Monthly Local Let Maintenance Report For Abilene District As Of Dec 9, 2016 Page 3 Of 3

Last Update: Friday, December 9, 2016
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCALLAHAN
Highway US0283
From VARIOUS LOCATIONS IN CALLAHAN
To VARIOUS LOCATIONS_IN CALLAHAN
CSJ 6295-87-001
Proj ID SUP - 629587001
Work Type LITTER REMOVAL IN CALLAHAN COUNTY
 
0.001 62240.39 4136.01 45060.07 72.3
Work Order 01-22-16
Work Began 02-01-16
Work Completed  
Time Computed 02-01-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 274
Percent Time Used 75
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12150830
Totals 62240.39 4136.01 45060.07 72.3

CountyTAYLOR
Highway US0083
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6295-88-001
Proj ID SUP - 629588001
Work Type LITTER REMOVAL
 
0.001 133577.22 6714.14 88513.98 66.2
Work Order 01-22-16
Work Began 02-01-16
Work Completed  
Time Computed 02-01-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 274
Percent Time Used 75
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6295-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12150831
Totals 133577.22 6714.14 88513.98 66.2

CountyTAYLOR
Highway US0083
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6295-95-001
Proj ID SUP - 629595001
Work Type ADDITIONAL LABOR ONSITE ATTENDANT
 
0.001 24960.00 0.00 17712.00 70.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-24-15
Work Began 01-01-16
Work Completed  
Time Computed 01-01-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 274
Percent Time Used 75
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11150831
Totals 24960.00 0.00 17712.00 70.9

CountyHOWARD
Highway MR0686
From BIG SPRING STATE HOSPITAL
To BIG SPRING STATE HOSPITAL
CSJ 6296-92-001
Proj ID RMC - 629692001
Work Type DRAINAGE AND DRIVEWAY IMPROVEMENTS
 
0.011 105953.18 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6296-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03160804
Totals 105953.18 0.00 0.00 0.0

CountyTAYLOR
Highway BI0020R
From VARIOUS LOCATIONS IN TAYLOR, CALLAHAN,
To SHACKELFORD, JONES & HASKELL COUNTIES
CSJ 6297-66-001
Proj ID RMC - 629766001
Work Type INSTALLATION OF PAVEMENT MARKINGS
 
0.010 210984.59 0.00 256504.99 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-26-16
Work Completed  
Time Computed 08-26-16
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 55
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6297-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06160801
Totals 210984.59 0.00 256504.99 99.9

CountyTAYLOR
Highway US0083
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6299-62-001
Proj ID SUP - 629962001
Work Type PREVENTATIVE MAINTENANE
 
0.001 121585.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6299-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07160830
Totals 121585.00 0.00 0.00 0.0

CountyTAYLOR
Highway US0083
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6301-21-001
Proj ID SUP - 630121001
Work Type JANITORIAL MAINTENANCE
 
0.001 77010.00 0.00 30040.00 39.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 141
Percent Time Used 38
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6301-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04160830
Totals 77010.00 0.00 30040.00 39.0

CountyTAYLOR
Highway IH0020
From VARIOUS LOCATIONS IN TAYLOR, CALLAHAN
To JONES AND SHACKELFORD COUNTIES
CSJ 6309-47-001
Proj ID RMC - 630947001
Work Type CLEAN AND SEAL CRACKS AND JOINTS
 
0.001 152961.64 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 24
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ARCC CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6309-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11160801
Totals 152961.64 0.00 0.00 0.0

CountyHOWARD
Highway IH0020
From VARIOUS LOCATIONS IN HOWARD, MITCHELL,
To NOLAN AND BORDEN COUNTIES
CSJ 6309-48-001
Proj ID RMC - 630948001
Work Type CRACK SEALING
 
0.001 175455.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-30-16
Work Began 11-30-16
Work Completed  
Time Computed 12-01-16
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6309-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11160802
Totals 175455.20 0.00 0.00 0.0

CountySCURRY
Highway US0180
From VARIOUS LOCATIONS IN SCURRY, FISHER
To AND HASKELL COUNTIES
CSJ 6309-49-001
Proj ID RMC - 630949001
Work Type CRACK SEALING
 
0.010 172304.00 0.00 10420.20 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-30-16
Work Began 11-30-16
Work Completed 10-05-16
Time Computed 12-01-16
Contract Working Days 31
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6309-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11160803
Totals 172304.00 0.00 10420.20 100.0