSION CONTROL, INC. | |SUB %: 1.20 | | | | ROADSAFE TRAFFIC SYSTEMS, INC. | |SUB %: 1.64 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 1.22 | | | | ADAM MEUTH CONSTRUCTION CO. | |SUB %: 28.39 | | | | BASTROP TREE SERVICE | |SUB %: 0.22 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.30 | | | | CONTRACTORS ASPHALT, LP | |SUB %: 0.33 | | | | | | | | | | CONTRACT 06113030 | TOTALS | 1,180,575.40| 0.00| 1,018,055.40| 86.6| ************************************************************************************************************************************ BASTROP SL 109 | 19.754 | 6,390,876.70| 202,999.75| 6,096,880.92| 95.3| FM 1704 FM 969 | | | | | | 1533-01-019 | | | | | | STP 1102(153)HES GUARDRAIL&SAFETY TREAT FIXED OBJCTS | | | | | | | | | | | | WORK ORDER- 07-19-11 WORK BEGAN- 09-12-11 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 09-12-11 | | | | | | CONTRACT WORKING DAYS- 143 ADDL DAYS GRANTED- 107 | | | | | | WORKING DAYS CHARGED- 228 PERCENT TIME USED- 91 | | | | | | | | | | | | KNIFE RIVER CORPORATION - SOUTH | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1533-01-019 | | | | | | APAC-TEXAS, INC. | |SUB %: 38.89 | | | | J & M CONTRACTING, COMPANY | |SUB %: 11.54 | | | | MURRAY CONSTRUCTION | |SUB %: 0.72 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 0.19 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 1.07 | | | | RICE ENVIRONMENTAL SERVICES | |SUB %: 3.26 | | | | TEXAS ALTERNATIVE GRASSER, INC. | |SUB %: 0.79 | | | | AUSTIN LAND SERVICE | |SUB %: 1.31 | | | | STATEWIDE MATERIALS TRANSPORT LTD | |SUB %: 2.15 | | | | | | | | | | CONTRACT 06113247 | TOTALS | 6,390,876.70| 202,999.75| 6,096,880.92| 95.3| ************************************************************************************************************************************ BASTROP COUNTY LINE RD. | 1.232 | 657,300.75| 64,867.82| 637,635.83| 97.0| FM 1100 1014 FT WEST OF SH 95 | | | | | | 1234-02-011 | | | | | | STP 1102(492)SRS CONST. SIDEWALKS & CROSSWALKS | | | | | | | | | | | | WORK ORDER- 08-20-12 WORK BEGAN- 10-15-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 09-05-12 | | | | | | CONTRACT WORKING DAYS- 100 ADDL DAYS GRANTED- 26 | | | | | | WORKING DAYS CHARGED- 126 PERCENT TIME USED- 100 | | | | | | | | | | | | BEAR CREEK CONSTRUCTION, LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1234-02-011 | | | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 1.06 | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 0.97 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 2.60 | | | | | | | | | | CONTRACT 07123205 | TOTALS | 657,300.75| 64,867.82| 637,635.83| 97.0| ************************************************************************************************************************************ BASTROP SH 21 | 7.286 | 4,348,946.83| 567,835.51| 1,654,154.34| 38.0| FM 535 FM 20 | | | | | | 0807-05-019 | | | | | | STP 2013(025)HES PROVIDE ADDITIONAL PAVED SURFACE WI | | | | | | | | | | | | WORK ORDER- 11-28-12 WORK BEGAN- 02-25-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 01-27-13 | | | | | | CONTRACT WORKING DAYS- 121 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 38 PERCENT TIME USED- 31 | | | | | | | | | | | | DEAN WORD COMPANY, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0807-05-019 | | | | | | AUSTIN WOOD RECYCLING | |SUB %: 1.75 | | | | WIMS ENVIRONMENTAL CONSTRUCTION, LTD. | |SUB %: 0.63 | | | | RELMCO, INC. | |SUB %: 13.62 | | | | DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) | |SUB %: 3.75 | | | | MURRAY CONSTRUCTION | |SUB %: 0.50 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 2.23 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.41 | | | | RICE ENVIRONMENTAL SERVICES | |SUB %: 0.11 | | | | G. CARTER CONSTRUCTION COMPANY, INC. | |SUB %: 0.29 | | | | | | | | | | CONTRACT 09123007 | TOTALS | 4,348,946.83| 567,835.51| 1,654,154.34| 38.0| ************************************************************************************************************************************ BASTROP WEST OF FM 20 | 1.354 | 12,032,551.48| 227,222.03| 9,005,489.86| 74.8| SH 71 EAST OF FM 969 | | | | | | 0265-04-057 | | | | | | SFT 265-4-57 CONSTRUCT OVERPASS | | | | | | | | | | | | BASTROP EAST OF FM 969 | 0.511 | 2,176,829.01| 24,755.68| 1,338,470.31| 61.4| SH 71 WEST OF SH 304 | | | | | | 0265-04-058 | | | | | | HP 2012(096) CONSTRUCT FRONTAGE ROADS & RAMPS | | | | | | | | | | | | WORK ORDER- 01-03-12 WORK BEGAN- 04-11-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 03-03-12 | | | | | | CONTRACT WORKING DAYS- 308 ADDL DAYS GRANTED- 70 | | | | | | WORKING DAYS CHARGED- 262 PERCENT TIME USED- 69 | | | | | | | | | | | | HUNTER INDUSTRIES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0265-04-057 | | | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 0.64 | | | | SOUTHERN STAR TRUCKING | |SUB %: 0.25 | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 4.07 | | | | DANRIDGE CONSTRUCTION, LLC. | |SUB %: 1.41 | | | | DUSTROL, INC. | |SUB %: 0.06 | | | | GK CONSTRUCTION, LLC | |SUB %: 0.06 | | | | HOUSTON SAWING & DRILLING | |SUB %: 0.02 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 1.43 | | | | PIONEER UTILITIES, INC. | |SUB %: 5.08 | | | | MURRAY CONSTRUCTION | |SUB %: 0.33 | | | | SPEEDY PAVING | |SUB %: 0.43 | | | | W. W. FOUNDATION DRILLING, LTD. | |SUB %: 0.55 | | | | S & S PAINTING | |SUB %: 0.02 | | | | GK CONSTRUCTION, LLC | |SUB %: 0.04 | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | |SUB %: 0.06 | | | | | | | | | | CONTRACT 11113201 | TOTALS | 14,209,380.49| 251,977.71| 10,343,960.17| 72.7| ************************************************************************************************************************************ BASTROP 0.28 MI EAST OF COUNTY LINE ROAD | 0.159 | 107,797.28| 39,100.52| 39,100.52| 36.2| US 290 0.44 MI EAST OF COUNTY LINE ROAD | | | | | | 0114-04-064 | | | | | | CC 114-4-64 EXTEND LEFT TURN LANE AT MEDIAN | | | | | | | | | | | | WORK ORDER- 02-19-13 WORK BEGAN- 03-27-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 03-07-13 | | | | | | CONTRACT WORKING DAYS- 41 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 15 PERCENT TIME USED- 36 | | | | | | | | | | | | DIAMOND X CONTRACTING, INC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0114-04-064 | | | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 6.18 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 6.48 | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | |SUB %: 2.28 | | | | LONE STAR PAVING CO. | |SUB %: 22.82 | | | | AARON CONCRETE CONTRACTORS, L.P. | |SUB %: 4.67 | | | | | | | | | | CONTRACT 12123205 | TOTALS | 107,797.28| 39,100.52| 39,100.52| 36.2| ************************************************************************************************************************************ BLANCO AT N CYPRESS CREEK | 0.071 | 742,748.14| 0.00| 811,696.19| 99.9| US 281 (STR 0252-03-010) | | | | | | 0252-03-045 | | | | | | BR 2011(955) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 06-14-11 WORK BEGAN- 01-10-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 06-30-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 99 ADDL DAYS GRANTED- 10 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 170 PERCENT TIME USED- 155 | |**************************************************| | | | | | | | DEAN WORD COMPANY, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0252-03-045 | | | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 1.33 | | | | DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) | |SUB %: 2.81 | | | | TURNKEY OPERATIONS | |SUB %: 0.67 | | | | BMP SPECIALIST, LLC | |SUB %: 1.38 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.50 | | | | | | | | | | CONTRACT 05113004 | TOTALS | 742,748.14| 0.00| 811,696.19| 99.9| ************************************************************************************************************************************ BLANCO SL 163 | 11.900 | 816,534.84| 49,955.09| 609,989.01| 74.7| RM 165 HAYS C/L | | | | | | 0954-02-016 | | | | | | STP 2012(553)HRR GUARDRAIL&SAFETY TREAT FIXED OBJCTS | | | | | | | | | | | | BLANCO SL 163 | 11.949 | 4,792,086.66| 174,187.09| 1,570,170.27| 32.7| RM 165 BLANCO/HAYS COUNTY LINE | | | | | | 0954-02-017 | | | | | | STP 2012(553)HRR PROVIDE ADDITIONAL PAVED SURFACE WI | | | | | | | | | | | | WORK ORDER- 07-12-12 WORK BEGAN- 10-02-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 09-10-12 | | | | | | CONTRACT WORKING DAYS- 261 ADDL DAYS GRANTED- 6 | | | | | | WORKING DAYS CHARGED- 137 PERCENT TIME USED- 51 | | | | | | | | | | | | DEAN WORD COMPANY, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0954-02-017 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 1.93 | | | | DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) | |SUB %: 3.76 | | | | ABC EROSION CONTROL, INC. | |SUB %: 0.72 | | | | AUSTIN WOOD RECYCLING | |SUB %: 1.45 | | | | JMHP, INC. | |SUB %: 0.85 | | | | | | | | | | CONTRACT 05123212 | TOTALS | 5,608,621.50| 224,142.18| 2,180,159.28| 38.8| ************************************************************************************************************************************ BLANCO ETC BURNET C/L | 66.151 | 1,471,795.60| 0.00| 1,631,966.84| 99.9| US 281 ETC US 290 IN JOHNSON CITY | | | | | | 0252-03-049 | | | | | | STP 2011(045)HES GUARDRAIL&SAFETY TREAT FIXED OBJCTS | | | | | | | | | | | | WORK ORDER- 09-01-10 WORK BEGAN- 10-25-10 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 10-25-10 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 360 ADDL DAYS GRANTED- 55 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 413 PERCENT TIME USED- 99 | |**************************************************| | | | | | | | WAGNER MATERIALS & CONSTRUCTION | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0252-03-049 | | | | | | HILL COUNTRY BRIDGE, INC. | |SUB %: 45.55 | | | | F.D. CONCRETE, LLC | |SUB %: 9.89 | | | | RICE ENVIRONMENTAL SERVICES | |SUB %: 16.33 | | | | M.V. HENKE ENTERPRISES, INC. | |SUB %: 0.95 | | | | | | | | | | CONTRACT 07103068 | TOTALS | 1,471,795.60| 0.00| 1,631,966.84| 99.9| ************************************************************************************************************************************ BURNET SH 71 | 3.093 | 1,090,537.74| 0.00| 0.00| 0.0| US 281 BLANCO COUNTY LINE | | | | | | 0252-02-053 | | | | | | STP 2013(247) MILL, SEAL & OVERLAY | | | | | | | | | | | | BLANCO BURNET COUNTY LINE | 15.051 | 3,601,894.57| 15,819.50| 26,729.50| 0.7| US 281 US 290 WEST IN JOHNSON CITY | | | | | | 0252-03-047 | | | | | | STP 2013(247) MILL, SEAL & OVERLAY | | | | | | | | | | | | WORK ORDER- 01-23-13 WORK BEGAN- 00-00-00 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 02-08-13 | | | | | | CONTRACT WORKING DAYS- 55 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | | | | | | | | | | | | CLARK CONSTRUCTION OF TEXAS, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0252-03-047 | | | | | | INTERSTATE BARRICADES & MARKINGS, INC. | |SUB %: 0.00 | | | | | | | | | | CONTRACT 12123010 | TOTALS | 4,692,432.31| 15,819.50| 26,729.50| 0.5| ************************************************************************************************************************************ BURNET ON US 281 AT COLORADO RIVER | 0.568 | 28,272,713.57| 521,409.40| 17,390,540.03| 61.5| US 281 (STR 0252-02-017) | | | | | | 0252-02-046 | | | | | | BR 2010(786) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | BURNET ON US 281 AT COLORADO RIVER | 0.001 | 375,131.40| -294.82| 366,309.84| 97.6| US 281 . | | | | | | 0252-02-049 | | | | | | BR 2009(641) ROW ACQ. AND RELOC. ASSIST. | | | | | | | | | | | | WORK ORDER- 07-15-10 WORK BEGAN- 12-07-10 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 12-07-10 | | | | | | CONTRACT WORKING DAYS- 1,177 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 676 PERCENT TIME USED- 57 | | | | | | | | | | | | ARCHER-WESTERN CONTRACTORS, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0252-02-046 | | | | | | AARON CONCRETE CONTRACTORS, L.P. | |SUB %: 0.65 | | | | AFS ENVIRONMENTAL, INC. | |SUB %: 0.22 | | | | APAC-TEXAS, INC. | |SUB %: 2.51 | | | | BPI ENVIRONMENTAL SERVICES INC. | |SUB %: 0.61 | | | | BREDA COMPANY, INC. | |SUB %: 0.37 | | | | CONCRETE CUTTING BY BOND | |SUB %: 0.11 | | | | DUSTROL, INC. (ROANOKE) | |SUB %: 0.01 | | | | PENHALL COMPANY | |SUB %: 0.07 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 1.73 | | | | SCOTT DERR PAINTING CO, LLC | |SUB %: 0.37 | | | | THE LEVY COMPANY, L.P. | |SUB %: 2.27 | | | | TREVCON, INC. | |SUB %: 1.90 | | | | W. W. FOUNDATION DRILLING, LTD. | |SUB %: 3.29 | | | | PANTHER CREEK TRANSPORTATION, INC. | |SUB %: 0.35 | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 0.02 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.23 | | | | SWEEP ACROSS TEXAS | |SUB %: 0.00 | | | | MUSTANG COLT SERVICES, INC. | |SUB %: 0.00 | | | | OMEGA DEMOLITION CORPORATION | |SUB %: 3.33 | | | | | | | | | | CONTRACT 05103201 | TOTALS | 28,647,844.97| 521,114.58| 17,756,849.87| 62.0| ************************************************************************************************************************************ BURNET FANIN STREET IN BURNET | 1.000 | 1,416,556.10| 0.00| 1,685,895.62| 99.9| SH 29 HILL STREET | | | | | | 0151-01-040 | | | | | | STP 2011(355) REHAB RDWY | | | | | | | | | | | | BURNET HOUSTON CLINTON DR | 2.300 | 3,255,002.03| 15,188.91| 3,486,903.59| 99.9| US 281 GREEN MILE RD | | | | | | 0252-01-069 | | | | | | STP 2011(355) REHAB RDWY | | | | | | | | | | | | WORK ORDER- 09-15-10 WORK BEGAN- 10-12-10 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 10-12-10 | | | | | | CONTRACT WORKING DAYS- 387 ADDL DAYS GRANTED- 66 | | | | | | WORKING DAYS CHARGED- 404 PERCENT TIME USED- 89 | | | | | | | | | | | | DAN WILLIAMS COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0252-01-069 | | | | | | J.D. RAMMING PAVING CO., LTD. | |SUB %: 27.80 | | | | WIMS ENVIRONMENTAL CONSTRUCTION, LTD. | |SUB %: 0.61 | | | | F & W ELECTRICAL CONTRACTORS, INC. | |SUB %: 2.47 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 0.71 | | | | | | | | | | CONTRACT 08103110 | TOTALS | 4,671,558.13| 15,188.91| 5,172,799.21| 99.9| ************************************************************************************************************************************ BURNET 0.678 MI. WEST OF US 281 | 0.900 | 711,727.24| 66,374.49| 378,165.39| 53.1| SH 71 0.111 MI. WEST OF US 281 | | | | | | 0700-01-037 | | | | | | STP 2013(103) CONSTR CONTINUOUS LEFT TURN LANE | | | | | | | | | | | | WORK ORDER- 11-09-12 WORK BEGAN- 01-14-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-25-12 | | | | | | CONTRACT WORKING DAYS- 117 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 74 PERCENT TIME USED- 63 | | | | | | | | | | | | AARON CONCRETE CONTRACTORS, L.P. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0700-01-037 | | | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 1.10 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 2.36 | | | | LONE STAR PAVING CO. | |SUB %: 39.25 | | | | RICE ENVIRONMENTAL SERVICES | |SUB %: 4.79 | | | | CHANDLER CONCRETE, INC. | |SUB %: 14.85 | | | | | | | | | | CONTRACT 10123211 | TOTALS | 711,727.24| 66,374.49| 378,165.39| 53.1| ************************************************************************************************************************************ CALDWELL SH 80 | 11.115 | 1,097,372.07| 0.00| 0.00| 0.0| FM 20 1.881 MI W OF US 183 | | | | | | 0115-02-017 | | | | | | STP 2013(473) FULL DEPTH REPAIR,LEVEL-UP & SEAL | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 26 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | RAMMING PAVING COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0115-02-017 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 03133004 | TOTALS | 1,097,372.07| 0.00| 0.00| 0.0| ************************************************************************************************************************************ CALDWELL GUADALUPE COUNTY LINE | 7.423 | 2,600,277.03| 0.00| 0.00| 0.0| US 90 IH 10 | | | | | | 0029-03-054 | | | | | | STP 2013(471) FULL DEPTH REPAIR, MILL, SEAL & TOM | | | | | | | | | | | | LEE 2.0 MILES EAST OF BASTROP C/L | 2.000 | 943,592.25| 0.00| 0.00| 0.0| US 290 4.0 MILES EAST OF BASTROP C/L | | | | | | 0114-07-074 | | | | | | NH 2013(472) SPOT REPAIR, LEVEL-UP & TOM | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 47 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | ANGEL BROTHERS ENTERPRISES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0029-03-054 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 03133210 | TOTALS | 3,543,869.28| 0.00| 0.00| 0.0| ************************************************************************************************************************************ CALDWELL 5.0 MI SOUTH OF FM 20 | 8.000 | 7,526,709.80| 0.00| 0.00| 0.0| US 183 0.5 MI SOUTH OF FM 86 | | | | | | 0152-03-053 | | | | | | NH 2013(553) PAVEMENT REPAIR,MILL,SEAL&OVERLAY | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 174 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | ANGEL BROTHERS ENTERPRISES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0152-03-053 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 04133206 | TOTALS | 7,526,709.80| 0.00| 0.00| 0.0| ************************************************************************************************************************************ CALDWELL SAN MARCOS RIVER | 0.104 | 1,254,724.88| 0.00| 0.00| 0.0| FM 1977 (STR 1434-03-002) | | | | | | 1434-03-010 | | | | | | BR 2013(250) REPLACE BRIDGE & APPROACHES | | | | | | | | | | | | WORK ORDER- 01-15-13 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 01-31-13 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 80 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | RELMCO, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1434-03-010 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 12123209 | TOTALS | 1,254,724.88| 0.00| 0.00| 0.0| ************************************************************************************************************************************ GILLESPIE US 290 | 8.977 | 5,106,864.29| 169,331.09| 169,331.09| 3.3| RM 783 8.977 MI S OF US 290 | | | | | | 1135-01-026 | | | | | | STP 2013(028)HES PROVIDE ADDITIONAL PAVED SURFACE WI | | | | | | | | | | | | WORK ORDER- 04-03-13 WORK BEGAN- 04-15-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-15-13 | | | | | | CONTRACT WORKING DAYS- 229 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 11 PERCENT TIME USED- 4 | | | | | | | | | | | | ALLEN KELLER COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1135-01-026 | | | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 3.51 | | | | DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) | |SUB %: 1.40 | | | | RELMCO, INC. | |SUB %: 31.14 | | | | | | | | | | CONTRACT 02133212 | TOTALS | 5,106,864.29| 169,331.09| 169,331.09| 3.3| ************************************************************************************************************************************ GILLESPIE JUNG LANE | 2.758 | 3,481,347.21| 307,414.37| 1,002,338.44| 28.7| US 290 1230' EAST OF JENSCHKE ROAD | | | | | | 0113-02-059 | | | | | | STP 2012(547) ADD TWO WAY LEFT TURN LANE | | | | | | | | | | | | WORK ORDER- 06-21-12 WORK BEGAN- 09-17-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 08-20-12 | | | | | | CONTRACT WORKING DAYS- 156 ADDL DAYS GRANTED- 15 | | | | | | WORKING DAYS CHARGED- 169 PERCENT TIME USED- 98 | | | | | | | | | | | | MATL CONSTRUCTION CORPORATION | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0113-02-059 | | | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.40 | | | | RICE ENVIRONMENTAL SERVICES | |SUB %: 1.13 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 1.67 | | | | ABC EROSION CONTROL, INC. | |SUB %: 0.52 | | | | SURVEYING AND MAPPING, INC. | |SUB %: 0.00 | | | | | | | | | | CONTRACT 05123032 | TOTALS | 3,481,347.21| 307,414.37| 1,002,338.44| 28.7| ************************************************************************************************************************************ GILLESPIE 0.101 MI W OF MARIPOSA DR. | 0.343 | 2,418,067.64| 75,797.02| 1,263,833.49| 52.2| US 290 0.021 MI W OF OLD SAN ANTONIO RD. | | | | | | 0113-01-041 | | | | | | STP 2012(442)SB INSTALL CTL & WIDEN PAVED SHOULDERS | | | | | | | | | | | | GILLESPIE 0.021 MI W OF OLD SAN ANTONIO RD. | 0.169 | 400,597.34| 46.00| 141,403.60| 35.2| US 290 0.148 MI E OF OLD SAN ANTONIO RD. | | | | | | 0113-02-058 | | | | | | STP 2012(442)SB INSTALL CTL & WIDEN PAVED SHOULDERS | | | | | | | | | | | | WORK ORDER- 07-16-12 WORK BEGAN- 10-30-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 10-30-12 | | | | | | CONTRACT WORKING DAYS- 157 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 116 PERCENT TIME USED- 73 | | | | | | | | | | | | SHANNON-MONK, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0113-01-041 | | | | | | INTERSTATE BARRICADES & MARKINGS, INC. | |SUB %: 1.64 | | | | EGGEMEYER LAND CLEARING, LLC | |SUB %: 0.35 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 6.16 | | | | HILL COUNTRY BRIDGE, INC. | |SUB %: 28.77 | | | | AVAILABLE CONSTRUCTION AND TRANSPORT SERVICES, INC. | |SUB %: 8.12 | | | | W. W. FOUNDATION DRILLING, LTD. | |SUB %: 2.89 | | | | GK CONSTRUCTION, LLC | |SUB %: 0.46 | | | | PRESIDIO ENGINEERS & CONTRACTORS, INC. | |SUB %: 2.34 | | | | | | | | | | CONTRACT 05123229 | TOTALS | 2,818,664.98| 75,843.02| 1,405,237.09| 49.8| ************************************************************************************************************************************ GILLESPIE RM 1631 | 6.022 | 2,899,581.31| 215,156.08| 763,834.47| 26.3| RM 2721 RM 1623 | | | | | | 2719-01-008 | | | | | | STP 2013(029)HES PROVIDE ADDITIONAL PAVED SURFACE WI | | | | | | | | | | | | WORK ORDER- 10-18-12 WORK BEGAN- 11-26-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-03-12 | | | | | | CONTRACT WORKING DAYS- 159 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 94 PERCENT TIME USED- 59 | | | | | | | | | | | | MATL CONSTRUCTION CORPORATION | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 2719-01-008 | | | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 1.49 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.36 | | | | RICE ENVIRONMENTAL SERVICES | |SUB %: 2.31 | | | | | | | | | | CONTRACT 09123212 | TOTALS | 2,899,581.31| 215,156.08| 763,834.47| 26.3| ************************************************************************************************************************************ HAYS REUNION BLVD (PROPOSED) | 0.341 | 536,804.60| 0.00| 0.00| 0.0| RM 1826 . | | | | | | 1754-02-021 | | | | | | CC 1754-2-21 ADD CENTER TURN LANE & SHOULDERS | | | | | | | | | | | | WORK ORDER- 05-13-13 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 05-29-13 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 44 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | BPI ENVIRONMENTAL SERVICES INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1754-02-021 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 01133222 | TOTALS | 536,804.60| 0.00| 0.00| 0.0| ************************************************************************************************************************************ HAYS AT CRYSTAL HILLS DR | 0.317 | 1,390,918.66| 87,017.80| 1,007,201.96| 73.1| RM 1826 . | | | | | | 1754-02-018 | | | | | | CC 1754-2-18 INSTALL TURN LANES & SHOULDERS | | | | | | | | | | | | WORK ORDER- 03-19-12 WORK BEGAN- 04-30-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-04-12 | | | | | | CONTRACT WORKING DAYS- 82 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 96 PERCENT TIME USED- 117 | | | | | | | | | | | | CAPITAL EXCAVATION COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1754-02-018 | | | | | | AUSTIN WOOD RECYCLING | |SUB %: 1.97 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 5.60 | | | | J.D. RAMMING PAVING CO., LTD. | |SUB %: 15.73 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 8.52 | | | | VOGES DRILLING | |SUB %: 2.67 | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | |SUB %: 7.20 | | | | | | | | | | CONTRACT 02123014 | TOTALS | 1,390,918.66| 87,017.80| 1,007,201.96| 73.1| ************************************************************************************************************************************ HAYS AT NUTTY BROWN RD | 0.372 | 695,276.85| 86,038.42| 146,362.16| 21.0| RM 1826 . | | | | | | 1754-02-017 | | | | | | CC 1754-2-17 ADD TURN LANE & SHOULDERS | | | | | | | | | | | | WORK ORDER- 05-10-12 WORK BEGAN- 02-04-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 05-26-12 | | | | | | CONTRACT WORKING DAYS- 85 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 8 PERCENT TIME USED- 9 | | | | | | | | | | | | ANGEL BROTHERS ENTERPRISES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1754-02-017 | | | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 11.26 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 2.87 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.45 | | | | M.V. HENKE ENTERPRISES, INC. | |SUB %: 1.27 | | | | | | | | | | CONTRACT 03123007 | TOTALS | 695,276.85| 86,038.42| 146,362.16| 21.0| ************************************************************************************************************************************ HAYS LEHMAN RD (CR 204) | 4.473 | 814,226.45| 0.00| 0.00| 0.0| RM 150 SH 21 | | | | | | 0805-01-019 | | | | | | STP 2013(475) REPAIR & THIN OVERLAY | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 59 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | DEAN WORD COMPANY, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0805-01-019 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 03133218 | TOTALS | 814,226.45| 0.00| 0.00| 0.0| ************************************************************************************************************************************ HAYS FISHER STORE RD | 2.829 | 3,273,604.25| 973.50| 3,303,104.50| 99.9| RM 2325 CARNEY LANE | | | | | | 0285-02-012 | | | | | | CC 285-2-12 CENTER TURN LN,RIGHT TURN LNS,SHLDR | | | | | | | | | | | | WORK ORDER- 05-18-11 WORK BEGAN- 06-13-11 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 06-03-11 | | | | | | CONTRACT WORKING DAYS- 205 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 294 PERCENT TIME USED- 143 | | | | | | | | | | | | ANGEL BROTHERS ENTERPRISES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0285-02-012 | | | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 4.36 | | | | J & M CONTRACTING, COMPANY | |SUB %: 12.09 | | | | J.A. ROAD BORING, INC. | |SUB %: 2.52 | | | | MENADE, INC. | |SUB %: 2.75 | | | | RICE ENVIRONMENTAL SERVICES | |SUB %: 4.55 | | | | SEMARCK LANDSCAPE SERVICES, INC. | |SUB %: 1.20 | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 0.19 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 3.71 | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | |SUB %: 1.11 | | | | | | | | | | CONTRACT 04113228 | TOTALS | 3,273,604.25| 973.50| 3,303,104.50| 99.9| ************************************************************************************************************************************ HAYS IH 35 NB FRT RD | 0.580 | 3,483,074.33| 206,855.91| 2,175,833.11| 62.4| RM 150 CR 204/LEHMAN RD | | | | | | 0805-01-017 | | | | | | PTF 2012(550) ROADWAY REALIGNMENT | | | | | | | | | | | | WORK ORDER- 07-12-12 WORK BEGAN- 09-04-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 09-04-12 | | | | | | CONTRACT WORKING DAYS- 274 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 157 PERCENT TIME USED- 57 | | | | | | | | | | | | CAPITAL EXCAVATION COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0805-01-017 | | | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | |SUB %: 10.55 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 1.20 | | | | MCKINNEY DRILLING__(BUDA) | |SUB %: 0.34 | | | | RAMMING PAVING COMPANY | |SUB %: 16.88 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 3.89 | | | | | | | | | | CONTRACT 05123028 | TOTALS | 3,483,074.33| 206,855.91| 2,175,833.11| 62.4| ************************************************************************************************************************************ HAYS FM 1626 (KYLE PARKWAY) | 2.746 | 6,298,068.75| 1,024,995.01| 4,760,546.96| 75.5| IH 35 S OF RM 150 | | | | | | 0016-02-127 | | | | | | PTF 2012(094) CONST SB FRONTAGE RD | | | | | | | | | | | | WORK ORDER- 07-18-12 WORK BEGAN- 08-13-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 08-03-12 | | | | | | CONTRACT WORKING DAYS- 264 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 181 PERCENT TIME USED- 68 | | | | | | | | | | | | HUNTER INDUSTRIES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0016-02-127 | | | | | | DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) | |SUB %: 2.00 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 1.68 | | | | THE LEVY COMPANY, L.P. | |SUB %: 5.04 | | | | MURRAY CONSTRUCTION | |SUB %: 0.55 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 1.36 | | | | S & S BRIDGE PAINTING, INC. | |SUB %: 0.01 | | | | | | | | | | CONTRACT 05123206 | TOTALS | 6,298,068.75| 1,024,995.01| 4,760,546.96| 75.5| ************************************************************************************************************************************ HAYS VARIOUS LOCATIONS IN HAYS COUNTY | 0.100 | 467,144.80| 0.00| 392,582.11| 84.0| VA ON IH 35 AND SH 80 | | | | | | 0914-33-063 | | | | | | STP 2012(552) LANDSCAPE AND IRRIGATION | | | | | | | | | | | | WORK ORDER- 06-14-12 WORK BEGAN- 07-09-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 72 ADDL DAYS GRANTED- 6 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 78 PERCENT TIME USED- 100 | |**************************************************| | | | | | | | LANDSCAPE CONTRACTING AND IRRIGATION, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-33-063 | | | | | | LONE STAR TRAFFIC SERVICE, INC. | |SUB %: 1.37 | | | | TERRY PRATHER | |SUB %: 16.78 | | | | | | | | | | CONTRACT 05123226 | TOTALS | 467,144.80| 0.00| 392,582.11| 84.0| ************************************************************************************************************************************ HAYS MCGREGOR LANE | 2.784 | 6,460,153.61| 957,906.35| 5,897,211.02| 91.2| US 290 MIGHTY TIGER TRAIL | | | | | | 0113-07-050 | | | | | | CC 113-7-50 ADD CENTER TURN LANE AND SHOULDERS | | | | | | | | | | | | WORK ORDER- 09-06-11 WORK BEGAN- 01-17-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 09-22-11 | | | | | | CONTRACT WORKING DAYS- 285 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 280 PERCENT TIME USED- 98 | | | | | | | | | | | | HUNTER INDUSTRIES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0113-07-050 | | | | | | BMP SPECIALIST, LLC | |SUB %: 0.98 | | | | CRAIG OLDEN, INC. | |SUB %: 1.76 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 1.08 | | | | F & W ELECTRICAL CONTRACTORS, INC. | |SUB %: 1.65 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 0.29 | | | | RELMCO, INC. | |SUB %: 13.16 | | | | RICE ENVIRONMENTAL SERVICES | |SUB %: 2.07 | | | | SCOTT DERR PAINTING CO, LLC | |SUB %: 0.07 | | | | SITE-SAFE PRODUCTS OF TEXAS, L.P. | |SUB %: 2.41 | | | | VOGES DRILLING CO. | |SUB %: 1.40 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.63 | | | | AUSTIN WOOD RECYCLING | |SUB %: 0.15 | | | | | | | | | | CONTRACT 07113019 | TOTALS | 6,460,153.61| 957,906.35| 5,897,211.02| 91.2| ************************************************************************************************************************************ HAYS 2250 FT N OF MAIN ST | 0.777 | 7,858,394.07| 0.00| 9,399,409.11| 99.9| IH 35 2000 FT S OF MAIN ST | | | | | | 0016-02-104 | | | | | | HP 2009(650)ES REPL BRIDGE & APPRS, WIDEN FRTG RDS | | | | | | | | | | | | HAYS 2000 FT N OF FM 2001 | 0.379 | 431,995.37| 0.00| 305,076.93| 70.6| IH 35 FM 2001 | | | | | | 0016-02-130 | | | | | | STP 2010(004)ES SEAL COAT, MILL&INLAY, OVERLAY PFC | | | | | | | | | | | | HAYS ON MAIN STREET 440' W OF CR 117 | 0.001 | 1,032,278.34| 0.00| 1,074,699.91| 99.9| CS 825' EAST OF CR 117 | | | | | | 0914-33-060 | | | | | | CC 914-33-60 WIDEN ROADWAY | | | | | | | | | | | | HAYS ON MAIN STEET 120' W OF CR 117 | 0.001 | 70,858.83| 0.00| 63,831.38| 90.0| CS 840' EAST OF CR 117 | | | | | | 0914-33-061 | | | | | | RW 914-33-61 UTILITY ADJ IN CONST. CONTRACT | | | | | | | | | | | | WORK ORDER- 10-09-09 WORK BEGAN- 11-02-09 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 10-25-09 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 603 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 644 PERCENT TIME USED- 106 | |**************************************************| | | | | | | | ZURICH AMERICAN INSURANCE COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0016-02-104 | | | | | | ASPHALT PAVING COMPANY OF AUSTIN, INC. | |SUB %: 16.75 | | | | AUSTEX TREE SERVICE, INC. | |SUB %: 0.01 | | | | BOOTHE BROTHERS PAVING COMPANY, INC. | |SUB %: 1.11 | | | | CARTEL PLACERS, LLC | |SUB %: 0.42 | | | | E W WELLS GROUP LLC | |SUB %: 0.84 | | | | F & W ELECTRICAL CONTRACTORS, INC. | |SUB %: 5.24 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 1.48 | | | | MCKINNEY DRILLING__(BUDA) | |SUB %: 1.43 | | | | RICE ENVIRONMENTAL SERVICES | |SUB %: 0.00 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 1.64 | | | | SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C. | |SUB %: 0.18 | | | | TEXAS HIGHWAY SYSTEMS, INC. | |SUB %: 0.25 | | | | EVANS ENVIRONMENTAL CONTRACTING, LLC. | |SUB %: 0.79 | | | | RIVER CITIES SAWING LLC | |SUB %: 0.05 | | | | LONE STAR TRAFFIC SERVICE, INC. | |SUB %: 0.45 | | | | LAND SOLUTIONS CONSTRUCTION, LLC | |SUB %: 0.22 | | | | ENVIRONMENTAL SERVICES, INC. | |SUB %: 0.08 | | | | WILLIAMS-JOHN CONSTRUCTION, LLC | |SUB %: 2.73 | | | | MUNDO VERDE IRRIGATION & LANDSCAPING, INC. | |SUB %: 1.78 | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | |SUB %: 0.47 | | | | | | | | | | CONTRACT 08093207 | TOTALS | 9,393,526.61| 0.00| 10,843,017.33| 99.9| ************************************************************************************************************************************ HAYS SH 80 | 0.975 | 248,787.75| 2,375.00| 214,755.18| 86.3| IH 35 LP 82 | | | | | | 0016-03-097 | | | | | | IM 0353(282) LANDSCAPING AND IRRIGATION | | | | | | | | | | | | WORK ORDER- 09-27-11 WORK BEGAN- 12-26-11 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 01-25-12 | | | | | | CONTRACT WORKING DAYS- 65 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 54 PERCENT TIME USED- 83 | | | | | | | | | | | | TEXAS ASPHALT | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0016-03-097 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 08113213 | TOTALS | 248,787.75| 2,375.00| 214,755.18| 86.3| ************************************************************************************************************************************ HAYS AT WILLOW SPRGS CRK IN SAN MARCOS | 0.074 | 1,130,054.99| 92,472.08| 92,472.08| 8.1| LP 82 STR 0366-01-033 | | | | | | 0366-01-070 | | | | | | BR 2012(692) REPLACE BRIDGE CLASS CULVERT | | | | | | | | | | | | WORK ORDER- 09-24-12 WORK BEGAN- 03-25-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 10-10-12 | | | | | | CONTRACT WORKING DAYS- 162 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 17 PERCENT TIME USED- 10 | | | | | | | | | | | | CAPITAL EXCAVATION COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0366-01-070 | | | | | | BMP SPECIALIST, LLC | |SUB %: 3.19 | | | | DOUBLE S PAVING, INC. | |SUB %: 7.28 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 3.20 | | | | SCOTT DERR PAINTING CO, LLC | |SUB %: 0.18 | | | | THE LEVY COMPANY, L.P. | |SUB %: 1.25 | | | | W. W. FOUNDATION DRILLING, LTD. | |SUB %: 11.85 | | | | AUSTIN WOOD RECYCLING | |SUB %: 0.53 | | | | DAVEY TREE & LAWN CARE | |SUB %: 0.53 | | | | | | | | | | CONTRACT 08123018 | TOTALS | 1,130,054.99| 92,472.08| 92,472.08| 8.1| ************************************************************************************************************************************ HAYS 0.075 MI WEST OF RUBY RANCH ROAD | 0.313 | 437,358.40| 34,683.45| 200,592.34| 45.8| RM 967 0.238 MI EAST OF RUBY RANCH ROAD | | | | | | 1776-01-030 | | | | | | CC 1776-1-30 CONSTRUCT TURN LANES | | | | | | | | | | | | WORK ORDER- 11-30-12 WORK BEGAN- 02-01-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 12-16-12 | | | | | | CONTRACT WORKING DAYS- 168 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 52 PERCENT TIME USED- 30 | | | | | | | | | | | | SEMA CONSTRUCTION, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1776-01-030 | | | | | | DUSTROL, INC. | |SUB %: 1.64 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 6.18 | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 3.20 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 6.51 | | | | APAC-TEXAS, INC. | |SUB %: 22.75 | | | | | | | | | | CONTRACT 10123022 | TOTALS | 437,358.40| 34,683.45| 200,592.34| 45.8| ************************************************************************************************************************************ HAYS IN WIMBERLEY AT OLD KYLE RD | 0.100 | 659,190.80| 136,409.15| 713,086.15| 99.9| RM 12 . | | | | | | 0683-03-032 | | | | | | C 683-3-32 INTERSECTION IMPROVEMENTS | | | | | | | | | | | | WORK ORDER- 01-15-13 WORK BEGAN- 02-04-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 01-31-13 | | | | | | CONTRACT WORKING DAYS- 32 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 38 PERCENT TIME USED- 118 | | | | | | | | | | | | CAPITAL EXCAVATION COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0683-03-032 | | | | | | APAC-TEXAS, INC. | |SUB %: 15.49 | | | | AVERY"S LAWN CARE | |SUB %: 6.09 | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | |SUB %: 18.05 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 2.10 | | | | TEX OP CONSTRUCTION, LP | |SUB %: 1.10 | | | | | | | | | | CONTRACT 12123234 | TOTALS | 659,190.80| 136,409.15| 713,086.15| 99.9| ************************************************************************************************************************************ LEE AT LAKE SOMMERVILLE SP, NAILS CRK | 0.001 | 725,104.15| 0.00| 0.00| 0.0| PW . | | | | | | 0914-21-027 | | | | | | C 914-21-27 PAVE VARIOUS ROADS/PARKING AREAS | | | | | | | | | | | | WORK ORDER- 04-10-13 WORK BEGAN- 05-06-13 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 56 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | KNIFE RIVER CORPORATION - SOUTH | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-21-027 | | | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 3.01 | | | | CEN TEX HYDROSEED, INC. | |SUB %: 0.20 | | | | PEDRO CARLOS CONSTRUCTION CO. | |SUB %: 1.01 | | | | | | | | | | CONTRACT 02133012 | TOTALS | 725,104.15| 0.00| 0.00| 0.0| ************************************************************************************************************************************ LEE ON CR 306 AT MIDDLE YEGUA CREEK | 0.059 | 255,411.33| 0.00| 0.00| 0.0| CR STR AA01-24-001 | | | | | | 0914-21-029 | | | | | | BR 2012(236) REPLACE BRIDGE & APPROACHES | | | | | | | | | | | | LEE ON CR 113 AT ELM CREEK | 0.072 | 314,588.67| 0.00| 0.00| 0.0| CR STR AA00-34-001 | | | | | | 0914-21-030 | | | | | | BR 2012(235) REPLACE BRIDGE & APPROACHES | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 98 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | LEGENDS LANDSCAPES LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-21-029 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 05133025 | TOTALS | 570,000.00| 0.00| 0.00| 0.0| ************************************************************************************************************************************ LEE 0.5 MILES WEST OF US 77 | 1.061 | 2,789,600.20| 248,777.94| 1,186,289.48| 42.5| SH 21 US 77 | | | | | | 0473-02-035 | | | | | | NH 2013(024) WIDEN BRIDGE & MODIFY APPROACHES | | | | | | | | | | | | WORK ORDER- 10-12-12 WORK BEGAN- 01-07-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 10-28-12 | | | | | | CONTRACT WORKING DAYS- 153 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 77 PERCENT TIME USED- 50 | | | | | | | | | | | | DAN WILLIAMS COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0473-02-035 | | | | | | M & D FOUNDATION DRILLING INDUSTRIES, INC. | |SUB %: 2.65 | | | | GK CONSTRUCTION, LLC | |SUB %: 0.41 | | | | RAMMING PAVING COMPANY | |SUB %: 16.56 | | | | TEX OP CONSTRUCTION, LP | |SUB %: 0.68 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 2.57 | | | | MURRAY CONSTRUCTION | |SUB %: 0.46 | | | | D S TEXAS ICON CONSTRUCTION, LLC | |SUB %: 0.63 | | | | NORTH TEXAS REBAR, LLC | |SUB %: 0.14 | | | | | | | | | | CONTRACT 09123033 | TOTALS | 2,789,600.20| 248,777.94| 1,186,289.48| 42.5| ************************************************************************************************************************************ LEE 0.249 MI N OF FM 1697 | 5.266 | 2,191,992.62| 296,576.26| 1,881,894.36| 85.8| FM 141 0.007 MI SW OF CR 119 | | | | | | 0334-05-030 | | | | | | STP 2013(022)HES PROVIDE ADDITIONAL PAVED SURFACE WI | | | | | | | | | | | | WORK ORDER- 11-09-12 WORK BEGAN- 12-18-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 12-18-12 | | | | | | CONTRACT WORKING DAYS- 77 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 60 PERCENT TIME USED- 77 | | | | | | | | | | | | KNIFE RIVER CORPORATION - SOUTH | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0334-05-030 | | | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 0.65 | | | | TEXAS ALTERNATIVE GRASSER, INC. | |SUB %: 0.67 | | | | CEN TEX HYDROSEED, INC. | |SUB %: 0.20 | | | | MURRAY CONSTRUCTION | |SUB %: 0.38 | | | | PEDRO CARLOS CONSTRUCTION CO. | |SUB %: 1.79 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.74 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 2.33 | | | | M.V. HENKE ENTERPRISES, INC. | |SUB %: 1.86 | | | | | | | | | | CONTRACT 09123232 | TOTALS | 2,191,992.62| 296,576.26| 1,881,894.36| 85.8| ************************************************************************************************************************************ LEE 0.383 MI. W OF FM 3403 | 10.251 | 7,525,070.79| 847,484.40| 1,282,412.22| 17.0| SH 21 0.009 MI. W OF FM 141 | | | | | | 0116-01-028 | | | | | | NH 2013(191) ADD SHLDRS., PAV REPAIR, SEAL COAT | | | | | | | | | | | | WORK ORDER- 01-23-13 WORK BEGAN- 03-11-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 03-11-13 | | | | | | CONTRACT WORKING DAYS- 204 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 32 PERCENT TIME USED- 15 | | | | | | | | | | | | HUNTER INDUSTRIES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0116-01-028 | | | | | | AUSTIN WOOD RECYCLING | |SUB %: 1.25 | | | | COWBELL TRAFFIC SERVICES, INC. | |SUB %: 0.13 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 3.55 | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | |SUB %: 1.91 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.37 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 1.92 | | | | WIMS ENVIRONMENTAL CONSTRUCTION, LTD. | |SUB %: 2.24 | | | | | | | | | | CONTRACT 11123217 | TOTALS | 7,525,070.79| 847,484.40| 1,282,412.22| 17.0| ************************************************************************************************************************************ LLANO 0.2 MILES WEST OF CR 303 | 7.350 | 6,036,480.35| 0.00| 0.00| 0.0| SH 71 0.1 MILES WEST OF CR 307 | | | | | | 0700-04-046 | | | | | | STP 2013(704) UPGRADE TO SUPER 2 & ADD LTL'S | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 227 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | HUNTER INDUSTRIES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0700-04-046 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 05133229 | TOTALS | 6,036,480.35| 0.00| 0.00| 0.0| ************************************************************************************************************************************ LLANO 0.1 MILES EAST OF CR 307 | 2.594 | 1,667,910.07| 0.00| 2,100,782.96| 99.9| SH 71 0.1 MILES WEST OF CR 308 | | | | | | 0700-04-044 | | | | | | STP 2012(087) UPGRADE TO SUPER 2 | | | | | | | | | | | | WORK ORDER- 10-19-11 WORK BEGAN- 01-11-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 01-11-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 130 ADDL DAYS GRANTED- 39 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 164 PERCENT TIME USED- 97 | |**************************************************| | | | | | | | HUNTER INDUSTRIES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0700-04-044 | | | | | | WIMS ENVIRONMENTAL CONSTRUCTION, LTD. | |SUB %: 2.42 | | | | AUSTIN WOOD RECYCLING | |SUB %: 1.97 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 2.49 | | | | ERFURT BLASTING COMPANY, INC. | |SUB %: 1.97 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 0.93 | | | | MPB, INC. | |SUB %: 6.05 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 5.82 | | | | | | | | | | CONTRACT 09113030 | TOTALS | 1,667,910.07| 0.00| 2,100,782.96| 99.9| ************************************************************************************************************************************ LLANO RM 2241 | 12.867 | 1,485,594.91| 860,687.67| 860,687.67| 57.9| SH 29 RM 1431 | | | | | | 0150-04-043 | | | | | | STP 2013(246) LEVEL-UP & SEAL COAT | | | | | | | | | | | | WORK ORDER- 03-08-13 WORK BEGAN- 04-08-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 03-24-13 | | | | | | CONTRACT WORKING DAYS- 32 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 13 PERCENT TIME USED- 40 | | | | | | | | | | | | ANGEL BROTHERS ENTERPRISES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0150-04-043 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 12123024 | TOTALS | 1,485,594.91| 860,687.67| 860,687.67| 57.9| ************************************************************************************************************************************ TRAVIS AT VARIOUS LOCATIONS DISTRICTWIDE | 0.100 | 848,814.95| 0.00| 885,772.29| 99.9| VA . | | | | | | 0914-00-290 | | | | | | STP 2011(751) FY 2012 SITE - SPECIFIC SIGNALS | | | | | | | | | | | | WORK ORDER- 02-18-11 WORK BEGAN- 07-13-11 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 03-06-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 120 ADDL DAYS GRANTED- 12 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 139 PERCENT TIME USED- 105 | |**************************************************| | | | | | | | HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-00-290 | | | | | | TX DOWN UNDER CONSTRUCTION LLC | |SUB %: 4.02 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.15 | | | | | | | | | | CONTRACT 01113008 | TOTALS | 848,814.95| 0.00| 885,772.29| 99.9| ************************************************************************************************************************************ TRAVIS VARIOUS LOCATIONS DISTRICTWIDE | 0.001 | 823,822.50| 0.00| 1,510,521.34| 99.9| VA VARIOUS LOCATIONS DISTRICTWIDE | | | | | | 0914-00-262 | | | | | | STP 2011(788) FY 2011 NON-SITE SPECIFIC SIGNALS | | | | | | | | | | | | WORK ORDER- 02-15-11 WORK BEGAN- 07-18-11 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 03-03-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 414 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 290 PERCENT TIME USED- 70 | |**************************************************| | | | | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-00-262 | | | | | | KRL CONSTRUCTION INC. | |SUB %: 8.95 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 1.89 | | | | | | | | | | CONTRACT 01113026 | TOTALS | 823,822.50| 0.00| 1,510,521.34| 99.9| ************************************************************************************************************************************ TRAVIS IN AUSTIN FROM 6TH ST TO 8TH ST | 0.140 | 254,930.73| 875.00| 251,408.15| 98.6| IH 35 GOVERNOR'S COMMUNITY ACHIEVEMENT | | | | | | 0015-13-353 | | | | | | IM 0353(279) LANDSCAPING | | | | | | | | | | | | WORK ORDER- 02-18-11 WORK BEGAN- 04-04-11 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 03-06-11 | | | | | | CONTRACT WORKING DAYS- 65 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 36 PERCENT TIME USED- 55 | | | | | | | | | | | | LEGENDS LANDSCAPES LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0015-13-353 | | | | | | LEXTEX, INC. | |SUB %: 4.11 | | | | | | | | | | CONTRACT 01113214 | TOTALS | 254,930.73| 875.00| 251,408.15| 98.6| ************************************************************************************************************************************ TRAVIS 67 FEET E OF TENNISON HILL DR | 6.604 | 1,926,950.48| 0.00| 1,786,436.21| 92.7| RM 2244 75 FEET W OF KNOLLWOOD DR | | | | | | 2102-01-065 | | | | | | STP 2012(157) SEAL COAT AND THIN OVERLAY | | | | | | | | | | | | WORK ORDER- 02-10-12 WORK BEGAN- 09-05-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 02-26-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 35 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 35 PERCENT TIME USED- 100 | |**************************************************| | | | | | | | RAMMING PAVING COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 2102-01-065 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 4.62 | | | | | | | | | | CONTRACT 01123010 | TOTALS | 1,926,950.48| 0.00| 1,786,436.21| 92.7| ************************************************************************************************************************************ TRAVIS WILLIAM CANNON BOULEVARD | 2.385 | 1,466,461.46| 0.00| 0.00| 0.0| LP 1 SLAUGHTER LANE | | | | | | 3136-01-179 | | | | | | STP 2013(341) REPAIR, LEVEL & THIN OVERLAY | | | | | | | | | | | | WORK ORDER- 04-15-13 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 05-01-13 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 60 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | RAMMING PAVING COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 3136-01-179 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 01133022 | TOTALS | 1,466,461.46| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TRAVIS 0.27 MI EAST OF RO DRIVE | 1.524 | 3,281,063.74| -7,983.64| 3,883,352.87| 99.9| SH 71 1.4 MI WEST OF BEE CREEK | | | | | | 0700-03-014 | | | | | | HP 2010(304)ES INSTALL CONT LFT TRN LN & SHOULDERS | | | | | | | | | | | | TRAVIS 0.2 MI WEST OF BEE CREEK RD | 0.070 | 202,557.12| 8,832.98| 376,368.17| 99.9| SH 71 0.13 MILES WEST OF BEE CREEK RD | | | | | | 0700-03-015 | | | | | | STP 2010(305)ES INSTALL CONT LFT TRN LN & SHOULDERS | | | | | | | | | | | | TRAVIS 1.4 MI W OF BEE CREEK RD | 1.200 | 4,596,768.39| 10,708.04| 4,795,426.39| 99.9| SH 71 0.2 MI W OF BEE CREEK RD | | | | | | 0700-03-111 | | | | | | STP 2010(318)SB CONVERT TO 4-LN DIV RD & ADD SHLDRS | | | | | | | | | | | | WORK ORDER- 04-08-10 WORK BEGAN- 06-07-10 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-24-10 | | | | | | CONTRACT WORKING DAYS- 369 ADDL DAYS GRANTED- 301 | | | | | | WORKING DAYS CHARGED- 670 PERCENT TIME USED- 100 | | | | | | | | | | | | AUSTIN BRIDGE & ROAD, LP | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0700-03-014 | | | | | | A BROTHERS | |SUB %: 0.28 | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 0.07 | | | | BPI ENVIRONMENTAL SERVICES INC. | |SUB %: 0.49 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 1.33 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 2.13 | | | | ROYAL VISTA INC. | |SUB %: 2.87 | | | | SCHNABEL FOUNDATION CO. (HOUSTON) | |SUB %: 5.52 | | | | SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C. | |SUB %: 0.11 | | | | PENHALL COMPANY (AUSTIN) | |SUB %: 0.04 | | | | RANGER EXCAVATING, L.P. | |SUB %: 0.00 | | | | APAC-TEXAS, INC. | |SUB %: 0.92 | | | | APAC-TEXAS, INC. | |SUB %: 7.06 | | | | | | | | | | CONTRACT 02103005 | TOTALS | 8,080,389.25| 11,557.38| 9,055,147.43| 99.9| ************************************************************************************************************************************ TRAVIS E OF S CONGRESS | 0.357 | 25,630,378.39| 0.00| 29,111,554.37| 99.9| US 290 W OF BURLESON RD | | | | | | 0113-13-106 | | | | | | NH 2010(122) CONST 4 REMAINING DIRECT CONNECTORS | | | | | | | | | | | | WORK ORDER- 04-06-10 WORK BEGAN- 05-03-10 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 04-22-10 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 468 ADDL DAYS GRANTED- 44 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 512 PERCENT TIME USED- 100 | |**************************************************| | | | | | | | SEMA CONSTRUCTION, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0113-13-106 | | | | | | AARON CONCRETE CONTRACTORS, L.P. | |SUB %: 2.48 | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 2.05 | | | | BMP SPECIALTIES, LLC. | |SUB %: 0.06 | | | | BOOTHE BROTHERS PAVING COMPANY, INC. | |SUB %: 0.53 | | | | CRAIG OLDEN, INC. | |SUB %: 0.44 | | | | J.D. RAMMING PAVING CO., LTD. | |SUB %: 5.29 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 1.68 | | | | MCKINNEY DRILLING COMPANY | |SUB %: 1.80 | | | | RIVER CITIES SAWING LLC | |SUB %: 0.10 | | | | LANDSCAPE CONTRACTING AND IRRIGATION, INC. | |SUB %: 0.54 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.66 | | | | ROYAL VISTA INC. | |SUB %: 1.69 | | | | INDUS CONSTRUCTION, L.P. | |SUB %: 1.42 | | | | CENTRAL TEXAS REINFORCEMENT | |SUB %: 0.17 | | | | PENNTEX MILLING, LLC | |SUB %: 0.15 | | | | DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. | |SUB %: 0.15 | | | | TEXAS CUTTING & CORING, INC. | |SUB %: 0.24 | | | | | | | | | | CONTRACT 02103039 | TOTALS | 25,630,378.39| 0.00| 29,111,554.37| 99.9| ************************************************************************************************************************************ TRAVIS FRONTAGE RDS & RAMPS | 1.123 | 591,231.61| 0.00| 569,337.54| 96.2| LP 1 AT 1ST & 5TH STREET INTERCHANGE | | | | | | 3136-01-168 | | | | | | STP 2012(309) PVMNT REPAIR,MILL,SEAL&THIN OVERLAY | | | | | | | | | | | | WORK ORDER- 03-16-12 WORK BEGAN- 10-18-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 05-15-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 32 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 30 PERCENT TIME USED- 93 | |**************************************************| | | | | | | | RAMMING PAVING COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 3136-01-168 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 8.16 | | | | AARON CONCRETE CONTRACTORS, L.P. | |SUB %: 6.76 | | | | | | | | | | CONTRACT 02123028 | TOTALS | 591,231.61| 0.00| 569,337.54| 96.2| ************************************************************************************************************************************ TRAVIS 1.000 MI S. OF US 290 | 3.587 | 1,217,042.82| 3,544.51| 1,247,663.56| 99.9| FM 3177 FM 969 | | | | | | 3277-01-020 | | | | | | STP 2012(310) PVMT REPAIR, SEAL & THIN OVERLAY | | | | | | | | | | | | WORK ORDER- 03-12-12 WORK BEGAN- 12-03-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 05-11-12 | | | | | | CONTRACT WORKING DAYS- 42 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 27 PERCENT TIME USED- 64 | | | | | | | | | | | | RAMMING PAVING COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 3277-01-020 | | | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | |SUB %: 0.52 | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 0.27 | | | | TEX OP CONSTRUCTION, LP | |SUB %: 1.60 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 5.70 | | | | | | | | | | CONTRACT 02123217 | TOTALS | 1,217,042.82| 3,544.51| 1,247,663.56| 99.9| ************************************************************************************************************************************ TRAVIS SAFE ROUTES TO SCHOOL-COUNTYLINE RD | 0.445 | 397,507.33| 0.00| 0.00| 0.0| VA NEIDIG ELEM & ELGIN H.S. | | | | | | 0914-00-326 | | | | | | STP 1102(490)SRS CONSTRUCT SIDEWALKS | | | | | | | | | | | | WORK ORDER- 05-13-13 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 05-29-13 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 48 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | BEAR CREEK CONSTRUCTION, LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-00-326 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 02133023 | TOTALS | 397,507.33| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TRAVIS 585 FT EAST OF CONVICT HILL | 1.176 | 5,090,960.00| 0.00| 0.00| 0.0| US 290 372 FT WEST OF JOE TANNER LANE | | | | | | 0113-08-076 | | | | | | NH 2013(403) INNOVATIVE INTERSECTION IMPROVEMENT | | | | | | | | | | | | TRAVIS 585 FT EAST OF CONVICT HILL | 1.176 | 900,042.50| 0.00| 0.00| 0.0| US 290 372 FT WEST OF JOE TANNER LANE | | | | | | 0113-08-079 | | | | | | RW 113-8-79 UTILITY ADJUSTMENTS | | | | | | | | | | | | TRAVIS 372 FT WEST OF JOE TANNER LANE | 0.222 | 532,369.00| 0.00| 0.00| 0.0| US 290 800 FT EAST OF JOE TANNER LANE | | | | | | 0113-09-069 | | | | | | NH 2013(403) INNOVATIVE INTERSECTION IMPROVEMENT | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 335 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | CF JORDAN CONSTRUCTION LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0113-08-076 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 02133227 | TOTALS | 6,523,371.50| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TRAVIS 1300' W OF LAGO VISTA W.C.L. | 0.402 | 494,228.44| 800.00| 800.00| 0.1| RM 1431 800' EAST OF WEST CITY LIMIT | | | | | | 1378-01-032 | | | | | | CC 1378-1-32 ADD LEFT TURN LANE | | | | | | | | | | | | WORK ORDER- 04-03-13 WORK BEGAN- 00-00-00 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-19-13 | | | | | | CONTRACT WORKING DAYS- 125 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | | | | | | | | | | | | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1378-01-032 | | | | | | RICE ENVIRONMENTAL SERVICES | |SUB %: 2.72 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 8.66 | | | | | | | | | | CONTRACT 02133230 | TOTALS | 494,228.44| 800.00| 800.00| 0.1| ************************************************************************************************************************************ TRAVIS ETC AT E MARTIN LUTHER KING BLVD | 0.900 | 1,035,409.77| 0.00| 1,074,788.81| 99.9| IH 35 ETC . | | | | | | 0015-13-357 | | | | | | STP 2011(771)HES IMPROVE TRAFFIC SIGNAL | | | | | | | | | | | | WORK ORDER- 04-18-11 WORK BEGAN- 07-13-11 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 05-04-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 170 ADDL DAYS GRANTED- 31 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 209 PERCENT TIME USED- 103 | |**************************************************| | | | | | | | HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0015-13-357 | | | | | | TX DOWN UNDER CONSTRUCTION LLC | |SUB %: 8.41 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.46 | | | | | | | | | | CONTRACT 03113006 | TOTALS | 1,035,409.77| 0.00| 1,074,788.81| 99.9| ************************************************************************************************************************************ TRAVIS AT VARIOUS LOCATIONS DISTRICTWIDE | 0.100 | 864,344.50| 46,511.06| 912,040.82| 99.9| VA . | | | | | | 0914-00-292 | | | | | | NH 2012(416) 2012 NON-SITE SPECIFIC SIGNALS | | | | | | | | | | | | WORK ORDER- 04-26-12 WORK BEGAN- 06-27-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 05-12-12 | | | | | | CONTRACT WORKING DAYS- 459 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 201 PERCENT TIME USED- 43 | | | | | | | | | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-00-292 | | | | | | AUSTIN UNDERGROUND INCORPORATED | |SUB %: 0.69 | | | | M.G. DRILLING | |SUB %: 3.57 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 3.12 | | | | KRL CONSTRUCTION INC. | |SUB %: 7.91 | | | | | | | | | | CONTRACT 03123009 | TOTALS | 864,344.50| 46,511.06| 912,040.82| 99.9| ************************************************************************************************************************************ TRAVIS VARIOUS ON-SYS LOCATIONS | 0.100 | 287,731.00| 26,906.24| 247,143.32| 85.8| VA DISTRICTWIDE | | | | | | 0914-00-345 | | | | | | NH 2012(379) SCHOOL ZONE UPGRADES | | | | | | | | | | | | WORK ORDER- 04-16-12 WORK BEGAN- 12-03-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 07-15-12 | | | | | | CONTRACT WORKING DAYS- 102 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 65 PERCENT TIME USED- 63 | | | | | | | | | | | | SIEMENS INDUSTRY, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-00-345 | | | | | | CODY DRILLING | |SUB %: 5.44 | | | | ESA ENGINEERING, LLC | |SUB %: 5.05 | | | | | | | | | | CONTRACT 03123023 | TOTALS | 287,731.00| 26,906.24| 247,143.32| 85.8| ************************************************************************************************************************************ TRAVIS 0.207 MI. EAST OF HARRISGLENN DRIVE | 0.154 | 118,691.50| 0.00| 0.00| 0.0| FM 734 0.361 MI. EAST OF HARRISGLENN DRIVE | | | | | | 3417-03-019 | | | | | | CC 3417-3-19 ADD EASTBOUND LEFT TURN LANE | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 21 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 3417-03-019 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 03133008 | TOTALS | 118,691.50| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TRAVIS FM 812 | 2.481 | 742,733.15| 0.00| 0.00| 0.0| FM 973 US 183 | | | | | | 1200-05-017 | | | | | | STP 2013(477) PVMT REPAIR, SEAL & THIN OVERLAY | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 102 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | HUNTER INDUSTRIES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1200-05-017 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 03133014 | TOTALS | 742,733.15| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TRAVIS 400' S OF WALNUT CREEK BRIDGE | 1.944 | 1,249,601.80| 0.00| 0.00| 0.0| LP 275 RUTLAND DR | | | | | | 0015-11-062 | | | | | | STP 2013(470) MILL, SEAL & THIN OVERLAY | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 42 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | RAMMING PAVING COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0015-11-062 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 03133031 | TOTALS | 1,249,601.80| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TRAVIS AT VARIOUS LOCATIONS DISTRICTWIDE | 0.100 | 865,508.00| 0.00| 0.00| 0.0| VA . | | | | | | 0914-00-322 | | | | | | STP 2013(476) FY 2013 NON-SITE SPECIFIC SIGNALS | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 457 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-00-322 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 03133223 | TOTALS | 865,508.00| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TRAVIS LP 1 | 2.500 | 2,027,036.96| 0.00| 0.00| 0.0| FM 1325 US 183 | | | | | | 1376-02-039 | | | | | | STP 2013(478) MILL, SEAL & THIN OVERLAY | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 50 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | RAMMING PAVING COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1376-02-039 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 03133230 | TOTALS | 2,027,036.96| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TRAVIS RM 620 WEST 0.75 MI | 0.753 | 3,637,513.40| 0.00| 4,192,658.05| 99.9| RM 2769 PROPOSED ANDERSON MILL RD | | | | | | 2718-01-009 | | | | | | STP 2010(690)ES RECONST TO 4-LANE DIVIDED | | | | | | | | | | | | TRAVIS RM 620 WEST OF 0.75 MILE | 0.001 | 455,772.60| 0.00| 482,366.00| 99.9| RM 2769 PROPOSED ANDERSON MILL RD | | | | | | 2718-01-011 | | | | | | RW 2718-1-11 ROW ACQUISITION, UTIL & RELOC | | | | | | | | | | | | WORK ORDER- 05-28-10 WORK BEGAN- 08-31-10 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 07-27-10 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 284 ADDL DAYS GRANTED- 97 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 377 PERCENT TIME USED- 98 | |**************************************************| | | | | | | | CASH CONSTRUCTION COMPANY, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 2718-01-009 | | | | | | GREATER AUSTIN DEVELOPMENT CO., INC. | |SUB %: 16.69 | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 3.75 | | | | BOOTHE BROTHERS PAVING COMPANY, INC. | |SUB %: 1.65 | | | | BRYANT & FREY CONSTRUCTION | |SUB %: 3.98 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 1.22 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.69 | | | | J.D. RAMMING PAVING CO., LTD. | |SUB %: 27.74 | | | | PANTHER CREEK TRANSPORTATION, INC. | |SUB %: 0.59 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 3.81 | | | | TEXAS TRUCKING COMPANY, INC. | |SUB %: 0.00 | | | | PENNTEX MILLING, LLC | |SUB %: 0.29 | | | | FUQUAY, INC. | |SUB %: 0.07 | | | | G & R SURVEYING, LLC | |SUB %: 0.12 | | | | GULF COAST GROUTING, INC. | |SUB %: 0.50 | | | | | | | | | | CONTRACT 04103006 | TOTALS | 4,093,286.00| 0.00| 4,675,024.05| 99.9| ************************************************************************************************************************************ TRAVIS AT VARIOUS LOCATIONS DISTRICTWIDE | 0.100 | 718,588.25| 0.00| 2,063,164.80| 99.9| VA . | | | | | | 0914-00-294 | | | | | | STP 2010(727) FY 2010 NON-SITE SPECIFIC SIGNALS | | | | | | | | | | | | WORK ORDER- 05-11-10 WORK BEGAN- 06-01-10 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 05-27-10 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 414 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 372 PERCENT TIME USED- 89 | |**************************************************| | | | | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-00-294 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 7.56 | | | | | | | | | | CONTRACT 04103211 | TOTALS | 718,588.25| 0.00| 2,063,164.80| 99.9| ************************************************************************************************************************************ TRAVIS AT VARIOUS LOCATIONS DISTRICTWIDE | 0.100 | 870,431.70| 0.00| 0.00| 0.0| VA . | | | | | | 0914-00-324 | | | | | | STP 2013(554) FY 2013 SITE-SPECIFIC SIGNALS | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 261 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | SIEMENS INDUSTRY, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-00-324 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 04133013 | TOTALS | 870,431.70| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TRAVIS 0.166 MI. NW OF DESSAU ROAD | 0.446 | 1,481,100.48| 0.00| 0.00| 0.0| FM 734 0.280 MI. SE OF DESSAU ROAD | | | | | | 3417-03-017 | | | | | | C 3417-3-17 ADD LEFT AND RIGHT TURN LANES | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 100 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | CAPITAL EXCAVATION COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 3417-03-017 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 04133027 | TOTALS | 1,481,100.48| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TRAVIS 490 FT. EAST OF SHADOWGLEN BLVD CTL | 0.599 | 372,486.10| 0.00| 0.00| 0.0| US 290 1020 FT. EAST OF FM 973 | | | | | | 0114-02-098 | | | | | | CC 114-2-98 ADD EB RIGHT TURN AND EB & WB LTLS | | | | | | | | | | | | TRAVIS 1775 FT. SOUTH OF US 290 | 0.336 | 397,395.50| 0.00| 0.00| 0.0| LP 212 US 290 | | | | | | 0114-20-010 | | | | | | CC 114-20-10 ADD SB RIGHT & NB LEFT TURN LANES | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 50 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | AARON CONCRETE CONTRACTORS, L.P. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0114-02-098 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 04133227 | TOTALS | 769,881.60| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TRAVIS 0.55 MILES W OF SOUTHWEST PKWY | 0.697 | 5,035,450.53| 56,031.18| 1,942,645.35| 40.0| SH 71 0.14 MILES E OF SOUTHWEST PKWY | | | | | | 0700-03-114 | | | | | | STP 2011(949)HES INSTALL CTL, ACCEL LN & SHLDRS | | | | | | | | | | | | TRAVIS 0.55 MILES W OF SOUTHWEST PKWY | 0.697 | 322,251.00| 0.00| 242,715.00| 75.3| SH 71 0.14 MILES E OF SOUTHWEST PKWY | | | | | | 0700-03-120 | | | | | | RW 700-3-120 UTILITY ADJUSTMENTS | | | | | | | | | | | | WORK ORDER- 07-27-11 WORK BEGAN- 01-23-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 08-12-11 | | | | | | CONTRACT WORKING DAYS- 244 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 312 PERCENT TIME USED- 127 | | | | | | | | | | | | ANGEL BROTHERS ENTERPRISES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0700-03-114 | | | | | | AUSTIN WOOD RECYCLING | |SUB %: 0.54 | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 0.87 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 2.03 | | | | J & M CONTRACTING, COMPANY | |SUB %: 13.54 | | | | MENADE, INC. | |SUB %: 22.85 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 2.04 | | | | WEBBER BARRIER SERVICES, INC. | |SUB %: 1.35 | | | | J.A. ROAD BORING, INC. | |SUB %: 2.03 | | | | FARR FOUNDATION, INC. | |SUB %: 2.78 | | | | KEN-WAY, INCORPORATED | |SUB %: 4.19 | | | | VOGES DRILLING CO. | |SUB %: 0.25 | | | | DRILL TECH DRILLING & SHORING, INC. | |SUB %: 3.15 | | | | CHLOR-SERV, INC. | |SUB %: 0.06 | | | | DESERT STEEL CO., INC. | |SUB %: 0.17 | | | | | | | | | | CONTRACT 05113226 | TOTALS | 5,357,701.53| 56,031.18| 2,185,360.35| 42.1| ************************************************************************************************************************************ TRAVIS VARIOUS LOCATIONS IN TRAVIS COUNTY | 0.100 | 775,000.00| 4,294.25| 653,817.18| 84.3| VA ON IH 35 AND ON US 183 | | | | | | 0914-04-269 | | | | | | STP 2012(551) LANDSCAPE AND IRRIGATION | | | | | | | | | | | | WORK ORDER- 07-12-12 WORK BEGAN- 08-13-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 08-13-12 | | | | | | CONTRACT WORKING DAYS- 105 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 103 PERCENT TIME USED- 98 | | | | | | | | | | | | LEGENDS LANDSCAPES LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-04-269 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 05123049 | TOTALS | 775,000.00| 4,294.25| 653,817.18| 84.3| ************************************************************************************************************************************ TRAVIS BRAKER LN | 11.000 | 1,651,934.64| 67,773.35| 252,139.41| 15.2| IH 35 BEN WHITE BLVD | | | | | | 0015-13-338 | | | | | | STP 2012(545)MM CONST SIDEWALKS ON BOTH SIDES IH 35 | | | | | | | | | | | | TRAVIS IH 35 | 0.474 | 234,806.96| 13,385.00| 234,159.75| 99.7| US 183 NORWOOD PARK | | | | | | 0151-09-144 | | | | | | NH 2012(546) CONSTRUCT SIDEWALKS | | | | | | | | | | | | WORK ORDER- 08-10-12 WORK BEGAN- 10-15-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 08-26-12 | | | | | | CONTRACT WORKING DAYS- 288 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 108 PERCENT TIME USED- 37 | | | | | | | | | | | | AUSTIN FILTER SYSTEMS, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0015-13-338 | | | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 0.91 | | | | PEK, INC. | |SUB %: 35.86 | | | | | | | | | | CONTRACT 05123246 | TOTALS | 1,886,741.60| 81,158.35| 486,299.16| 25.7| ************************************************************************************************************************************ TRAVIS SH 130 | 2.373 | 1,224,218.25| 0.00| 365,883.00| 29.8| FM 685 PECAN ST | | | | | | 0757-02-015 | | | | | | STP 2012(549) MILL, SEAL & OVERLAY | | | | | | | | | | | | WORK ORDER- 06-15-12 WORK BEGAN- 11-05-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 08-14-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 41 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 11 PERCENT TIME USED- 26 | |**************************************************| | | | | | | | RAMMING PAVING COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0757-02-015 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 2.28 | | | | PENNTEX MILLING, LLC | |SUB %: 3.77 | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 0.78 | | | | | | | | | | CONTRACT 05123249 | TOTALS | 1,224,218.25| 0.00| 365,883.00| 29.8| ************************************************************************************************************************************ TRAVIS 1630 FEET WEST OF LP 1 | 0.590 | 335,191.45| 0.00| 0.00| 0.0| FM 734 TOMANET TRAIL | | | | | | 3417-01-027 | | | | | | NH 2013(706) OVERLAY & RESTRIPE FOR BICYCLE LANE | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 21 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | APAC-TEXAS, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 3417-01-027 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 05133039 | TOTALS | 335,191.45| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TRAVIS AT LOOP 1 | 1.018 | 8,418,678.59| 17,949.00| 8,770,614.75| 99.9| US 290 . | | | | | | 0113-09-052 | | | | | | PTF 2010(873) PHASE IV:CONST 2 REMAINING DIRECT C | | | | | | | | | | | | WORK ORDER- 08-20-10 WORK BEGAN- 10-06-10 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 10-06-10 | | | | | | CONTRACT WORKING DAYS- 370 ADDL DAYS GRANTED- 45 | | | | | | WORKING DAYS CHARGED- 536 PERCENT TIME USED- 129 | | | | | | | | | | | | SAFECO INSURANCE COMPANIES | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0113-09-052 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.33 | | | | MCKINNEY DRILLING__(BUDA) | |SUB %: 2.77 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.89 | | | | ASPHALT PAVING COMPANY OF AUSTIN, INC. | |SUB %: 1.50 | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 2.27 | | | | PRIME CONTRACTING, LLC | |SUB %: 17.20 | | | | CHOCTAW ERECTORS, INC. | |SUB %: 6.09 | | | | BREDA COMPANY, INC. | |SUB %: 1.50 | | | | ARICON 3, INC. | |SUB %: 6.27 | | | | A & R DEMOLITION | |SUB %: 0.19 | | | | INDUS CONSTRUCTION, L.P. | |SUB %: 1.25 | | | | KEYSTONE CONSTRUCTION INC. | |SUB %: 0.99 | | | | ANDERSON COLUMBIA CO., INC. | |SUB %: 0.00 | | | | PRIMATE CONSTRUCTION, INC. | |SUB %: 0.14 | | | | SCOTT DERR PAINTING CO | |SUB %: 0.23 | | | | | | | | | | CONTRACT 06103202 | TOTALS | 8,418,678.59| 17,949.00| 8,770,614.75| 99.9| ************************************************************************************************************************************ TRAVIS 0.30 MI. W. OF HUNTERS BEND RD. | 0.303 | 398,287.40| 0.00| 396,471.18|100.0| FM 969 HUNTERS BEND RD. | | | | | | 1186-01-088 | | | | | | CC 1186-1-88 ADD DUAL LEFT FROM HUNTERS BEND RD. | | | | | | | | | | | | WORK ORDER- 07-14-11 WORK BEGAN- 09-06-11 | |**************************************************| | DATE WORK COMPLETED- 05-10-13 TIME COMPUTED- 09-06-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 57 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 39 PERCENT TIME USED- 68 | |**************************************************| | | | | | | | AARON CONCRETE CONTRACTORS, L.P. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1186-01-088 | | | | | | APAC-TEXAS, INC. | |SUB %: 28.09 | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 22.90 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 4.74 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 3.69 | | | | | | | | | | CONTRACT 06113234 | TOTALS | 398,287.40| 0.00| 396,471.18|100.0| ************************************************************************************************************************************ TRAVIS BURNET RD | 3.476 | 1,912,437.45| 0.00| 1,957,389.26|100.0| US 183 IH 35 | | | | | | 0151-06-135 | | | | | | STP 1102(322) MILL, SEAL & OVERLAY FRONTAGE RDS | | | | | | | | | | | | WORK ORDER- 07-19-11 WORK BEGAN- 09-12-11 | |**************************************************| | DATE WORK COMPLETED- 04-17-13 TIME COMPUTED- 09-12-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 58 ADDL DAYS GRANTED- 6 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 74 PERCENT TIME USED- 115 | |**************************************************| | | | | | | | ANGEL BROTHERS ENTERPRISES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0151-06-135 | | | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 4.24 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 7.03 | | | | | | | | | | CONTRACT 06113246 | TOTALS | 1,912,437.45| 0.00| 1,957,389.26|100.0| ************************************************************************************************************************************ TRAVIS 175' S. OF FM 969 | 2.910 | 1,342,739.02| 0.00| 1,435,764.47| 99.9| FM 973 1922' S. GREEN GROVE DR | | | | | | 1200-03-030 | | | | | | STP 1102(371) REHABILITATE ROADWAY | | | | | | | | | | | | WORK ORDER- 08-10-11 WORK BEGAN- 10-04-11 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 55 ADDL DAYS GRANTED- 5 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 58 PERCENT TIME USED- 96 | |**************************************************| | | | | | | | RAMMING PAVING COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1200-03-030 | | | | | | A GREATER AUSTIN DEVELOPMENT COMPANY, LTD. | |SUB %: 6.37 | | | | AARON CONCRETE CONTRACTORS, L.P. | |SUB %: 15.67 | | | | M.V. HENKE ENTERPRISES, INC. | |SUB %: 1.40 | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 0.52 | | | | PENNTEX MILLING, LLC | |SUB %: 0.61 | | | | RICE ENVIRONMENTAL SERVICES | |SUB %: 2.91 | | | | TRP CONSTRUCTION GROUP, LLC | |SUB %: 3.62 | | | | | | | | | | CONTRACT 07113037 | TOTALS | 1,342,739.02| 0.00| 1,435,764.47| 99.9| ************************************************************************************************************************************ TRAVIS CIRCLE DR | 0.730 | 2,493,084.79| 0.00| 2,493,017.13| 99.9| US 290 OLIVER DR | | | | | | 0113-08-069 | | | | | | NH 1102(368) INSTALL CTL & PAVED SHOULDERS | | | | | | | | | | | | WORK ORDER- 09-02-11 WORK BEGAN- 10-19-11 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 09-18-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 275 ADDL DAYS GRANTED- 15 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 266 PERCENT TIME USED- 91 | |**************************************************| | | | | | | | CAPITAL EXCAVATION COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0113-08-069 | | | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 0.00 | | | | FARR FOUNDATION, INC. | |SUB %: 0.66 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 0.75 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.76 | | | | J.D. RAMMING PAVING CO., LTD. | |SUB %: 0.81 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 2.50 | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | |SUB %: 8.09 | | | | | | | | | | CONTRACT 07113049 | TOTALS | 2,493,084.79| 0.00| 2,493,017.13| 99.9| ************************************************************************************************************************************ TRAVIS HARRIS BRANCH BLVD | 3.455 | 7,482,979.00| 0.00| 7,533,112.05| 99.9| FM 734 US 290 | | | | | | 3417-03-015 | | | | | | STP 1102(372) REHAB ROADWAY | | | | | | | | | | | | WORK ORDER- 08-15-11 WORK BEGAN- 11-01-11 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 10-14-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 294 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 245 PERCENT TIME USED- 83 | |**************************************************| | | | | | | | AARON CONCRETE CONTRACTORS, L.P. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 3417-03-015 | | | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 1.04 | | | | APAC-TEXAS, INC. | |SUB %: 42.98 | | | | BMP SPECIALIST, LLC | |SUB %: 1.19 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 2.45 | | | | | | | | | | CONTRACT 07113247 | TOTALS | 7,482,979.00| 0.00| 7,533,112.05| 99.9| ************************************************************************************************************************************ TRAVIS IH 35 | 6.360 | 519,513.90| 2,800.00| 544,626.46| 99.9| SH 71 1500' EAST OF MONTOPOLIS DR. | | | | | | 0113-13-148 | | | | | | STP 2011(108) LANDSCAPING AND IRRIGATION | | | | | | | | | | | | WORK ORDER- 09-14-10 WORK BEGAN- 01-03-11 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-13-10 | | | | | | CONTRACT WORKING DAYS- 88 ADDL DAYS GRANTED- 10 | | | | | | WORKING DAYS CHARGED- 77 PERCENT TIME USED- 78 | | | | | | | | | | | | LEGENDS LANDSCAPES LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0113-13-148 | | | | | | LONE STAR TRAFFIC SERVICE, INC. | |SUB %: 0.69 | | | | DOWN UNDER CONSTRUCTION | |SUB %: 3.00 | | | | CARTER PLUMBING, INC. | |SUB %: 4.23 | | | | | | | | | | CONTRACT 08103019 | TOTALS | 519,513.90| 2,800.00| 544,626.46| 99.9| ************************************************************************************************************************************ TRAVIS EAST OF MONTOPOLIS DR | 1.419 | 33,460,488.85| 998,393.65| 14,099,609.17| 42.1| SH 71 US 183 | | | | | | 0113-13-149 | | | | | | NH 1102(240) CONST UNDERPASS, FRT RDS&MAIN LANES | | | | | | | | | | | | TRAVIS EAST OF MONTOPOLIS DR | 1.300 | 1,522,117.70| 0.00| 1,123,929.41| 73.8| SH 71 US 183 | | | | | | 0113-13-151 | | | | | | RW 113-13-151 ROW ACQ. AND UTL. ADJ. | | | | | | | | | | | | WORK ORDER- 09-27-11 WORK BEGAN- 01-26-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 12-25-11 | | | | | | CONTRACT WORKING DAYS- 581 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 246 PERCENT TIME USED- 42 | | | | | | | | | | | | SEMA CONSTRUCTION, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0113-13-149 | | | | | | RICE ENVIRONMENTAL SERVICES | |SUB %: 0.33 | | | | SCOTT DERR PAINTING CO, LLC | |SUB %: 0.14 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.22 | | | | AUSTIN WOOD RECYCLING | |SUB %: 0.09 | | | | INDUS CONSTRUCTION, L.P. | |SUB %: 0.39 | | | | PRIMATE CONSTRUCTION, INC. | |SUB %: 0.21 | | | | BMP SPECIALIST, LLC | |SUB %: 0.08 | | | | TEX OP CONSTRUCTION, LP | |SUB %: 0.01 | | | | PERFORMANCE EQUIPMENT | |SUB %: 0.13 | | | | AUSTIN FILTER SYSTEMS, INC. | |SUB %: 3.34 | | | | J.D. RAMMING PAVING CO., LTD. | |SUB %: 11.54 | | | | CRAIG OLDEN, INC. | |SUB %: 12.42 | | | | MCKINNEY DRILLING__(BUDA) | |SUB %: 0.66 | | | | ROYAL VISTA INC. | |SUB %: 9.79 | | | | AARON CONCRETE CONTRACTORS, L.P. | |SUB %: 4.70 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.54 | | | | BOOTHE BROTHERS PAVING COMPANY, INC. | |SUB %: 1.34 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 5.73 | | | | RANGER EXCAVATING, L.P. | |SUB %: 0.00 | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION (OLD PRIME) | |SUB %: 2.11 | | | | BRYANT & FREY CONSTRUCTION | |SUB %: 0.00 | | | | CHAMPION SITE PREP, L.P. | |SUB %: 0.00 | | | | CENTRAL TEXAS REINFORCEMENT | |SUB %: 0.01 | | | | CHANDLER CONCRETE, INC. | |SUB %: 0.57 | | | | MG DRILLING | |SUB %: 0.00 | | | | REINFORCING STEEL SUPPLY | |SUB %: 0.00 | | | | LONE STAR SITEWORK, LLC | |SUB %: 0.57 | | | | KRL CONSTRUCTION INC. | |SUB %: 0.11 | | | | | | | | | | CONTRACT 08113002 | TOTALS | 34,982,606.55| 998,393.65| 15,223,538.58| 43.5| ************************************************************************************************************************************ TRAVIS ON OLD MANOR RD AT TANNEHILL BRANCH | 0.001 | 948,392.97| 0.00| 921,369.93| 97.1| CS STR B021-07-001 | | | | | | 0914-04-187 | | | | | | BR 2002(468) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | TRAVIS ON OLD MANOR RD AT TANNEHILL BRANCH | 0.001 | 328,656.38| 0.00| 287,575.00| 87.5| CS STR B021-07-001 | | | | | | 0914-04-262 | | | | | | RW 914-4-262 ROW UTL. ADJ. | | | | | | | | | | | | WORK ORDER- 09-14-11 WORK BEGAN- 11-07-11 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 09-30-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 237 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 237 PERCENT TIME USED- 100 | |**************************************************| | | | | | | | CAPITAL EXCAVATION COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-04-187 | | | | | | AUSTIN WOOD RECYCLING | |SUB %: 1.47 | | | | BRYANT & FREY CONSTRUCTION | |SUB %: 9.50 | | | | EW WELLS GROUP LLC | |SUB %: 15.66 | | | | F & W ELECTRICAL CONTRACTORS, INC. | |SUB %: 3.07 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 11.47 | | | | J.D. RAMMING PAVING CO., LTD. | |SUB %: 3.92 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 3.59 | | | | S & S PAINTING | |SUB %: 0.21 | | | | VOGES DRILLING | |SUB %: 4.44 | | | | SITESAFE PRODUCTS TEXAS | |SUB %: 1.01 | | | | | | | | | | CONTRACT 08113023 | TOTALS | 1,277,049.35| 0.00| 1,208,944.93| 94.6| ************************************************************************************************************************************ TRAVIS VARIOUS LOCATIONS IN TRAVIS COUNTY | 0.100 | 1,195,085.00| 0.00| 1,571,173.89| 99.9| VA . | | | | | | 0914-04-268 | | | | | | STP 2012(055) CONSTRUCT CURB RAMPS | | | | | | | | | | | | WORK ORDER- 10-07-11 WORK BEGAN- 03-19-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 12-06-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 213 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 171 PERCENT TIME USED- 80 | |**************************************************| | | | | | | | TI-ZACK CONCRETE, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-04-268 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.58 | | | | FUQUAY, INC. | |SUB %: 4.69 | | | | FAASS TRUCKING, INC. | |SUB %: 0.00 | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 1.75 | | | | | | | | | | CONTRACT 08113047 | TOTALS | 1,195,085.00| 0.00| 1,571,173.89| 99.9| ************************************************************************************************************************************ TRAVIS 0.2 MILES WEST OF REDBUD TRAIL | 0.412 | 1,020,547.37| 0.00| 1,179,166.53| 99.9| RM 2244 SUNDOWN PARKWAY | | | | | | 2102-01-062 | | | | | | STP 1102(247)MM CONST 4 LN URBAN RDWY W/ CONT LTL | | | | | | | | | | | | TRAVIS 0.2 MILES WEST OF REDBUD TRAIL | 0.331 | 451,051.54| 0.00| 660,549.52| 99.9| RM 2244 SUNDOWN PARKWAY | | | | | | 2102-01-063 | | | | | | RW 2102-1-63 ROW UTL. ADJ. | | | | | | | | | | | | WORK ORDER- 09-13-11 WORK BEGAN- 01-16-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 03-14-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 162 ADDL DAYS GRANTED- 92 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 253 PERCENT TIME USED- 99 | |**************************************************| | | | | | | | DAN WILLIAMS COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 2102-01-062 | | | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 1.80 | | | | F & W ELECTRICAL CONTRACTORS, INC. | |SUB %: 9.38 | | | | J.A. ROAD BORING, INC. | |SUB %: 2.95 | | | | RICE ENVIRONMENTAL SERVICES | |SUB %: 0.73 | | | | J.D. RAMMING PAVING CO., LTD. | |SUB %: 13.07 | | | | MICKIE SERVICE, INC. | |SUB %: 0.94 | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | |SUB %: 0.76 | | | | TEX OP CONSTRUCTION, LP | |SUB %: 0.56 | | | | | | | | | | CONTRACT 08113060 | TOTALS | 1,471,598.91| 0.00| 1,839,716.05| 99.9| ************************************************************************************************************************************ TRAVIS MANCHACA RD | 2.331 | 1,192,681.83| 0.00| 1,206,410.59| 99.9| US 290 EAST OF CONGRESS AVE | | | | | | 0113-13-144 | | | | | | NH 1102(426) REHABILITATE ROADWAY | | | | | | | | | | | | WORK ORDER- 09-13-11 WORK BEGAN- 07-02-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 49 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 53 PERCENT TIME USED- 108 | |**************************************************| | | | | | | | RAMMING PAVING COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0113-13-144 | | | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 4.79 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 11.77 | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 0.24 | | | | TEX OP CONSTRUCTION, LP | |SUB %: 8.67 | | | | | | | | | | CONTRACT 08113221 | TOTALS | 1,192,681.83| 0.00| 1,206,410.59| 99.9| ************************************************************************************************************************************ TRAVIS US 290 | 1.935 | 246,629.48| 0.00| 214,609.16| 87.0| LP 1 BRUSH COUNTRY ROAD | | | | | | 3136-01-169 | | | | | | STP 1102(330) LANDSCAPING AND IRRIGATION | | | | | | | | | | | | WORK ORDER- 09-13-11 WORK BEGAN- 03-05-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 12-12-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 65 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 31 PERCENT TIME USED- 47 | |**************************************************| | | | | | | | LEGENDS LANDSCAPES LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 3136-01-169 | | | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 1.52 | | | | | | | | | | CONTRACT 08113269 | TOTALS | 246,629.48| 0.00| 214,609.16| 87.0| ************************************************************************************************************************************ TRAVIS BEE CAVES RD | 3.912 | 1,640,002.97| 0.00| 1,838,316.76| 99.9| LP 360 LP 1 | | | | | | 0113-13-152 | | | | | | NH 1102(427) MILL, SEAL & THIN OVERLAY | | | | | | | | | | | | WORK ORDER- 09-14-11 WORK BEGAN- 09-05-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 09-30-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 39 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 39 PERCENT TIME USED- 100 | |**************************************************| | | | | | | | RAMMING PAVING COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0113-13-152 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 6.04 | | | | | | | | | | CONTRACT 08113273 | TOTALS | 1,640,002.97| 0.00| 1,838,316.76| 99.9| ************************************************************************************************************************************ TRAVIS 0.23 MI. N. OF CAPITAL OF TEXAS HWY | 0.527 | 249,789.50| 1,910.41| 336,661.65|100.0| LP 1 0.30 MI. S. OF CAPITAL OF TEXAS HWY | | | | | | 3136-01-171 | | | | | | CC 3136-1-171 WIDEN NBFR & INSTALL AUXILIARY LANE | | | | | | | | | | | | WORK ORDER- 09-14-12 WORK BEGAN- 09-17-12 | | | | | | DATE WORK COMPLETED- 05-06-13 TIME COMPUTED- 09-30-12 | | | | | | CONTRACT WORKING DAYS- 33 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 31 PERCENT TIME USED- 93 | | | | | | | | | | | | COPPEDGE CONSTRUCTION COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 3136-01-171 | | | | | | DUSTROL, INC. | |SUB %: 2.84 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 2.79 | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 1.04 | | | | APAC-TEXAS, INC. | |SUB %: 46.36 | | | | G. CARTER CONSTRUCTION COMPANY, INC. | |SUB %: 2.23 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 5.77 | | | | H.R. MARC COMPANY,INC. | |SUB %: 5.97 | | | | | | | | | | CONTRACT 08123218 | TOTALS | 249,789.50| 1,910.41| 336,661.65|100.0| ************************************************************************************************************************************ TRAVIS BOLM RD | 0.486 | 117,198.00| 0.00| 115,928.43|100.0| LP 111 US 183 | | | | | | 0151-06-130 | | | | | | STP 2012(049)MM CONSTRUCT SIDEWALK ON AIRPORT BLVD | | | | | | | | | | | | WORK ORDER- 11-08-11 WORK BEGAN- 02-13-12 | |**************************************************| | DATE WORK COMPLETED- 05-01-13 TIME COMPUTED- 01-07-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 51 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 25 PERCENT TIME USED- 49 | |**************************************************| | | | | | | | GARCIA J CONTRACTORS, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0151-06-130 | | | | | | TEXAS CONCRETE COMPANY | |SUB %: 18.21 | | | | | | | | | | CONTRACT 09113027 | TOTALS | 117,198.00| 0.00| 115,928.43|100.0| ************************************************************************************************************************************ TRAVIS VARIOUS | 0.100 | 4,204,759.50| 75,926.60| 1,698,454.98| 40.3| VA . | | | | | | 0914-00-301 | | | | | | NH 2012(007) FY 2012 NON-SITE SPECIFIC ITS MAINT | | | | | | | | | | | | WORK ORDER- 10-25-11 WORK BEGAN- 02-21-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-10-11 | | | | | | CONTRACT WORKING DAYS- 508 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 243 PERCENT TIME USED- 47 | | | | | | | | | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-00-301 | | | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 2.80 | | | | AUSTIN UNDERGROUND INCORPORATED | |SUB %: 2.05 | | | | M.G. DRILLING | |SUB %: 0.62 | | | | | | | | | | CONTRACT 09113230 | TOTALS | 4,204,759.50| 75,926.60| 1,698,454.98| 40.3| ************************************************************************************************************************************ TRAVIS AT VARIOUS LOCATIONS DISTRICTWIDE | 0.100 | 357,642.60| 0.00| 0.00| 0.0| VA . | | | | | | 0914-00-291 | | | | | | NH 2013(026) FY 2012 SIGNING | | | | | | | | | | | | WORK ORDER- 10-12-12 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 67 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-00-291 | | | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 5.83 | | | | | | | | | | CONTRACT 09123044 | TOTALS | 357,642.60| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TRAVIS VARIOUS | 0.100 | 2,958,819.25| 0.00| 0.00| 0.0| VA (ON-SYSTEM) | | | | | | 0914-00-314 | | | | | | NH 2013(027) FY 2013 NON-SITE SPECIFIC ITS MAINT | | | | | | | | | | | | WORK ORDER- 10-12-12 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 10-28-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 508 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-00-314 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 09123244 | TOTALS | 2,958,819.25| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TRAVIS WEST OF RM 1826 | 0.860 | 4,079,142.96| 0.00| 0.00| 0.0| US 290 EAST OF CONVICT HILL | | | | | | 0113-08-075 | | | | | | NH 2012(641) PROVIDE SIGNALIZED INTERSECTIONS | | | | | | | | | | | | TRAVIS WEST OF RM 1826 | 0.860 | 559,727.70| 0.00| 0.00| 0.0| US 290 EAST OF CONVICT HILL | | | | | | 0113-08-078 | | | | | | RW 113-8-78 ROW UTL. ADJ. | | | | | | | | | | | | WORK ORDER- 01-04-13 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 217 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | CAPITAL EXCAVATION COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0113-08-075 | | | | | | AUSTIN WOOD RECYCLING | |SUB %: 0.92 | | | | BRYANT & FREY CONSTRUCTION | |SUB %: 4.55 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 2.34 | | | | RAMMING PAVING COMPANY | |SUB %: 22.40 | | | | THE LEVY COMPANY, L.P. | |SUB %: 13.88 | | | | | | | | | | CONTRACT 10123228 | TOTALS | 4,638,870.66| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TRAVIS SAN JOSE AVE. | 5.008 | 1,174,207.13| 0.00| 1,688,655.48| 99.9| FM 812 BASTROP C/L | | | | | | 1149-01-025 | | | | | | STP 2011(687) PAVEMENT REPAIR,SEAL & THIN OVERLAY | | | | | | | | | | | | WORK ORDER- 12-06-10 WORK BEGAN- 09-15-11 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 03-06-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 57 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 57 PERCENT TIME USED- 100 | |**************************************************| | | | | | | | ANGEL BROTHERS ENTERPRISES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1149-01-025 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 3.92 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 8.61 | | | | PRIMATE CONSTRUCTION, INC. | |SUB %: 2.94 | | | | | | | | | | CONTRACT 11103229 | TOTALS | 1,174,207.13| 0.00| 1,688,655.48| 99.9| ************************************************************************************************************************************ TRAVIS 0.46 MI W. OF SPRINGDALE | 6.939 | 1,359,831.37| 0.00| 1,672,906.21|100.0| US 183 0.68 MI S. OF BOLM RD | | | | | | 0151-09-139 | | | | | | NH 2011(722) PVMT SURF REHAB - 2IN ML IP RCYC | | | | | | | | | | | | WORK ORDER- 01-06-11 WORK BEGAN- 04-18-11 | |**************************************************| | DATE WORK COMPLETED- 04-17-13 TIME COMPUTED- 04-06-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 53 ADDL DAYS GRANTED- 12 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 65 PERCENT TIME USED- 100 | |**************************************************| | | | | | | | ANGEL BROTHERS ENTERPRISES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0151-09-139 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 7.14 | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 2.32 | | | | AGGREGATE TECHNOLOGIES, INC. | |SUB %: 2.10 | | | | BMP SPECIALIST, LLC | |SUB %: 0.32 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 4.13 | | | | | | | | | | CONTRACT 12103224 | TOTALS | 1,359,831.37| 0.00| 1,672,906.21|100.0| ************************************************************************************************************************************ TRAVIS ONION CREEK | 5.773 | 1,818,505.76| 0.00| 167,403.29| 9.2| SH 71 BASTROP COUNTY LINE | | | | | | 0265-02-033 | | | | | | NH 2012(154) MILL, SEAL & THIN OVERLAY | | | | | | | | | | | | WORK ORDER- 01-18-12 WORK BEGAN- 08-21-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 02-03-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 85 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 5 PERCENT TIME USED- 5 | |**************************************************| | | | | | | | APAC-TEXAS, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0265-02-033 | | | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.52 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.78 | | | | JAVELINA CONSTRUCTION SOUTH, INC. | |SUB %: 1.41 | | | | MPB, INC. | |SUB %: 1.74 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 8.99 | | | | | | | | | | CONTRACT 12113215 | TOTALS | 1,818,505.76| 0.00| 167,403.29| 9.2| ************************************************************************************************************************************ TRAVIS 1250' WEST OF FM 973 | 1.583 | 2,744,957.75| 553,269.82| 2,707,132.17| 98.8| SH 71 1275' EAST OF FM 973 | | | | | | 0265-01-107 | | | | | | NH 2012(153) CONSTR TURNLANES &INSTALL TRF SGNLS | | | | | | | | | | | | TRAVIS US 183 @ SH 71 | 0.996 | 66,579.00| 0.00| 68,917.27| 99.9| SH 71 SPIRIT OF TEXAS DRIVE | | | | | | 0265-01-111 | | | | | | CC 265-1-111 ROW UTL. ADJ. | | | | | | | | | | | | WORK ORDER- 02-22-12 WORK BEGAN- 04-18-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 03-09-12 | | | | | | CONTRACT WORKING DAYS- 110 ADDL DAYS GRANTED- 26 | | | | | | WORKING DAYS CHARGED- 144 PERCENT TIME USED- 105 | | | | | | | | | | | | SEMA CONSTRUCTION, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0265-01-107 | | | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 3.98 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 6.95 | | | | ROYAL VISTA INC. | |SUB %: 5.42 | | | | J.D. RAMMING PAVING CO., LTD. | |SUB %: 29.43 | | | | PERFORMANCE EQUIPMENT | |SUB %: 2.05 | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 9.46 | | | | AARON CONCRETE CONTRACTORS, L.P. | |SUB %: 0.51 | | | | | | | | | | CONTRACT 12113229 | TOTALS | 2,811,536.75| 553,269.82| 2,776,049.44| 98.9| ************************************************************************************************************************************ TRAVIS BLANCO COUNTY LINE | 3.406 | 416,703.68| 3,230.00| 3,230.00| 0.7| SH 71 PEDERNALES RIVER | | | | | | 0700-03-129 | | | | | | STP 2013(276) LEVEL & SEAL COAT | | | | | | | | | | | | WORK ORDER- 01-17-13 WORK BEGAN- 00-00-00 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 02-02-13 | | | | | | CONTRACT WORKING DAYS- 32 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | | | | | | | | | | | | CLARK CONSTRUCTION OF TEXAS, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0700-03-129 | | | | | | CHICO TRUCKING CO., INC. | |SUB %: 25.20 | | | | RAMI MATERIALS TRANSPORT, LLC | |SUB %: 31.37 | | | | INTERSTATE BARRICADES & MARKINGS, INC. | |SUB %: 19.01 | | | | | | | | | | CONTRACT 12123030 | TOTALS | 416,703.68| 3,230.00| 3,230.00| 0.7| ************************************************************************************************************************************ TRAVIS 63 FT EAST OF RM 2222 | 0.204 | 781,980.95| 0.00| 0.00| 0.0| RM 620 1014 FT WEST OF RM 2222 | | | | | | 0683-02-056 | | | | | | STP 2013(248) RESTRIPE,ADD DUAL RTL &REPL SIGNALS | | | | | | | | | | | | WORK ORDER- 03-15-13 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 03-31-13 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 80 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | AARON CONCRETE CONTRACTORS, L.P. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0683-02-056 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 12123231 | TOTALS | 781,980.95| 0.00| 0.00| 0.0| ************************************************************************************************************************************ WILLIAMSON SH 138 | 7.026 | 39,167,328.18| 431,291.84| 21,683,070.47| 55.3| SH 195 3.4 MI S OF SH 138 | | | | | | 0440-01-035 | | | | | | STP 2011(738) WIDEN GR, STRS & SURF | | | | | | | | | | | | WORK ORDER- 03-04-11 WORK BEGAN- 03-28-11 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 03-20-11 | | | | | | CONTRACT WORKING DAYS- 765 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 518 PERCENT TIME USED- 67 | | | | | | | | | | | | JAMES CONSTRUCTION GROUP, L.L.C. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0440-01-035 | | | | | | TEXAS ALTERNATIVE GRASSER, INC. | |SUB %: 1.51 | | | | TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. | |SUB %: 0.46 | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 0.22 | | | | RICE ENVIRONMENTAL SERVICES | |SUB %: 0.21 | | | | STAR OPERATIONS, INC. | |SUB %: 1.84 | | | | INDUS CONSTRUCTION, L.P. | |SUB %: 0.82 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.56 | | | | SOUTH TEXAS PAINTING COMPANY | |SUB %: 0.05 | | | | RANGER EXCAVATING, L.P. | |SUB %: 22.22 | | | | HOUSTON SAWING & DRILLING | |SUB %: 0.06 | | | | BEAIRD DRILLING | |SUB %: 0.87 | | | | COWBELL TRAFFIC SERVICES, INC. | |SUB %: 0.02 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 0.64 | | | | WOLFF CONSTRUCTION | |SUB %: 1.05 | | | | J.D. RAMMING PAVING CO., LTD. | |SUB %: 29.54 | | | | AUSTIN WOOD RECYCLING | |SUB %: 0.11 | | | | GK CONSTRUCTION, LLC | |SUB %: 0.05 | | | | JAG TRUCKING INC | |SUB %: 0.00 | | | | AUSTIN POWDER COMPANY | |SUB %: 0.09 | | | | | | | | | | CONTRACT 01113020 | TOTALS | 39,167,328.18| 431,291.84| 21,683,070.47| 55.3| ************************************************************************************************************************************ WILLIAMSON 0.2 MI E OF CR 185 | 6.888 | 2,895,175.70| 0.00| 0.00| 0.0| RM 1431 IH 35 | | | | | | 1378-02-033 | | | | | | STP 2012(251) FULL DEPTH REPAIR, SEAL & THIN OV | | | | | | | | | | | | WORK ORDER- 02-22-12 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 03-09-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 66 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | ANGEL BROTHERS ENTERPRISES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1378-02-033 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 01123226 | TOTALS | 2,895,175.70| 0.00| 0.00| 0.0| ************************************************************************************************************************************ WILLIAMSON 1145 FT. WEST OF CR 200 | 1.542 | 509,202.94| 0.00| 0.00| 0.0| SH 29 FM 1869 | | | | | | 0151-03-039 | | | | | | STP 2013(338) MILL, SEAL & OVERLAY | | | | | | | | | | | | WILLIAMSON FM 1869 | 0.704 | 217,918.73| 0.00| 0.00| 0.0| SH 29 1775 FT. EAST OF EAST END OF LP 332 | | | | | | 0151-04-068 | | | | | | STP 2013(338) MILL, SEAL & OVERLAY | | | | | | | | | | | | WORK ORDER- 04-15-13 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 05-01-13 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 25 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | RAMMING PAVING COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0151-03-039 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 01133029 | TOTALS | 727,121.67| 0.00| 0.00| 0.0| ************************************************************************************************************************************ WILLIAMSON DISCOVERY BLVD | 2.626 | 1,366,638.30| 417,473.14| 418,256.04| 30.6| US 183 AVERY RANCH BLVD | | | | | | 0151-05-095 | | | | | | NH 2012(306) MILL, SEAL & OVERLAY | | | | | | | | | | | | WORK ORDER- 03-12-12 WORK BEGAN- 12-10-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 05-11-12 | | | | | | CONTRACT WORKING DAYS- 49 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 12 PERCENT TIME USED- 24 | | | | | | | | | | | | RAMMING PAVING COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0151-05-095 | | | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | |SUB %: 1.33 | | | | MPB, INC. | |SUB %: 0.37 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 5.73 | | | | TEX OP CONSTRUCTION, LP | |SUB %: 4.76 | | | | | | | | | | CONTRACT 02123031 | TOTALS | 1,366,638.30| 417,473.14| 418,256.04| 30.6| ************************************************************************************************************************************ WILLIAMSON SAM BASS RD. | 2.073 | 621,913.61| 0.00| 627,092.65|100.0| FM 3406 IH 35 | | | | | | 1378-06-012 | | | | | | STP 2011(905) MILL, SEAL & OVERLAY | | | | | | | | | | | | WORK ORDER- 04-18-11 WORK BEGAN- 09-19-11 | |**************************************************| | DATE WORK COMPLETED- 05-06-13 TIME COMPUTED- 06-17-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 30 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 23 PERCENT TIME USED- 76 | |**************************************************| | | | | | | | APAC-TEXAS, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1378-06-012 | | | | | | TEX OP CONSTRUCTION, LP | |SUB %: 2.96 | | | | | | | | | | CONTRACT 03113015 | TOTALS | 621,913.61| 0.00| 627,092.65|100.0| ************************************************************************************************************************************ WILLIAMSON BELL C/L | 7.520 | 6,421,595.35| 0.00| 49,200.00| 0.7| FM 487 BELL C/L IN BARTLETT | | | | | | 1201-03-021 | | | | | | STP 2012(417) PAVMNT RESTORATION AND ADD SHLDRS | | | | | | | | | | | | BELL WILLIAMSON CO LINE W OF FM 2115 | 0.395 | 285,832.17| 0.00| 0.00| 0.0| FM 487 WILLIAMSON CO LINE E OF FM 2115 | | | | | | 1201-05-010 | | | | | | STP 2012(423) PAV RESTORATION AND ADD SHOULDERS | | | | | | | | | | | | WORK ORDER- 05-04-12 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 05-20-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 391 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | JAMES CONSTRUCTION GROUP, L.L.C. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1201-03-021 | | | | | | SOUTHWEST ENVIRONMENT SERVICES LLC | |SUB %: 2.36 | | | | SILVA CONTRACTING COMPANY, INC. | |SUB %: 11.18 | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 0.62 | | | | MURRAY CONSTRUCTION | |SUB %: 0.48 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 1.28 | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | |SUB %: 4.04 | | | | | | | | | | CONTRACT 03123002 | TOTALS | 6,707,427.52| 0.00| 49,200.00| 0.7| ************************************************************************************************************************************ WILLIAMSON BELL COUNTY LINE | 5.590 | 3,350,557.08| 456,848.00| 2,141,584.02| 63.9| SH 95 FM 971 WEST | | | | | | 0320-03-091 | | | | | | STP 2012(307) UPGRADE TO SUPER 2 | | | | | | | | | | | | WORK ORDER- 04-26-12 WORK BEGAN- 06-11-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 06-15-12 | | | | | | CONTRACT WORKING DAYS- 281 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 182 PERCENT TIME USED- 64 | | | | | | | | | | | | JAMES CONSTRUCTION GROUP, L.L.C. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0320-03-091 | | | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | |SUB %: 0.18 | | | | J.D. RAMMING PAVING CO., LTD. | |SUB %: 50.21 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 1.99 | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 1.39 | | | | JCS LOGISTICS, LLC | |SUB %: 3.17 | | | | J.E.D. TRUCKING, INC. | |SUB %: 0.00 | | | | FRANK PRASIFKA & SONS, INC. | |SUB %: 0.41 | | | | EDGAR GALAVAN DBA TRISA TRUCKING | |SUB %: 0.39 | | | | TIM ARMSTRONG TRUCKING, INC. | |SUB %: 0.14 | | | | JUAN MALDONADO DBA KRUNC TRANSPORTATION | |SUB %: 0.29 | | | | CTBX, INC. | |SUB %: 1.35 | | | | TEXAS TRUCKING COMPANY, INC. | |SUB %: 0.00 | | | | PENNTEX MILLING, LLC | |SUB %: 0.25 | | | | PANTHER CREEK TRANSPORTATION, INC. | |SUB %: 0.00 | | | | BLACKTOPPER TECHNOLOGY, INC. | |SUB %: 4.18 | | | | | | | | | | CONTRACT 03123226 | TOTALS | 3,350,557.08| 456,848.00| 2,141,584.02| 63.9| ************************************************************************************************************************************ WILLIAMSON APPROX. 920' S OF 183A | 1.824 | 867,875.03| 0.00| 0.00| 0.0| US 183 RM 2243 | | | | | | 0151-04-067 | | | | | | NH 2013(474) PAVEMENT REPAIR,UNDERSEAL & OVERLAY | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 33 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | RAMMING PAVING COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0151-04-067 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 03133034 | TOTALS | 867,875.03| 0.00| 0.00| 0.0| ************************************************************************************************************************************ WILLIAMSON SS 158 IN GEORGETOWN | 15.615 | 1,487,610.02| 0.00| 0.00| 0.0| FM 971 SH 95 IN GRANGER | | | | | | 2690-01-033 | | | | | | STP 2013(479) SPOT PAVEMENT REPAIR & 1-CST | | | | | | | | | | | | WORK ORDER- 05-14-13 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 38 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | BIG CREEK CONSTRUCTION, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 2690-01-033 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 03133235 | TOTALS | 1,487,610.02| 0.00| 0.00| 0.0| ************************************************************************************************************************************ WILLIAMSON 252 FT NORTH OF US 79 CENTERLINE | 0.568 | 155,600.10| 422.50| 154,470.63| 99.2| SH 130 2748 FT SOUTH OF US 79 CENTERLINE | | | | | | 0440-05-008 | | | | | | NH 2012(481) LANDSCAPING | | | | | | | | | | | | WORK ORDER- 05-15-12 WORK BEGAN- 06-18-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 06-18-12 | | | | | | CONTRACT WORKING DAYS- 45 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 37 PERCENT TIME USED- 82 | | | | | | | | | | | | NALLE LANDSCAPE LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0440-05-008 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 04123233 | TOTALS | 155,600.10| 422.50| 154,470.63| 99.2| ************************************************************************************************************************************ WILLIAMSON US 183 | 7.571 | 1,198,349.00| 0.00| 309,313.17| 25.8| FM 3405 RM 2338 | | | | | | 1755-03-007 | | | | | | STP 2012(554) BASE REPAIR & OVERLAY | | | | | | | | | | | | WORK ORDER- 06-15-12 WORK BEGAN- 11-05-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 08-14-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 24 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 9 PERCENT TIME USED- 37 | |**************************************************| | | | | | | | BIG CREEK CONSTRUCTION, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1755-03-007 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 05123038 | TOTALS | 1,198,349.00| 0.00| 309,313.17| 25.8| ************************************************************************************************************************************ WILLIAMSON ON CR 351 AT DONAHOE CREEK | 0.066 | 596,333.03| 0.00| 659,926.73| 99.9| CR (STR AA02-90-002) | | | | | | 0914-05-172 | | | | | | BR 1102(528) REPLACE BRIDGE & APPROACHES | | | | | | | | | | | | WORK ORDER- 07-12-12 WORK BEGAN- 08-06-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 07-28-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 115 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 85 PERCENT TIME USED- 73 | |**************************************************| | | | | | | | JAMES CONSTRUCTION GROUP, L.L.C. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0914-05-172 | | | | | | BEAIRD DRILLING | |SUB %: 1.82 | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | |SUB %: 4.00 | | | | A & R DEMOLITION | |SUB %: 0.58 | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 1.10 | | | | RAMMING PAVING COMPANY | |SUB %: 1.71 | | | | RICE ENVIRONMENTAL SERVICES | |SUB %: 27.08 | | | | BREDA COMPANY, INC. | |SUB %: 0.55 | | | | GK CONSTRUCTION, LLC | |SUB %: 0.05 | | | | | | | | | | CONTRACT 05123052 | TOTALS | 596,333.03| 0.00| 659,926.73| 99.9| ************************************************************************************************************************************ WILLIAMSON ETC AT PARK PLACE | 0.579 | 472,438.87| 0.00| 456,127.77| 96.5| SH 29 ETC . | | | | | | 0337-01-034 | | | | | | STP 1102(079)HESG INSTALL TRAFFIC SIGNAL | | | | | | | | | | | | WORK ORDER- 08-05-11 WORK BEGAN- 12-12-11 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 08-21-11 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 98 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 87 PERCENT TIME USED- 88 | |**************************************************| | | | | | | | HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0337-01-034 | | | | | | TX DOWN UNDER CONSTRUCTION LLC | |SUB %: 4.41 | | | | APAC-TEXAS, INC. | |SUB %: 6.51 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 4.20 | | | | | | | | | | CONTRACT 06113018 | TOTALS | 472,438.87| 0.00| 456,127.77| 96.5| ************************************************************************************************************************************ WILLIAMSON WEST OF RATTAN CRK | 1.256 | 24,729,960.53| 108,958.10| 10,303,073.76| 41.6| SH 45 MCNEIL ROAD | | | | | | 0683-06-027 | | | | | | C 683-6-27 GR, BASE, STRUC, ACP, SGN & PVMT MK | | | | | | | | | | | | WORK ORDER- 09-27-11 WORK BEGAN- 11-08-11 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-08-11 | | | | | | CONTRACT WORKING DAYS- 495 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 359 PERCENT TIME USED- 72 | | | | | | | | | | | | LIBERTY MUTUAL INSURANCE COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0683-06-027 | | | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION (OLD PRIME) | |SUB %: 3.26 | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | |SUB %: 0.81 | | | | AUSTIN WOOD RECYCLING | |SUB %: 0.04 | | | | BEAIRD DRILLING | |SUB %: 1.05 | | | | CARTEL PLACERS, LLC | |SUB %: 0.00 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 0.36 | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 0.27 | | | | PRIMATE CONSTRUCTION, INC. | |SUB %: 0.12 | | | | SITE-SAFE PRODUCTS OF TEXAS, L.P. | |SUB %: 0.80 | | | | H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. | |SUB %: 0.49 | | | | VALLEY PLACERS, LLC | |SUB %: 0.10 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.54 | | | | TEXAS HIGHWAY WALLS | |SUB %: 3.26 | | | | ZACHRY CONSTRUCTION CORPORATION | |SUB %: 78.32 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.00 | | | | | | | | | | CONTRACT 07113013 | TOTALS | 24,729,960.53| 108,958.10| 10,303,073.76| 41.6| ************************************************************************************************************************************ WILLIAMSON 0.710 MI SOUTH OF LAKEWAY DRIVE | 1.810 | 5,649,298.80| 157,672.71| 2,297,065.30| 40.6| IH 35 0.246 MI NORTH OF LAKEWAY DRIVE | | | | | | 0015-08-116 | | | | | | IM 0353(283) REPLACE EXISTING UNDERPASS STRUCTUR | | | | | | | | | | | | WILLIAMSON AT BI 35M NORTH AND LAKEWAY DR | 0.001 | 98,041.62| 0.00| 37,620.21| 38.3| IH 35 . | | | | | | 0015-08-126 | | | | | | RW 15-8-126 ROW ACQUISITION, UTIL & RELOC | | | | | | | | | | | | WORK ORDER- 10-05-11 WORK BEGAN- 11-08-11 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 10-21-11 | | | | | | CONTRACT WORKING DAYS- 481 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 356 PERCENT TIME USED- 74 | | | | | | | | | | | | LIBERTY MUTUAL INSURANCE COMPANY | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0015-08-116 | | | | | | BEAIRD DRILLING | |SUB %: 0.84 | | | | BMP SPECIALIST, LLC | |SUB %: 0.87 | | | | CERTIFIED PLACERS LLC | |SUB %: 1.06 | | | | EW WELLS GROUP LLC | |SUB %: 0.91 | | | | ENVIRONMENTAL SAFETY SERVICES, INC. | |SUB %: 1.04 | | | | FLASHER EQUIPMENT COMPANY | |SUB %: 1.29 | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 1.64 | | | | J.D. RAMMING PAVING CO., LTD. | |SUB %: 17.37 | | | | PRIMATE CONSTRUCTION, INC. | |SUB %: 0.09 | | | | SITE-SAFE PRODUCTS OF TEXAS, L.P. | |SUB %: 0.18 | | | | SOUTH TEXAS PAINTING COMPANY | |SUB %: 0.13 | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 5.68 | | | | MONTELONGO"S CONCRETE | |SUB %: 1.57 | | | | CHASCO CONSTRUCTORS | |SUB %: 94.71 | | | | APAC-TEXAS, INC. | |SUB %: 22.38 | | | | HAYWARD BAKER, INC. | |SUB %: 0.90 | | | | | | | | | | CONTRACT 07113238 | TOTALS | 5,747,340.42| 157,672.71| 2,334,685.51| 40.6| ************************************************************************************************************************************ WILLIAMSON US 183 | 0.904 | 357,255.50| 1,500.00| 322,358.62| 90.2| RM 1431 183-A | | | | | | 1378-02-037 | | | | | | STP 1102(351) LANDSCAPING, IRRIGATION & PAVERS | | | | | | | | | | | | WORK ORDER- 09-13-11 WORK BEGAN- 03-05-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 12-12-11 | | | | | | CONTRACT WORKING DAYS- 65 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 62 PERCENT TIME USED- 95 | | | | | | | | | | | | LEGENDS LANDSCAPES LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1378-02-037 | | | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 1.04 | | | | | | | | | | CONTRACT 08113010 | TOTALS | 357,255.50| 1,500.00| 322,358.62| 90.2| ************************************************************************************************************************************ WILLIAMSON 1310 FT SOUTH OF LAKEWAY DRIVE | 0.815 | 418,380.00| 0.00| 0.00| 0.0| IH 35 2250 FT NORTH OF LAKEWAY DRIVE | | | | | | 0015-08-137 | | | | | | IM 0353(285) LANDSCAPING AND IRRIGATION | | | | | | | | | | | | WORK ORDER- 09-24-12 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 72 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | TEXAS TREE & LANDSCAPE, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0015-08-137 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 08123043 | TOTALS | 418,380.00| 0.00| 0.00| 0.0| ************************************************************************************************************************************ WILLIAMSON 9.271 MI S OF SH 138 | 5.179 | 18,778,887.62| 993,503.60| 3,904,836.93| 20.7| SH 195 IH 35 | | | | | | 0440-02-010 | | | | | | HP 2013(023) WIDEN GR, STRS & SURF | | | | | | | | | | | | WORK ORDER- 11-16-12 WORK BEGAN- 01-10-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 12-02-12 | | | | | | CONTRACT WORKING DAYS- 368 ADDL DAYS GRANTED- 145 | | | | | | WORKING DAYS CHARGED- 75 PERCENT TIME USED- 14 | | | | | | | | | | | | SEMA CONSTRUCTION, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0440-02-010 | | | | | | G. CARTER CONSTRUCTION COMPANY, INC. | |SUB %: 2.15 | | | | PERFORMANCE EQUIPMENT | |SUB %: 0.46 | | | | AUSTIN WOOD RECYCLING | |SUB %: 0.62 | | | | N-LINE TRAFFIC MAINTENANCE, L.P. | |SUB %: 0.33 | | | | ROYAL VISTA INC. | |SUB %: 5.40 | | | | AARON CONCRETE CONTRACTORS, L.P. | |SUB %: 0.25 | | | | BMP SPECIALIST, LLC | |SUB %: 1.37 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 1.02 | | | | RAMMING PAVING COMPANY | |SUB %: 42.87 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 0.69 | | | | TOM ARNOLD DRILLING CONTRACTOR II, LLC | |SUB %: 0.02 | | | | TEXAS TRUCKING COMPANY, INC. | |SUB %: 2.43 | | | | | | | | | | CONTRACT 09123203 | TOTALS | 18,778,887.62| 993,503.60| 3,904,836.93| 20.7| ************************************************************************************************************************************ WILLIAMSON WEST ROW OF US 183 | 0.452 | 347,970.79| 0.00| 359,116.60| 99.9| RM 2243 CR 273 (LEANDER ROAD) | | | | | | 2103-01-030 | | | | | | DMO 1102(515) TRAFFIC SIGNAL & RR PRE-EMPTION | | | | | | | | | | | | WORK ORDER- 11-16-11 WORK BEGAN- 09-19-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 01-15-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 146 ADDL DAYS GRANTED- 19 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 158 PERCENT TIME USED- 95 | |**************************************************| | | | | | | | THE LEVY COMPANY, L.P. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 2103-01-030 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.64 | | | | ROADWAY SPECIALTIES, INC. | |SUB %: 6.79 | | | | JCD CONSTRUCTION, LLC | |SUB %: 15.44 | | | | WESTERN TOWERS | |SUB %: 15.26 | | | | D. I. J. CONSTRUCTION, INC. | |SUB %: 6.79 | | | | LONE STAR TOWER | |SUB %: 1.43 | | | | | | | | | | CONTRACT 10113018 | TOTALS | 347,970.79| 0.00| 359,116.60| 99.9| ************************************************************************************************************************************ WILLIAMSON FM 3406 | 6.380 | 3,689,560.42| 835.43| 1,004,776.56| 27.2| IH 35 S. SAN GABRIEL RIVER | | | | | | 0015-09-165 | | | | | | IM 0353(284) PAVEMENT REPAIR AND OVERLAY | | | | | | | | | | | | WORK ORDER- 11-16-11 WORK BEGAN- 07-17-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 12-02-11 | | | | | | CONTRACT WORKING DAYS- 73 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 57 PERCENT TIME USED- 78 | | | | | | | | | | | | ANGEL BROTHERS ENTERPRISES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0015-09-165 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 8.21 | | | | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. | |SUB %: 0.11 | | | | SCR CONSTRUCTION CO., INC. | |SUB %: 1.32 | | | | | | | | | | CONTRACT 10113219 | TOTALS | 3,689,560.42| 835.43| 1,004,776.56| 27.2| ************************************************************************************************************************************ DISTRICT CONTRACT AMOUNT 450,202,322.37 DISTRICT ESTIMATES THIS MONTH 12,826,586.49 DISTRICT TOTAL ESTIMATES PAID TO DATE 251,151,915.85