Monthly Local Let Maintenance Report For Atlanta District As Of Feb 10, 2017 Page 3 Of 5

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTITUS
HighwayUS0271
FromVARIOUS
To.
CSJ6304-17-001
Proj IDSUP - 630417001
Work TypeJANITORIAL SERVICE - MT. PLEASANT
 
0.0019311.724975.2953.4
Work Order05-01-16
Work Began06-01-16
Work Completed
Time Computed05-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged276
Percent Time Used75
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-17-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #04161932
Totals9311.72552.814975.2953.4

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6304-27-001
Proj IDRMC - 630427001
Work TypeGUIDE & CALL-OUT SIGN INSTALLATION
 
0.001254550.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted0
Working Days Charged39
Percent Time Used15
Contractor(s)
ODUM SERVICES, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6304-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161901
Totals254550.000.000.000.0

CountyCASS
HighwaySH0008
FromVARIOUS
To.
CSJ6304-79-001
Proj IDSUP - 630479001
Work TypeGROUNDS MAINTENANCE - LINDEN
 
0.0017587.603161.5041.6
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged274
Percent Time Used75
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-79-001
SDR & ASSOC. INC. (100.00)
Contract #05161931
Totals7587.600.003161.5041.6

CountyBOWIE
HighwaySH0008
FromVARIOUS
To.
CSJ6304-80-001
Proj IDSUP - 630480001
Work TypeGROUNDS MAINTENANCE
 
0.0019497.283561.4837.5
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged245
Percent Time Used67
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-80-001
SDR & ASSOC. INC. (100.00)
Contract #05161932
Totals9497.280.003561.4837.5

CountyBOWIE
HighwayIH0030
FromVARIOUS
To.
CSJ6307-90-001
Proj IDRMC - 630790001
Work TypeTREE AND STUMP REMOVAL (NORTH)
 
0.001321174.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-30-17
Work Began00-00-00
Work Completed
Time Computed01-30-17
Contract Working Days150
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-90-001
BRYDL CONTRACTING, INC. (49.80)
Contract #12161901
Totals321174.000.000.000.0

CountyBOWIE
HighwayUS0059
FromVARIOUS
To.
CSJ6308-09-001
Proj IDSUP - 630809001
Work TypeLITTER PICKUP & DISPOSAL
 
0.001212200.1485712.9440.3
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS,INC
SUBCONTRACTOR(S) FOR CCSJ: 6308-09-001
VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS,INC (100.00)
Contract #08161932
Totals212200.1421513.2185712.9440.3

CountyCAMP
HighwayUS0271
FromVARIOUS
To.
CSJ6308-10-001
Proj IDSUP - 630810001
Work TypeLITTER PICKUP & DISPOSAL
 
0.001112311.9253864.0147.9
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged183
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6308-10-001
CAMP COUNTY SERVICE INDUSTRIES (100.00)
Contract #08161931
Totals112311.9211285.9753864.0147.9

CountyHARRISON
HighwayUS0059
FromVARIOUS
To.
CSJ6308-11-001
Proj IDSUP - 630811001
Work TypeLITTER PICKUP AND DISPOSAL
 
0.00167068.7028431.5142.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days304
Addl Days Granted0
Working Days Charged93
Percent Time Used30
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6308-11-001
CAMP COUNTY SERVICE INDUSTRIES (100.00)
Contract #08161933
Totals67068.700.0028431.5142.3

CountyBOWIE
HighwayIH0030
FromVARIOUS
To.
CSJ6308-20-001
Proj IDSUP - 630820001
Work TypeJANITORIAL AND GROUNDS
 
0.001404368.9084751.2920.9
Work Order08-26-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161902
Totals404368.9017171.8384751.2920.9

CountyHARRISON
HighwayIH0020
FromVARIOUS
To.
CSJ6308-21-001
Proj IDSUP - 630821001
Work TypeJANITORIAL AND GROUNDS
 
0.001410654.2086068.6220.9
Work Order08-26-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161903
Totals410654.2017438.7486068.6220.9

CountyCASS
HighwayUS0059
FromVARIOUS
To.
CSJ6308-92-001
Proj IDSUP - 630892001
Work TypePICNIC AREA MAINT.-BOWIE, CASS &
 
0.00143250.006700.0015.4
Work Order10-25-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6308-92-001
CAMP COUNTY SERVICE INDUSTRIES (100.00)
Contract #10161931
Totals43250.001900.006700.0015.4

CountyUPSHUR
HighwayUS0271
FromVARIOUS
To.
CSJ6308-93-001
Proj IDSUP - 630893001
Work TypeJANITORIAL SERVICE
 
0.00110111.302852.5428.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-21-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6308-93-001
THE ARC OF HARRISON COUNTY (100.00)
Contract #09161934
Totals10111.300.002852.5428.2

CountyMARION
HighwaySH0049
FromVARIOUS
To.
CSJ6308-94-001
Proj IDSUP - 630894001
Work TypeJANITORIAL MAINTENANCE - JEFFERSON
 
0.0016073.791136.6018.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-21-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6308-94-001
THE ARC OF HARRISON COUNTY (100.00)
Contract #09161935
Totals6073.790.001136.6018.7

CountyCASS
HighwaySH0008
FromVARIOUS
To.
CSJ6308-95-001
Proj IDSUP - 630895001
Work TypeJANITORIAL SERVICE - LINDEN
 
0.0015481.081078.3819.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-21-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6308-95-001
THE ARC OF HARRISON COUNTY (100.00)
Contract #09161933
Totals5481.080.001078.3819.6

CountyHARRISON
HighwaySL0390
FromVARIOUS
To.
CSJ6308-96-001
Proj IDSUP - 630896001
Work TypeJANITORIAL MAINTENANCE
 
0.00116266.433465.0021.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-21-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6308-96-001
THE ARC OF HARRISON COUNTY (100.00)
Contract #09161932
Totals16266.430.003465.0021.3

CountyTITUS
HighwayUS0271
FromVARIOUS
To.
CSJ6308-97-001
Proj IDSUP - 630897001
Work TypeGROUNDS MAINTENANCE - MT. PLEASANT
 
0.0014320.000.000.0
Work Order09-29-16
Work Began00-00-00
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6308-97-001
CAMP COUNTY SERVICE INDUSTRIES (100.00)
Contract #09161936
Totals4320.000.000.000.0

CountyHARRISON
HighwayUS0059
FromVARIOUS
To.
CSJ6308-98-001
Proj IDSUP - 630898001
Work TypePICNIC AREA MAINTENANCE
 
0.00136770.0013580.0036.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-31-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6308-98-001
THE ARC OF HARRISON COUNTY (100.00)
Contract #08161934
Totals36770.000.0013580.0036.9

CountyPANOLA
HighwayBU0059D
FromVARIOUS
To.
CSJ6308-99-001
Proj IDSUP - 630899001
Work TypeCARTHAGE JANITORIAL
 
0.0016807.041491.7821.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-21-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged91
Percent Time Used24
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6308-99-001
THE ARC OF HARRISON COUNTY (100.00)
Contract #09161931
Totals6807.040.001491.7821.9

CountyCASS
HighwayFM0249
FromVARIOUS
To.
CSJ6309-00-001
Proj IDSUP - 630900001
Work TypeGROUNDS MAINTENANCE
 
0.00126640.004440.0016.6
Work Order09-29-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6309-00-001
CAMP COUNTY SERVICE INDUSTRIES (100.00)
Contract #09161937
Totals26640.000.004440.0016.6

CountyPANOLA
HighwayUS0059
FromVARIOUS
To.
CSJ6309-01-001
Proj IDRMC - 630901001
Work TypeFULL-WIDTH MOWING (TRACT 1-PANOLA)
 
0.001174371.040.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days53
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6309-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161901
Totals174371.040.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5