MIS.CIS.19 MONTHLY STATE LET CONSTRUCTION REPORT DISTRICT 04 AS OF MAY 15, 2013 PAGE 10 ************************************************************************************************************************************ * | | CONTRACT | AMOUNT THIS | TOTAL ESTIMATE | % * * CONTRACT IDENTIFICATION AND INFORMATION | LENGTH | AMOUNT | ESTIMATE | TO DATE | COMP* ************************************************************************************************************************************ ARMSTRONG 0.3 MI WEST OF CLAUDE CITY LIMITS | 1.461 | 6,066,806.51| 163,774.53| 2,554,372.98| 42.1| US 287 0.037 MI EAST OF TRICE ST | | | | | | 0042-03-040 | | | | | | NH 2012(544) REHAB EXISTING ROADWAY | | | | | | | | | | | | ARMSTRONG 0.037 MI EAST OF TRICE ST | 1.179 | 3,713,109.66| 178,612.29| 1,299,671.56| 35.0| US 287 0.146 MI EAST OF FM 1151 | | | | | | 0042-04-039 | | | | | | NH 2012(544) REHAB EXISTING ROADWAY | | | | | | | | | | | | WORK ORDER- 07-03-12 WORK BEGAN- 08-02-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 07-19-12 | | | | | | CONTRACT WORKING DAYS- 386 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 184 PERCENT TIME USED- 47 | | | | | | | | | | | | J. LEE MILLIGAN, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0042-03-040 | | | | | | ALAMO BROTHERS CONCRETE | |SUB %: 7.64 | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 2.45 | | | | DUSTROL, INC. | |SUB %: 0.05 | | | | WILLIS ELECTRIC CO., LP | |SUB %: 0.53 | | | | TEX OP CONSTRUCTION, LP | |SUB %: 1.53 | | | | | | | | | | CONTRACT 05123203 | TOTALS | 9,779,916.17| 342,386.82| 3,854,044.54| 39.4| ************************************************************************************************************************************ ARMSTRONG US 287 AT GOODNIGHT TEXAS | 0.001 | 615,000.00| 18,450.00| 645,473.00| 99.9| VA . | | | | | | 0904-06-009 | | | | | | STP 2011(261)TE CONSTRUCTION OF VISITOR'S CENTER | | | | | | | | | | | | WORK ORDER- 09-17-12 WORK BEGAN- 10-01-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 10-03-12 | | | | | | CONTRACT WORKING DAYS- 170 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 147 PERCENT TIME USED- 86 | | | | | | | | | | | | PIONEER GENERAL CONTRACTORS, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0904-06-009 | | | | | | HOLMES CONSTRUCTION CO., L.P. | |SUB %: 0.00 | | | | | | | | | | CONTRACT 08123212 | TOTALS | 615,000.00| 18,450.00| 645,473.00| 99.9| ************************************************************************************************************************************ CARSON 2.0 MILES WEST OF GROOM | 4.297 | 3,773,636.82| 10,431.00| 3,810,621.05| 99.9| IH 40 GRAY COUNTY LINE | | | | | | 0275-04-048 | | | | | | IM 0401(206) REHAB EXISTING ROADWAY | | | | | | | | | | | | GRAY CARSON COUNTY LINE | 1.258 | 973,863.80| 0.00| 1,218,770.24| 99.9| IH 40 2.0 MILES EAST OF GROOM | | | | | | 0275-05-042 | | | | | | IM 0401(206) REHAB EXISTING ROADWAY | | | | | | | | | | | | WORK ORDER- 04-17-12 WORK BEGAN- 04-19-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 05-03-12 | | | | | | CONTRACT WORKING DAYS- 256 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 229 PERCENT TIME USED- 89 | | | | | | | | | | | | GILVIN-TERRILL, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0275-04-048 | | | | | | WINDING ROAD CONSTRUCTION, INC. | |SUB %: 30.42 | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 1.75 | | | | DUSTROL, INC. | |SUB %: 0.57 | | | | RAY ELECTRIC COMPANY | |SUB %: 0.30 | | | | TEXAS ALTERNATIVE GRASSER, INC. | |SUB %: 0.38 | | | | INTERSTATE IMPROVEMENT, INC. | |SUB %: 1.76 | | | | RPV CONSTRUCTION | |SUB %: 1.63 | | | | | | | | | | CONTRACT 03123004 | TOTALS | 4,747,500.62| 10,431.00| 5,029,391.29| 99.9| ************************************************************************************************************************************ CARSON 3.0 MI EAST OF POTTER CO. LINE | 7.759 | 5,177,809.06| 0.00| 28,877.40| 0.5| IH 40 3.7 MI WEST OF CONWAY | | | | | | 0275-02-069 | | | | | | IM 0401(208) REHAB EXISTING ROADWAY | | | | | | | | | | | | WORK ORDER- 01-15-13 WORK BEGAN- 00-00-00 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 01-31-13 | | | | | | CONTRACT WORKING DAYS- 85 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 12 PERCENT TIME USED- 14 | | | | | | | | | | | | J. LEE MILLIGAN, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0275-02-069 | | | | | | AMARILLO RMT ENTERPRISE | |SUB %: 0.78 | | | | WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED | |SUB %: 1.05 | | | | O. TREVINO CONSTRUCTION, LLC | |SUB %: 7.18 | | | | TEX OP CONSTRUCTION, LP | |SUB %: 1.36 | | | | WEST TEXAS RUMBLE STRIP | |SUB %: 0.11 | | | | | | | | | | CONTRACT 11123206 | TOTALS | 5,177,809.06| 0.00| 28,877.40| 0.5| ************************************************************************************************************************************ DALLAM US 87 | 1.866 | 1,621,574.25| 0.00| 1,669,784.29| 99.9| SS 17 US 385 | | | | | | 1702-03-001 | | | | | | STP 2011(992) NEW LOCATION 2 LANE RDWY | | | | | | | | | | | | WORK ORDER- 06-14-11 WORK BEGAN- 02-06-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 02-28-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 150 ADDL DAYS GRANTED- 17 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 174 PERCENT TIME USED- 104 | |**************************************************| | | | | | | | HOLMES CONSTRUCTION CO., L.P. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1702-03-001 | | | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 3.37 | | | | SECRET GARDENER | |SUB %: 0.94 | | | | | | | | | | CONTRACT 05113008 | TOTALS | 1,621,574.25| 0.00| 1,669,784.29| 99.9| ************************************************************************************************************************************ DALLAM DALHART CURB & GUTTER | 23.304 | 6,417,952.72| 178,732.95| 2,273,813.10| 35.4| US 54 CHAMBERLIN | | | | | | 0238-03-052 | | | | | | C 238-3-52 REHAB EXIST RDWY & ADD PASSING LNS | | | | | | | | | | | | WORK ORDER- 08-20-12 WORK BEGAN- 09-10-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 09-05-12 | | | | | | CONTRACT WORKING DAYS- 172 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 159 PERCENT TIME USED- 92 | | | | | | | | | | | | J. LEE MILLIGAN, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0238-03-052 | | | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 2.67 | | | | DUSTROL, INC. | |SUB %: 0.34 | | | | | | | | | | CONTRACT 06123007 | TOTALS | 6,417,952.72| 178,732.95| 2,273,813.10| 35.4| ************************************************************************************************************************************ DEAF SMITH RANDALL COUNTY LINE | 13.103 | 3,419,940.93| 0.00| 0.00| 0.0| US 60 HEREFORD CITY LIMITS | | | | | | 0168-07-042 | | | | | | NH 2013(311) REHAB EXISTING RDWY WB LANES | | | | | | | | | | | | WORK ORDER- 03-15-13 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 03-31-13 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 127 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | J. LEE MILLIGAN, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0168-07-042 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 01133217 | TOTALS | 3,419,940.93| 0.00| 0.00| 0.0| ************************************************************************************************************************************ HARTLEY EAST OF US 385 INTERCHANGE | 22.251 | 21,250,815.26| 32,942.15| 1,799,602.58| 8.4| US 87 MOORE COUNTY LINE | | | | | | 0425-01-019 | | | | | | C 425-1-19 REHAB EXISTING RDWY & PASSING LANES | | | | | | | | | | | | WORK ORDER- 10-24-12 WORK BEGAN- 11-19-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-09-12 | | | | | | CONTRACT WORKING DAYS- 370 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 107 PERCENT TIME USED- 28 | | | | | | | | | | | | RK HALL, LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0425-01-019 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.28 | | | | TEXAS ALTERNATIVE GRASSER, INC. | |SUB %: 0.02 | | | | DUSTROL, INC. | |SUB %: 1.94 | | | | HOLMES CONSTRUCTION CO., L.P. | |SUB %: 10.19 | | | | HJC FARMS, INC. | |SUB %: 0.95 | | | | BALLOU PAVEMENT SOLUTIONS INC. | |SUB %: 14.78 | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 1.34 | | | | BRUSH EATERS, INC. | |SUB %: 0.12 | | | | KOSS CONSTRUCTION COMPANY | |SUB %: 14.78 | | | | | | | | | | CONTRACT 08123002 | TOTALS | 21,250,815.26| 32,942.15| 1,799,602.58| 8.4| ************************************************************************************************************************************ HEMPHILL ON CR 20 AND GAGEBY CREEK | 0.060 | 386,684.00| 30,740.00| 335,717.00| 93.0| CR . | | | | | | 0904-03-012 | | | | | | BR 2011(439) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | HEMPHILL AT CR EE & DRAW CREEK | 0.130 | 581,809.50| 0.00| 574,715.50| 98.7| CR . | | | | | | 0904-03-016 | | | | | | BR 2011(435) REPLACE BRIDGE & APPR | | | | | | | | | | | | ROBERTS AT NO NAME CREEK | 0.028 | 279,183.00| 67,815.00| 253,340.32| 90.7| CR . | | | | | | 0904-10-002 | | | | | | BR 2011(675) REPLACE BRIDGE & APPROACHES | | | | | | | | | | | | WORK ORDER- 06-18-12 WORK BEGAN- 08-13-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 07-04-12 | | | | | | CONTRACT WORKING DAYS- 128 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 163 PERCENT TIME USED- 127 | | | | | | | | | | | | EARTH BUILDERS, L.P. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0904-03-012 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.47 | | | | LANCO TURF & SEEDING, INC. | |SUB %: 2.39 | | | | | | | | | | CONTRACT 05123029 | TOTALS | 1,247,676.50| 98,555.00| 1,163,772.82| 95.1| ************************************************************************************************************************************ HEMPHILL LIPSCOMB COUNTY LINE | 6.267 | 4,019,598.98| 238,045.25| 270,169.25| 6.7| US 83 HORSE CREEK | | | | | | 0030-05-062 | | | | | | STP 2013(003) REHAB EXISTING RDWY | | | | | | | | | | | | WORK ORDER- 11-09-12 WORK BEGAN- 00-00-00 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 11-25-12 | | | | | | CONTRACT WORKING DAYS- 85 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 22 PERCENT TIME USED- 25 | | | | | | | | | | | | J. LEE MILLIGAN, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0030-05-062 | | | | | | KOSS CONSTRUCTION COMPANY | |SUB %: 24.72 | | | | O. TREVINO CONSTRUCTION, LLC | |SUB %: 5.11 | | | | AMARILLO RMT ENTERPRISE | |SUB %: 0.54 | | | | WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED | |SUB %: 2.57 | | | | | | | | | | CONTRACT 09123220 | TOTALS | 4,019,598.98| 238,045.25| 270,169.25| 6.7| ************************************************************************************************************************************ HEMPHILL 1.66 MILES SOUTH OF FM 277 | 3.671 | 1,972,769.95| 0.00| 0.00| 0.0| US 83 WHEELER COUNTY LINE | | | | | | 0030-07-017 | | | | | | STP 2013(236) REHAB EXISTING ROADWAY | | | | | | | | | | | | WORK ORDER- 03-06-13 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 03-22-13 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 64 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | L. A. FULLER & SONS CONSTRUCTION, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0030-07-017 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 12123020 | TOTALS | 1,972,769.95| 0.00| 0.00| 0.0| ************************************************************************************************************************************ HUTCHINSON AT ROCK CREEK | 0.151 | 2,716,537.03| 0.00| 0.00| 0.0| SH 136 . | | | | | | 0356-01-091 | | | | | | BR 2013(375) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 05-06-13 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 05-22-13 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 241 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | RK HALL, LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0356-01-091 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 02133215 | TOTALS | 2,716,537.03| 0.00| 0.00| 0.0| ************************************************************************************************************************************ HUTCHINSON PLEMONS RD & CANADIAN RIVER PLEMONS | 0.679 | 3,192,061.68| 0.00| 3,166,191.49| 99.1| CR . | | | | | | 0904-07-011 | | | | | | BR 2008(471) REPLACE BRIDGE & APPROACHES | | | | | | | | | | | | WORK ORDER- 09-06-11 WORK BEGAN- 10-03-11 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 09-22-11 | | | | | | CONTRACT WORKING DAYS- 325 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 287 PERCENT TIME USED- 88 | | | | | | | | | | | | J. LEE MILLIGAN, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0904-07-011 | | | | | | WESTERN FENCE CO. | |SUB %: 1.39 | | | | S & S BRIDGE PAINTING, INC. | |SUB %: 0.28 | | | | HOUSTON SAWING & DRILLING | |SUB %: 0.37 | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 0.32 | | | | WEBBER-BALKE FOUNDATION COMPANY, INC. | |SUB %: 9.38 | | | | AMARILLO RMT ENTERPRISE | |SUB %: 0.29 | | | | | | | | | | CONTRACT 08113029 | TOTALS | 3,192,061.68| 0.00| 3,166,191.49| 99.1| ************************************************************************************************************************************ LIPSCOMB FM 377 | 10.063 | 5,502,012.06| 64,700.42| 455,112.98| 8.2| SH 23 11.05 MI N OF US 83 | | | | | | 1337-01-022 | | | | | | C 1337-1-22 REHAB & WIDEN EXISTING RDWY | | | | | | | | | | | | WORK ORDER- 11-19-12 WORK BEGAN- 01-09-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 12-05-12 | | | | | | CONTRACT WORKING DAYS- 250 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 73 PERCENT TIME USED- 29 | | | | | | | | | | | | MITCHELL ENTERPRISES, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1337-01-022 | | | | | | WIMS ENVIRONMENTAL CONSTRUCTION, LTD. | |SUB %: 1.68 | | | | HJC FARMS, INC. | |SUB %: 1.81 | | | | TOTAL HIGHWAY MAINTENANCE, LLC | |SUB %: 2.18 | | | | B&B SOLVENT, LTD. | |SUB %: 42.44 | | | | | | | | | | CONTRACT 07123220 | TOTALS | 5,502,012.06| 64,700.42| 455,112.98| 8.2| ************************************************************************************************************************************ LIPSCOMB 11.05 MI N OF US 83 | 11.050 | 6,406,551.08| 312,550.77| 906,503.58| 14.1| SH 23 US 83 | | | | | | 1337-02-010 | | | | | | STP 2013(086) REHAB & WIDEN EXISTING RDWY | | | | | | | | | | | | WORK ORDER- 01-03-13 WORK BEGAN- 01-07-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 01-19-13 | | | | | | CONTRACT WORKING DAYS- 190 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | | | | | | | | | | | | J. LEE MILLIGAN, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 1337-02-010 | | | | | | AMARILLO RMT ENTERPRISE | |SUB %: 2.63 | | | | CUTRELL TRUCKING COMPANY, INC. | |SUB %: 3.97 | | | | TEXAS ENVIRONMENTAL MANAGEMENT, INC | |SUB %: 0.80 | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 2.04 | | | | | | | | | | CONTRACT 10123014 | TOTALS | 6,406,551.08| 312,550.77| 906,503.58| 14.1| ************************************************************************************************************************************ OCHILTREE 6TH AVE | 0.494 | 1,347,836.50| 2,258.72| 760,080.58| 56.3| US 83 13TH AVE | | | | | | 0030-02-042 | | | | | | STP 2011(262)TE PERRYTON MAIN ST ENHANCEMENT II | | | | | | | | | | | | WORK ORDER- 04-26-12 WORK BEGAN- 05-14-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 05-12-12 | | | | | | CONTRACT WORKING DAYS- 150 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 144 PERCENT TIME USED- 96 | | | | | | | | | | | | B&B SOLVENT, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0030-02-042 | | | | | | B & G ELECTRIC | |SUB %: 55.08 | | | | | | | | | | CONTRACT 02123231 | TOTALS | 1,347,836.50| 2,258.72| 760,080.58| 56.3| ************************************************************************************************************************************ OCHILTREE US 83 | 15.205 | 3,838,624.15| 0.00| 0.00| 0.0| SH 15 LIPSCOMB COUNTY LINE | | | | | | 0355-03-028 | | | | | | STP 2013(442) OVERLAY | | | | | | | | | | | | OCHILTREE PERRYTON C&G | 14.665 | 1,443,103.90| 0.00| 0.00| 0.0| SH 15 LIPSCOMB COUNTY LINE | | | | | | 0355-03-029 | | | | | | STP 2013(442) OVERLAY | | | | | | | | | | | | WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 82 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | RK HALL, LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0355-03-028 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 03133013 | TOTALS | 5,281,728.05| 0.00| 0.00| 0.0| ************************************************************************************************************************************ OCHILTREE 1.4 MILES N OF NORTHUP CREEK | 11.232 | 11,848,782.75| 436,431.49| 5,826,869.95| 50.1| US 83 LIPSCOMB COUNTY LINE | | | | | | 0030-03-025 | | | | | | STP 1102(341) REHABILITATE EXISTING ROADWAY | | | | | | | | | | | | WORK ORDER- 08-19-11 WORK BEGAN- 09-06-11 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 09-04-11 | | | | | | CONTRACT WORKING DAYS- 300 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 384 PERCENT TIME USED- 128 | | | | | | | | | | | | GILVIN-TERRILL, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0030-03-025 | | | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 1.96 | | | | CUTRELL TRUCKING COMPANY, INC. | |SUB %: 3.86 | | | | G. B. & G TRANSPORT, LLP | |SUB %: 3.78 | | | | J. V. CONSTRUCTION | |SUB %: 2.53 | | | | TEXAS ALTERNATIVE GRASSER, INC. | |SUB %: 0.97 | | | | COLORADO DOUBLE D CONSTRUCTION LLC | |SUB %: 1.25 | | | | E. DIAZ TRUCKING | |SUB %: 0.00 | | | | | | | | | | CONTRACT 06113248 | TOTALS | 11,848,782.75| 436,431.49| 5,826,869.95| 50.1| ************************************************************************************************************************************ OCHILTREE WOLF CREEK BRIDGE | 6.535 | 5,839,756.54| 50,828.24| 5,471,688.41| 97.6| US 83 1.4 MILES N OF NORTHUP CREEK | | | | | | 0030-03-023 | | | | | | STP 2011(209)ES REHABILITATE EXISTING ROADWAY | | | | | | | | | | | | WORK ORDER- 12-06-10 WORK BEGAN- 01-25-11 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 12-22-10 | | | | | | CONTRACT WORKING DAYS- 259 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 471 PERCENT TIME USED- 181 | | | | | | | | | | | | GILVIN-TERRILL, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0030-03-023 | | | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 1.70 | | | | CUTRELL TRUCKING COMPANY, INC. | |SUB %: 4.54 | | | | JONA CONTRACTING, INC. | |SUB %: 0.74 | | | | TEXAS ALTERNATIVE GRASSER, INC. | |SUB %: 0.86 | | | | G. B. & G TRANSPORT, LLP | |SUB %: 1.38 | | | | E. DIAZ TRUCKING | |SUB %: 0.00 | | | | | | | | | | CONTRACT 10103004 | TOTALS | 5,839,756.54| 50,828.24| 5,471,688.41| 97.6| ************************************************************************************************************************************ OCHILTREE ETC SH 15 | 347.995 | 10,212,987.82| 395,372.85| 1,475,781.84| 14.4| US 83 ETC 1 MILE SOUTH OF LP 143 | | | | | | 0030-02-043 | | | | | | STP 2013(084) SEAL COAT | | | | | | | | | | | | WORK ORDER- 11-14-12 WORK BEGAN- 00-00-00 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 05-15-13 | | | | | | CONTRACT WORKING DAYS- 76 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | | | | | | | | | | | | MISSOURI PETROLEUM PRODUCTS COMPANY LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0030-02-043 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 10123204 | TOTALS | 10,212,987.82| 395,372.85| 1,475,781.84| 14.4| ************************************************************************************************************************************ POTTER VARIOUS LOCATIONS DISTRICTWIDE | 0.100 | 1,074,590.66| 0.00| 0.00| 0.0| VA . | | | | | | 0904-00-144 | | | | | | STP 2013(376) THERMOPLASTIC STRIPING | | | | | | | | | | | | WORK ORDER- 04-23-13 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 05-14-13 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 54 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | TEXAS PANHANDLE CONSTRUCTION, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0904-00-144 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 02133025 | TOTALS | 1,074,590.66| 0.00| 0.00| 0.0| ************************************************************************************************************************************ POTTER AT MOBLEY AVE | 0.001 | 1,688,123.28| 0.00| 0.00| 0.0| US 87 . | | | | | | 0041-07-100 | | | | | | BR 2013(374) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 04-19-13 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 05-05-13 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 86 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | COPPELL CONSTRUCTION CO., INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0041-07-100 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.58 | | | | L. A. FULLER & SONS CONSTRUCTION, LTD. | |SUB %: 3.06 | | | | M & D FOUNDATION DRILLING INDUSTRIES, INC. | |SUB %: 5.13 | | | | SCOTT DERR PAINTING CO | |SUB %: 0.41 | | | | VANN/ELLI, INC. | |SUB %: 7.15 | | | | WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED | |SUB %: 0.57 | | | | | | | | | | CONTRACT 02133224 | TOTALS | 1,688,123.28| 0.00| 0.00| 0.0| ************************************************************************************************************************************ POTTER AT LP 335 (ST FRANCIS AVE) | 0.126 | 2,245,899.16| 232,864.90| 2,000,466.78| 89.0| US 87 . | | | | | | 0041-07-097 | | | | | | BR 2012(362) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | POTTER AT WILLOW CREEK DR | 0.099 | 1,135,322.53| 2,407.00| 105,183.98| 9.2| US 87 . | | | | | | 0041-07-098 | | | | | | BR 2012(362) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | POTTER AT CHERRY AVE | 0.102 | 1,164,718.11| 121,452.01| 1,178,129.20| 99.9| US 87 . | | | | | | 0041-07-099 | | | | | | BR 2012(362) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | POTTER AT FM 1719 | 0.093 | 1,115,502.85| 46,468.95| 431,822.57| 38.7| US 87 . | | | | | | 0041-07-101 | | | | | | BR 2012(362) REPLACE BRIDGE AND APPROACHES | | | | | | | | | | | | WORK ORDER- 04-17-12 WORK BEGAN- 06-04-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 05-03-12 | | | | | | CONTRACT WORKING DAYS- 556 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 227 PERCENT TIME USED- 40 | | | | | | | | | | | | COPPELL CONSTRUCTION CO., INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0041-07-097 | | | | | | HOLMES CONSTRUCTION CO., L.P. | |SUB %: 7.77 | | | | HOUSTON SAWING & DRILLING | |SUB %: 0.19 | | | | LANCO TURF & SEEDING, INC. | |SUB %: 0.08 | | | | M & D FOUNDATION DRILLING INDUSTRIES, INC. | |SUB %: 4.80 | | | | RAY ELECTRIC COMPANY | |SUB %: 0.15 | | | | SCOTT DERR PAINTING CO | |SUB %: 0.62 | | | | SHINN & GREGORY, INC. | |SUB %: 1.50 | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 1.57 | | | | DUSTIN ALLEN, INC. | |SUB %: 2.49 | | | | | | | | | | CONTRACT 03123209 | TOTALS | 5,661,442.65| 403,192.86| 3,715,602.53| 65.6| ************************************************************************************************************************************ POTTER ON GRAND ST AND SE 3RD AVE | 0.442 | 5,073,269.94| 103,589.25| 4,758,518.42| 95.5| VA AT BNSF RR | | | | | | 0904-02-035 | | | | | | STP 2010(401)ES CONSTRUCT RR OVERPASS | | | | | | | | | | | | WORK ORDER- 05-26-10 WORK BEGAN- 07-27-10 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 06-11-10 | | | | | | CONTRACT WORKING DAYS- 400 ADDL DAYS GRANTED- 26 | | | | | | WORKING DAYS CHARGED- 505 PERCENT TIME USED- 118 | | | | | | | | | | | | RK HALL, LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0904-02-035 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.38 | | | | J.V. CONCRETE CONSTRUCTION | |SUB %: 2.80 | | | | J & M ELECTRIC | |SUB %: 1.66 | | | | M & D FOUNDATION DRILLING INDUSTRIES, INC. | |SUB %: 1.44 | | | | SITESAFE PRODUCTS TEXAS | |SUB %: 0.69 | | | | SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C. | |SUB %: 0.22 | | | | TEXAS ENVIRONMENTAL MANAGEMENT, INC | |SUB %: 0.51 | | | | TOTAL HIGHWAY MAINTENANCE, LLC | |SUB %: 1.15 | | | | DUSTROL, INC. (ROANOKE) | |SUB %: 0.49 | | | | NORTH TEXAS REBAR, LLC | |SUB %: 0.19 | | | | T-BAR FENCE, INC. | |SUB %: 1.12 | | | | ARTEX ELECTRIC, INC. | |SUB %: 1.04 | | | | HJC FARMS, INC. | |SUB %: 0.47 | | | | WEBBER BARRIER SERVICES, INC. | |SUB %: 1.42 | | | | HOLMES CONSTRUCTION CO., L.P. | |SUB %: 0.29 | | | | PRIMATE CONSTRUCTION, INC. | |SUB %: 0.48 | | | | SOUTHEAST GRINDING & GROOVING, LLC | |SUB %: 0.58 | | | | L. A. FULLER & SONS CONSTRUCTION, LTD. | |SUB %: 0.08 | | | | | | | | | | CONTRACT 04103005 | TOTALS | 5,073,269.94| 103,589.25| 4,758,518.42| 95.5| ************************************************************************************************************************************ POTTER VARIOUS LOCATIONS IN AMARILLO | 0.100 | 2,062,945.48| 72,108.10| 1,261,150.27| 65.0| VA (ON SYSTEM) | | | | | | 0904-00-148 | | | | | | STP 2012(052) STATEWIDE CURB RAMP PROGRAM | | | | | | | | | | | | WORK ORDER- 01-03-12 WORK BEGAN- 01-23-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 01-19-12 | | | | | | CONTRACT WORKING DAYS- 175 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 277 PERCENT TIME USED- 158 | | | | | | | | | | | | SCR CONSTRUCTION CO., INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0904-00-148 | | | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 5.28 | | | | RAY ELECTRIC COMPANY | |SUB %: 7.14 | | | | SECRET GARDENER | |SUB %: 0.00 | | | | SPEEDY PAVING | |SUB %: 2.25 | | | | | | | | | | CONTRACT 10113013 | TOTALS | 2,062,945.48| 72,108.10| 1,261,150.27| 65.0| ************************************************************************************************************************************ POTTER VARIOUS LOCATIONS DISTRICTWIDE | 0.100 | 2,916,208.80| 158,906.79| 930,735.56| 31.9| VA (ON SYSTEM) | | | | | | 0904-00-154 | | | | | | STP 2013(085) STATEWIDE CURB RAMP PROGRAM | | | | | | | | | | | | WORK ORDER- 12-04-12 WORK BEGAN- 01-08-13 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 12-20-12 | | | | | | CONTRACT WORKING DAYS- 206 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 79 PERCENT TIME USED- 38 | | | | | | | | | | | | ENCINO LANDSCAPE, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0904-00-154 | | | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 6.11 | | | | CLASSIC TEJAS CONSTRUCTION, INC. | |SUB %: 14.48 | | | | | | | | | | CONTRACT 10123029 | TOTALS | 2,916,208.80| 158,906.79| 930,735.56| 31.9| ************************************************************************************************************************************ POTTER VARIOUS LOCATIONS DISTRICTWIDE | 195.587 | 651,808.43| 0.00| 616,085.35| 97.1| VA . | | | | | | 0904-00-149 | | | | | | STP 2012(092) CRACK SEAL | | | | | | | | | | | | WORK ORDER- 12-05-11 WORK BEGAN- 01-10-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 01-02-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 65 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 93 PERCENT TIME USED- 143 | |**************************************************| | | | | | | | L. A. FULLER & SONS CONSTRUCTION, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0904-00-149 | | | | | | TEXAS BARRICADE & SIGNS, INC. | |SUB %: 2.53 | | | | | | | | | | CONTRACT 11113014 | TOTALS | 651,808.43| 0.00| 616,085.35| 97.1| ************************************************************************************************************************************ POTTER HESTER ROAD | 0.846 | 4,172,496.27| 174,043.45| 3,679,445.25| 88.1| LP 335 NORTH COULTER ST | | | | | | 2635-04-025 | | | | | | STP 2012(139) CONSTRUCT FUTURE I/C CONNECTORS | | | | | | | | | | | | WORK ORDER- 01-11-12 WORK BEGAN- 01-16-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 01-27-12 | | | | | | CONTRACT WORKING DAYS- 337 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 294 PERCENT TIME USED- 87 | | | | | | | | | | | | GILVIN-TERRILL, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 2635-04-025 | | | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 0.34 | | | | L. A. FULLER & SONS CONSTRUCTION, LTD. | |SUB %: 24.63 | | | | NORTH TEXAS REBAR, LLC | |SUB %: 0.75 | | | | M & D FOUNDATION DRILLING INDUSTRIES, INC. | |SUB %: 4.01 | | | | NORTH TEXAS REBAR, LLC | |SUB %: 0.22 | | | | ALAMO BROTHERS CONCRETE | |SUB %: 2.85 | | | | RAY ELECTRIC COMPANY | |SUB %: 0.40 | | | | AMARILLO RMT ENTERPRISE | |SUB %: 0.37 | | | | FARR FOUNDATION, INC. | |SUB %: 4.29 | | | | TEXAS ALTERNATIVE GRASSER, INC. | |SUB %: 0.47 | | | | SCOTT DERR PAINTING CO, LLC | |SUB %: 0.31 | | | | | | | | | | CONTRACT 12113023 | TOTALS | 4,172,496.27| 174,043.45| 3,679,445.25| 88.1| ************************************************************************************************************************************ RANDALL AT US 87 & US 60 CONNECTOR IN CANYO | 0.098 | 1,009,919.88| 1,524.51| 1,178,087.77| 99.9| US 60 . | | | | | | 0168-08-062 | | | | | | BR 2012(477) REPLACE BRIDGE & APPROACHES | | | | | | | | | | | | WORK ORDER- 06-21-12 WORK BEGAN- 08-28-12 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 07-07-12 | | | | | | CONTRACT WORKING DAYS- 75 ADDL DAYS GRANTED- 19 | | | | | | WORKING DAYS CHARGED- 86 PERCENT TIME USED- 91 | | | | | | | | | | | | GILVIN-TERRILL, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0168-08-062 | | | | | | ATS DRILLING, INC. | |SUB %: 8.41 | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 1.07 | | | | J.L. STEEL REINFORCING, LLC | |SUB %: 0.89 | | | | SCOTT DERR PAINTING CO, LLC | |SUB %: 0.08 | | | | DUSTROL, INC. | |SUB %: 1.40 | | | | HJC FARMS, INC. | |SUB %: 2.39 | | | | HOLMES CONSTRUCTION CO., L.P. | |SUB %: 9.34 | | | | HOUSTON SAWING & DRILLING | |SUB %: 0.18 | | | | TEXAS ALTERNATIVE GRASSER, INC. | |SUB %: 0.96 | | | | S & S BRIDGE PAINTING, INC. | |SUB %: 1.40 | | | | | | | | | | CONTRACT 05123242 | TOTALS | 1,009,919.88| 1,524.51| 1,178,087.77| 99.9| ************************************************************************************************************************************ RANDALL IN PALO DURO CANYON STATE PARK | 0.001 | 394,526.70| 0.00| 239,437.52| 61.1| PW . | | | | | | 0904-11-049 | | | | | | C 904-11-49 CONSTRUCT NEW CAMP LOOP AND PARKING | | | | | | | | | | | | WORK ORDER- 08-21-12 WORK BEGAN- 11-05-12 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 10-21-12 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 60 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 63 PERCENT TIME USED- 105 | |**************************************************| | | | | | | | HOLMES CONSTRUCTION CO., L.P. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0904-11-049 | | | | | | HIGHWAY TECHNOLOGIES, INC. | |SUB %: 0.31 | | | | ALAMO BROTHERS CONCRETE | |SUB %: 7.37 | | | | EWING CABLE | |SUB %: 1.52 | | | | BRUSH EATERS, INC. | |SUB %: 1.90 | | | | WEST TEXAS UTILITY CONTRACTORS, INC. | |SUB %: 0.45 | | | | TEXAS ALTERNATIVE GRASSER, INC. | |SUB %: 1.20 | | | | | | | | | | CONTRACT 07123024 | TOTALS | 394,526.70| 0.00| 239,437.52| 61.1| ************************************************************************************************************************************ RANDALL SPUR 48 (RUSSELL LONG BLVD) | 0.145 | 837,902.85| 637.50| 830,726.76| 99.0| US 87 300 FT NORTH OF RR UNDERPASS | | | | | | 0067-01-077 | | | | | | STP 2011(263)TE CANYON US 87 GATEWAY ENHANCEMENT | | | | | | | | | | | | RANDALL SPUR 48 (RUSSELL LONG BLVD) | 0.145 | 118,627.40| 0.00| 136,148.00| 99.9| US 87 300 FT NORTH OF RR UNDERPASS | | | | | | 0067-01-078 | | | | | | NH 1102(298) IMPROVE INTERSECTION AND DRAINAGE | | | | | | | | | | | | WORK ORDER- 09-30-11 WORK BEGAN- 11-15-11 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 10-16-11 | | | | | | CONTRACT WORKING DAYS- 110 ADDL DAYS GRANTED- 82 | | | | | | WORKING DAYS CHARGED- 195 PERCENT TIME USED- 101 | | | | | | | | | | | | L. A. FULLER & SONS CONSTRUCTION, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0067-01-077 | | | | | | A-1 SERVICES | |SUB %: 0.08 | | | | ALAMO BROTHERS CONCRETE | |SUB %: 18.43 | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 1.95 | | | | RAY ELECTRIC COMPANY | |SUB %: 8.03 | | | | CONCRETE PAVER SYSTEMS, INC. | |SUB %: 18.41 | | | | SECRET GARDENER | |SUB %: 14.39 | | | | MISSOURI PETROLEUM PRODUCTS COMPANY LLC | |SUB %: 2.02 | | | | | | | | | | CONTRACT 08113216 | TOTALS | 956,530.25| 637.50| 966,874.76| 99.9| ************************************************************************************************************************************ RANDALL DEAF SMITH COUNTY LINE | 14.789 | 7,931,426.33| 443,516.50| 477,116.50| 6.0| US 60 US 87 | | | | | | 0168-08-068 | | | | | | NH 2013(088) OVERLAY | | | | | | | | | | | | WORK ORDER- 01-03-13 WORK BEGAN- 00-00-00 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 01-19-13 | | | | | | CONTRACT WORKING DAYS- 220 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 72 PERCENT TIME USED- 32 | | | | | | | | | | | | J. LEE MILLIGAN, INC. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0168-08-068 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 10123227 | TOTALS | 7,931,426.33| 443,516.50| 477,116.50| 6.0| ************************************************************************************************************************************ RANDALL ON FARMERS AVE, FROM WESTERN ST | 0.996 | 1,400,000.00| 0.00| 0.00| 0.0| CS GEORGIA ST | | | | | | 0904-11-053 | | | | | | STP 2013(143) REHAB EXISTING ROADWAY | | | | | | | | | | | | WORK ORDER- 01-04-13 WORK BEGAN- 00-00-00 | |**************************************************| | DATE WORK COMPLETED- TIME COMPUTED- 05-06-13 | |* NO CURRENT ESTIMATE PROCESSED AT THE *| | CONTRACT WORKING DAYS- 83 ADDL DAYS GRANTED- 0 | |* TIME OF THIS RUN *| | WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 | |**************************************************| | | | | | | | L. A. FULLER & SONS CONSTRUCTION, LTD. | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0904-11-053 | | | | | | NO SUBCONTRACTORS FOR THIS CCSJ | | | | | | | | | | | | CONTRACT 11123019 | TOTALS | 1,400,000.00| 0.00| 0.00| 0.0| ************************************************************************************************************************************ SHERMAN COUNTY ROAD G | 9.953 | 3,252,696.71| 0.00| 3,199,800.07| 99.9| US 54 OKLAHOMA STATE LINE | | | | | | 0238-06-026 | | | | | | NH 1102(367) REHAB EXISTING RDWY & PASSING LANES | | | | | | | | | | | | WORK ORDER- 08-15-11 WORK BEGAN- 09-19-11 | | | | | | DATE WORK COMPLETED- TIME COMPUTED- 08-31-11 | | | | | | CONTRACT WORKING DAYS- 110 ADDL DAYS GRANTED- 0 | | | | | | WORKING DAYS CHARGED- 193 PERCENT TIME USED- 175 | | | | | | | | | | | | RK HALL, LLC | | | | | | SUBCONTRACTOR(S) FOR CCSJ: 0238-06-026 | | | | | | WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED | |SUB %: 2.00 | | | | HOLMES CONSTRUCTION CO., L.P. | |SUB %: 6.96 | | | | DUSTROL, INC. | |SUB %: 4.25 | | | | TOTAL HIGHWAY MAINTENANCE, LLC | |SUB %: 0.27 | | | | LANCO TURF & SEEDING, INC. | |SUB %: 0.10 | | | | | | | | | | CONTRACT 07113066 | TOTALS | 3,252,696.71| 0.00| 3,199,800.07| 99.9| ************************************************************************************************************************************ DISTRICT CONTRACT AMOUNT 150,864,793.33 DISTRICT ESTIMATES THIS MONTH 3,539,204.62 DISTRICT TOTAL ESTIMATES PAID TO DATE 55,820,011.10