Monthly State Let Maintenance Report For Atlanta District As Of Oct 16, 2017 Page 1 Of 1

Last Update: Monday, October 16, 2017
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCASS
Highway0000000
From701 EAST MAIN STREET ATLANTA, TX 75551
To701 EAST MAIN STREET ATLANTA, TX 75551
CSJ4704-01-645
Proj IDCBC - 470401645
Work TypeRENOVATION OR REPAIR
 
0.001379500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTEGRITY ELECTRICAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-645
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164219
Totals379500.000.000.000.0

CountyHARRISON
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN ATL DIST
To.
CSJ6270-45-001
Proj IDRMC - 627045001
Work TypeCALLOUT MILL AND INLAY
 
0.0012093008.007999552.5099.9
Work Order09-28-15
Work Began10-05-15
Work Completed
Time Computed10-05-15
Contract Working Days80
Addl Days Granted0
Working Days Charged58
Percent Time Used72
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-45-001
RK HALL, LLC (52.48)
TEXOP CONSTRUCTION (9.74)
Contract #09144210
Totals2093008.000.007999552.5099.9

CountyCASS
HighwayUS0059
FromDISTRICT WIDE
To.
CSJ6284-08-001
Proj IDRMC - 628408001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0013284725.006372343.8099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-19-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days366
Addl Days Granted365
Working Days Charged731
Percent Time Used100
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6284-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07154009
Totals3284725.000.006372343.8099.9

CountyHARRISON
HighwayUS0059
FromVARIOUS
To.
CSJ6286-74-001
Proj IDRMC - 628674001
Work TypeCALLOUT CONCRETE PAVEMENT REPAIR
 
0.0011622025.002522439.8599.9
Work Order05-30-16
Work Began06-06-16
Work Completed
Time Computed06-06-16
Contract Working Days110
Addl Days Granted90
Working Days Charged135
Percent Time Used67
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01164207
Totals1622025.000.002522439.8599.9

CountyBOWIE
HighwayUS0059
FromVARIOUS
To.
CSJ6299-30-001
Proj IDRMC - 629930001
Work TypeON-CALL PREFABRICATED PAVEMENT MARKINGS
 
0.001475100.00304260.7864.0
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days255
Addl Days Granted255
Working Days Charged280
Percent Time Used54
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6299-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03164010
Totals475100.0020722.05304260.7864.0

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToVARIOUS
CSJ6300-24-001
Proj IDRMC - 630024001
Work TypeCALLOUT PAVEMENT MARKINGS
 
0.001469839.00451929.0296.1
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days255
Addl Days Granted255
Working Days Charged253
Percent Time Used49
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164220
Totals469839.0029918.05451929.0296.1

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
To.
CSJ6300-47-001
Proj IDRMC - 630047001
Work TypeCALLOUT RAISED PAVEMENT MARKERS
 
0.001293120.16251321.6985.7
Work Order10-03-16
Work Began10-03-16
Work Completed
Time Computed10-03-16
Contract Working Days254
Addl Days Granted254
Working Days Charged230
Percent Time Used45
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164007
Totals293120.160.00251321.6985.7

CountyCAMP
HighwayFM0993
FromVARIOUS LOCATIONS
To.
CSJ6304-13-001
Proj IDBPM - 630413001
Work TypeBRIDGE PROTECTIVE MAINTENANCE
 
0.001743840.73324804.2943.6
Work Order05-15-17
Work Began05-23-17
Work Completed
Time Computed05-22-17
Contract Working Days150
Addl Days Granted0
Working Days Charged52
Percent Time Used34
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6304-13-001
PANOLA SIGN & BARRICADE, INC. (2.37)
MORRIS COUNTY CONTRACTORS, L.L.C. (5.19)
STRIPE-A-ZONE, INC. (0.46)
Contract #02174016
Totals743840.7330412.50324804.2943.6

CountyBOWIE
HighwayFM1397
From6.0 MI N OF FM 2240
To0.3 MI N OF FM 2240
CSJ6305-92-001
Proj IDRMC - 630592001
Work TypeSEAL COAT
 
123.8423109249.303204828.1799.9
Work Order00-00-00
Work Began06-12-17
Work Completed
Time Computed06-12-17
Contract Working Days60
Addl Days Granted0
Working Days Charged46
Percent Time Used76
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6305-92-001
STRIPING TECHNOLOGY, L.P. (8.36)
BRYDL CONTRACTING, INC. (1.21)
BARRICADES PLUS, LLC (2.18)
Contract #11164213
Totals3109249.300.003204828.1799.9

CountyHARRISON
HighwayUS0059
FromVARIOUS
To.
CSJ6307-91-001
Proj IDRMC - 630791001
Work TypeTREE & STUMP REMOVAL (SOUTH)
 
0.001420575.00268234.0063.7
Work Order03-27-17
Work Began03-27-17
Work Completed
Time Computed03-27-17
Contract Working Days150
Addl Days Granted0
Working Days Charged90
Percent Time Used60
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6307-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174017
Totals420575.0062678.00268234.0063.7

CountyUPSHUR
HighwayUS0259
FromVARIOUS
To.
CSJ6307-92-001
Proj IDRMC - 630792001
Work TypeTREE & STUMP REMOVAL (WEST)
 
0.001521765.00389184.0074.5
Work Order03-01-17
Work Began03-27-16
Work Completed
Time Computed03-20-17
Contract Working Days150
Addl Days Granted0
Working Days Charged56
Percent Time Used37
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6307-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12164017
Totals521765.0037058.00389184.0074.5

CountyCASS
HighwayUS0059
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6310-98-001
Proj IDRMC - 631098001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0015646100.00236524.754.1
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged30
Percent Time Used4
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174013
Totals5646100.00236524.75236524.754.1

CountyBOWIE
HighwayUS0059
FromVARIOUS LOCATIONS IN THE ATL DISTRICT
To.
CSJ6315-26-001
Proj IDRMC - 631526001
Work TypeINSTALLATION OF TRAFFIC SIGNALS
 
0.001951725.0094370.509.9
Work Order00-00-00
Work Began07-24-17
Work Completed
Time Computed07-24-17
Contract Working Days306
Addl Days Granted0
Working Days Charged36
Percent Time Used11
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6315-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174009
Totals951725.0063597.0094370.509.9

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6316-19-001
Proj IDRMC - 631619001
Work TypeGUIDE & CALL-OUT SIGN INSTALLATION
 
0.001437900.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174206
Totals437900.000.000.000.0

page 1