Monthly Local Let Maintenance Report For Atlanta District As Of Apr 11, 2014 Page 2 Of 3

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCASS
Highway FM0249
From VARIOUS
To .
CSJ 6262-28-001
Proj ID SUP - 626228001
Work Type GROUNDS MAINTENANCE
 
0.001 26640.00 2220.00 7770.00 29.1
Work Order 08-01-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6262-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131931
Totals 26640.00 2220.00 7770.00 29.1

CountyHARRISON
Highway LP0390
From VARIOUS
To .
CSJ 6262-29-001
Proj ID SUP - 626229001
Work Type JANITORIAL MAINTENANCE
 
0.001 16266.43 1155.00 6930.00 42.6
Work Order 09-24-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6262-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131930
Totals 16266.43 1155.00 6930.00 42.6

CountyHARRISON
Highway IH0020
From VARIOUS
To .
CSJ 6262-59-001
Proj ID RMC - 626259001
Work Type DEBRIS REMOVAL (S)
 
106.000 35076.00 1896.00 11376.00 32.4
Work Order 10-07-13
Work Began 10-14-13
Work Completed  
Time Computed 10-21-13
Contract Working Days 306
Addl Days Granted 0
Working Days Charged 135
Percent Time Used 44
Contractor(s)
WILLIAM DUNCAN
SUBCONTRACTOR(S) FOR CCSJ: 6262-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09131902
Totals 35076.00 1896.00 11376.00 32.4

CountyBOWIE
Highway IH0030
From VARIOUS
To .
CSJ 6262-71-001
Proj ID RMC - 626271001
Work Type DEBRIS REMOVAL (N)
 
124.000 33226.00 1796.00 9878.00 29.7
Work Order 10-22-13
Work Began 11-01-13
Work Completed  
Time Computed 11-08-13
Contract Working Days 306
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 38
Contractor(s)
WILLIAM DUNCAN
SUBCONTRACTOR(S) FOR CCSJ: 6262-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09131903
Totals 33226.00 1796.00 9878.00 29.7

CountyPANOLA
Highway US0059
From VARIOUS
To .
CSJ 6263-01-001
Proj ID RMC - 626301001
Work Type FULL WIDTH ROW MOWING - TRACT 1 - PANOLA
 
0.001 134932.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LANGFORD CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6263-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131901
Totals 134932.00 0.00 0.00 0.0

CountyMORRIS
Highway FM0161
From VARIOUS
To .
CSJ 6263-02-001
Proj ID RMC - 626302001
Work Type FULL WIDTH MOWING - TRACT 2 MORRIS, ETC
 
0.001 131662.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HX FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131902
Totals 131662.40 0.00 0.00 0.0

CountyUPSHUR
Highway FM0556
From VARIOUS
To .
CSJ 6263-03-001
Proj ID RMC - 626303001
Work Type FULL WIDTH MOWING - TRACT 3 UPSHUR, ETC.
 
0.001 130527.36 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HX FARMS
SUBCONTRACTOR(S) FOR CCSJ: 6263-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131903
Totals 130527.36 0.00 0.00 0.0

CountyMARION
Highway SH0049
From VARIOUS
To .
CSJ 6263-04-001
Proj ID RMC - 626304001
Work Type FULL WIDTH MOWING - TRACT 4 MARION, ETC.
 
0.001 117909.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TERRY ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6263-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131904
Totals 117909.00 0.00 0.00 0.0

CountyCASS
Highway FM0251
From VARIOUS
To .
CSJ 6263-05-001
Proj ID RMC - 626305001
Work Type FULL WIDTH MOWING - TRACT 5 MARION, ETC.
 
0.001 154756.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TERRY ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6263-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131905
Totals 154756.00 0.00 0.00 0.0

CountyHARRISON
Highway US0080
From VARIOUS
To .
CSJ 6263-06-001
Proj ID RMC - 626306001
Work Type FULL WIDTH MOWING - TRACT 6 HARRISON ETC
 
0.001 115005.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 44
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TERRY ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6263-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131906
Totals 115005.00 0.00 0.00 0.0

CountyTITUS
Highway US0271
From VARIOUS
To .
CSJ 6263-07-001
Proj ID RMC - 626307001
Work Type FULL WIDTH MOWING - TRACT 7 TITUS, ETC.
 
0.001 116583.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EASTGATE SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6263-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131907
Totals 116583.30 0.00 0.00 0.0

CountyBOWIE
Highway US0259
From VARIOUS
To .
CSJ 6263-08-001
Proj ID RMC - 626308001
Work Type FULL WIDTH MOWING - TRACT 8 BOWIE, ETC.
 
0.001 97400.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES R. BRADFORD
SUBCONTRACTOR(S) FOR CCSJ: 6263-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131908
Totals 97400.00 0.00 0.00 0.0

CountyBOWIE
Highway IH0030
From VARIOUS
To .
CSJ 6263-09-001
Proj ID RMC - 626309001
Work Type RIGHT OF WAY MOWING - TRACT 9 BOWIE
 
0.001 85184.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 27
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES R. BRADFORD
SUBCONTRACTOR(S) FOR CCSJ: 6263-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131909
Totals 85184.00 0.00 0.00 0.0

CountyBOWIE
Highway IH0030
From VARIOUS
To .
CSJ 6263-10-001
Proj ID RMC - 626310001
Work Type RIGHT OF WAY MOWING - TRACT 10
 
0.001 83156.19 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES R. BRADFORD
SUBCONTRACTOR(S) FOR CCSJ: 6263-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131910
Totals 83156.19 0.00 0.00 0.0

CountyHARRISON
Highway IH0020
From VARIOUS
To .
CSJ 6263-11-001
Proj ID RMC - 626311001
Work Type FULL WIDTH MOWING - TRACT 11 HARRISON
 
0.001 78750.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 24
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES R. BRADFORD
SUBCONTRACTOR(S) FOR CCSJ: 6263-11-001
LANGFORD CONTRACTORS ( 12.13%)
Contract # 11131911
Totals 78750.00 0.00 0.00 0.0

CountyHARRISON
Highway IH0020
From VARIOUS
To .
CSJ 6263-12-001
Proj ID RMC - 626312001
Work Type FULL WIDTH MOWING - TRACT 16 HARRISON
 
0.001 88704.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 27
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HX FARMS
SUBCONTRACTOR(S) FOR CCSJ: 6263-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131912
Totals 88704.00 0.00 0.00 0.0

CountyBOWIE
Highway IH0030
From VARIOUS
To .
CSJ 6263-13-001
Proj ID RMC - 626313001
Work Type FULL WIDTH MOWING - TRACT 18 BOWIE, ETC.
 
0.001 86517.09 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 31
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES R. BRADFORD
SUBCONTRACTOR(S) FOR CCSJ: 6263-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131913
Totals 86517.09 0.00 0.00 0.0

CountyBOWIE
Highway IH0030
From VARIOUS
To .
CSJ 6263-67-001
Proj ID RMC - 626367001
Work Type LANDSCAPE MAINTENANCE IH 30 & US 59
 
0.001 98919.00 8076.00 11002.00 11.1
Work Order 01-15-14
Work Began 02-18-14
Work Completed  
Time Computed 02-05-14
Contract Working Days 358
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 15
Contractor(s)
MORTON ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 6263-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131914
Totals 98919.00 8076.00 11002.00 11.1

CountyPANOLA
Highway BU0059D
From VARIOUS
To .
CSJ 6263-74-001
Proj ID SUP - 626374001
Work Type CARTHAGE JANITORIAL
 
0.001 6807.04 471.00 3075.37 45.1
Work Order 09-26-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6263-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131936
Totals 6807.04 471.00 3075.37 45.1

CountyUPSHUR
Highway US0271
From VARIOUS
To .
CSJ 6263-75-001
Proj ID SUP - 626375001
Work Type JANITORIAL SERVICE
 
0.001 10111.30 700.55 4203.30 41.5
Work Order 09-06-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6263-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131937
Totals 10111.30 700.55 4203.30 41.5