Monthly Local Let Maintenance Report For Atlanta District As Of Jul 11, 2014 Page 1 Of 3

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBOWIE
Highway IH0030
From VARIOUS
To .
CSJ 6236-21-001
Proj ID RMC - 623621001
Work Type ILLUMINATION MAINTENANCE
 
0.001 164755.00 5400.00 248831.00 99.9
Work Order 04-19-12
Work Began 05-02-12
Work Completed  
Time Computed 05-01-12
Contract Working Days 306
Addl Days Granted 306
Working Days Charged 558
Percent Time Used 91
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6236-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03121901
Totals 164755.00 5400.00 248831.00 99.9

CountyBOWIE
Highway US0059
From VARIOUS
To .
CSJ 6240-42-001
Proj ID RMC - 624042001
Work Type CALLOUT MBGF REPAIR
 
0.001 178415.00 8488.50 229097.75 99.9
Work Order 07-12-12
Work Began 07-19-12
Work Completed  
Time Computed 07-19-12
Contract Working Days 306
Addl Days Granted 306
Working Days Charged 596
Percent Time Used 97
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6240-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05121902
Totals 178415.00 8488.50 229097.75 99.9

CountyBOWIE
Highway IH0030
From VARIOUS
To .
CSJ 6240-43-001
Proj ID RMC - 624043001
Work Type DEBRIS REMOVAL (NORTH)
 
124.000 41600.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 306
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BENNIE JOHNSON CO.
SUBCONTRACTOR(S) FOR CCSJ: 6240-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05121901
Totals 41600.00 0.00 0.00 0.0

CountyCASS
Highway US0059
From VARIOUS
To .
CSJ 6245-03-001
Proj ID SUP - 624503001
Work Type PICNIC AREA MAINTENANCE - BOWIE / CASS
 
0.001 50325.02 0.00 36225.85 71.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6245-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08121932
Totals 50325.02 0.00 36225.85 71.9

CountyBOWIE
Highway US0059
From VARIOUS
To .
CSJ 6245-82-001
Proj ID SUP - 624582001
Work Type LITTER PICKUP & DISPOSAL
 
0.001 45630.32 0.00 42255.32 92.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS,INC
SUBCONTRACTOR(S) FOR CCSJ: 6245-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08121936
Totals 45630.32 0.00 42255.32 92.6

CountyHARRISON
Highway US0059
From VARIOUS
To .
CSJ 6245-84-001
Proj ID SUP - 624584001
Work Type LITTER PICKUP AND DISPOSAL
 
0.001 39215.25 0.00 35840.25 91.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6245-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08121934
Totals 39215.25 0.00 35840.25 91.3

CountyPANOLA
Highway BU0059D
From VARIOUS
To .
CSJ 6258-99-001
Proj ID SUP - 625899001
Work Type GROUNDS MAINTENANCE
 
0.001 7248.00 0.00 906.00 12.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-13
Work Began 06-01-13
Work Completed  
Time Computed 06-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05131933
Totals 7248.00 0.00 906.00 12.5

CountyHARRISON
Highway SH0043
From VARIOUS
To .
CSJ 6260-48-001
Proj ID SUP - 626048001
Work Type PICNIC AREA MAINTENANCE
 
0.001 37169.27 3152.11 26827.53 72.1
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6260-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131931
Totals 37169.27 3152.11 26827.53 72.1

CountyCASS
Highway US0059
From VARIOUS
To .
CSJ 6260-49-001
Proj ID SUP - 626049001
Work Type PICNIC AREA MAINTENANCE - BOWIE / CASS / TITUS
 
0.001 56435.02 5893.35 36401.40 64.5
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6260-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131935
Totals 56435.02 5893.35 36401.40 64.5

CountyHARRISON
Highway US0059
From VARIOUS
To .
CSJ 6261-13-001
Proj ID SUP - 626113001
Work Type LITTER PICKUP AND DISPOSAL
 
0.001 61209.52 0.00 28917.26 47.2
Work Order 08-23-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6261-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131934
Totals 61209.52 0.00 28917.26 47.2

CountyCAMP
Highway US0271
From VARIOUS
To .
CSJ 6261-14-001
Proj ID SUP - 626114001
Work Type LITTER PICKUP AND DISPOSAL
 
0.001 100841.64 22781.11 72644.75 72.0
Work Order 08-06-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6261-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131932
Totals 100841.64 22781.11 72644.75 72.0

CountyBOWIE
Highway US0059
From VARIOUS
To .
CSJ 6261-15-001
Proj ID SUP - 626115001
Work Type LITTER PICKUP & DISPOSAL
 
0.001 132184.73 5287.68 82822.12 62.6
Work Order 08-12-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS,INC
SUBCONTRACTOR(S) FOR CCSJ: 6261-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131933
Totals 132184.73 5287.68 82822.12 62.6

CountyCASS
Highway FM0249
From VARIOUS
To .
CSJ 6262-28-001
Proj ID SUP - 626228001
Work Type GROUNDS MAINTENANCE
 
0.001 26640.00 1110.00 17760.00 66.6
Work Order 08-01-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 74
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6262-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131931
Totals 26640.00 1110.00 17760.00 66.6

CountyHARRISON
Highway LP0390
From VARIOUS
To .
CSJ 6262-29-001
Proj ID SUP - 626229001
Work Type JANITORIAL MAINTENANCE
 
0.001 16266.43 1155.00 10395.00 63.9
Work Order 09-24-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 74
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6262-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131930
Totals 16266.43 1155.00 10395.00 63.9

CountyHARRISON
Highway IH0020
From VARIOUS
To .
CSJ 6262-59-001
Proj ID RMC - 626259001
Work Type DEBRIS REMOVAL (S)
 
106.000 35076.00 3792.00 21804.00 62.1
Work Order 10-07-13
Work Began 10-14-13
Work Completed  
Time Computed 10-21-13
Contract Working Days 306
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 69
Contractor(s)
WILLIAM DUNCAN
SUBCONTRACTOR(S) FOR CCSJ: 6262-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09131902
Totals 35076.00 3792.00 21804.00 62.1

CountyBOWIE
Highway IH0030
From VARIOUS
To .
CSJ 6262-71-001
Proj ID RMC - 626271001
Work Type DEBRIS REMOVAL (N)
 
124.000 33226.00 3592.00 18858.00 56.7
Work Order 10-22-13
Work Began 11-01-13
Work Completed  
Time Computed 11-08-13
Contract Working Days 306
Addl Days Granted 0
Working Days Charged 195
Percent Time Used 63
Contractor(s)
WILLIAM DUNCAN
SUBCONTRACTOR(S) FOR CCSJ: 6262-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09131903
Totals 33226.00 3592.00 18858.00 56.7

CountyPANOLA
Highway US0059
From VARIOUS
To .
CSJ 6263-01-001
Proj ID RMC - 626301001
Work Type FULL WIDTH ROW MOWING - TRACT 1 - PANOLA
 
0.001 134932.00 15456.35 39014.15 28.9
Work Order 04-23-14
Work Began 05-17-14
Work Completed  
Time Computed 05-19-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 28
Contractor(s)
LANGFORD CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6263-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131901
Totals 134932.00 15456.35 39014.15 28.9

CountyMORRIS
Highway FM0161
From VARIOUS
To .
CSJ 6263-02-001
Proj ID RMC - 626302001
Work Type FULL WIDTH MOWING - TRACT 2 MORRIS, ETC
 
0.001 131662.40 28733.70 28733.70 21.8
Work Order 06-03-14
Work Began 06-20-14
Work Completed  
Time Computed 06-16-14
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 19
Contractor(s)
HX FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131902
Totals 131662.40 28733.70 28733.70 21.8

CountyUPSHUR
Highway FM0556
From VARIOUS
To .
CSJ 6263-03-001
Proj ID RMC - 626303001
Work Type FULL WIDTH MOWING - TRACT 3 UPSHUR, ETC.
 
0.001 130527.36 29033.28 64700.64 49.5
Work Order 04-28-14
Work Began 05-12-14
Work Completed  
Time Computed 05-19-14
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 25
Contractor(s)
HX FARMS
SUBCONTRACTOR(S) FOR CCSJ: 6263-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131903
Totals 130527.36 29033.28 64700.64 49.5

CountyMARION
Highway SH0049
From VARIOUS
To .
CSJ 6263-04-001
Proj ID RMC - 626304001
Work Type FULL WIDTH MOWING - TRACT 4 MARION, ETC.
 
0.001 117909.00 47142.00 47142.00 39.9
Work Order 05-05-14
Work Began 06-09-14
Work Completed  
Time Computed 05-27-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 44
Contractor(s)
TERRY ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6263-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131904
Totals 117909.00 47142.00 47142.00 39.9