| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | HOWARD |
| Highway |
IH0020 |
| From |
IH 20 @ |
| To |
RATTLESNAKE GAP BRIDGE |
| CSJ |
6132-72-001 |
| Proj ID |
BPM - 613272001 |
| Work Type |
SPALL AND BENT REPAIR |
| |
|
0.079 |
385165.31 |
60168.78 |
201557.20 |
52.3 |
| Work Order |
07-07-08 |
| Work Began |
07-14-08 |
| Work Completed |
|
| Time Computed |
07-14-08 |
| Contract Working Days |
80 |
| Addl Days Granted |
0 |
| Working Days Charged |
76 |
| Percent Time Used |
95 |
| Contractor(s) |
| VILLA & SONS CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6132-72-001 GIBSON & ASSOCIATES, INC.( 44.99%) CHEROKEE SERVICES( 12.11%) CONTRACTORS SERVICE COMPANY(1.42%)
|
| Contract # |
05084035 |
|
Totals |
385165.31 |
60168.78 |
201557.20 |
52.3 |
|
| County | SHACKELFORD |
| Highway |
US0180 |
| From |
VARIOUS LOCATIONS IN SHACKELFORD, JONES |
| To |
AND STONEWALL COUNTIES |
| CSJ |
6166-75-001 |
| Proj ID |
BPM - 616675001 |
| Work Type |
BRIDGE SPALL REPAIR |
| |
|
0.316 |
299726.00 |
77875.28 |
152901.80 |
51.0 |
| Work Order |
06-30-08 |
| Work Began |
07-29-08 |
| Work Completed |
|
| Time Computed |
07-21-08 |
| Contract Working Days |
61 |
| Addl Days Granted |
0 |
| Working Days Charged |
56 |
| Percent Time Used |
91 |
| Contractor(s) |
| SCR CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6166-75-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04084002 |
|
Totals |
299726.00 |
77875.28 |
152901.80 |
51.0 |
|
| County | HOWARD |
| Highway |
IH0020 |
| From |
IH 20 @ BEALS CREEK AND |
| To |
FM 700 @ BEALS CREEK |
| CSJ |
6166-76-001 |
| Proj ID |
BPM - 616676001 |
| Work Type |
MISCELLANEOUS BRIDGE REPAIR |
| |
|
0.188 |
274327.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
11-10-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
11-17-08 |
| Contract Working Days |
33 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| GIBSON & ASSOCIATES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6166-76-001 UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(1.61%) CONTRACT PAVING CO.( 16.14%)
|
| Contract # |
05084016 |
|
Totals |
274327.00 |
0.00 |
0.00 |
0.0 |
|
| County | TAYLOR |
| Highway |
IH0020 |
| From |
TAYLOR, CALLAHAN, JONES, SHACKELFORD, |
| To |
STONEWALL & HASKELL COUNTIES |
| CSJ |
6170-09-001 |
| Proj ID |
RMC - 617009001 |
| Work Type |
"ON DEMAND" MBGF |
| |
|
0.010 |
556800.25 |
29200.98 |
533905.87 |
95.8 |
| Work Order |
02-04-08 |
| Work Began |
02-05-08 |
| Work Completed |
|
| Time Computed |
02-11-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
270 |
| Percent Time Used |
73 |
| Contractor(s) |
| HJC FARMS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6170-09-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12074029 |
|
Totals |
556800.25 |
29200.98 |
533905.87 |
95.8 |
|