Monthly Local Let Maintenance Report For Abilene District As Of Jul 13, 2015 Page 3 Of 3

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCALLAHAN
Highway IH0020
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6280-06-001
Proj ID RMC - 628006001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 165348.00 0.00 0.00 0.0
Work Order 06-08-15
Work Began 00-00-00
Work Completed  
Time Computed 06-15-15
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 20
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6280-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11140801
Totals 165348.00 0.00 0.00 0.0

CountyJONES
Highway US0083
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6280-07-001
Proj ID RMC - 628007001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 176160.00 31320.00 31320.00 17.7
Work Order 06-15-15
Work Began 00-00-00
Work Completed  
Time Computed 06-22-15
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 9
Contractor(s)
KENNETH THOMASON
SUBCONTRACTOR(S) FOR CCSJ: 6280-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11140802
Totals 176160.00 31320.00 31320.00 17.7

CountyKENT
Highway US0380
From VARIOUS LOCATIONS IN KENT CO.
To VARIOUS LCOATIONS IN SCURRY CO.
CSJ 6280-08-001
Proj ID RMC - 628008001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 178589.61 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KENNETH THOMASON
SUBCONTRACTOR(S) FOR CCSJ: 6280-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11140803
Totals 178589.61 0.00 0.00 0.0

CountyNOLAN
Highway IH0020
From VARIOUS LOCATIONS IN NOLAN CO.
To VARIOUS LOCATIONS IN FISHER CO.
CSJ 6280-09-001
Proj ID RMC - 628009001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 275580.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-15-15
Work Began 00-00-00
Work Completed  
Time Computed 06-22-15
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 8
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6280-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11140804
Totals 275580.00 0.00 0.00 0.0

CountySTONEWALL
Highway US0380
From VARIOUS LOCATIONS IN STONEWALL CO.
To VARIOUS LOCATIONS IN HASKELL CO.
CSJ 6280-10-001
Proj ID RMC - 628010001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 185400.00 0.00 44952.75 24.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-24-15
Work Began 00-00-00
Work Completed  
Time Computed 07-01-15
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FOUR R OILFIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6280-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11140805
Totals 185400.00 0.00 44952.75 24.2

CountyTAYLOR
Highway IH0020
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6280-11-001
Proj ID RMC - 628011001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 156330.00 20599.00 20599.00 13.1
Work Order 06-01-15
Work Began 00-00-00
Work Completed  
Time Computed 06-08-15
Contract Working Days 47
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 31
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6280-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11140806
Totals 156330.00 20599.00 20599.00 13.1

CountyHOWARD
Highway IH0020
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6281-02-001
Proj ID SUP - 628102001
Work Type LITTER REMOVAL
 
0.001 55769.08 6854.75 33229.21 59.5
Work Order 12-01-14
Work Began 12-01-14
Work Completed  
Time Computed 12-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6281-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10140831
Totals 55769.08 6854.75 33229.21 59.5

CountyTAYLOR
Highway US0083
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6281-03-001
Proj ID SUP - 628103001
Work Type ADDITIONAL LABOR ONSITE ATTENDANT
 
0.001 0.00 0.00 9504.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 01-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10140830
Totals 0.00 0.00 9504.00 0.0

CountyCALLAHAN
Highway US0283
From VARIOUS LOCATIONS IN CALLAHAN
To VARIOUS LOCATIONS IN CALLAHAN
CSJ 6281-04-001
Proj ID SUP - 628104001
Work Type LITTER REMOVAL IN CALLAHAN COUNTY
 
0.001 57498.98 3911.23 23666.50 41.1
Work Order 01-27-15
Work Began 02-01-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 150
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01150830
Totals 57498.98 3911.23 23666.50 41.1

CountyTAYLOR
Highway US0083
From VARIOUS LOCATIONS IN TAYLOR CO.TY
To VARIOUS LOCATIONS IN JONES & NOLAN CO.
CSJ 6281-05-001
Proj ID SUP - 628105001
Work Type LITTER REMOVAL
 
0.001 117571.48 0.00 41503.48 35.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 02-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 150
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6281-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01150831
Totals 117571.48 0.00 41503.48 35.3

CountySCURRY
Highway US0084
From US 84 @ SH 208 BRIDGE
To .
CSJ 6281-25-001
Proj ID RMC - 628125001
Work Type HEAT STRAIGHTENING BENT BEAMS
 
0.010 107776.00 58388.00 107776.00 99.9
Work Order 00-00-00
Work Began 04-22-15
Work Completed  
Time Computed 04-28-15
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 35
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150803
Totals 107776.00 58388.00 107776.00 99.9

CountySCURRY
Highway US0084
From SCURRY, KENT, STONEWALL, HASKELL,
To FISHER AND JONES COUNTIES
CSJ 6283-09-001
Proj ID RMC - 628309001
Work Type ON DEMAND MBGF
 
0.010 58755.00 8279.50 19282.50 32.8
Work Order 03-23-15
Work Began 03-23-15
Work Completed  
Time Computed 03-30-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 93
Percent Time Used 25
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6283-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150801
Totals 58755.00 8279.50 19282.50 32.8

CountyHOWARD
Highway IH0020
From HOWARD, MITCHELL, NOLAN
To AND BORDEN COUNTIES
CSJ 6283-10-001
Proj ID RMC - 628310001
Work Type ON DEMAND MBGF
 
0.010 310697.00 32359.60 64955.70 20.9
Work Order 03-23-15
Work Began 03-23-15
Work Completed  
Time Computed 03-30-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 93
Percent Time Used 25
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6283-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150802
Totals 310697.00 32359.60 64955.70 20.9

CountyTAYLOR
Highway US0083
From VARIOUS LOCATIONS IN TAYLOR CO.
To VARIOUS LOCATIONS IN TAYLOR CO.
CSJ 6284-19-001
Proj ID RMC - 628419001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 159562.00 0.00 0.00 0.0
Work Order 06-18-15
Work Began 00-00-00
Work Completed  
Time Computed 06-25-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 1
Contractor(s)
COASTAL MAINTENANCE CONCEPTS L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6284-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05150801
Totals 159562.00 0.00 0.00 0.0

CountyMITCHELL
Highway IH0020
From VARIOUS LOCATIONS IN MITCHELL COUNTY
To VARIOUS LOCATIONS IN HOWARD COUNTY
CSJ 6284-22-001
Proj ID SUP - 628422001
Work Type PICNIC AREA AND LANDSCAPE MAINTENANCE
 
0.001 151814.02 5347.63 24742.37 16.2
Work Order 01-25-15
Work Began 02-01-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 150
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6284-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01150832
Totals 151814.02 5347.63 24742.37 16.2

CountySHACKELFORD
Highway US0283
From VARIOUS LOCATIONS IN SHACKELFORD
To VARIOUS LOCATIONS IN JONES
CSJ 6285-77-001
Proj ID SUP - 628577001
Work Type PICNIC AREA MAINTENANCE
 
0.001 67566.40 5827.92 5827.92 8.6
Work Order 05-22-15
Work Began 06-01-15
Work Completed  
Time Computed 06-01-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6285-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150830
Totals 67566.40 5827.92 5827.92 8.6

CountyHASKELL
Highway US0277
From VARIOUS LOCATIONS IN HASKELL COUNTY
To VARIOUS LOCATIONS IN STONEWALL COUNTY
CSJ 6288-71-001
Proj ID SUP - 628871001
Work Type PICNIC AREA MAINTENANCE
 
0.001 31344.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-09-15
Work Began 00-00-00
Work Completed  
Time Computed 08-01-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6288-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06150830
Totals 31344.00 0.00 0.00 0.0