| AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - ATLANTA DISTRICT | ||||
| Last Update: Thursday, October 29, 2009 |
| ITEMS 100 2002 TO 169 2003 |
| Items | Items | Bid Code Range |
|---|---|---|
| 0100 - 0169 0247 - 0275 0305 - 0360 0400 - 0496 0500 - 0560 0610 - 0688 0770 - 0770 |
2007 - 2007 3120 - 3165 5049 - 5049 6007 - 6986 8251 - 8362 |
100 2002 - 169 2003 |
| Item No | Description | Units | October 31, 2009 | Twelve Month Moving | Usage | ||
|---|---|---|---|---|---|---|---|
| Quantity | Avg Bid | Quantity | Avg Bid | ||||
| 100 2002 | PREPARING ROW | STA | 234.410 | 1,749.91562 | 11 | ||
| 100 2004 | PREPARING ROW (TREE) (12" TO 24" DIA) | EA | 4.000 | 1,000.00000 | 1 | ||
| 100 2006 | PREP ROW (TREE) (LESS THAN 24" DIA) | EA | 8.000 | 700.00000 | 1 | ||
| 104 2009 | REMOVING CONC (RIPRAP) | SY | 9,038.000 | 7.43008 | 8 | ||
| 104 2010 | REMOVING CONC (RIPRAP) | CY | 61.000 | 7.50000 | 1 | ||
| 104 2013 | REMOVING CONC (FOUNDATIONS) | SY | 7,114.000 | 2.00000 | 1 | ||
| 104 2015 | REMOVING CONC (SIDEWALKS) | SY | 912.000 | 4.00000 | 1 | ||
| 104 2017 | REMOVING CONC (DRIVEWAYS) | SY | 3,644.000 | 7.60113 | 7 | ||
| 104 2022 | REMOVING CONC (CURB AND GUTTER) | LF | 4,845.000 | 3.13484 | 5 | ||
| 104 2027 | REMOVING CONC (APPR SLAB) | SY | 420.000 | 29.88095 | 2 | ||
| 104 2033 | REMOVING CONC (DRAIN) | SY | 97.900 | 15.03493 | 3 | ||
| 105 2013 | REMOVING STAB BASE & ASPH PAV (9") | SY | 3,987.000 | 3.00000 | 1 | ||
| 105 2015 | REMOVING STAB BASE & ASPH PAV (8" - 10") | SY | 116.800 | 29.00000 | 1 | ||
| 105 2020 | REMOVING STAB BASE & ASPH PAV (12") | SY | 1,599.000 | 4.10000 | 1 | ||
| 105 2047 | REMOVING STAB BASE & ASPH PAV (1.5") | SY | 532.000 | 4.99000 | 1 | ||
| 110 2001 | EXCAVATION (ROADWAY) | CY | 118,225.000 | 2.98557 | 9 | ||
| 110 2002 | EXCAVATION (CHANNEL) | CY | 356.000 | 5.65584 | 2 | ||
| 112 2001 | SUBGRADE WIDENING (ORD COMP) | STA | 7,385.900 | 119.79336 | 8 | ||
| 112 2002 | SUBGRADE WIDENING (DENS CONT) | STA | 962.630 | 140.43394 | 3 | ||
| 132 2002 | EMBANKMENT (FINAL) (DENS CONT) (TY A) | CY | 2,144.000 | 8.00000 | 1 | ||
| 132 2003 | EMBANKMENT (FINAL) (ORD COMP) (TY B) | CY | 631.000 | 12.00000 | 2 | ||
| 132 2005 | EMBANKMENT (FINAL) (ORD COMP) (TY C) | CY | 1,614.000 | 8.00000 | 1 | ||
| 132 2006 | EMBANKMENT (FINAL) (DENS CONT) (TY C) | CY | 174,335.000 | 5.11317 | 8 | ||
| 132 2019 | EMBANKMENT (VEHICLE) (ORD COMP) (TY B) | CY | 1,542.000 | 11.20233 | 4 | ||
| 132 2021 | EMBANKMENT (VEHICLE) (ORD COMP) (TY C) | CY | 173.900 | 19.57562 | 2 | ||
| 134 2002 | BACKFILL (TY B) | STA | 8,413.190 | 112.45270 | 11 | ||
| 134 2003 | BACKFILL (TY C) | STA | 1,197.230 | 142.07877 | 5 | ||
| 150 2001 | BLADING | STA | 1,655.200 | 61.57473 | 11 | ||
| 158 2006 | SPEC EXCAV WORK (VEHICLE) | CY | 35.000 | 10.00000 | 1 | ||
| 160 2003 | FURNISHING AND PLACING TOPSOIL (4") | SY | 2,759.400 | .60000 | 1 | ||
| 160 2004 | FURNISHING AND PLACING TOPSOIL (6") | SY | 32,988.000 | 1.60466 | 2 | ||
| 160 2005 | FURNISHING AND PLACING TOPSOIL | CY | 303.000 | 8.00000 | 1 | ||
| 162 2005 | MULCH SODDING | CY | 16,928.000 | 8.63353 | 8 | ||
| 164 2001 | BROADCAST SEED (PERM) (RURAL) (SANDY) | SY | 1,941,968.000 | .06149 | 14 | ||
| 164 2009 | BROADCAST SEED (TEMP) (WARM) | SY | 608,053.000 | .06522 | 18 | ||
| 164 2011 | BROADCAST SEED (TEMP) (COOL) | SY | 608,053.000 | .07140 | 18 | ||
| 164 2013 | STRAW / HAY MLCH SEED (PERM) (RURAL) (SANDY | SY | 405,691.000 | .17699 | 9 | ||
| 168 2001 | VEGETATIVE WATERING | MG | 41,693.900 | 2.80380 | 22 | ||
| 169 2001 | SOIL RETENTION BLANKETS (CL 1) (TY A) | SY | 1,100.000 | 2.54545 | 5 | ||
| 169 2002 | SOIL RETENTION BLANKETS (CL 1) (TY B) | SY | 4,100.000 | 1.75610 | 4 | ||
| 169 2003 | SOIL RETENTION BLANKETS (CL 1) (TY C) | SY | 4,335.000 | 1.41453 | 3 | ||
| | ||||
|