Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBOWIE
Highway IH0030
From VARIOUS
To VARIOUS
CSJ 6018-35-001
Proj ID RMC - 601835001
Work Type REMOVAL OF TREES, ETC.
 
0.001 35850.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-08-98
Work Began 00-00-00
Work Completed  
Time Computed 06-15-98
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SOUTHWEST ENVIROTECH SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6018-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10971906
Totals 35850.00 0.00 0.00 0.0

CountyBOWIE
Highway US0059
From US 82
To SH 93
CSJ 6058-88-001
Proj ID RMC - 605888001
Work Type LANDSCAPE MAINTENANCE
 
0.001 14850.00 1100.00 4400.00 29.6
Work Order 07-21-08
Work Began 07-21-08
Work Completed  
Time Computed 07-28-08
Contract Working Days 358
Addl Days Granted 0
Working Days Charged 95
Percent Time Used 26
Contractor(s)
SCOTT A. RIDDLE
SUBCONTRACTOR(S) FOR CCSJ: 6058-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06081901
Totals 14850.00 1100.00 4400.00 29.6

CountyCASS
Highway SH0008
From VARIOUS
To .
CSJ 6071-33-001
Proj ID SUP - 607133001
Work Type JANTIORIAL SERVICES
 
0.001 6921.00 576.75 1730.25 25.0
Work Order 07-22-08
Work Began 08-01-08
Work Completed  
Time Computed 08-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 25
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6071-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081932
Totals 6921.00 576.75 1730.25 25.0

CountyHARRISON
Highway IH0020
From IH 20
To IH 20
CSJ 6073-45-001
Proj ID RMC - 607345001
Work Type JANITORIAL & GROUNDS MAINT REST AREA
 
0.001 52800.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REED & REED MAINTANANCE
SUBCONTRACTOR(S) FOR CCSJ: 6073-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07011902
Totals 52800.00 0.00 0.00 0.0

CountyBOWIE
Highway IH0030
From VARIOUS
To .
CSJ 6106-78-001
Proj ID RMC - 610678001
Work Type MOWING HIGHWAY ROW TRACT 9
 
0.001 47170.50 0.00 12248.40 25.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-26-04
Work Began 05-27-04
Work Completed 07-14-04
Time Computed 06-02-04
Contract Working Days 27
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 40
Contractor(s)
TEXAS MOWING SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6106-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03041904
Totals 47170.50 0.00 12248.40 25.9

CountyMARION
Highway US0059
From VARIOUS
To .
CSJ 6153-77-001
Proj ID RMC - 615377001
Work Type TREE AND STUMP REMOVAL_NORTH
 
0.001 125911.75 31548.27 87805.25 69.7
Work Order 01-24-08
Work Began 02-13-08
Work Completed  
Time Computed 02-11-08
Contract Working Days 207
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 44
Contractor(s)
R. K. HALL CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6153-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11071901
Totals 125911.75 31548.27 87805.25 69.7

CountyUPSHUR
Highway US0271
From VARIOUS
To .
CSJ 6162-40-001
Proj ID SUP - 616240001
Work Type JANITORIAL MAINTENANCE - GILMER
 
0.001 26400.00 737.00 10670.00 40.4
Work Order 09-27-07
Work Began 10-01-07
Work Completed  
Time Computed 10-01-07
Contract Working Days 730
Addl Days Granted 1
Working Days Charged 397
Percent Time Used 54
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6162-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09071934
Totals 26400.00 737.00 10670.00 40.4

CountyBOWIE
Highway US0059
From VARIOUS
To .
CSJ 6162-41-001
Proj ID RMC - 616241001
Work Type CALLOUT METAL BEAM GUARD FENCE
 
0.001 244835.00 6245.00 32680.75 13.3
Work Order 06-17-08
Work Began 07-05-08
Work Completed  
Time Computed 07-03-08
Contract Working Days 305
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 33
Contractor(s)
JAMES BRADFORD
SUBCONTRACTOR(S) FOR CCSJ: 6162-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05081902
Totals 244835.00 6245.00 32680.75 13.3

CountyMARION
Highway SH0049
From VARIOUS
To .
CSJ 6170-86-001
Proj ID RMC - 617086001
Work Type MOWING RIGHT OF WAY TRACT 4
 
0.001 85300.40 29125.40 71925.40 84.3
Work Order 04-22-08
Work Began 06-02-08
Work Completed 07-02-08
Time Computed 06-03-08
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 60
Contractor(s)
TERRY ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6170-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12071904
Totals 85300.40 29125.40 71925.40 84.3

CountyTITUS
Highway US0271
From VARIOUS
To .
CSJ 6170-90-001
Proj ID RMC - 617090001
Work Type MOWING RIGHT OF WAY TRACT 7
 
0.001 83960.00 16020.00 64151.65 77.4
Work Order 05-12-08
Work Began 06-04-08
Work Completed 06-24-08
Time Computed 06-02-08
Contract Working Days 42
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 85
Contractor(s)
LANGFORD CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6170-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12071908
Totals 83960.00 16020.00 64151.65 77.4

CountyBOWIE
Highway IH0030
From VARIOUS
To .
CSJ 6170-94-001
Proj ID RMC - 617094001
Work Type MOWING RIGHT OF WAY TRACT 10
 
0.001 77978.88 11289.60 64715.71 83.7
Work Order 05-05-08
Work Began 05-05-08
Work Completed 05-21-08
Time Computed 05-12-08
Contract Working Days 36
Addl Days Granted 9
Working Days Charged 12
Percent Time Used 26
Contractor(s)
PERRY WEST
SUBCONTRACTOR(S) FOR CCSJ: 6170-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12071912
Totals 77978.88 11289.60 64715.71 83.7

CountyHARRISON
Highway IH0020
From VARIOUS
To .
CSJ 6170-98-001
Proj ID SUP - 617098001
Work Type JANITORIAL / GROUNDS @ WASKOM TIC
 
0.001 252907.92 0.00 73462.65 32.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-01-08
Work Began 01-01-08
Work Completed  
Time Computed 01-01-08
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 305
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6170-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12071931
Totals 252907.92 0.00 73462.65 32.3

CountyTITUS
Highway US0271
From VARIOUS
To .
CSJ 6171-40-001
Proj ID SUP - 617140001
Work Type GROUNDS MAINTENANCE - MT. PLEASANT
 
0.001 5388.12 0.00 3592.08 66.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-22-07
Work Began 11-01-07
Work Completed  
Time Computed 11-01-07
Contract Working Days 365
Addl Days Granted 1
Working Days Charged 366
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6171-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10071932
Totals 5388.12 0.00 3592.08 66.6

CountyCASS
Highway FM0249
From VARIOUS
To .
CSJ 6172-71-001
Proj ID SUP - 617271001
Work Type JANITORIAL SERVICE - ATLANTA DISTRICT
 
0.001 93345.00 6724.51 60786.80 65.1
Work Order 10-06-07
Work Began 11-01-07
Work Completed  
Time Computed 11-01-07
Contract Working Days 365
Addl Days Granted 31
Working Days Charged 366
Percent Time Used 92
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6172-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10071931
Totals 93345.00 6724.51 60786.80 65.1

CountyPANOLA
Highway BU0059D
From VARIOUS
To .
CSJ 6175-77-001
Proj ID SUP - 617577001
Work Type JANITORIAL SERVICES
 
0.001 8321.28 693.44 6240.96 75.0
Work Order 02-01-08
Work Began 02-01-08
Work Completed  
Time Computed 02-01-08
Contract Working Days 365
Addl Days Granted 1
Working Days Charged 274
Percent Time Used 74
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6175-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01081931
Totals 8321.28 693.44 6240.96 75.0

CountyHARRISON
Highway LP0390
From VARIOUS
To .
CSJ 6176-72-001
Proj ID SUP - 617672001
Work Type JANITORIAL SERVICE - MARSHALL
 
0.001 20751.48 1729.29 12301.34 66.6
Work Order 02-26-08
Work Began 02-29-08
Work Completed  
Time Computed 02-29-08
Contract Working Days 365
Addl Days Granted 1
Working Days Charged 246
Percent Time Used 67
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6176-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02081933
Totals 20751.48 1729.29 12301.34 66.6

CountyMORRIS
Highway US0259
From VARIOUS
To .
CSJ 6176-73-001
Proj ID SUP - 617673001
Work Type DAINGERFIELD GROUNDS - CAMP COUNTY
 
0.001 10440.00 580.00 6670.00 63.8
Work Order 04-01-08
Work Began 04-01-08
Work Completed  
Time Computed 04-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 214
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6176-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02081931
Totals 10440.00 580.00 6670.00 63.8

CountyUPSHUR
Highway US0271
From VARIOUS
To .
CSJ 6176-74-001
Proj ID SUP - 617674001
Work Type GILMER GROUNDS - CAMP COUNTY
 
0.001 6480.00 360.00 2700.00 41.6
Work Order 04-01-08
Work Began 04-01-08
Work Completed  
Time Computed 04-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 214
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6176-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02081932
Totals 6480.00 360.00 2700.00 41.6

CountyHARRISON
Highway LP0390
From VARIOUS
To .
CSJ 6176-75-001
Proj ID SUP - 617675001
Work Type GROUNDS MAINTENANCE - MARSHALL OFFICES
 
0.001 19671.12 1092.84 9835.56 50.0
Work Order 05-01-08
Work Began 05-01-08
Work Completed  
Time Computed 05-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 184
Percent Time Used 50
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6176-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04081931
Totals 19671.12 1092.84 9835.56 50.0

CountyMARION
Highway SH0049
From VARIOUS
To .
CSJ 6176-78-001
Proj ID SUP - 617678001
Work Type JEFFERSON JANITORIAL
 
0.001 14527.44 605.31 4237.17 29.1
Work Order 04-01-08
Work Began 04-01-08
Work Completed  
Time Computed 04-01-08
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 214
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6176-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03081931
Totals 14527.44 605.31 4237.17 29.1