Monthly State Let Maintenance Report For Atlanta District As Of Jul 14, 2017 Page 1 Of 1

Last Update: Monday, July 17, 2017
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCASS
Highway0000000
From701 EAST MAIN STREET ATLANTA, TX 75551
To701 EAST MAIN STREET ATLANTA, TX 75551
CSJ4704-01-645
Proj IDCBC - 470401645
Work TypeRENOVATION OR REPAIR
 
0.001379500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTEGRITY ELECTRICAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-645
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164219
Totals379500.000.000.000.0

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToVARIOUS
CSJ6269-96-001
Proj IDRMC - 626996001
Work TypeINSTALLATION OF PAVEMENT MARKINGS
 
0.001766525.36745146.17100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-23-16
Work Began05-23-16
Work Completed11-09-16
Time Computed05-23-16
Contract Working Days99
Addl Days Granted0
Working Days Charged83
Percent Time Used83
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6269-96-001
STRIPING SYSTEMS, INC. (1.18)
Contract #04164013
Totals766525.360.00745146.17100.0

CountyHARRISON
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN ATL DIST
To.
CSJ6270-45-001
Proj IDRMC - 627045001
Work TypeCALLOUT MILL AND INLAY
 
0.0012093008.006714896.9599.9
Work Order09-28-15
Work Began10-05-15
Work Completed
Time Computed10-05-15
Contract Working Days80
Addl Days Granted0
Working Days Charged47
Percent Time Used58
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-45-001
RK HALL, LLC (52.48)
TEXOP CONSTRUCTION (9.74)
Contract #09144210
Totals2093008.001138170.806714896.9599.9

CountyBOWIE
HighwayUS0059
FromVARIOUS
To.
CSJ6275-68-001
Proj IDRMC - 627568001
Work TypeINSTALLATION OF TRAFFIC SIGNALS
 
0.001631703.50947778.1199.9
Work Order01-15-15
Work Began01-27-15
Work Completed
Time Computed01-25-15
Contract Working Days306
Addl Days Granted306
Working Days Charged593
Percent Time Used96
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6275-68-001
BANNER SIGN & BARRICADE, INC. (TYLER) (3.79)
CARTHAGE DRILLING, INC. (3.15)
R & R TELCO ENTERPRISES, INC. (8.10)
DIRECTIONAL DRILLING (6.07)
Contract #10144008
Totals631703.5053886.70947778.1199.9

CountyBOWIE
HighwayUS0059
FromVARIOUS
To.
CSJ6283-63-001
Proj IDRMC - 628363001
Work TypeCALLOUT PAVEMENT MARKINGS
 
0.001381718.50356162.26100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-11-15
Work Began07-01-15
Work Completed09-28-16
Time Computed07-01-15
Contract Working Days255
Addl Days Granted16
Working Days Charged269
Percent Time Used99
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04154029
Totals381718.500.00356162.26100.0

CountyMARION
HighwayUS0059
FromVARIOUS LOCATIONS
To.
CSJ6283-84-001
Proj IDBPM - 628384001
Work TypeBRIDGE PROTECTIVE MAINTENANCE
 
0.001783833.10942990.0799.9
Work Order04-11-16
Work Began04-26-16
Work Completed
Time Computed04-26-16
Contract Working Days140
Addl Days Granted21
Working Days Charged145
Percent Time Used90
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6283-84-001
PANOLA SIGN & BARRICADE, INC. (1.40)
DUSTIN ALLEN, INC. (4.10)
STRIPING TECHNOLOGY, L.P. (3.88)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.64)
CHEROKEE SERVICES (14.20)
Contract #01164014
Totals783833.101918.50942990.0799.9

CountyCASS
HighwayUS0059
FromDISTRICT WIDE
To.
CSJ6284-08-001
Proj IDRMC - 628408001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0013284725.005763869.8099.9
Work Order08-19-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days366
Addl Days Granted365
Working Days Charged669
Percent Time Used91
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6284-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07154009
Totals3284725.00333762.805763869.8099.9

CountyHARRISON
HighwayUS0059
FromVARIOUS
To.
CSJ6286-74-001
Proj IDRMC - 628674001
Work TypeCALLOUT CONCRETE PAVEMENT REPAIR
 
0.0011622025.002522439.8599.9
Work Order05-30-16
Work Began06-06-16
Work Completed
Time Computed06-06-16
Contract Working Days110
Addl Days Granted90
Working Days Charged135
Percent Time Used67
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01164207
Totals1622025.000.002522439.8599.9

CountyBOWIE
HighwayUS0059
FromVARIOUS
To.
CSJ6299-30-001
Proj IDRMC - 629930001
Work TypeON-CALL PREFABRICATED PAVEMENT MARKINGS
 
0.001475100.00268441.9256.5
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days255
Addl Days Granted0
Working Days Charged233
Percent Time Used91
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6299-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03164010
Totals475100.0028278.40268441.9256.5

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToVARIOUS
CSJ6300-24-001
Proj IDRMC - 630024001
Work TypeCALLOUT PAVEMENT MARKINGS
 
0.001469839.00348857.2574.2
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days255
Addl Days Granted255
Working Days Charged205
Percent Time Used40
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164220
Totals469839.000.00348857.2574.2

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
To.
CSJ6300-47-001
Proj IDRMC - 630047001
Work TypeCALLOUT RAISED PAVEMENT MARKERS
 
0.001293120.16177918.7960.6
Work Order10-03-16
Work Began10-03-16
Work Completed
Time Computed10-03-16
Contract Working Days254
Addl Days Granted254
Working Days Charged184
Percent Time Used36
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164007
Totals293120.162329.34177918.7960.6

CountyCAMP
HighwayFM0993
FromVARIOUS LOCATIONS
To.
CSJ6304-13-001
Proj IDBPM - 630413001
Work TypeBRIDGE PROTECTIVE MAINTENANCE
 
0.001743840.73230203.6230.9
Work Order05-15-17
Work Began05-23-17
Work Completed
Time Computed05-22-17
Contract Working Days150
Addl Days Granted0
Working Days Charged25
Percent Time Used16
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6304-13-001
PANOLA SIGN & BARRICADE, INC. (2.37)
MORRIS COUNTY CONTRACTORS, L.L.C. (5.19)
STRIPE-A-ZONE, INC. (0.46)
Contract #02174016
Totals743840.73174313.62230203.6230.9

CountyBOWIE
HighwayFM1397
From6.0 MI N OF FM 2240
To0.3 MI N OF FM 2240
CSJ6305-92-001
Proj IDRMC - 630592001
Work TypeSEAL COAT
 
123.8423109249.30893547.8328.7
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days60
Addl Days Granted0
Working Days Charged12
Percent Time Used20
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6305-92-001
STRIPING TECHNOLOGY, L.P. (8.36)
BRYDL CONTRACTING, INC. (1.21)
BARRICADES PLUS, LLC (2.18)
Contract #11164213
Totals3109249.300.00893547.8328.7

CountyHARRISON
HighwayUS0059
FromVARIOUS
To.
CSJ6307-91-001
Proj IDRMC - 630791001
Work TypeTREE & STUMP REMOVAL (SOUTH)
 
0.001420575.00108082.0025.6
Work Order03-27-17
Work Began03-27-17
Work Completed
Time Computed03-27-17
Contract Working Days150
Addl Days Granted0
Working Days Charged36
Percent Time Used24
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6307-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174017
Totals420575.0017126.00108082.0025.6

CountyUPSHUR
HighwayUS0259
FromVARIOUS
To.
CSJ6307-92-001
Proj IDRMC - 630792001
Work TypeTREE & STUMP REMOVAL (WEST)
 
0.001521765.00352126.0067.4
Work Order03-01-17
Work Began03-27-16
Work Completed
Time Computed03-20-17
Contract Working Days150
Addl Days Granted0
Working Days Charged37
Percent Time Used24
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6307-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12164017
Totals521765.000.00352126.0067.4

CountyTITUS
HighwayIH0030
FromVARIOUS
To.
CSJ6308-16-001
Proj IDRMC - 630816001
Work TypeTREE TRIMMING - ATLANTA DISTRICTWIDE
 
279.750391870.25393269.25100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-17
Work Began02-01-17
Work Completed04-27-17
Time Computed02-01-17
Contract Working Days35
Addl Days Granted0
Working Days Charged26
Percent Time Used74
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6308-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12164018
Totals391870.250.00393269.25100.0

CountyCASS
HighwayUS0059
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6310-98-001
Proj IDRMC - 631098001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0015646100.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174013
Totals5646100.000.000.000.0

CountyBOWIE
HighwayUS0059
FromVARIOUS LOCATIONS IN THE ATL DISTRICT
To.
CSJ6315-26-001
Proj IDRMC - 631526001
Work TypeINSTALLATION OF TRAFFIC SIGNALS
 
0.001951725.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days306
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6315-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174009
Totals951725.000.000.000.0

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6316-19-001
Proj IDRMC - 631619001
Work TypeGUIDE & CALL-OUT SIGN INSTALLATION
 
0.001437900.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174206
Totals437900.000.000.000.0

page 1