Monthly State Let Maintenance Report For Abilene District As Of May 15, 2013 Page 1 Of 1

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyKENT
Highway SH0070
From ABC CREEK; BUTTE CREEK AND
To THE SALT FORK OF THE BRAZOS
CSJ 6215-55-001
Proj ID BPM - 621555001
Work Type BRIDGE REPAIR
 
0.010 396374.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-06-13
Work Began 05-14-13
Work Completed  
Time Computed 05-13-13
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6215-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03134029
Totals 396374.75 0.00 0.00 0.0

CountyTAYLOR
Highway US0083
From SOUTH END OF ANTILLEY ROAD BRIDGE
To SOUTH OF IBERIS ROAD
CSJ 6233-65-001
Proj ID RMC - 623365001
Work Type BASE FAILURE REPAIR AND SEAL COAT
 
2.122 693671.42 0.00 398525.65 57.4
Work Order 12-03-12
Work Began 12-13-12
Work Completed  
Time Computed 12-10-12
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 63
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 6233-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09124013
Totals 693671.42 0.00 398525.65 57.4

CountyTAYLOR
Highway MR0676
From ABILENE STATE SCHOOL
To ABILENE STATE SCHOOL
CSJ 6241-68-001
Proj ID RMC - 624168001
Work Type PARKING AREA AND ROADWAY REPAIR
 
0.010 412342.85 0.00 425300.85 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-18-13
Work Began 02-18-13
Work Completed  
Time Computed 02-25-13
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 86
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6241-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09124003
Totals 412342.85 0.00 425300.85 99.9

CountyCALLAHAN
Highway IH0020
From VARIOUS LOCATIONS ACROSS THE
To ABILENE DISTRICT
CSJ 6248-51-001
Proj ID RMC - 624851001
Work Type DISTRICT SEAL COAT
 
0.010 4450333.60 0.00 1193268.00 26.8
Work Order 01-31-13
Work Began 01-31-13
Work Completed  
Time Computed 02-07-13
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6248-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11124011
Totals 4450333.60 0.00 1193268.00 26.8

CountyTAYLOR
Highway IH0020
From TAYLOR, CALLAHAN, SHACKELFORD,JONES
To HASKELL, STONEWALL COUNTIES
CSJ 6249-60-001
Proj ID RMC - 624960001
Work Type ON CALL MBGF
 
0.001 569199.42 48410.00 59209.00 10.4
Work Order 03-26-13
Work Began 03-27-13
Work Completed  
Time Computed 04-02-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6249-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01134041
Totals 569199.42 48410.00 59209.00 10.4

CountyNOLAN
Highway BI0020M
From VAR LOCATIONS IN THE ABILENE DISTRICT
To VAR LOCATIONS IN THE ABILENE DISTRICT
CSJ 6250-39-001
Proj ID RMC - 625039001
Work Type INSTALL THERMOPLASTIC PAVEMENT MARKINGS
 
0.001 958053.02 552275.82 705659.82 73.6
Work Order 03-29-13
Work Began 03-31-13
Work Completed  
Time Computed 04-05-13
Contract Working Days 53
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 32
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6250-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11124002
Totals 958053.02 552275.82 705659.82 73.6

page 1