MIS.CIS.19 MONTHLY STATE LET CONSTRUCTION REPORT DISTRICT 19 AS OF DEC 11, 2008 PAGE 54 ************************************************************************************************************************************ * | | CONTRACT | AMOUNT THIS | TOTAL ESTIMATE | % * * CONTRACT IDENTIFICATION AND INFORMATION | LENGTH | AMOUNT | ESTIMATE | TO DATE | COMP* ************************************************************************************************************************************ BOWIE US 67 | 61.082 | 5,963,878.59| 0.00| 4,105,946.21| 71.7| FM 991 ETC 1.8 MI S OF US 67 | | | | | | 0010-19-008 | | | | | | SFT 10-19-8 SUBGRADE WIDENING & SURFACING | | | | | | | | | | | | WORK ORDER- 02-07-06 WORK BEGAN- 06-13-07 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 02-07-07 | | | | | | CONTRACT WORKING DAYS- 480 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 266 PERCENT TIME USED- 55 | | | | | | | | | | | | J-W PAYNE CONSTRUCTION COMPANY, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0010-19-008 | | | | | | TEXAS HIGHWAY MARKINGS, LLC | |SUB %: 2.41 | | | | | | | | | | CONTRACT 01063220 | TOTALS | 5,963,878.59| 0.00| 4,105,946.21| 71.7| ************************************************************************************************************************************ BOWIE AT US 67 INTERSECTION | 0.146 | 954,803.33| 197,873.03| 949,420.98| 99.4| SH 8 . | | | | | | 0062-01-032 | | | | | | STP 2006(415) GR, STR, BS, & SURF | | | | | | | | | | | | WORK ORDER- 03-18-08 WORK BEGAN- 05-06-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-03-08 | | | | | | CONTRACT WORKING DAYS- 151 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 111 PERCENT TIME USED- 73 | | | | | | | | | | | | EAST TEXAS BRIDGE, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0062-01-032 | | | | | | D. B. INDUSTRIES, INC. | |SUB %: 0.13 | | | | R. K. HALL CONSTRUCTION, LTD. | |SUB %: 45.57 | | | | COWBELL TRAFFIC SERVICES, INC. | |SUB %: 1.15 | | | | ODUM SERVICES, L.P. | |SUB %: 1.39 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 2.93 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 5.23 | | | | TEX OP CONSTRUCTION, LP | |SUB %: 0.39 | | | | | | | | | | CONTRACT 01083235 | TOTALS | 954,803.33| 197,873.03| 949,420.98| 99.4| ************************************************************************************************************************************ BOWIE 0.1 MI N OF FM 989 | 1.299 | 10,066,833.47| 130,523.62| 3,047,827.82| 30.2| FM 559 0.2 MI N OF FM 2240 | | | | | | 1020-01-038 | | | | | | STP 2008(219) GR,STR,CONC PAV,C&G,TRF SIG,PAV MAR | | | | | | | | | | | | BOWIE 0.1 MI N OF FM 989 | 1.299 | 1,449,160.60| 0.00| 0.00| 0.0| FM 559 0.2 MI N OF FM 2240 | | | | | | 1020-01-046 | | | | | | STP 2008(220)SB SAFETY TREAT FIXED OBJECTS, ETC. | | | | | | | | | | | | WORK ORDER- 03-18-08 WORK BEGAN- 04-02-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-03-08 | | | | | | CONTRACT WORKING DAYS- 618 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 56 PERCENT TIME USED- 9 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1020-01-038 | | | | | | HIGHWAY TECHNOLOGIES | |SUB %: 0.28 | | | | EAST TEXAS SIGN & SUPPLY, INC. | |SUB %: 0.32 | | | | D. B. INDUSTRIES, INC. | |SUB %: 0.27 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.26 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 7.89 | | | | R.K. HALL CONSTRUCTION,(APAC -SULPHER SPRINGS) | |SUB %: 12.89 | | | | | | | | | | CONTRACT 02083011 | TOTALS | 11,515,994.07| 130,523.62| 3,047,827.82| 26.4| ************************************************************************************************************************************ BOWIE ANDERSON CREEK | 24.058 | 989,668.00| 188,129.60| 638,813.58| 64.5| US 67 ELLIOT CREEK | | | | | | 0010-12-064 | | | | | | STP 2008(655)HES SAFETY TREAT FIXED OBJECTS,ETC. | | | | | | | | | | | | WORK ORDER- 07-14-08 WORK BEGAN- 08-04-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 07-30-08 | | | | | | CONTRACT WORKING DAYS- 166 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 59 PERCENT TIME USED- 35 | | | | | | | | | | | | A R BROTHERS CONSTRUCTION SERVICES, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0010-12-064 | | | | | | PANOLA SIGN & BARRICADE, INC. | |SUB %: 1.22 | | | | STATEWIDE GUARDRAIL SERVICE | |SUB %: 12.50 | | | | | | | | | | CONTRACT 06083007 | TOTALS | 989,668.00| 188,129.60| 638,813.58| 64.5| ************************************************************************************************************************************ BOWIE AT US 59/71 (STATELINE) INTERCHANGE | 9.080 | 153,539,064.68| 2,363,865.23| 68,300,689.92| 44.4| IH 30 ETC . | | | | | | 0610-07-085 | | | | | | IMD 0303(120) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 10-03-06 WORK BEGAN- 10-17-06 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 10-19-06 | | | | | | CONTRACT WORKING DAYS- 717 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 353 PERCENT TIME USED- 49 | | | | | | | | | | | | AUSTIN BRIDGE & ROAD, LP | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0610-07-085 | | | | | | TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. | |SUB %: 1.41 | | | | RENAISSANCE CONTRACTORS PARTNERSHIP | |SUB %: 3.32 | | | | ADVANCE CONSTRUCTION SERVICES, INC. | |SUB %: 8.84 | | | | JACKSON LOGGING | |SUB %: 0.03 | | | | W. W. FOUNDATION DRILLING, LTD. | |SUB %: 3.32 | | | | CAPROCK SPECIALITY CONTRACTORS | |SUB %: 0.28 | | | | DUSTROL, INC. (ROANOKE) | |SUB %: 0.01 | | | | ODUM SERVICES, L.P. | |SUB %: 0.63 | | | | GIBSON & ASSOCIATES, INC. | |SUB %: 0.24 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 0.90 | | | | J & V COMMUNICATION SERVICES, INC. | |SUB %: 5.32 | | | | CRAIG OLDEN, INC. | |SUB %: 0.15 | | | | RAYMOND PAINTING, INC. | |SUB %: 0.13 | | | | R.K. HALL CONSTRUCTION,(APAC -SULPHER SPRINGS) | |SUB %: 19.56 | | | | INDUS CONSTRUCTION, L.P. | |SUB %: 0.74 | | | | QUALITY TRUCKING, LLC | |SUB %: 0.00 | | | | RICK HARGROVE TRUCKING | |SUB %: 0.16 | | | | CARTHAGE DRILLING, INC. | |SUB %: 0.54 | | | | LIL DAN TRUCKING | |SUB %: 0.16 | | | | INDUS CONSTRUCTION, L.P. | |SUB %: 0.19 | | | | GREG'S TRUCKING | |SUB %: 0.14 | | | | SHABUCK CONSTRUCTION | |SUB %: 0.03 | | | | 3-BAR-S CONSTRUCTION | |SUB %: 0.05 | | | | HBL CONTRACTING, INC. | |SUB %: 0.05 | | | | CODE J TRANSPORT, INC. | |SUB %: 0.03 | | | | ROLL & ROCK | |SUB %: 0.05 | | | | E. WALKER CONSTRUCTION CO., INC. | |SUB %: 0.13 | | | | R.K. HALL CONSTRUCTION,(APAC -SULPHER SPRINGS) | |SUB %: 0.15 | | | | JODEEO TRUCKING | |SUB %: 0.00 | | | | ADAMS EXCAVATION | |SUB %: 0.00 | | | | RICK HARGROVE TRUCKING | |SUB %: 0.05 | | | | TEC, INC. | |SUB %: 0.04 | | | | WRIGHT BROTHERS EXCAVATING CO. | |SUB %: 0.03 | | | | MIKE LEMLEY CONSTRUCTION | |SUB %: 0.01 | | | | DAVID J. PICKETT | |SUB %: 0.00 | | | | THOMAS HALL TRUCKING | |SUB %: 0.01 | | | | THOMPSON HAULING | |SUB %: 0.00 | | | | BELLEW TRUCKING | |SUB %: 0.00 | | | | CAIN FENCE | |SUB %: 0.02 | | | | EXTREME TRUCKING LLC | |SUB %: 0.06 | | | | RTI RELIABLE TRANSPORT, INC. | |SUB %: 0.00 | | | | JODEEO TRUCKING | |SUB %: 0.02 | | | | CODE J TRANSPORT, INC. | |SUB %: 0.02 | | | | | | | | | | CONTRACT 07063001 | TOTALS | 153,539,064.68| 2,363,865.23| 68,300,689.92| 44.4| ************************************************************************************************************************************ BOWIE ETC AT SH 98/FM 3378 IN NEW BOSTON | 1.200 | 769,577.50| 742.72| 795,717.19| 99.9| US 82 ETC . | | | | | | 0046-04-056 | | | | | | NH 2008(002) INSTALL NEW TRAFFIC SIGNALS | | | | | | | | | | | | WORK ORDER- 10-10-07 WORK BEGAN- 01-30-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 01-30-08 | | | | | | CONTRACT WORKING DAYS- 187 ADDL DAYS GRANTED- 2 | | | | | | WORKING DAYS CHARGED- 181 PERCENT TIME USED- 95 | | | | | | | | | | | | TEXAS TRAFFIC CONTROL SYSTEMS, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0046-04-056 | | | | | | C/T UNDERGROUND, LLC | |SUB %: 2.86 | | | | CARTHAGE DRILLING, INC. | |SUB %: 0.40 | | | | COWBELL TRAFFIC SERVICES, INC. | |SUB %: 0.25 | | | | LUCKETT CRANE SERVICE | |SUB %: 0.08 | | | | | | | | | | CONTRACT 09073213 | TOTALS | 769,577.50| 742.72| 795,717.19| 99.9| ************************************************************************************************************************************ BOWIE ETC SS 86 | 112.174 | 5,891,203.67| 0.00| 0.00| 0.0| US 82 ETC FM 1398 W | | | | | | 0046-05-045 | | | | | | STP 2009(127) SEAL COAT | | | | | | | | | | | | WORK ORDER- 12-05-08 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 12-21-08 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 95 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | CLARK CONSTRUCTION OF TEXAS, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0046-05-045 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 11083016 | TOTALS | 5,891,203.67| 0.00| 0.00| 0.0| ************************************************************************************************************************************ BOWIE AT US 259 UNDERPASS | 0.214 | 1,772,382.20| 0.00| 0.00| 0.0| US 82 . | | | | | | 0046-03-034 | | | | | | BR 2008(804) REHABILITATE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 208 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | HODGES AND SON CONSTRUCTION COMPANY, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0046-03-034 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 11083209 | TOTALS | 1,772,382.20| 0.00| 0.00| 0.0| ************************************************************************************************************************************ BOWIE AT SH 8 UNDERPASS | 0.001 | 2,784,908.34| 253,254.99| 553,547.18| 19.8| US 82 . | | | | | | 0046-05-036 | | | | | | BR 2007(574) REPLACE BRIDGE & APPROACHES | | | | | | | | | | | | WORK ORDER- 09-25-08 WORK BEGAN- 10-13-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 10-11-08 | | | | | | CONTRACT WORKING DAYS- 161 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 25 PERCENT TIME USED- 15 | | | | | | | | | | | | J-W PAYNE CONSTRUCTION COMPANY, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0046-05-036 | | | | | | S & S BRIDGE PAINTING | |SUB %: 0.21 | | | | PRIMATE CONSTRUCTION, INC. | |SUB %: 0.31 | | | | BANNER SIGN & BARRICADE, INC. (HOOKS) | |SUB %: 0.35 | | | | R. K. HALL CONSTRUCTION, LTD. | |SUB %: 10.32 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 2.17 | | | | NE-TEX CONSTRUCTION, LTD. | |SUB %: 20.86 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.79 | | | | ODUM SERVICES, L.P. | |SUB %: 4.37 | | | | LAWNS ETC., L.L.C. | |SUB %: 3.63 | | | | M & D FOUNDATION DRILLING INDUSTRIES, INC. | |SUB %: 2.37 | | | | STOMPER DEMOLITION | |SUB %: 1.89 | | | | | | | | | | CONTRACT 12073016 | TOTALS | 2,784,908.34| 253,254.99| 553,547.18| 19.8| ************************************************************************************************************************************ CAMP AT KCS RAILWAY OVERPASS | 0.750 | 3,366,536.67| 205,470.34| 1,464,547.18| 43.5| SH 11 . | | | | | | 0083-08-043 | | | | | | BR 2006(788) WIDEN BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 04-11-07 WORK BEGAN- 05-07-07 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-27-07 | | | | | | CONTRACT WORKING DAYS- 275 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 183 PERCENT TIME USED- 66 | | | | | | | | | | | | EAST TEXAS BRIDGE, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0083-08-043 | | | | | | D. B. INDUSTRIES, INC. | |SUB %: 0.38 | | | | EAST TEXAS SIGN & SUPPLY, INC. | |SUB %: 0.12 | | | | JAVELINA CONSTRUCTION SOUTH, INC. | |SUB %: 0.17 | | | | WEBBER-BALKE FOUNDATION COMPANY, INC. | |SUB %: 2.66 | | | | CARTHAGE DRILLING, INC. | |SUB %: 2.41 | | | | R.K. HALL CONSTRUCTION,(APAC -SULPHER SPRINGS) | |SUB %: 14.98 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 0.65 | | | | STATEWIDE GUARDRAIL SERVICE | |SUB %: 1.50 | | | | L.S. EQUIPMENT CO., INC. | |SUB %: 0.66 | | | | PANOLA LIGHT & SIGN | |SUB %: 0.50 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.16 | | | | | | | | | | CONTRACT 02073009 | TOTALS | 3,366,536.67| 205,470.34| 1,464,547.18| 43.5| ************************************************************************************************************************************ CAMP ETC UPSHUR COUNTY LINE | 48.500 | 2,269,669.40| 8,608.91| 2,227,378.76| 98.2| US 271 ETC FM 3384 (N) | | | | | | 0248-03-021 | | | | | | STP 2007(238)SB SAFETY TREAT FIXED OBJECTS, ETC. | | | | | | | | | | | | WORK ORDER- 04-09-07 WORK BEGAN- 04-18-07 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-25-07 | | | | | | CONTRACT WORKING DAYS- 300 ADDL DAYS GRANTED- 21 | | | | | | WORKING DAYS CHARGED- 308 PERCENT TIME USED- 95 | | | | | | | | | | | | EAST TEXAS BRIDGE, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0248-03-021 | | | | | | PANOLA LIGHT & SIGN | |SUB %: 1.65 | | | | D. B. INDUSTRIES, INC. | |SUB %: 2.20 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.72 | | | | STATEWIDE GUARDRAIL SERVICE | |SUB %: 5.31 | | | | | | | | | | CONTRACT 02073021 | TOTALS | 2,269,669.40| 8,608.91| 2,227,378.76| 98.2| ************************************************************************************************************************************ CAMP AT DARBY CREEK TRIBUTARY | 0.405 | 1,363,513.15| 19,739.85| 531,866.55| 39.0| FM 3384 . | | | | | | 0248-08-007 | | | | | | BR 2008(370) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 04-01-08 WORK BEGAN- 05-07-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-17-08 | | | | | | CONTRACT WORKING DAYS- 448 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 133 PERCENT TIME USED- 29 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0248-08-007 | | | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.35 | | | | D. B. INDUSTRIES, INC. | |SUB %: 5.35 | | | | PANOLA LIGHT & SIGN | |SUB %: 1.11 | | | | EAST TEXAS SIGN & SUPPLY, INC. | |SUB %: 0.78 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 0.64 | | | | JONA CONTRACTING, INC. | |SUB %: 7.26 | | | | | | | | | | CONTRACT 02083209 | TOTALS | 1,363,513.15| 19,739.85| 531,866.55| 39.0| ************************************************************************************************************************************ CAMP LP 179 IN PITTSBURG | 4.235 | 14,554,144.65| 566,809.73| 11,276,202.05| 80.7| US 271 TITUS COUNTY LINE (BIG CYPRESS CREE | | | | | | 0248-02-053 | | | | | | SFT 248-2-53 GR,STR,BASE,SURF,PAV MK & SIGN | | | | | | | | | | | | WORK ORDER- 06-08-06 WORK BEGAN- 07-10-06 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 06-24-06 | | | | | | CONTRACT WORKING DAYS- 387 ADDL DAYS GRANTED- 54 | | | | | | WORKING DAYS CHARGED- 363 PERCENT TIME USED- 82 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0248-02-053 | | | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 2.01 | | | | PANOLA LIGHT & SIGN | |SUB %: 0.66 | | | | TEXAS SHAFTS, INC. | |SUB %: 0.69 | | | | ODUM SERVICES, L.P. | |SUB %: 1.23 | | | | D. B. INDUSTRIES, INC. | |SUB %: 0.29 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.70 | | | | MIDWEST ASPHALT CORPORATION (GAINESVILLE) | |SUB %: 1.32 | | | | | | | | | | CONTRACT 05063004 | TOTALS | 14,554,144.65| 566,809.73| 11,276,202.05| 80.7| ************************************************************************************************************************************ CAMP ETC AT INTERSECTION OF FM 1399 | 2.559 | 2,919,371.37| 20,167.28| 3,527,564.05| 99.9| SH 11 ETC . | | | | | | 0083-07-035 | | | | | | SFT 83-7-35 INSTALL LEFT TURN LANE | | | | | | | | | | | | WORK ORDER- 08-08-06 WORK BEGAN- 08-23-06 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 08-24-06 | | | | | | CONTRACT WORKING DAYS- 272 ADDL DAYS GRANTED- 10 | | | | | | WORKING DAYS CHARGED- 254 PERCENT TIME USED- 90 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0083-07-035 | | | | | | PANOLA LIGHT & SIGN | |SUB %: 0.82 | | | | ODUM SERVICES, L.P. | |SUB %: 2.00 | | | | DUSTROL, INC. (ROANOKE) | |SUB %: 0.27 | | | | D. B. INDUSTRIES, INC. | |SUB %: 0.39 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.15 | | | | EAST TEXAS SIGN & SUPPLY, INC. | |SUB %: 0.19 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 4.98 | | | | | | | | | | CONTRACT 07063050 | TOTALS | 2,919,371.37| 20,167.28| 3,527,564.05| 99.9| ************************************************************************************************************************************ CAMP AT PRAIRIE CK & PRAIRIE CK RELIEF | 0.483 | 1,592,264.86| 13,325.00| 1,509,402.34| 94.7| FM 557 . | | | | | | 1019-02-016 | | | | | | BR 2007(684) REPLACE BRIDGES & APPRS | | | | | | | | | | | | WORK ORDER- 08-30-07 WORK BEGAN- 09-13-07 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 09-15-07 | | | | | | CONTRACT WORKING DAYS- 170 ADDL DAYS GRANTED- 2 | | | | | | WORKING DAYS CHARGED- 121 PERCENT TIME USED- 70 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1019-02-016 | | | | | | D. B. INDUSTRIES, INC. | |SUB %: 0.75 | | | | EAST TEXAS SIGN & SUPPLY, INC. | |SUB %: 0.41 | | | | M & D FOUNDATION DRILLING INDUSTRIES, INC. | |SUB %: 2.56 | | | | ODUM SERVICES, L.P. | |SUB %: 1.44 | | | | PANOLA LIGHT & SIGN | |SUB %: 0.50 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.74 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 0.95 | | | | | | | | | | CONTRACT 07073023 | TOTALS | 1,592,264.86| 13,325.00| 1,509,402.34| 94.7| ************************************************************************************************************************************ CAMP ETC FM 556 | 134.191 | 7,899,083.92| 101,770.62| 7,553,367.35| 99.6| FM 1519 ETC FM 3042 | | | | | | 0633-05-013 | | | | | | STP 2005(804)SFT SAFETY TRT STR & WIDEN LANES | | | | | | | | | | | | WORK ORDER- 10-14-05 WORK BEGAN- 10-24-05 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 10-30-05 | | | | | | CONTRACT WORKING DAYS- 506 ADDL DAYS GRANTED- 104 | | | | | | WORKING DAYS CHARGED- 434 PERCENT TIME USED- 71 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0633-05-013 | | | | | | STATEWIDE GUARDRAIL SERVICE | |SUB %: 1.26 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 2.11 | | | | D. B. INDUSTRIES, INC. | |SUB %: 2.13 | | | | EAST TEXAS SIGN & SUPPLY, INC. | |SUB %: 0.38 | | | | | | | | | | CONTRACT 08053048 | TOTALS | 7,899,083.92| 101,770.62| 7,553,367.35| 99.6| ************************************************************************************************************************************ CASS ETC MARION COUNTY LINE | 62.756 | 3,983,115.90| 49,901.00| 3,588,401.94| 90.0| SH 49 ETC SH 155 | | | | | | 0222-04-051 | | | | | | STP 2007(171)SB SAFETY TREAT FIXED OBJECTS, ETC. | | | | | | | | | | | | WORK ORDER- 02-16-07 WORK BEGAN- 03-05-07 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 03-04-07 | | | | | | CONTRACT WORKING DAYS- 465 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 370 PERCENT TIME USED- 79 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0222-04-051 | | | | | | PANOLA LIGHT & SIGN | |SUB %: 0.79 | | | | D. B. INDUSTRIES, INC. | |SUB %: 4.69 | | | | EAST TEXAS SIGN & SUPPLY, INC. | |SUB %: 4.09 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.58 | | | | ODUM SERVICES, L.P. | |SUB %: 7.71 | | | | | | | | | | CONTRACT 01073228 | TOTALS | 3,983,115.90| 49,901.00| 3,588,401.94| 90.0| ************************************************************************************************************************************ CASS ETC SH 77 | 76.546 | 7,223,832.87| 39,378.99| 4,486,602.17| 65.3| FM 1399 ETC FM 251 | | | | | | 0546-08-010 | | | | | | SFT 546-8-10 SUBGRADE WIDENING & SURFACING | | | | | | | | | | | | WORK ORDER- 04-18-06 WORK BEGAN- 05-18-06 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 05-04-06 | | | | | | CONTRACT WORKING DAYS- 410 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 231 PERCENT TIME USED- 56 | | | | | | | | | | | | H. V. CAVER, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0546-08-010 | | | | | | TEXAS HIGHWAY MARKINGS, LLC | |SUB %: 2.88 | | | | BAHENA CONSTRUCTION CO.,INC. | |SUB %: 3.13 | | | | D. B. INDUSTRIES, INC. | |SUB %: 1.51 | | | | PANOLA LIGHT & SIGN | |SUB %: 1.43 | | | | TEXAS ALTERNATIVE GRASSER, INC. | |SUB %: 0.39 | | | | | | | | | | CONTRACT 03063238 | TOTALS | 7,223,832.87| 39,378.99| 4,486,602.17| 65.3| ************************************************************************************************************************************ CASS 4.1 MI NW OF FM 251 | 0.511 | 1,124,923.75| 5,212.79| 1,387,067.17| 99.9| FM 3129 5.3 MI NW OF FM 251 | | | | | | 0945-05-016 | | | | | | STP 2008(557) CRCP, ACP BASE & SURF, PAV MRKS | | | | | | | | | | | | WORK ORDER- 04-14-08 WORK BEGAN- 04-28-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-30-08 | | | | | | CONTRACT WORKING DAYS- 87 ADDL DAYS GRANTED- 10 | | | | | | WORKING DAYS CHARGED- 118 PERCENT TIME USED- 121 | | | | | | | | | | | | EAST TEXAS BRIDGE, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0945-05-016 | | | | | | D. B. INDUSTRIES, INC. | |SUB %: 0.65 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.28 | | | | R. K. HALL CONSTRUCTION, LTD. | |SUB %: 25.77 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 5.28 | | | | EAST TEXAS SIGN & SUPPLY, INC. | |SUB %: 0.06 | | | | TEX OP CONSTRUCTION, LP | |SUB %: 2.39 | | | | BANNER SIGN & BARRICADE, INC. (HOOKS) | |SUB %: 0.38 | | | | CAPROCK SPECIALITY CONTRACTORS | |SUB %: 2.13 | | | | | | | | | | CONTRACT 03083218 | TOTALS | 1,124,923.75| 5,212.79| 1,387,067.17| 99.9| ************************************************************************************************************************************ CASS 0.3 MI N OF JIM'S BAYOU | 13.440 | 80,437,941.27| 876,922.42| 41,652,517.05| 53.9| US 59 MARION C/L | | | | | | 0062-04-035 | | | | | | C 62-4-35 GR, STRS & SURF | | | | | | | | | | | | WORK ORDER- 07-19-06 WORK BEGAN- 09-12-06 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 08-01-06 | | | | | | CONTRACT WORKING DAYS- 1,310 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 615 PERCENT TIME USED- 46 | | | | | | | | | | | | INTERSTATE HIGHWAY CONSTRUCTION, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0062-04-035 | | | | | | UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH) | |SUB %: 0.30 | | | | T. J. LAMBRECHT CONSTRUCTION, INC. | |SUB %: 19.27 | | | | WS CONSTRUCTION CO. | |SUB %: 3.62 | | | | MIDWEST ASPHALT CORPORATION | |SUB %: 0.85 | | | | TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. | |SUB %: 1.32 | | | | DUSTROL, INC. (ROANOKE) | |SUB %: 0.11 | | | | EAST TEXAS BRIDGE, INC. | |SUB %: 1.51 | | | | EAST TEXAS SIGN & SUPPLY, INC. | |SUB %: 0.24 | | | | JONA CONTRACTING, INC. | |SUB %: 0.24 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 1.22 | | | | CAPROCK SPECIALITY CONTRACTORS | |SUB %: 0.60 | | | | INDUS CONSTRUCTION, L.P. | |SUB %: 1.23 | | | | R. K. HALL CONSTRUCTION, LTD. | |SUB %: 11.92 | | | | CHOCTAW WATER WELLS | |SUB %: 0.05 | | | | HOUSTON SAWING & DRILLING | |SUB %: 0.00 | | | | TEXAS SHAFTS, INC. | |SUB %: 0.16 | | | | LONE STAR EQUIPMENT CO. INC. (INACTIVE--SEE 12687) | |SUB %: 2.08 | | | | COLUMBIA ENVIRONMENTAL SERVICES, INC. | |SUB %: 0.57 | | | | LIL DAN TRUCKING | |SUB %: 17.49 | | | | APARICIO & APARICIO | |SUB %: 1.40 | | | | | | | | | | CONTRACT 06063202 | TOTALS | 80,437,941.27| 876,922.42| 41,652,517.05| 53.9| ************************************************************************************************************************************ CASS ON CR 1599 AT SIMPSON LAKE | 0.106 | 572,638.00| 155,145.33| 271,035.50| 47.3| CR . | | | | | | 0919-14-017 | | | | | | BR 2007(634) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 08-18-08 WORK BEGAN- 09-18-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 09-03-08 | | | | | | CONTRACT WORKING DAYS- 57 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 40 PERCENT TIME USED- 70 | | | | | | | | | | | | HODGES AND SON CONSTRUCTION COMPANY, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0919-14-017 | | | | | | PANOLA SIGN & BARRICADE, INC. | |SUB %: 0.44 | | | | JONA CONTRACTING, INC. | |SUB %: 3.28 | | | | JUST GROOVING, LTD. | |SUB %: 0.22 | | | | | | | | | | CONTRACT 07083025 | TOTALS | 572,638.00| 155,145.33| 271,035.50| 47.3| ************************************************************************************************************************************ CASS SH 43 | 41.344 | 3,535,272.00| 86,793.50| 86,793.50| 2.4| FM 248 MARION COUNTY LINE | | | | | | 0138-10-026 | | | | | | STP 2008(805)HES SUBGRADE WIDENING AND SURFACING | | | | | | | | | | | | WORK ORDER- 10-16-08 WORK BEGAN- 11-17-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-01-08 | | | | | | CONTRACT WORKING DAYS- 140 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 14 PERCENT TIME USED- 10 | | | | | | | | | | | | KNIFE RIVER CORPORATION - SOUTH | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0138-10-026 | | | | | | BANNER SIGN & BARRICADE, INC. (HOOKS) | |SUB %: 0.39 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.49 | | | | TEX OP CONSTRUCTION, LP | |SUB %: 6.82 | | | | J & M CONTRACTING, COMPANY | |SUB %: 1.99 | | | | | | | | | | CONTRACT 09083004 | TOTALS | 3,535,272.00| 86,793.50| 86,793.50| 2.4| ************************************************************************************************************************************ CASS ETC BOWIE C/L | 160.108 | 6,212,837.52| 11,992.00| 4,776,779.71| 76.8| US 59 ETC 0.2 MI N OF SL 236 | | | | | | 0218-03-080 | | | | | | NH 2008(064) SEAL COAT | | | | | | | | | | | | WORK ORDER- 11-08-07 WORK BEGAN- 06-16-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 06-02-08 | | | | | | CONTRACT WORKING DAYS- 130 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 103 PERCENT TIME USED- 79 | | | | | | | | | | | | J-W PAYNE CONSTRUCTION COMPANY, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0218-03-080 | | | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 19.10 | | | | | | | | | | CONTRACT 10073205 | TOTALS | 6,212,837.52| 11,992.00| 4,776,779.71| 76.8| ************************************************************************************************************************************ HARRISON AT SP 156 UNDERPASS | 0.002 | 1,846,853.83| 158,792.80| 863,758.48| 46.7| IH 20 . | | | | | | 0495-10-078 | | | | | | BR 2008(371) REHABILITATE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 04-10-08 WORK BEGAN- 04-28-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-26-08 | | | | | | CONTRACT WORKING DAYS- 212 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 109 PERCENT TIME USED- 51 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0495-10-078 | | | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.58 | | | | D. B. INDUSTRIES, INC. | |SUB %: 0.93 | | | | PANOLA SIGN & BARRICADE, INC. | |SUB %: 0.71 | | | | ODUM SERVICES, L.P. | |SUB %: 9.92 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 1.42 | | | | TEXAS SHAFTS, INC. | |SUB %: 5.95 | | | | | | | | | | CONTRACT 02083208 | TOTALS | 1,846,853.83| 158,792.80| 863,758.48| 46.7| ************************************************************************************************************************************ HARRISON ELYSIAN FIELDS ELEMENTARY SCHOOL & | 0.653 | 461,616.43| 8,524.21| 389,213.41| 85.5| FM 451 ELYSIAN FIELDS HIGH SCHOOL | | | | | | 0632-04-026 | | | | | | STP 2008(407) INSTALL TURN LANES | | | | | | | | | | | | WORK ORDER- 04-14-08 WORK BEGAN- 06-16-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-30-08 | | | | | | CONTRACT WORKING DAYS- 30 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 41 PERCENT TIME USED- 136 | | | | | | | | | | | | EAST TEXAS BRIDGE, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0632-04-026 | | | | | | BANNER SIGN & BARRICADE, INC. (HOOKS) | |SUB %: 0.37 | | | | D. B. INDUSTRIES, INC. | |SUB %: 2.46 | | | | EAST TEXAS SIGN & SUPPLY, INC. | |SUB %: 0.21 | | | | L.S. EQUIPMENT CO., INC. | |SUB %: 16.49 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.54 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 21.30 | | | | | | | | | | CONTRACT 03083226 | TOTALS | 461,616.43| 8,524.21| 389,213.41| 85.5| ************************************************************************************************************************************ HARRISON AT HARRISON BAYOU & HARRISON BAYOU | 1.187 | 2,899,788.54| 117,799.34| 1,531,493.00| 52.8| FM 134 RELIEF | | | | | | 0632-03-025 | | | | | | BR 2008(473) REPLACE 2 BRIDGES AND APPROACHES | | | | | | | | | | | | WORK ORDER- 06-05-08 WORK BEGAN- 06-26-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 06-21-08 | | | | | | CONTRACT WORKING DAYS- 145 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 72 PERCENT TIME USED- 49 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0632-03-025 | | | | | | D. B. INDUSTRIES, INC. | |SUB %: 0.98 | | | | DENMAN DRILLING CO., INC. | |SUB %: 1.21 | | | | JONA CONTRACTING, INC. | |SUB %: 1.77 | | | | PANOLA SIGN & BARRICADE, INC. | |SUB %: 0.23 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.51 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 1.44 | | | | | | | | | | CONTRACT 04083005 | TOTALS | 2,899,788.54| 117,799.34| 1,531,493.00| 52.8| ************************************************************************************************************************************ HARRISON SH 43 | 1.659 | 4,267,321.71| 2,550.45| 4,303,290.88| 99.9| LP 390 0.2 MI S OF W UNIV. AVE IN MARSHALL | | | | | | 0402-05-002 | | | | | | HP 2006(810) GR, BS, ACP, STR, C&G, AND TRAF SIG | | | | | | | | | | | | WORK ORDER- 09-25-06 WORK BEGAN- 05-23-07 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 03-01-07 | | | | | | CONTRACT WORKING DAYS- 163 ADDL DAYS GRANTED- 30 | | | | | | WORKING DAYS CHARGED- 192 PERCENT TIME USED- 99 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0402-05-002 | | | | | | PANOLA LIGHT & SIGN | |SUB %: 0.57 | | | | D. B. INDUSTRIES, INC. | |SUB %: 0.35 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.16 | | | | EAST TEXAS SIGN & SUPPLY, INC. | |SUB %: 0.41 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 8.06 | | | | | | | | | | CONTRACT 08063221 | TOTALS | 4,267,321.71| 2,550.45| 4,303,290.88| 99.9| ************************************************************************************************************************************ HARRISON AT US 80 UNDERPASS | 0.001 | 1,966,160.99| 181,108.89| 1,649,466.93| 83.8| IH 20 . | | | | | | 0495-10-075 | | | | | | IM 0207(065) REHABILITATE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 10-18-07 WORK BEGAN- 11-13-07 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-03-07 | | | | | | CONTRACT WORKING DAYS- 263 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 247 PERCENT TIME USED- 93 | | | | | | | | | | | | EAST TEXAS BRIDGE, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0495-10-075 | | | | | | PANOLA LIGHT & SIGN | |SUB %: 1.08 | | | | REYNOLDS & KAY, LTD. | |SUB %: 7.75 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.21 | | | | HIGHWAY TECHNOLOGIES | |SUB %: 4.35 | | | | LONE STAR EQUIPMENT CO. INC. (INACTIVE--SEE 12687) | |SUB %: 0.28 | | | | CARTHAGE DRILLING, INC. | |SUB %: 1.25 | | | | SCOTT DERR PAINTING CO | |SUB %: 0.03 | | | | CAPROCK SPECIALITY CONTRACTORS | |SUB %: 0.47 | | | | D. B. INDUSTRIES, INC. | |SUB %: 0.49 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 2.05 | | | | | | | | | | CONTRACT 08073235 | TOTALS | 1,966,160.99| 181,108.89| 1,649,466.93| 83.8| ************************************************************************************************************************************ HARRISON AT LITTLE CYPRESS BAYOU RELIEF BRG | 2.045 | 7,241,751.53| 0.00| 0.00| 0.0| SH 154 . | | | | | | 0402-03-023 | | | | | | BR 2008(806) REPLACE BRIDGE & APPROACHES | | | | | | | | | | | | WORK ORDER- 10-10-08 WORK BEGAN- 12-01-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-01-08 | | | | | | CONTRACT WORKING DAYS- 311 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0402-03-023 | | | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 1.06 | | | | PANOLA SIGN & BARRICADE, INC. | |SUB %: 0.21 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 0.74 | | | | ODUM SERVICES, L.P. | |SUB %: 1.10 | | | | | | | | | | CONTRACT 08083003 | TOTALS | 7,241,751.53| 0.00| 0.00| 0.0| ************************************************************************************************************************************ HARRISON AT CADDO LAKE STATE PARK RECREATION | 0.472 | 1,955,675.68| 139,458.16| 808,738.41| 43.5| VA . | | | | | | 0919-03-031 | | | | | | C 919-3-31 RECONSTRUCT PARKING & PROVIDE ADA A | | | | | | | | | | | | WORK ORDER- 11-13-07 WORK BEGAN- 12-17-07 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-29-07 | | | | | | CONTRACT WORKING DAYS- 290 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 110 PERCENT TIME USED- 37 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0919-03-031 | | | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 1.46 | | | | D. B. INDUSTRIES, INC. | |SUB %: 1.22 | | | | ODUM SERVICES, L.P. | |SUB %: 0.77 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 1.43 | | | | PANOLA LIGHT & SIGN | |SUB %: 0.95 | | | | | | | | | | CONTRACT 10073209 | TOTALS | 1,955,675.68| 139,458.16| 808,738.41| 43.5| ************************************************************************************************************************************ MORRIS FM 144 | 31.510 | 1,944,728.75| 55,745.44| 1,077,228.75| 55.3| FM 997 3.8 MI S OF FM 144 | | | | | | 0392-06-008 | | | | | | STP 2008(217)SB SAFETY TREAT FIXED OBJECTS, ETC. | | | | | | | | | | | | WORK ORDER- 01-30-08 WORK BEGAN- 02-06-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 02-15-08 | | | | | | CONTRACT WORKING DAYS- 290 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 161 PERCENT TIME USED- 55 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0392-06-008 | | | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.23 | | | | D. B. INDUSTRIES, INC. | |SUB %: 2.68 | | | | JONA CONTRACTING, INC. | |SUB %: 10.48 | | | | PANOLA LIGHT & SIGN | |SUB %: 0.81 | | | | | | | | | | CONTRACT 12073220 | TOTALS | 1,944,728.75| 55,745.44| 1,077,228.75| 55.3| ************************************************************************************************************************************ PANOLA AT IRONS BAYOU | 0.183 | 972,548.30| 0.00| 974,385.12| 99.9| US 79 . | | | | | | 0246-02-043 | | | | | | BR 2008(274) REHABILITATE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 03-07-08 WORK BEGAN- 03-25-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 03-23-08 | | | | | | CONTRACT WORKING DAYS- 103 ADDL DAYS GRANTED- 13 | | | | | | WORKING DAYS CHARGED- 117 PERCENT TIME USED- 100 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0246-02-043 | | | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.40 | | | | D. B. INDUSTRIES, INC. | |SUB %: 0.72 | | | | ODUM SERVICES, L.P. | |SUB %: 5.09 | | | | COWBELL TRAFFIC SERVICES, INC. | |SUB %: 0.46 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 11.23 | | | | | | | | | | CONTRACT 01083039 | TOTALS | 972,548.30| 0.00| 974,385.12| 99.9| ************************************************************************************************************************************ PANOLA 1.15 MI. E. OF FM 3231 | 0.743 | 2,821,475.92| 132,737.49| 2,443,998.03| 90.5| FM 1251 1.893 MI. E. OF FM 3231 | | | | | | 1388-02-008 | | | | | | CC 1388-2-8 GR,STR,BS,SURF,PAV MK | | | | | | | | | | | | WORK ORDER- 04-11-07 WORK BEGAN- 04-30-07 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-27-07 | | | | | | CONTRACT WORKING DAYS- 175 ADDL DAYS GRANTED- 1 | | | | | | WORKING DAYS CHARGED- 187 PERCENT TIME USED- 106 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1388-02-008 | | | | | | M & D FOUNDATION DRILLING INDUSTRIES, INC. | |SUB %: 1.85 | | | | PANOLA LIGHT & SIGN | |SUB %: 0.27 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 0.69 | | | | D. B. INDUSTRIES, INC. | |SUB %: 0.71 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.66 | | | | ODUM SERVICES, L.P. | |SUB %: 0.72 | | | | | | | | | | CONTRACT 03073008 | TOTALS | 2,821,475.92| 132,737.49| 2,443,998.03| 90.5| ************************************************************************************************************************************ PANOLA AT MURVAUL CREEK | 0.148 | 814,365.30| 0.00| 0.00| 0.0| FM 1970 . | | | | | | 0428-02-021 | | | | | | BR 2008(565) REHABILITATE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 07-10-08 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 03-15-09 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 71 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0428-02-021 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 05083019 | TOTALS | 814,365.30| 0.00| 0.00| 0.0| ************************************************************************************************************************************ PANOLA FM 123 | 33.778 | 3,642,709.40| 0.00| 0.00| 0.0| FM 31 4.5 MI. NORTH OF LOUISIANA STATE LI | | | | | | 0731-01-047 | | | | | | STP 2008(807)HES SUBGRADE WIDENING AND SURFACING | | | | | | | | | | | | WORK ORDER- 11-18-08 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 12-04-08 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 170 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | L.S. EQUIPMENT CO., INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0731-01-047 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 10083210 | TOTALS | 3,642,709.40| 0.00| 0.00| 0.0| ************************************************************************************************************************************ PANOLA AT SIX MILE CREEK, SIX MILE CREEK R | 2.261 | 5,816,981.05| 0.00| 0.00| 0.0| FM 2517 SABINE RIVER & SABINE RIVER RELIEF | | | | | | 2239-01-021 | | | | | | BR 2008(808) REPLACE/WIDEN BRIDGES & APPROACHES | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 385 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 2239-01-021 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 11083203 | TOTALS | 5,816,981.05| 0.00| 0.00| 0.0| ************************************************************************************************************************************ TITUS ETC FM 21 | 89.897 | 9,443,858.50| 166,596.31| 5,588,377.31| 61.6| FM 1001 ETC FM 127 | | | | | | 0734-02-016 | | | | | | SFT 734-2-16 SUBGRADE WIDENING & SURFACING | | | | | | | | | | | | WORK ORDER- 04-13-06 WORK BEGAN- 08-15-06 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-29-06 | | | | | | CONTRACT WORKING DAYS- 455 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 340 PERCENT TIME USED- 74 | | | | | | | | | | | | J-W PAYNE CONSTRUCTION COMPANY, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0734-02-016 | | | | | | TEXAS HIGHWAY MARKINGS, LLC | |SUB %: 2.69 | | | | | | | | | | CONTRACT 03063042 | TOTALS | 9,443,858.50| 166,596.31| 5,588,377.31| 61.6| ************************************************************************************************************************************ TITUS ON CR 1250 AT RIPLEY CREEK AND | 0.335 | 907,870.00| 10,892.23| 972,577.96| 99.9| CR RIPLEY CREEK TRIB. | | | | | | 0919-30-039 | | | | | | BR 2002(376) REPLACE BRIDGES AND APPROACHES | | | | | | | | | | | | WORK ORDER- 08-14-07 WORK BEGAN- 08-28-07 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 08-30-07 | | | | | | CONTRACT WORKING DAYS- 255 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 173 PERCENT TIME USED- 67 | | | | | | | | | | | | EAST TEXAS BRIDGE, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0919-30-039 | | | | | | D. B. INDUSTRIES, INC. | |SUB %: 2.14 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.68 | | | | ODUM SERVICES, L.P. | |SUB %: 6.95 | | | | | | | | | | CONTRACT 07073032 | TOTALS | 907,870.00| 10,892.23| 972,577.96| 99.9| ************************************************************************************************************************************ TITUS ON CR 2400 AT DRAGOO CREEK | 0.207 | 751,113.85| 32,722.16| 75,870.55| 10.1| CR . | | | | | | 0919-30-049 | | | | | | BR 2006(464) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 10-06-08 WORK BEGAN- 10-28-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 10-22-08 | | | | | | CONTRACT WORKING DAYS- 177 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 10 PERCENT TIME USED- 5 | | | | | | | | | | | | J-W PAYNE CONSTRUCTION COMPANY, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0919-30-049 | | | | | | ODUM SERVICES, L.P. | |SUB %: 5.98 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 1.55 | | | | | | | | | | CONTRACT 08083021 | TOTALS | 751,113.85| 32,722.16| 75,870.55| 10.1| ************************************************************************************************************************************ UPSHUR AT INT. OF FM 1795 | 0.815 | 765,253.00| 65,463.00| 532,057.78| 69.5| SH 154 . | | | | | | 0401-04-029 | | | | | | STP 2008(406)HES INSTALL LEFT TURN LANES | | | | | | | | | | | | WORK ORDER- 04-14-08 WORK BEGAN- 05-06-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-30-08 | | | | | | CONTRACT WORKING DAYS- 125 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 96 PERCENT TIME USED- 76 | | | | | | | | | | | | L.S. EQUIPMENT CO., INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0401-04-029 | | | | | | STATEWIDE GUARDRAIL SERVICE | |SUB %: 1.24 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 9.22 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.63 | | | | | | | | | | CONTRACT 03083022 | TOTALS | 765,253.00| 65,463.00| 532,057.78| 69.5| ************************************************************************************************************************************ UPSHUR AT WALNUT CREEK | 0.148 | 621,123.42| 59,211.50| 360,590.46| 58.0| FM 726 . | | | | | | 1895-01-024 | | | | | | BR 2008(566) REHABILITATE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 07-10-08 WORK BEGAN- 07-30-08 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 07-26-08 | | | | | | CONTRACT WORKING DAYS- 80 ADDL DAYS GRANTED- 3 | | | | | | WORKING DAYS CHARGED- 49 PERCENT TIME USED- 59 | | | | | | | | | | | | LONGVIEW BRIDGE AND ROAD, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1895-01-024 | | | | | | JONA CONTRACTING, INC. | |SUB %: 8.04 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 9.71 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.51 | | | | D. B. INDUSTRIES, INC. | |SUB %: 1.08 | | | | PANOLA SIGN & BARRICADE, INC. | |SUB %: 1.05 | | | | | | | | | | CONTRACT 05083219 | TOTALS | 621,123.42| 59,211.50| 360,590.46| 58.0| ************************************************************************************************************************************ UPSHUR AT BIG SANDY CREEK | 1.401 | 6,020,883.58| 232,020.81| 4,067,912.03| 67.5| SH 155 0.6 MI S OF FM 1002 | | | | | | 0520-02-036 | | | | | | BR 2007(683) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 08-09-07 WORK BEGAN- 10-23-07 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 08-25-07 | | | | | | CONTRACT WORKING DAYS- 271 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 185 PERCENT TIME USED- 68 | | | | | | | | | | | | H. H. HOWARD & SONS, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0520-02-036 | | | | | | D. B. INDUSTRIES, INC. | |SUB %: 0.48 | | | | EAST TEXAS SIGN & SUPPLY, INC. | |SUB %: 0.26 | | | | HODGES AND SON CONSTRUCTION COMPANY, INC. | |SUB %: 40.94 | | | | ODUM SERVICES, L.P. | |SUB %: 1.04 | | | | PANOLA LIGHT & SIGN | |SUB %: 0.32 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.24 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 0.84 | | | | DENMAN DRILLING CO., INC. | |SUB %: 0.51 | | | | | | | | | | CONTRACT 07073208 | TOTALS | 6,020,883.58| 232,020.81| 4,067,912.03| 67.5| ************************************************************************************************************************************ UPSHUR AT INTERSECTION OF SH 155 | 1.016 | 10,058,859.83| 40,118.60| 7,983,715.30| 83.5| US 259 . | | | | | | 0392-02-071 | | | | | | SFT 392-2-71 GRADING,STRUCTURES,BASE & SURFACING | | | | | | | | | | | | WORK ORDER- 09-13-06 WORK BEGAN- 04-02-07 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 04-01-07 | | | | | | CONTRACT WORKING DAYS- 236 ADDL DAYS GRANTED- 81 | | | | | | WORKING DAYS CHARGED- 203 PERCENT TIME USED- 64 | | | | | | | | | | | | H. H. HOWARD & SONS, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0392-02-071 | | | | | | BANNER SIGN & BARRICADE, INC. (TYLER) | |SUB %: 0.39 | | | | D. B. INDUSTRIES, INC. | |SUB %: 0.58 | | | | HODGES AND SON CONSTRUCTION COMPANY, INC. | |SUB %: 24.45 | | | | ODUM SERVICES, L.P. | |SUB %: 1.22 | | | | R. K. HALL CONSTRUCTION, LTD. | |SUB %: 32.57 | | | | SOUTHWEST ENVIRONMENT SERVICES, INC. | |SUB %: 0.45 | | | | STRIPING TECHNOLOGY, L.P. | |SUB %: 3.73 | | | | MIDWEST ASPHALT CORPORATION (GAINESVILLE) | |SUB %: 0.18 | | | | TEXAS SHAFTS, INC. | |SUB %: 0.98 | | | | | | | | | | CONTRACT 08063208 | TOTALS | 10,058,859.83| 40,118.60| 7,983,715.30| 83.5| ************************************************************************************************************************************ UPSHUR AT GLADE CREEK | 0.142 | 637,773.56| 0.00| 0.00| 0.0| FM 2685 . | | | | | | 2157-01-016 | | | | | | BR 2009(147) REHABILITATE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 80 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | EAST TEXAS BRIDGE, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 2157-01-016 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 12083014 | TOTALS | 637,773.56| 0.00| 0.00| 0.0| ************************************************************************************************************************************ DISTRICT CONTRACT AMOUNT 387,095,338.88 DISTRICT ESTIMATES THIS MONTH 6,699,368.34 DISTRICT TOTAL ESTIMATES PAID TO DATE 196,354,162.60